Documentos de Académico
Documentos de Profesional
Documentos de Cultura
C
]
0
20
40
60
80
100
V
i
b
r
a
t
i
o
n
l
e
v
e
l
[
G
r
m
s
]
AIR-TEMP PV
PTC PV
Control
FIG. 5.3 The recorded temperature and vibration log.
Terma A/S supplied 3 modules for the testing. The first 2 modules were tested mounted
in the cabinet, whereas the last module was tested clamped directly to the vibrator plane
without the motherboard and the cabinet in order to eliminate possible failures
originating from the motherboard. The cabinet provided a rigid fixture, to which it was
simple to connect. The cabinet with the DC/DC converter weighed approx 1.5 kg. Fig.
5.4 shows the DC/DC converter when mounted in the HALT chamber.
FIG. 5.4 The DC/DC converter mounted in the HALT chamber. Mounted via its
cabinet (left) and the DC/DC converter clamped to the vibration plane via a
mounting plate (right).
41
The function test during HALT consisted of loading by load resistors on the 4 voltage
outputs of the DC/DC converter. 4 of the voltage outputs were monitored by means of
multi meters whereas 2 of the voltage outputs were monitored by means of oscilloscope.
See fig. 5.5 for the function test set-up.
FIG. 5.5 The function test set-up.
The complete test log can be found in annex 3. The table 5.2 below summarises the
HALT.
42
TABLE 5.2 Summary of HALT of DC/DC converter performed for Terma A/S.
Exposure Remark
LOTL
-70C (start-up)
-76C (operation)
Lower Operational
Temperature Limit.
LDTL Not found
Lower Destruct Temperature
Limit
Low temperature
Weakness Start-up unstable
UOTL +125C
Upper Operational
Temperature Limit.
UDTL Not found
Upper Destruct Temperature
Limit
High temperature
Weakness 12 V disappeared
OVL
Approx. 30 grms (loose
screw), 60 grms (unstable
voltages)
Operational Vibration Level
VDL Approx. 60 grms Vibration Destruct Level
Vibration
Weakness Further examination required
Temperature cycling
(-70C/+125C,
4-10 min. dwell
> 20 cycles)
Weakness Not found
Combined vibration and
temperature
40, 50 and 60 grms,
-70C/ +125C
Weakness
V59, V53, R104 fell off.
Problems regarding the 5
VDC
After a general visual inspection performed at DELTA the conclusion was that there
were found weaknesses, which can be seen in table 5.3. However, it was recommended
that a thorough visual inspection should be performed on all test specimens in order to
uncover other potential weaknesses. Table 5.3 also includes Terma A/S' information
regarding relevance, possible cause and corrective actions as informed during the final
meeting.
43
TABLE 5.3 Weaknesses found during HALT.
Relevance Possible cause Action Weakness found
Yes No (e.g. reference to failure report, etc.).
Unstable start-up of 5V and
3.3V (low temperatures)
X
The characteristics started to change
ripple occurred probably due to limit
of technology.
None
12V disappeared
(high temperatures)
X
Internal temperature limit causing
shut-down, planned to be bypassed.
None
Loose PCB screw
(vibration)
X
The screw might not be tightened
from the beginning.
Locktight
Voltages dropped
(high levels of vibration)
X
Current sense transformer failed due
to hand soldering near 70 Cu which
drained the soldering heat. The
components were designed for vapour
phase soldering.
Review of
production
procedures
V59 and V63 fell off X
Successive failure caused by the
above.
Review of
production
procedures
R104 fell off X
Further
examination
required
Failure during combined tem-
perature cycling and vibration
X
Further
examination
required
The infrared thermography showed that the temperature distribution was OK. It also
helped in identifying the cause of failure when the current sense failed. This lead the
MOSFET transistor controlling the PWM to fail leaving the diodes and rectifiers ON
permanently. Further, comparing the infrared thermogram taken before and after the
HALT revealed elevated temperatures of 2 pins of the connector coupling. The
temperature rise was caused by fretting of the connectors due to a poor test set-up.
44
FIG. 5.6 Infrared thermogram of the component side of the DC/DC converter.
Normal operation.
FIG. 5.7 Infrared thermogram of the component side of the DC/DC converter.
Failure mode.
45
FIG. 5.8 Infrared thermogram of the lead side of the DC/DC converter. Failure mode.
High temperature seen near the diode and rectifier.
FIG. 5.9 Infrared thermogram showing the elevated temperatures of 2 pins of the
connector coupling due to fretting.
46
5.1.4 Comparison with other quality advancing methods and conclusion
The purpose of the HALT performed for Terma A/S was to evaluate HALT against other
quality advancing methods as well as a tool for finding failures not found otherwise.
In the following HALT is compared with the other quality advancing methods utilised by
Terma A/S on this or similar projects.
The in-house design guidelines ensure that in the first place the design is in accordance
with good design practice. The design guidelines include formulas for calculation of
maximum displacement within the frequency range for various leaded components. It
should be noted that the present printed circuit board is more rigid than usual due to the
frame and the gluing process replacing the normal heat sink compound. Further, it is
normal practice at Terma A/S to support large components by glue. Design failures
found during HALT are to be transferred into design guidelines in the future. Thus the
methods support each other, rather than excluding one another.
Calculations of the cooling of the power module performed by Terma A/S (see annex 3)
showed a negligible temperature rise over the flange from the frame to chassis. This was
verified by the infrared thermography.
MTBF-calculations were performed according to MIL-HDCK-217, Notice 2, the use
environment, 55C and 30,000 h inhabited fighter. Presently, the HALT does not provide
any figures for the MTBF or the life time.
Terma A/S performed qualification including random vibration and gunfire vibration i.e.
sine-on random according to MIL-STD-810F. The qualification testing verified the
ability of the test specimen to withstand the level of testing. No failures were found
during these tests though the testing was quite severe. Generally, except the odd loose
screw very few weaknesses were found during vibration testing.
Further, the qualification did not give any indication of the margin. The HALT showed
that the 3 test specimens were similar with design margins way beyond the qualification
limits.
The ESS performed on similar products included one temperature cycle from -40C to
+71C at a rate of 10C/min. and 45 min. of cold soak at -40C and 1 h dwell at +71C
and then back to ambient. Generally, very few weaknesses were found during ESS.
Thus, Terma A/S concluded that HALT was a valuable supplement to the quality
advancing methods normally performed by Terma A/S. It provided a measure of the
design margins. Further, it highlighted potential failures and workmanship failures which
were not found by any of the other methods.
47
5.2 Adapto BTE (Behind The Ear) hearing aid supplied by Oticon A/S
5.2.1 Test specimen
This case demonstrated customised HALT on a medical product with the aim of
evaluating HALT with other exposures than "classic" HALT. Medical products are
special in that respect that the requirements are very severe as it has to be verified that
they are safe for humans to use.
Oticon A/Swanted to include this particular product in the project as it represented a
product which Oticon A/S knew very well both with respect to testing and information
from the field. Oticon A/Shad experimented accelerating various tests in particular a
corrosion test i.e. the sweat test.
The test specimen was a hearing aid called Adapto BTE. The hearing aid is shown in fig.
5.10.
FIG. 5.10 Adapto BTE hearing aid.
5.2.2 Purpose of HALT
Oticon A/S was interested in HALT but found that "classic" HALT did not fit well with
the relevant failure mechanisms of their product. The failure mechanisms of primary
interest were corrosion and mechanical failures originating from drops.
Oticon A/S wanted to evaluate relevant customised HALT exposures - i.e. bounce and
corrosion. First of all, failure mechanisms experienced from the field seemed to point
towards different thing of which corrosion and mechanical failures originating from
drops were of primary interest. They also wanted to see if it was possible to design an
accelerated corrosion/sweat test lasting less than a week reducing the present test time
significantly. Finally, they wanted to compare weakness found during HALT with field
48
failures in order to evaluate the relevance of the failures as well as to evaluate HALT as a
method.
Oticon A/S had performed a number of environmental tests both as part of product
development and qualification of the product e.g.:
Qualification tests
Dry heat
Temperature shock
Damp heat, steady state
Sweat (both as standard Oticon in-house procedure and extended i.e. 3 times normal
duration)
Free fall
ESD
5.2.3 Description of HALT
Based on the considerations described in section 5.1.2 it was decided to include bounce
and sweat in the HALT sequence. It consisted of:
1) Vibration characterisation by bounce.
2) Preconditioning by bounce and sweat exposure.
The bounce exposure is very effective in case of light plastic encapsulated test
specimens, which are typically experiencing failures related to mechanical impact from
all possible angles.
This also solves the problem that this type of product is difficult to fixture securely to the
HALT vibration table during exposure to very high vibration levels.
The sequence of the HALT was as shown schematically in fig. 5.11.
The duration of the sweat exposure and the temperature/humidity cycling was longer
than normally seen in HALT. This is due to the nature of the failure mechanism.
49
FIG. 5.11 The sequence of the HALT performed on the Adapto BTE hearing aid.
It was decided to use an artificial sweat which is widely used within the medical industry
in Denmark and is referred to as DIN 53160 sweat. It had the following specification:
Sweat solution: 1 litre distilled water
5 gram NaCl
5 gram Dinatriumfosfat
Acetic acid (to reach the specified ph value, approx. 3 ml)
pH: 4.7
Oticon A/S supplied 10 hearing aids for the testing. The function test during HALT
included the following steps:
1) Programming in technical setting
2) Current consumption mA@1.3 V
3) Electrical/mechanical test with service software tool
4) Listening with press and twist
5) Visual check.
All steps were performed initially, whereas steps 3 - 5 were performed after each of the
exposures.
Fig. 5.12 shows the function test set-up.
Vibration characterisation,
bounce
Pre-conditioning
by bouncing
Sweat exposure
24h@40C/50C/60C/70C/80C
96 h@40C
Reference
HALT
50
FIG. 5.12 The function test set-up.
Fig. 5.13 shows the Adapto BTE hearing aids ready for the bounce exposure. Where the
hearing aids were lying loose and lifting from the vibration table during the exposure.
FIG. 5.13 The Adapto BTE hearing aid ready for bounce exposure.
During the sweat test the test specimens were placed on a plate in an excicator with the
sweat solution in the bottom. The entire set-up was placed in a room at
+40C/+50C/+60C/+70C. The air inside the excicator was changed every hour (see
also fig. 5.14 below). The test specimens were unpowered during the exposure. A func-
tional test and a visual inspection were performed after recovery.
51
FIG. 5.14 The test specimens in the excicator during the sweat exposure.
The complete test log can be found in annex 4. The table below summarises the HALT.
5.2.4 Test results
TABLE 5.4 Summary of HALT of Adapto BTE hearing aid performed for Oticon A/S.
Exposure Remark
OVL 5.0 g Operational Vibration Level
VDL 12.5 g Vibration Destruct Level
Vibration - bounce
Weakness
Function failure and
mechanical failures
OSL 40C, 24 hours Operational sweat/temperature level
SDL 80C, 24 hours
Sweat/temperature destruct level Sweat/temperature
Weakness Function failure
After a visual inspection the conclusion performed by Poul Hilding Andersson, Oticon
was the weaknesses shown in table 5.5. The table also includes Oticon's information
regarding relevance, possible cause and corrective action.
5
2
Relevance Possible cause Actions / Comments
Observations Photos
found in
fig. 5.14
Yes No
Stay in assembly shell breaks
off/shells separate
1 x Overstress during bounce/bump Failure type not seen by free fall test.
Observed as field failure by service
department.
VC wheel falls into instrument and
cannot rotate
- x Consecutive failure from broken stay Failure type not seen by free fall test.
Observed as field failure by service
department.
Wire for telecoil breaks off 2 x Insufficient stress relief. Failure type not seen by free fall test. Never
observed as field failure. Single strand wires
are generally wear at solder joints.
PCB tracks break in flex zone 3 x Lack of flexibility/insufficient stress relief Failure type seen occasionally from rough
handling of instruments in service. Not seen
as field failure. No corrosion seen in
connection with broken track. Possibly a
consecutive failure from broken telecoil
wires.
Litze wire for microphone breaks 4 x Insufficient stress relief. Failure type not seen by free fall test. Never
observed as field failure. Possibly a
consecutive failure from broken telecoil
wires.
Compensation loop on telecoil
loosens
2 x Insufficient stress relief. Adhesive type too
inflexible.
Failure type not seen by free fall test.
Observed as field failure by service
department. Also seen during development
phase as critical assembly detail.
MT0 switch fails/function failure - x Failure is most likely related to thermal
overstress (80C) of the amplifier.
Failure is not considered as relevant based on
field failure data for this instrument. MT0
switch is found to be mechanically ok.
Battery drawer opens and battery
may fall out
- x Holding force for battery drawer too low
to withstand bump forces.
Not considered as failure. Design choice wrt.
user requirements.
Microphone fails - x Possibly damaged when instrument was
opened for inspection.
Failure cause not determined.
T
A
B
L
E
5
.
5
W
e
a
k
n
e
s
s
e
s
f
o
u
n
d
d
u
r
i
n
g
H
A
L
T
.
5
3
Photo 1 Photo 2
Photo 3 Photo 4
F
I
G
.
5
.
1
4
P
h
o
t
o
s
r
e
f
e
r
r
e
d
t
o
i
n
t
a
b
l
e
5
.
5
.
54
5.2.5 Failure analysis after exposure to artificial sweat
A failure analysis was performed after the exposure to artificial sweat at various
temperatures. The failure analysis consisted of external and internal optical inspection by
stereo microscope with enlargement up to 40 times. The results of the visual inspection
are shown in annex 4.
In general it could be concluded that no corrosion/migration were observed. Salt residues
were present inside the samples.
5.2.6 Evaluation of exposures and conclusion
The purpose of the HALT performed for Oticon A/S was to evaluate customised HALT
exposures - i.e. bounce and corrosion. They also wanted to see if it was possible to
design an accelerated corrosion/sweat test. Further, they wanted to compare weakness
found during HALT with field failures in order to evaluate the relevance of the failures
as well as to evaluate HALT as a method.
The Adapto BTE hearing aids were exposed to characterisation with bounce and pre-
conditioning with bounce and sweat. The testing revealed a number of mechanical
failures originating from the bounce test. Investigations on the part of Oticon A/S
revealed that a number of the failures found were seen in the field or during service but
not in the free fall test performed as part of the qualification testing. Thus, HALT with
the bounce exposure may be considered as a useful supplement to the testing already
performed by Oticon A/S.
The sweat exposure with the DIN 53160 sweat did not lead to any significant failures
other than some was considered to be related to the high temperature. Thus, the first
attempt to design an accelerated corrosion test was unsuccessful. It is generally accepted
to be difficult to accelerate failures related to corrosion.
However, later failure analysis of the corrosion of field returns by means of EDX was
performed on field samples in order to evaluate the composition of the artificial sweat
use for the sweat exposure. The failure analysis revealed aggressive chloride (NaCl and
KCl) in the corrosion on the printed circuit board and the switch, whereas Na, Ka and
Oxide i.e. bases were found on the other specimens.
Thus it was suggested that future testing should include the evaluation of sweat with the
2 following compositions suggested by Oticon A/S; 1 solution comprising the same ions
as sweat and 1 solution with a significantly higher concentration:
Sweat solution 1: 1 litre distilled water
9 gram NaCl
9 gram Dinatriumfosfat (Na
2
HPO
4
12H
2
O)
Approx. 3 ml. 90% lactic acid (to reach the specified ph value)
pH: 5.0
55
Sweat solution 2: 1 litre distilled water
50 gram NaCl
50 gram Dinatriumfosfat (Na
2
HPO
4
12H
2
O)
80% acetic acid (to reach the specified ph value)
pH: 5.0
Further, it was suggested to expose open samples. This exposure will be performed as
part of the next HALT project "Generalisation of HALT".
5.3 Ultrasound scanner electronics from B-K Medical A/S
5.3.1 Test specimen
The test specimen demonstrated HALT on yet another medical product with the aim of
evaluating HALT by comparison with field failures.
The test specimen was a cassette for the ultrasound scanner type 2102 EXL from B-K
Medical A/S. An ultrasound scanner is showing differences in acoustical impedance as
2D-images. The present scanner was designed to perform non-inversive diagnosis of the
soft parts of the human body for e.g. urology, gynecology, obstetric, etc. or even as part
of surgery in order to see what was happening before, during and after operation.
B-K Medical A/S wanted to include the cassette in the project as it is the back bone of a
product family. Further, it has been in the field for 2-3 years. Thus, B-K Medical A/S has
extensive information from the field.
The ultrasound scanner is shown in fig. 5.16.
56
FIG. 5.16 Ultrasound scanner 2120 EXL.
The cassette consists of 3 large printed circuit boards approx. 300 mm x 400 mm and a
SMPS (Switch Mode Power Supply).
B-K Medical A/S also wanted to include a small embedded PC. The PC was accessory to
the scanner. The purpose of the testing was to find weak points of the embedded PC.
This was particularly interesting as it might be implemented on a large number of
systems. However, it was a fairly new product which was only released approx. half a
year prior to the testing. Thus, B-K medical A/S had very limited field experience of the
PC. However, it was decided to withdraw the PC from the testing in case it became a
showstopper.
5.3.2 Purpose of HALT
A successful introduction of a portable scanner following a HALT has made B-K
Medical experienced and convinced HALT users. It is company policy to perform HALT
on all new products.
However, B-K Medical A/S wanted to evaluate HALT as a tool by comparing the
failures found during the HALT with field failures.
57
5.3.3 Description of HALT
The inspection of the product together with discussion with B-K Medical regarding their
qualitative impression of the field information (no thorough analysis had been performed
prior to the testing) led to believe that the majority of the relevant failure mechanisms
would be thermo-mechanical. Thus it was decided to perform a classic HALT.
The sequence of the HALT was as shown schematically in fig. 5.17.
FIG. 5.17 The sequence of the HALT performed on ultrasound scanner electronics.
The actually recorded temperature and vibration log is shown in fig. 5.18. The testing
was performed over 2 periods with reworking in between. The complete HALT lasted 4
days as it can be seen.
Low temperature characterisation
0C and down in steps of 10C
High temperature characterisation +40C and up in steps of 10C
Temperature cycling
-20C - +80C, 6 cycles
Vibration characterisation
in steps of 5 grms
Reworking at B-K Medical
Different extra tests at DELTA
Combined temperature cycling and vibration
58
E501048 B temperature and vibration log, day 1
-50
-30
-10
10
30
50
70
90
09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00
Date, time
T
e
m
p
e
r
a
t
u
r
e
[
C
]
0
10
20
30
40
50
60
70
V
i
b
r
a
t
i
o
n
[
G
r
m
s
]
Tair [C]
PTC [C]
Vibration [Grms]
E501048 B temperature and vibration log, day 2
-50
-30
-10
10
30
50
70
90
08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00
Date, time
T
e
m
p
e
r
a
t
u
r
e
[
C
]
0
10
20
30
40
50
60
70
V
i
b
r
a
t
i
o
n
[
G
r
m
s
]
Tair [C]
PTC [C]
Vibration [Grms]
59
E501048 B temperature and vibration log, day 3
-50
-30
-10
10
30
50
70
90
08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00
Date, time
T
e
m
p
e
r
a
t
u
r
e
[
C
]
0
10
20
30
40
50
60
70
V
i
b
r
a
t
i
o
n
[
G
r
m
s
]
Tair [C]
PTC [C]
Vibration [Grms]
E501048 B temperature and vibration log, day 4
-50
-30
-10
10
30
50
70
90
08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00
Date, time
T
e
m
p
e
r
a
t
u
r
e
[
C
]
0
10
20
30
40
50
60
70
V
i
b
r
a
t
i
o
n
[
G
r
m
s
]
Tair [C]
PTC [C]
Vibration [Grms]
FIG. 5.18 The recorded temperature and vibration log, day 1 to 4.
B-K Medical A/S supplied one set of electronics together with loose modules and
components for the testing. Fig. 5.19 shows the cassette, the keyboard and the PC when
mounted in the HALT chamber.
60
FIG. 5.19 The cassette together with the embedded PC on the side and the keyboard
mounted in the HALT chamber.
The function test during HALT consisted of the steps shown in table 5.5.
61
TABLE 5.5 Function test.
Test Description
Low voltage Off/on at 90 VAC, Scanning with 8660 on phantom
High Voltage Off/on at 264 VAC, Scanning with 8660 on phantom
Nom. Voltage Off/on at 230VAC
+5V D 5V digital +/- 2% (4.9 5.1V)
+3.3VD 3.3V digital +/- 5% (0.31 - 3.47V)
+5V A 5V analog +/- 5% (4.75 5.25V)
-5V A -5V analog +/- 5% (-4.75 -5.25V)
+12V A 12V analog +/- 5% (11.4 12.6V)
-12V A -12V analog +/- 5% (-11.4 -12.6V)
+5VD ripple Ripple on 5V digital
B-Mode B-Mode scanning with 8660 on phantom
B-Mode MFI 5, 7 and MHz
3-D system Capture scan
Triplex Doppler on phantom
Triplex Doppler noise (gain)
B-Mode 1 element sweep on 8660
Test osc Analog test oscillator
Fig. 5.20 overleaf shows the fairly extensive function test set-up.
62
FIG. 5.20 The function test set-up.
The complete test log can be found in annex 6. Table 5.6 overleaf summarises the
HALT.
63
TABLE 5.6 Summary of HALT of ultrasound scanner electronics performed for B-K
Medical A/S.
Exposure Remark
LOTL
-35C (cassette)
-10C (PC)
Lower Operational
Temperature Limit.
LDTL Not found
Lower Destruct
Temperature Limit
Low temperature
Weakness VGA image falls out
UOTL +59C
Upper Operational
Temperature Limit
UDTL Not found
Upper Destruct
Temperature Limit
High temperature
Weakness
Scanner converting
unstable
OVL Approx. 35 grms (cassette) Operational Vibration Level
VDL Approx. 30 grms (SMPS) Vibration Destruct Level Vibration
Weakness
SMPS fails due to loose
screw in fan
Further examination
required
Temperature cycling
(-20C/+85C, 10 min.
dwell
6 cycles)
Weakness Not found
Combined vibration
and temperature
30, 40 and 50 grms, -
70C/+125C
Weakness
Doppler and 3D function
unstable
(It was not possible to
perform detailed function
test during combined
vibration/-temperature)
The conclusion after a general visual inspection performed at DELTA was that the
weaknesses listed in table 5.7 were found. Table 5.7 gives also a hint on the root cause
and actions as stated by B-K Medical A/S.
64
TABLE 5.7 Weaknesses found by HALT.
Stress level Error description Failing
module
Component
-20 to -40C 3D system stops Error disappears when stress is
removed
ZN0377 -
-20C VGA output unstable (White stripes) ZH0743 Error not found , but
similar problems seen in
production during cold
start at 10C
+60C Scanner stops after Switching task ZD0767 M. osc
+60C Fan on 3D system does not start. OK when
cooled again
ZN0377 -
+70C 3.3V shorted after adjusting master osc. ZD0767 U48 (VD7046)
+70C Keyboard error (Not initialised) ZD0767 U51
5G Keyboard error (Not initialised) ZD0767 U51
20G Doppler stopped and B-picture was not updated ZD0767 Rework at U117
50G Lines on composite video (only visual
inspection)
ZD0743 Loose capacitor ?
50G Keyboard not responsive ZH0676 C10 loose and cable to
keyboard loose
50G Scanner stopped SMPS Short circuit in filter
board in SMPS
50G Front-end board error, No Doppler information ZE0724 Crystal defective
MB0074
50G Front-end error ZE0724
(ZE0728)
4 pcs. transmitters
defective
10G temp cycle Doppler board stopped ZD0758 Trouble shooting in
progress
30G temp cycle Keyboard error ZD0767 U51 and reset of
NVRAM
30G temp cycle
+80C
Test impossible as master oscillator stopped ZD0767 -
50G temp cycle
-20C
Language changed during test ZD0767 Battery ?
50G temp cycle Cassette unable to start ZE0728 Defective
50G temp cycle Cassette unable to start SMPS Filterboard
50G temp cycle Cassette unable to start ZH0795 F1 loose
65
5.3.4 Failure analysis of Octal D-type flip-flops
During vibration it was not possible to activate the keyboard. The 2 Octal D-type flip-
flops were considered to be part of the cause of that failure. The 2 flip-flops were
positioned on the same board in the centre of the board.
The failure analysis consisted of external visual inspection, electrical measurements, X-
ray inspection, chemical stripping and internal visual inspection. The complete report of
failure analysis can be found in annex 5.
The I/V characterisation showed results as could be expected for one of the flip-flops
(S/N 00222). Whereas output 12 of the other flip-flop (S/N 00227) was observed to be
degraded, see fig. 5.21 below.
FIG. 5.21 Left: Characteristic of good flip-flop output.
Right: Characteristic of flip-flop output 12 of S/N 00227.
External visual and X-ray inspection showed nothing unusual on any of the flip-flops.
By internal visual inspection after decapping a severe degradation was observed on S/N
0227 at pin 12 and on part of the GND metallisation (see figs. 5.22 and 5.23). Nothing
unusual was observed on S/N 00222 after decapping.
66
FIG. 5.22 Optical micrograph of S/N 0227 showing survey of the die and location of
the observed degradation.
FIG. 5.23 Optical micrograph of S/N 00227 showing an enlargement of the degraded
area of pin 12.
67
Based on the appearance of the failure site it was concluded that excessive current load
had occurred on pin 12. B-K Medical A/S was recommended to evaluate whether the
functional testing performed during HALT could have caused this electrical overstress or
whether the root cause of the observed failure was degradation of other components in
the application.
B-K Medical A/S concluded that the error was probably caused by a bad connection in
the keyboard connector. This could also explain the problems experienced during
vibration, where the keyboard reacted slowly on key-press and the hourglass popping up
continuously. The flip-flop controls the reset of the keyboard and the load of the cable
and the input filter in the keyboard circuit, switching on and off during vibration might
have caused the excessive current in the output. The flip-flop has never been reported
failing in the field.
5.3.5 Evaluation of exposures and conclusion
The purpose of the HALT performed for B-K Medical A/S was to evaluate HALT as a
tool by comparing the failures found during the HALT with field failures.
B-K Medical A/S went through a tedious process of transforming the field data from
ASCII files into lists giving an overview of field failures. When this was done a top 10 of
the failures could be listed in order of occurrence:
1) Keyboard ZH0676
2) SMPS
3) UL0018 (not tested)
4) Doppler
5) Front end VE5274 (HV-Mux)
6) Front end ZE0728 (X-mit module)
7) Core board VC1506 (Master oscillator)
8) Core board VE5279(OP-AMP for AD converter)
9) Core board - QB0041 (battery)
10) Core board VD7046 (U48)
When the top 10 list of field failures was compared to the failures found during HALT it
could be seen that all the field failures except the UL0018 - which was not tested - were
found during HALT. Further, all failures found during HALT had been seen in the field
one way or the other.
68
In general B-K Medical A/S viewed the HALT very positively and will go on exposing
new products to HALT.
5.4 Modules for BeoSound 1 and BeoSound 3000 from Bang & Olufsen A/S
5.4.1 Test specimens
The case demonstrated HALT on audio modules with the aim of finding weaknesses as
well as evaluating HALT by comparison with Bang & Olufsen A/S' Accelerated Thermal
Stress Test (ATST).
The test specimens were modules for audio equipment namely BeoSound 1 and
BeoSound 3000.
The modules were a Switch Mode Power Supply (SMPS) for BeoSound 1 and PCB 12
i.e. Input-select for BeoSound 3000.
The BeoSound 1 and BeoSound 3000 are shown in fig. 5.24.
FIG. 5.24 BeoSound 1 and BeoSound 3000.
5.4.2 Purpose of HALT
Bang & Olufsen A/S wanted to evaluate HALT with respect to finding potential
weaknesses as well as to compare it with the Bang & Olufsen ATST.
The ATST is a famous Bang & Olufsen speciality. The purpose of the ATST is to verify
that solder joints will not fail due to fatigue, which caused by improper design of solder
joints, physical placement and fixation of components or mismatch between coefficients
of thermal expansion for different materials. It is performed on all new printed circuit
boards designed by and for Bang & Olufsen A/S.
69
5.4.3 Description of HALT
It was decided to perform a classic HALT particularly aiming at thermo-mechanical
failure mechanisms in order to make it comparable to the Bang & Olufsen ATST-test.
Fig. 5.25 shows the sequence of the HALT performed.
FIG. 5.25 The sequence of the HALT performed on the modules for BeoSound 1 and
BeoSound 3000.
The actually recorded temperature and vibration log is shown in fig. 5.26. As it can be
seen the complete HALT lasted 3 days.
Low temperature characterisation
+10C and down in steps of 10C by approx. 2C/min.
High temperature characterisation
+40C and up in steps of 10C by approx. 5C/min.
Temperature cycling
-55C - +110C, 30 min. dwell, 10 cycles
Vibration characterisation
in steps of 5 grms
Combined temperature cycling and vibration
-55C - +110C/ 30, 40 50 grms, 1 cycle each vibration level
70
E501018 A Overall logcurve
-80
-60
-40
-20
0
20
40
60
80
100
120
14-apr 09:00 14-apr 15:00 14-apr 21:00 15-apr 03:00 15-apr 09:00 15-apr 15:00 15-apr 21:00 16-apr 03:00 16-apr 09:00
Date, time
T
e
m
p
e
r
a
t
u
r
e
[
C
]
0
10
20
30
40
50
60
70
80
90
100
V
i
b
r
a
t
i
o
n
l
e
v
e
l
[
G
r
m
s
]
Tair [C]
Tproduct [C]
Vibration [Grms]
FIG. 5.26 The recorded temperature and vibration log, day 1 to 3.
Bang & Olufsen A/S supplied 5 SMPS modules and 3 PCB 12 in order to have extra
samples for by-pass of failures and modification. Fig. 5.27 shows the modules when
mounted in the HALT chamber.
SMPS
PCB 12
FIG. 5.27 The SMPS module for BeoSound 1 and PCB 12 for BeoSound 3000
mounted in the HALT chamber.
71
The accelerometers and temperature sensors were placed as shown in fig. 5.28.
SMPS
Accelerometer at fixture
near SMPS, Z-axis
Product Temperature
Control sensor (PTC)
PCB 12
Accelerometer at fixture
near PCB 12, Z-axis
Accelerometer on PCB 12,
Z-axis
Temperature sensor - 3
FIG. 5.28 The location of accelerometers and temperature sensor.
The modules were monitored by means of a complete Bang & Olufsen A/S equipment.
The function test included power off and power on.
The complete test log can be found in annex 6.
72
5.4.4 Summary of HALT
Table 5.8 below summarises the HALT.
TABLE 5.8 Summary of HALT of SMPS module for BeoSound 1 and PCB 12 for
BeoSound 3000 performed for Bang & Olufsen A/S.
Exposure SMPS PCB 12 Remark
LOTL -55C -35C
Lower Operational
Temperature Limit
LDTL Not found Not found
Lower Destruct
Temperature Limit
Low temperature
Weakness
Noise during
change between
radio and CD
Radio "scratches"
UOTL Not found Not found
Upper Operational
Temperature Limit
UDTL Not found Not found
Upper Destruct
Temperature Limit
High temperature
Weakness
(Stopped at
+110C due to
test cables)
(Stopped at
+110C due to
test cables)
OVL
25 grms
(5 components)
30 grms by L7)
Not found
Operational
Vibration Level
VDL Approx. 35 grms Approx. 65 grms
Vibration Destruct
Level
Vibration
Weakness
Mounting of C1,
C21, C22, C54,
C55, RT1 and L7
Mounting of C97
and C107.
Mounting flange
on mains bar
Temperature cycling
(-55C/+110C,
30 min.dwell
10 cycles)
Weakness
Incipient stress
symptoms at
solderings of
heavy com-
ponents (not
critical yet)
Incipient stress
symptoms at
solderings of
heavy
components (not
critical yet)
Combined vibration
and temperature
cycling
10, 20, 30, 40 and
50 grms, -55C and
+110C
Weakness
Problems
regarding CD
playing at low
temperatures.
Mounting of C11
and U2
Mounting of C89.
Mounting flange
on mains bar.
Antenna
connector broken
in one side
73
The conclusion after a general visual inspection performed at DELTA was that the
weaknesses listed in table 5.9 were found. However, it was recommended that a
thorough visual inspection should be performed on all test specimens in order to uncover
other potential weaknesses.
TABLE 5.9 Weaknesses found by HALT.
SMPS for BeoSound 1 Relevance Possible cause Action Re-HALT
Weakness found Yes No (e.g. reference to failure
report, etc.)
Yes No
Noise during change of between
radio and CD X
No
RT1 fell off
X
Yes
C21, C22, C54 and C55 fell off
X
Bonded by adhesives in
portable equipment
L7 fell off
X
No
C11 fell of
X
No
U2 broke off
X
No
CD playing stopped at low
temperature/vibration X
No
PCB 12 for BeoSound 3000 Relevance Possible cause Action Re-HALT
Weakness found Yes No (e.g. reference to failure
report, etc.)
Yes No
Radio "scratches" at low
temperature X
C97 and C107 fell off
X
C89 broke off
2
X
Mounting flange of the mains bar
broke off
1
X
Antenna connector broke off
2
X
Note 1: The mains bar was used as part of the mounting of the PCB during the HALT
Note 2: Caused by the mains bar breaking off.
Bang & Olufsen A/S commented that even though the failures had been seen, it was very
rarely, due to the nature of the use pattern and thus not subject to corrective actions.
5.4.5 Comparison between ATST and HALT
In order to compare the ATST and the HALT extra HALT temperature cycling were
performed in addition to the previously described HALT.
74
The following tests were performed on the SMPS for BeoSound 1.
HALT temperature cycling: -55C/+110C, up to 30 cycles air to air. The solder
joints were evaluated by external visual inspection after 10, 20 and 30 cycles.
ATST temperature cycling: +5C/+80C, up to 1500 cycles, liquid to liquid. The
solder joints were evaluated by external visual inspection after each 300 cycles.
The Bang & Olufsen procedure for the ATST is as follows:
1) The PCB is cleaned, if necessary, before testing, so that faulty soldered
joints are easy to detect.
2) The PCB is cycled between hot and cold water baths at least 2100 times at
each bath in sequences of 300 cycles followed by inspection.
3) The PCB must be in each bath for at least 300 sec.
4) The temperature in the cold bath must be below +5C.
5) The temperature in the hot bath must be approx. +80C.
6) The test period is approx. 3-4 weeks.
The results of the tests can be found in table 5.10 below.
TABLE 5.10 Results of comparison between HALT and ATST.
HALT cycling ATST cycling
10 cycles 20 cycles 30 cycles 900 cycles 1200 cycles 1500 cycles
U6 + + U2 + +
R6 U2 - D1 L2
R58 L2 L7
L7 TB1 Q1
C31 RT1 T2
C21 C15
C22 J1/JST
C55 SMD resistor
75
Fig. 5.29 shows examples of solderings from Bang & Olufsen guideline for ATST with
the Bang & Olufsen A/S characterisation in white print on the photo.
76
77
FIG. 5.29 Examples of solderings from Bang & Olufsen's guideline for ATST.
78
Figs. 5.30 5.33 show photos of the failures found during HALT.
FIG. 5.30 C21.
FIG. 5.31 RT1.
79
FIG. 5.32 C22.
FIG. 5.33 U2.
80
Further, cross-sectioning of selected components from the HALT were made by Bang &
Olufsen A/S. For examples see figs. 5.34, 5.35 and 5.36.
FIG. 5.34 BeoSound 1 SMPS, component U2. The soldering is characterised by
degraded surface with a number of stress lines.
FIG. 5.35 BeoSound 1 SMPS, component U2. The photo was taken with fluorescence
filter. A crack is seen around the component lead.
81
FIG. 5.36 BeoSound 1 SMPS, component C21. Degradation of the surface with little
cracks is seen. A crack in the soldering near component lead has developed.
It can be seen that the cracks were caused by vibration rather than tempera-
ture cycling from the way the cracks run.
5.4.6 Evaluation of test and conclusion
Bang & Olufsen A/S concluded:
Bang & Olufsen A/S found HALT interesting. They believed that HALT could be
a useful supplement to extensive testing and analysis already done by Bang &
Olufsen A/S. It was found particularly interesting as a means of evaluating
subsuppliers.
Some of the results were comparable, however, in general the results obtained by
HALT cycling were not the same as the ones found by the ATST cycling.
Some of the weaknesses found during HALT occur at or near the component body
rather than in the soldering e.g. cracks in the housing or broken leads. However,
they still provided a good indication of weaknesses in the design.
Both ATST and HALT helped eliminating weaknesses of the design. However,
one of the tests alone would not find all weaknesses. HALT performed on a new
design would certainly give a lot of hints on weaknesses, as this investigation
showed good correlation between most of the weaknesses of the BeoSound 1
SMPS and field failures. However, ATST should not be omitted as a lot of the
early weaknesses of the SMPS had been found and corrected by this method.
The BeoSound 3000 PCB 12 was so robust that only very few weaknesses were
found. However, this is in good correlation with the fact that field failures did not
seem to occur at PCB level.
82
6. Survey of results
Specification limits HALT limits found Product Application
Low
temp.
High
temp.
Vibration LOL UOL VOL SOL
DC/DC
converter
Air fighter -40C +85C 12.6 grms -70C +125C 60 grms -
Hearing aid Human body -25C +55C - - - 7.5 grms 24 h@40C
Ultrasound
scanner
electronics
Clinic/lab -10C +40C 2 g -35C +59C 35 grms
Modules for
audio
equipment
Indoors living
room
+10C 40C 2 grms -55C/
-35C
Not
found
30 grms/
Not
found
-
83
7. Guidelines
The findings of this project resulted in the formulation of guidelines for introduction of
HALT & HASS, guidelines for selection of HALT exposures and guidelines for design
of HASS cycle. The guidelines are presented in this chapter.
7.1 Guideline for introduction of HALT & HASS
When introducing HALT into a company it was important to realise it was a completely
new philosophy and not just a new way to do what were already done. Otherwise the
results would be misinterpreted. Thus, some information as well as a lot of planning
were required. In order to prepare the companies participating in this project as well as
other companies performing their first HALT the checklist below was made by DELTA
and supplemented by the Bang & Olufsen participants in the HALT testing.
Purpose of the testing
All involved parties have to know of the philosophy of HALT & HASS prior to
the testing.
The purpose of the testing has to be decided e.g. investigation of a new product,
benchmarking of different versions of a new product, investigation of field
failures, benchmarking or check of subsuppliers.
Planning of the testing
Economical and human resources have to be earmarked.
The time frame has to be planned.
Considerations of the exposure of the test specimens
What are the test specimens?
Can more test specimens be tested at the same time in order to save cost?
Is it relevant to perform the testing on sub-modules due to weight, size, thermal
mass or complexity of the test specimen?
Is it relevant to introduce a reference specimen i.e. a specimen with a well known
field record, a competitive product etc. together with the actual test specimen in
order to evaluate the result of the testing or to give an absolute measure of the
result?
How is the test specimen used during normal life?
What are the specification limits?
84
What are the top-10 list of failure mechanisms of similar products?
What exposures are relevant?
How is the specimen to be fixed onto the HALT vibration table?
Who is responsible for the fixture?
Is it relevant to reduce the thermal time constant by removing or making holes in
cover plates?
Where to place temperature sensors and accelerometers; Are there points of
particular interest on the test specimen?
What to bring to the test facility
3-5 test specimens are desirable. However, cost and availability often have to be
considered.
Spare modules, parts and components.
Toolbox with components, fuses, adhesives (a hot-melt, which stays solid above
110C is useful e.g. RTV 133), straps etc.
Measuring equipment.
Extension and connecting cables to connect to the test specimen from the outside
of the HALT chamber. 2-3 m of cable are required in order to operate the
equipment under test without being in the way of the HALT operator. Be aware of
the temperature range of test wires. It is wise to use original connectors and solder
extensions on to them. Check all wires by microscope prior to the test. Different
colours of the wires are recommended a bundle and 16 connectors all with
black wires are difficult to distinguish.
Diagram and manuals.
Camera.
ESD and clear bags for broken bits.
A good microscope if relevant.
Protection box i.e. provision for decoupling mechanical impact and keeping
temperature within narrow limits e.g. for sensitive circuits which have to be inside
the HALT chamber.
85
Necessary manning of the test
Designers responsible for electronics, mechanical construction or other relevant
disciplines.
Observer responsible for reporting, registration of failures, etc.
Considerations regarding the monitoring of the function of the test specimen
Monitoring of as many functions as possible.
Continuous monitoring.
Remote operation of switches, etc.
Timing of manual operation of test specimen with respect to the HALT exposures.
The function test sequence has to be carried out within approx. 10 min.
Determination of malfunction criteria prior to the testing.
Check of function test sequence and set-up the company prior to testing at HALT
facility.
Evaluation of the result of the HALT
Is the result adequate? Fig. 7.1 shows a paradigm for summarising of results?
Is further failure analysis and root cause analysis required
Has the action list been filled in?
Is re-HALT required?
Is HASS required?
Is a HASS cycle required to be designed?
86
TABLE 7.1 Paradigm for summarising of results.
Weakness Relevance Possible cause Action Re-HALT
Yes No (e.g. reference to failure report, etc.
7.2 Guideline for selection of HALT exposures
The HALT exposures are selected from the list below in order to expose relevant failure
mechanisms. The selection is based on an evaluation of the design of the product, a
review of the top-10 list of field failures of similar products already in the field if
possible as well as in-house experience.
According to Hobbs (ref. [16] the exposures may be selected from this list:
High temperature in combination with powering and possibly reverse bias which
reveals diffusion processes in Silicon, oxidation of cracks and timing problems.
Clock variation which reveals timing problems.
Power cycling possibly in combination with temperature cycling and 6-axis
vibration which reveals thermo-mechanical weaknesses, design weaknesses and
accelerated electro migration.
Temperature cycling (particularly in combination with modulated excitation)
which reveals interconnection problems, poor solderings, bonding failures and
timing problems.
Power variations in combination with temperature which reveals marginal design.
Vibration which reveals mechanical design weaknesses e.g. large components not
supported sufficiently, weak cable locks and other problems related to cabling.
Vibration in combination with temperature cycling which reveals poor solderings.
Humidity which reveals corrosion problems.
87
Humidity in combination with high pressure which reveals poor grounding and
insulation problems.
ESD which reveals design robustness.
Electro Magnetic Interference which reveals design margin.
When relevant failure mechanisms have been thermo-mechanical in nature a classic
HALT sequence is suggested, see below:
1) High and low temperature characterisation in order to find operating and destruct
limit. Power ON/OFF.
2) Temperature cycling between the low and high operating limits.
3) Vibration characterisation; 6-axis vibration.
4) Combined temperature cycling and vibration exposure.
However, experience has shown that it can be very effective to replace 6-axis vibration
by bounce in case of small plastic products which are typically experiencing failures
related to mechanical impact from all possible angles. This also solves the problem that
this type of product is difficult to fixture securely to the HALT vibration table during
exposure to the very high vibration levels.
In other cases it has been successful to expose failures related to bonding weaknesses
and interconnection of sensor cables in small light plastic products by the following
sequence:
1) Temperature characterisation.
2) High temperature/humidity.
3) Low temperature.
4) Drop when product still at low temperature.
88
FIG. 7.2 Drop exposure performed on test specimen still at low temperature.
When it comes to corrosion related weakness the selection of the relevant corrosive
exposure has been based on a failure analysis of similar products in the market in
combination with evaluation of the materials forming the design.
7.3 Guideline for design of HASS cycle
HASS is a screening test aimed at finding failures originating from the production
process. The purpose of HASS is:
to expose the largest number of latent failures at the lowest possible cost in the
shortest possible time in order to reduce feedback delay.
to establish the basis of a program of failure analysis and corrective actions for all
failures found during screening.
to increase field reliability by reducing the total number of failures sent to the
market.
to reduce the total production, screening, maintenance and warranty cost.
89
to increase customer satisfaction and thus market share.
to increase profit due to increased volume.
All production samples are tested and shipped to customers afterwards. Thus, the
specimens are stressed well below the destruction limit. However, the duration of the
HASS also has to be very short in order not to increase production time significantly.
This is the trade off to be made when designing the HASS cycle. The procedure is as
follows:
1) The design of the HASS cycle is based on relevant failure mechanisms.
2) HALT is performed and design failures are eliminated.
3) The first suggestion based on the results of the HALT is made.
4) 3-5 HASS cycles are performed. Failures are recorded as a function of the cycle
number.
5) The HASS cycle is optimised based on Miners criterion in order to reduce the
number of cycles to 1.
6) The resulting HASS cycle is verified.
7) Safety of HASS is verified by performing 20-50 of the resulting HASS cycles on a
number of test specimens and afterwards performing a full qualification test on the
same test specimens in order to verify that sufficient life is remaining in the test
specimen.
90
8. Discussion and conclusion
The purpose of this project was to give Scandinavian companies who want to explore the
new exciting test philosophy of HALT &HASS an input to decision making on when and
how HALT & HASS is relevant to their product by answering the following questions:
How does HALT & HASS fit in with other test and analysis method?
What is there to gain from HALT & HASS?
How do HALT results compare to field failures?
How to get started?
Which HALT & HASS exposures are relevant?
How to come from HALT to HASS?
It should be noted that focus of the project was on classic HALT i.e. HALT with thermo-
mechanical exposures as it fitted best with the cases supplied by the various companies.
The first question has been answered by describing HALT & HASS and relating them to
other test strategies. Further, a description of failure analysis in relation to HALT is
given. Failure analysis form an important part of the HALT process. From this
description it can be concluded that HALT & HASS is a completely new philosophy and
not just a new way of doing what has already been done for a long time. In HALT focus
is on finding relevant failure mechanisms as fast and efficiently as possible rather than
simulation of real environmental conditions in a well-defined and reproducible manner.
It also has to be concluded that HALT & HASS is a valuable supplement to the
conventional tests rather than a replacement for these tests.
The main focus of the project was on the practical part demonstrating the application of
HALT on the following very different products:
DC for aircrafts from Terma A/S
Adapto BTE hearing aid from Oticon A/S
Electronics for ultrasound scanner from B-K Medical A/S
Parts for radios from Bang & Olufsen A/S
From the testing it could be concluded that there was a lot to be gained from HALT i.e.:
Large and well-know margins of strength compared to use conditions.
A lot of relevant failures, not found by other tests or analysis methods used by the
participating companies, were revealed.
HALT is a fast and efficient way of developing reliable products as opposed to
qualification tests which are aimed at verifying that minimum requirements are
91
fulfilled. Popularly, it can be said that HALT is based on the reliability
experienced by the user i.e. real life reliability.
There is generally good correlation between failures found during HALT and field
failures this is particularly the case of thermo-mechanical failures.
HALT is a very useful tool for fast evaluation of new processes, different variants
of the same product or benchmarking of sub-suppliers.
It is important to base the selection of HALT exposures on all relevant failure
mechanisms and thus also consider customised exposures i.e. bounce, humidity
and corrosion. However, due to the focus on HALT with thermo-mechanical
exposures in this project. These other exposures have to be investigated further.
It is difficult to accelerate failure mechanisms related to corrosion. It has to be
further investigated.
A new HALT project namely Generalisation of HALT focusing on HALT with
non thermo-mechanical exposures have already been planned.
Representatives from the different companies participated in the HALT with their own
product. Thus, they experienced on first hand how a HALT was prepared and performed.
They were present when the test specimens failed and evaluated the relevance of the
failure and took part in the repair/bypassing of the failure in order to proceed with the
test. The experiences and the comments of the companies are described in the report and
form the basis of the formulation of guidelines of chapter 7; guidelines for introduction
of HALT & HASS, guidelines for selection of HALT exposures and guidelines for
design of HASS cycle.
The guidelines for introduction of HALT & HASS were first formulated as a checklist
by DELTA in order to prepare the companies participating in this project as well as other
companies performing their first HALT. Later it was supplemented by the Bang &
Olufsen participants in the HALT testing.
The guidelines are intended to serve as a tool for present and future users of HALT.
92
Annex 1
Literature references
(2 pages)
93
Literature references
1) IEC 60068-1: Environmental testing General and guidance.
2) IEC 60068-2: Environmental testing Tests.
3) IEC 60721-1: Classification of environmental conditions Environmental
conditions and their severities.
4) IEC 60721-2: Classification of environmental conditions Environmental
conditions appearing in nature.
5) IEC 60721-3: Classification of environmental conditions Classification of groups
of environmental conditions and their severities.
6) IEC 60721-4: Classification of environmental conditions Guidance for the
correlation and transformation of the environmental classes of IEC 60721-3 and
the environmental tests of IEC 60068-2- Introduction. (104/143/CDV).
7) IEC 60605-1: Equipment reliability testing General requirements
8) IEC 60605-2: Equipment reliability testing Design of test cycles.
9) IEC 60605-3: Equipment reliability testing Preferred test conditions.
10) IEC 61014: Programmes for reliability growth
11) IEC61163-1: Reliability stress screening Repairable items manufactured in lots
12) MIL-STD-810F: Environmental engineering considerations and laboratory tests
13) MIL-STD-883E: Test method standard, microcircuits
14) NORMIC D6-3: Environmental classification of microsystems and introduction to
qualification testing. ELTA project no.: P1404-1 1999-09-22
15) JESD22 standard series from JEDEC. JEDEC Solid State Technology Association
is the semiconductor engineering standardisation body of the Electronic Industries
Alliance. The documents are currently published on www.jedec.org on the
internet.
16) Accelerated reliability engineering. HALT and HASS. Gregg K. Hobbs. Wiley &
Sons Ltd, 2000.
17) HALT, HASS & HASA Explained. Accelerated Reliability Techniques. Harry W.
McLean. American Society for Quality, 2000.
18) Failure and yield analysis handbook
D.L. Burgess and O.D. Trapp from Technology Associates
94
19) NORMIC D6-5: Guidelines for testing of microsystems
Jesper Bay, Povl K. Birch, Jens Branebjerg, Viggo Brndegaard Nielsen, Susanne
Otto, Bjarke Schnwandt, DELTA
95
Annex 2
DELTA HALT facilities
(2 pages)
T H E K N O W L E D G E C E N T R E
HALT and HASS
A vaccine against teething troubles in new products
P127 ver.010
Why HALT and HASS?
HALT (Highly Accelerated Life Testing)
and HASS (Highly Accelerated Stress
Screening) find and rectify weaknesses
in products. The result is more reli-
able products, more satisfied custom-
ers, reduced warranty service costs
and shorter time-to-market. Our first
HALT test run on a brand new type of
product was very positive. We found
failures that might well have resulted
in increased warranty service costs if
they hadnt been rectified, commented
Flemming Nielsen, Hardware Engineer
at B-K Medical A/S
What is HALT and HASS?
HALT identifies design weaknesses
whereas HASS identifies weaknesses
resulting from the manufacturing pro-
cess. Both tools are highly effective.
This capability is achieved by testing at
extreme levels, well beyond the specifi-
cations. In this way, failures are detec-
ted within a few hours instead of after
weeks of traditional testing or years on
the market.
The benefits of HALT and HASS
The advantages of HALT and HASS are:
Huge savings in warranty and servi-
cing costs
Shorter time-to-market
Confidence and insights when intro-
ducing new products
Large and known strength margins
to operational stress
Product is mature and free from
teething troubles when it goes into
production
Reduced rework in production
Failures practically never occur
when product in use
Possibility of investigating field
failures
Customer requirements satisfied.
T H E K N O W L E D G E C E N T R E
DELTA
.
Venlighedsvej 4
.
2970 Hrsholm
.
Denmark
Tel. +45 72 19 40 00
.
Fax +45 72 19 40 01
.
email: halt@delta.dk
Also see www.delta.dk/halt
How is HALT carried out?
Testing procedures are selected on the
basis of relevant failure mechanisms.
There is no standard procedure.
Testing might include:
1. Temperature characterisation; low
and high temperatures; functional
and destruction limits defined.
Power ON/OFF
2. Extremely rapid temperature cycling
between the limits identified
3. Vibration characterisation
4. Combined temperature cycling and
vibration stress testing
5. Where relevant, combined tempera-
ture and humidity stress-testing and
cold/drop stress tests.
How is HASS carried out?
HASS testing procedure is designed
on the basis of the limits identified by
HALT. A typical procedure consists of
rapidly induced temperature changes
combined with 6-axis vibration. Tests
are of short duration - ideally lasting
just a few minutes. It is critical to
ensure sufficient lifetime remaining
in the products after screening, and
that all induced failures are found.
Otherwise the customers will discover
them later!
It is the HALT and HASS fault analysis com-
bined with the improvement process that
results in enhanced products.
Failure analysis
Failure analysis is an important com-
ponent of HALT and HASS in determin-
ing if a given failure is relevant. An
appreciation of the mechanism behind
the failure increases the chances of
choosing the right solution. Failure
analysis can also reveal failures not
found by the functional screening pro-
cess. Analysis is performed using tools/
techniques such as:
External and internal visual inspec-
tions
X-ray inspection
Electrical metering
Mechanical and/or chemical sec-
tioning
Scanning Electron Microscope com-
bined with EDX analysis.
Equipment
DELTA has a dedicated HALT equipment
specially intended for temperature,
extreme rapid temperature change and
vibration stress-testing.
Dimensions:
1.06 m x 1.06 m x 1.01 m (W x D x H)
0.91 m x 0.91 m (table)
Temperature:
-100C - +200C, ca. 60C/min.
Vibration:
Up to 70 grms (2 - 10 kHz), 6-axis vibra-
tion.
DELTA also has testing equipment
for e.g. thermal shock in fluid baths,
bounce tests and immediate switching
between low temperature and high
temperature and high humidity.
DELTAs equipment for inducing rapid tempera-
ture changes and 6-axis vibration.
Who stands to benefit from HALT
and HASS?
Generally speaking, HALT and HASS
are ideal for high volume and low value
products or small volume and high
value products. A number of technolo-
gies and industries are already employ-
ing HALT and HASS. These include
space technology, the military, avia-
tion, telecommunication, Information
Technology, medico, automotive, sensor
devices, metering and electronic control
devices
For further information
Contact
halt@delta.dk
Susanne Otto B.Sc.E.E., B Com(Org.),
Consultant
tel. (+45) 65 41 31 52
mobile (+45) 24 23 36 60
suo@delta.dk
or
Kim A. Schmidt, B.Sc.M.E.,
Project Manager
tel. (+45) 72 19 4271
kas@delta.dk
98
Annex 3
Case study - DC/DC converter for use in jet fighters
supplied by Terma A/S - detailed test log,
Cooling of power module, vibrations tests
performed according to MIL-STD-810F
(7 pages)
99
100
101
DELTA/KAS Oversigt over testemner
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Eksponering Dato "A" (ser. No. 3006) "B" (ser. No. 3004) "C" (ser. No. 3007)
Kulde 12-maj x
Varme 12-maj x
Temperaturcycling ( 1cycle) 12-maj x
Vibration 12-maj x
Temperaturcycling ( 20 + 2 cycles) 12 - 13 may x
Kombineret vibration og temperatur 14-maj x
Termovision 14-maj x x
Temperaturcycling ( 5 cycles) 14-maj
x, repareret og
stttelimet
Kombineret vibration og temperatur 14-maj x
Kombineret vibration og temperatur 14-maj x
Bemrkninger:
Denne test blev overvret af: Jrn Gaardsvig Nielsen
Henrik Ibsen
Preben Simonsen
Funktionstest bestod af: Belastning p de 4 spndingsudgange
Overvgning af 4 spndingsudgange vha. multimetre
Overvgning af 2 spndingudgange vha. oscilloskop
Denne HALT test blev udfrt vha. flgende udstyr: Thermotron AST-35 HALT test system
Unit ID
CCA, Power supply
102
DELTA/KAS Kuldeeksponering
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Resultat
Aktivitet Dato Tid Init. Bemrkning
Initial F-test 12-maj 10:00 Ter OK
Ned til -40C 12-maj 10:01 KAS
F-test ved -40C 12-maj 10:12 Ter OK
Ned til -50C 12-maj 10:16 KAS
F-test ved -50C 12-maj 10:27 Ter OK
Ned til -60C 12-maj 10:31 KAS
F-test ved -60C 12-maj 10:43 Ter OK En enkelt trigning p skop (evt. stjpuls)
Ned til -70C 12-maj 10:46 KAS
F-test ved -70C 12-maj 10:56 Ter
Problemer med opstart p 5 V og 3,3 V,
OK efter et par sekunder
Ned til -80C 12-maj 11:01 KAS Input strm svinger noget
F-test ved -80C 12-maj 11:06 Ter Alle udgangsspndinger falder noget Forsgt med 31 V input
Lidt ekstra forsg 12-maj 11:33 Ter Fejler ved -76C
Tilabge til ambient 12-maj 11:37 KAS
Lower Operational Temperature Limit LOTL -70C (opstart), -76C (drift)
Lower Destruct Temperature Limit LDTL Ikke fundet
DELTA/KAS Varmeeksponering
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Resultat
Aktivitet Dato Tid Init. Bemrkning
Initial F-test 12-maj 11:52 Ter OK 2 ekstra temp. Flere, T2 p kasse og T3 p print
Optil +70C 12-maj 11:58 KAS
F-test ved +70C 12-maj 12:35 Ter OK
Optil +85C 12-maj 12:35 KAS
F-test ved +85C 12-maj 12:39 Ter OK
Optil +95C 12-maj 12:45 KAS
F-test ved +95C 12-maj 12:50 Ter OK
Optil +100C 12-maj 12:52 KAS
F-test ved +100C 12-maj 12:57 Ter OK
Optil +105C 12-maj 12:57 KAS
F-test ved +105C 12-maj 13:03 Ter OK
Optil +110C 12-maj 13:03 KAS
F-test ved +110C 12-maj 13:09 Ter OK
Optil +115C 12-maj 13:10 KAS
F-test ved +115C 12-maj 13:13 Ter OK
Optil +120C 12-maj 13:14 KAS
F-test ved +120C 12-maj 13:20 Ter OK
Optil +125C 12-maj 13:21 KAS
F-test ved +125C 12-maj 13:23 Ter OK
Optil +130C 12-maj 13:24 KAS
F-test ved +130C 12-maj 13:28 Ter +12 V vk ellers OK OK et kort jeblik ved power off/on
Ned til +125C 12-maj 13:30 KAS
F-test ved +125C 12-maj 13:32 Ter OK efter power off/on
Upper Operational Temperature Limit UOTL +130C
Upper Destruct Temperature Limit UDTL Ikke fundet
103
DELTA/KAS Temperaturcycling
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Resultat
Aktivitet Dato Tid Init. Bemrkning
Start cycling 12-maj 13:45 KAS OK
Temperaturcycling 12-maj KAS OK
1 cykle med 15 min dwell time. Tlow = -70C, Thigh =
+125C.
F-test ved ambient 12-maj 16:21 Ter OK Ny power supply ("B") monteret
Temperaturcycling 12-maj 16:25 KAS Et enkelt trig p skop
20 cykles med 10 min dwell time. Tlow = -70C, Thigh =
+125C.
F-test ved ambient 13-maj 08:05 Ter OK
Temperaturcycling 13-maj 08:10 KAS OK
2 cykles med 10 min dwell time. Tlow = -70C, Thigh =
+125C.
Ny power supply ("A") monteret
Temperaturcycling 14-maj 10:51 KAS OK
1,5 cykles med 4 min dwell time. Tlow = -70C, Thigh =
+125C. Emne A
ndring i program
Temperaturcycling 14-maj 11:17 KAS OK
4 cykles med 4 min dwell time. Tlow = -70C, Thigh =
+125C. Emne A
DELTA/KAS Vibrationseksponering
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Aktivitet Dato Tid Init. Funktion Bemrkning
Initial F-test
Random 10 grms 12-maj 14:49 KAS OK Ca. 10 minutter
Random 20 grms 12-maj 14:59 KAS OK Ca. 10 minutter
Random 30 grms 12-maj 15:10 KAS Ls PCB skrue efter ca. 4 minutter Ca. 4 minutter
Fejlretning 12-maj 15:18 KAS
Skrue genmonteret og alle 5 skruer
spndt med 0,4 Nm
Ingen locktite p skruerne
Random 30 grms 12-maj 15:26 KAS OK Mleaccelerometre falder af. Ca. 10 minutter
Random 40 grms 12-maj 15:37 KAS OK Kort pause efter ca. 1 minut
Random 50 grms 12-maj 15:51 KAS Ca. 10 minutter
Random 60 grms 12-maj 16:03 KAS Spndinger frst urolige, derefter faldende Stoppet efter ca. 4 minutter
Fejlsgning 12-maj 16:20 Ter Power supply skiftet
Herefter temperaturcykling
Operational Vibration Level KAS ca. 60 grms
Vibration Destruct Level KAS ca. 60 grms
Eksponering udfrt med random vibration i 6 akser. Minimum 10
minutter ved hvert niveau. 10 grms step
104
DELTA/KAS Kombineret vibrations- og temperatureksponering
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Aktivitet Dato Tid Init. Resultat Bemrkning
Initial F-test 14-maj 08:25 Ter OK
Kombineret vibration
og temperatur
cycling
14-maj 08:30 KAS
Lidt ustabilitet ved den sidste del af lav
temp delen. Begynder at svigte efter ca.
5 minutter ved den hje temp
1 cykle med 15 min dwell time. Tlow = -70C, Thigh = +125C.
Vibrationsniveau 40 grms.
Funktionstest 14-maj 09:08 Ter Virker ikke, heller ikke efter power off/on
Fejlsgning 14-maj 09:44 Ter
2 stk. komponenter (V59 og V63) faldet
af.
Forstrkning af "A" 14-maj 09:59 Ter
V59 og V63 stttelimet med "Super
Epoxy"
Hrdet 15 minutter ved 125C
Kombineret vibration
og temperatur
cycling
14-maj 12:37 KAS Problemer efter f minutter ved hj temp
1 cykle med 15 min dwell time. Tlow = -70C, Thigh = +125C.
Vibrationsniveau 40 grms.
Skiftet til anden
fixtur
Kombineret vibration
og temperatur
cycling
14-maj 13:50 KAS
1 cykle med ca. 15 min dwell time. Tlow = -70C, Thigh = +125C.
Vibrationsniveau 40 grms. Krt manuelt
Kombineret vibration
og temperatur
cycling
14-maj 14:22 KAS Begyndende problemer med 5 V
1 cykle med ca. 15 min dwell time. Tlow = -70C, Thigh = +125C.
Vibrationsniveau 50 grms. Krt manuelt
Kombineret vibration
og temperatur
cycling
14-maj 14:47 KAS
Permanente problemer efter f minutter
ved hj temp
Ca. 3 minutter ved Thigh = +125C. Vibrationsniveau 60 grms. Krt
manuelt
Fejlsgning Fejl kan ikke umiddelbart lokaliseres (modstand R104 faldet af)
Nyt emne "C"
Kombineret vibration
og temperatur
cycling
14-maj 15:54 KAS
1 cykle med ca. 10 min dwell time. Tlow = -70C, Thigh = +125C.
Vibrationsniveau 60 grms. Krt manuelt
105
DELTA/KAS Resume
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Bemrkning
LOTL
-70C (opstart)
-76C (drift)
Lower Operational Temperature Limit.
LDTL Ikke fundet Lower Destruct Temperature Limit
Svaghed Opstart usikker
UOTL +125C Upper Operational Temperature Limit.
UDTL Ikke fundet Upper Destruct Temperature Limit
Svaghed 12 V forsvinder
OVL
ca. 30 grms (ls skrue),
60 grms (ustabile spndinger)
Operational Vibration Level
VDL ca. 60 grms Vibration Destruct Level
Svaghed ? Skal undersges nrmere
Temperatur cycling
(-70C/+125C, 4 - 10 min.dwell
> 20 cycles)
Svaghed Ikke fundet
Kombineret vibration og
temperatur
40, 50 og 60 grms, -70C og
+125C
Svaghed
V59, V53, R104 falder af.
Problemer med 5 VDC
Bemrkning: Der br udfres en detaljeret visuel inspektion af alle emner for at afdkke eventuelle andre svagheder
Eksponering
Kulde
Varme
Vibration
DELTA/KAS Konklusioner efter overordnet visuel inspektion udfrt p DELTA
HALT test af DC/DC converter udfrt for TERMA A/S
DELTA sag nr. E501018 C
Forml At finde de svage punkter for CCA, Power Supply
Her er der plads til Terma's
kommentarer
Mulig rsag Aktion
Fundne svagheder Ja Nej (evt. henvisning til fejlrapport etc.) Ja Nej
Opstart af 5 V og 3.3 V (lave temperaturer)
12 V forsinder (hje temperaturer)
Ls PCB skrue (ved vibration)
Spndinger falder (ved hje vibrationsniveauer)
V59 og V63 falder af
R104 falder af
Fejl ved kombineret temp. cykling og vibration
Relevant RE-HALT
106
Annex 4
Case study CQ-6263 Adapto BTE hearing aid supplied by Oticon A/S -
detailed test log
(8 pages)
107
CQ-6263 Adapto HALT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 26-30 31-37
Reference x
Vibrationskarakterisering - bounce x x x
Svedtest, 40C, prkond. med bounce x x x
Cyklus: Varme/fugt, kulde, bounce x x x
Svedtest, 24h@50C, prkond. med bounce x x x
Svedtest, 24h@60C, prkond. med bounce x x x
Svedtest, 24h@70C, prkond. med bounce x x x
Svedtest, 24h@80C, prkond. med bounce x x
Svedtest, 96h@40C, prkond. med bounce x x x
Svedtest II, prcond. med 10.000 P1/P2 skift x x
Fejl / testemne
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Stag i montageskal knkket
- x x x x x - x x x x x x x x x x x - x x
VC hjul falder ind i apparat
og kan ikke dreje
- x x x - - - - - - - - - - - - - - - - -
Trde til telespole knkker
- x x x - - - x x x x x - x x x x x - - -
Lederbaner knkker i
flexzone
- x x x - - - - x - - - - - - - - - - x -
Litzetrd til mikrofon
knkker
- - x x - - - - - - - - - - - - - - - - -
Kompensationssljfe p
telespole lsner
- - x - x - - - - - - - - - - x - - - - -
MT0-omskifter
svigter/fejlfunktion
- - - - - - - - - - - - - - - - x x - - -
Batteriskuffe bner sig og
batteri evt. falder ud
- x x x - - - x x x x x x x x x x - - - -
Mikrofon fejler
- - - - - - - - - x - - - - - - - - - - -
1
Vibrationskarakterisering - bounce
Initial Programering A0 ok 10-07-2003 pha
Acoustical measurements 000-000-01 10-07-2003 hlc
Current consumption mA@1,3V
El./mech. test w/OtiTest ok 10-07-2003 pha
Listen w/press & twist ok 10-07-2003 pha
Visual check ok 10-07-2003 pha
108
2 3 4
Vibrationskarakterisering - bounce
Initial Programmering A0 ok ok ok 10-07-2003 pha
Acoustical measurements 000-000-02 000-000-03 000-000-04 10-07-2003 hlc
Current consumption mA@1,3V 1,4 1,3 1,4 10-07-2003 pha
El./mech. test w/OtiTest ok ok ok 10-07-2003 pha
Listen w/press & twist ok ok ok 10-07-2003 pha
Visual check ok ok ok 10-07-2003 pha
Exposure: Bounce Test udfrt med batteri i skuffe,
tndt i M mode.
Testes med lytteslange
monteret, "danser" ikke
s tilfldigt som vrige.
Prop p hook Prop p hook
Sinus, 2,5g, 12Hz Exposure 15 min ok ok ok 11-07-2003 KAS
Listen w/press & twist ok ok ok 11-07-2003 KAS/pha
Current consumption 1,4 1,3 1,4 11-07-2003 KAS
El./mech. test w/OtiTest ok ok ok 11-07-2003 pha
Visual check ok ok ok 11-07-2003 KAS
Sinus, 5g, 13Hz Exposure 15 min ok ok ok 11-07-2003 KAS
Listen w/press & twist ok ok ok 11-07-2003 KAS/pha
Current consumption 1,4 1,3 1,4 11-07-2003 KAS
El./mech. test w/OtiTest ok ok ok 11-07-2003 pha
Visual check ok ok ok 11-07-2003 KAS/pha
Sinus, 7,5g, 16Hz Exposure 15 min ok ok ok 11-07-2003 KAS
Listen w/press & twist ok ok Intet/meget svagt output
i T mode
11-07-2003 KAS/pha
Current consumption 1,4 1,3 1,4 11-07-2003 KAS
El./mech. test w/OtiTest ok ok ok 11-07-2003 pha
Visual check ok Tydeligt slid p kant af
batteriskuffe.
Tydeligt slid p kant af
batteriskuffe.
11-07-2003 KAS/pha
Sinus, 10g , 16Hz Exposure 15 min Apparat reset'er af og til
under testen
ok ok 11-07-2003 KAS
Listen w/press & twist ok Intet/meget svagt output
i T mode
Intet/meget svagt output
i T mode
11-07-2003 pha
Current consumption 1,4 1,3 1,4 11-07-2003 KAS
El./mech. test w/OtiTest ok ok ok 11-07-2003 pha
Visual check ok + slidmrker i
batteri/skuffe
+ slidmrker i
batteri/skuffe
11-07-2003 pha
Sinus, 12,5g, 19Hz Exposure 15 min Batteriskuffe bner sig -
lukket igen under test
Batteriskuffe bner sig -
lukket igen under test
Batteri falder ud af
apparat - sat tilbage
igen under test
11-07-2003 KAS/pha
Listen w/press & twist Fejlfunktion i T mode,
stj og kratten.
Intet output Intet output 11-07-2003 pha
Current consumption 1,4 0,17 0,44 11-07-2003 KAS/pha
El./mech. test w/OtiTest VC test fail no connection no connection 11-07-2003 pha
Visual check VC trykket ind i
apparatet. Skaller har
bnet sig, VC klemmer.
VC trykket skv og ind
i apparatet.
VC trykket skv og ind
i apparatet.
11-07-2003 pha
Final inspection,
Oticon
Visual inspection Se ovenfor Se ovenfor Se ovenfor 28-10-2003 pha
Acoustical measurements Ingen mling, HA adskilt Ingen mling, HA adskilt Ingen mling, HA adskilt 28-10-2003 pha
Internal visual inspection 2 stag knkket af p
montageskal. Rd trd
til telespole knkket
ved lodning p PCB.
Ledebane knkket i
flexzone.
3 stag fra montageskal
knkket af.
Grn trd til telespole
knkket ved spole.
Rd trd til telespole
knkket ved PCB.
Mik.+ litze knkket af
p PCB ved lodning.
Mulig kortslutning af
mik. bl litze (signal) til
telespole grn PCB
lodning.
Telespole komp.
2 stag fra montageskal
knkket af.
Grn trd til telespole
knkket ved spole.
Rd trd til telespole
knkket ved PCB.
Mik.+ litze knkket af
p PCB ved lodning.
Isolering i flexzone
knkket, lederbaner
afbrudt.
28-10-2003 pha
109
5 6 7
Svedtest, prkond. med bounce
Initial Acoustical measurements - - -
Current consumption 1,3 1,4 1,2 11-07-2003 KAS
El./mech. test w/OtiTest + A0 ok ok ok 11-07-2003 pha
Listen w/press & twist ok ok ok 11-07-2003 pha
Visual check ok ok ok 11-07-2003 pha
Prconditionering med bounce Med batteri i skuffe, men slukket apparat
Sinus, 7,5g, 16Hz Exposure 15 min ok ok ok 11-07-2003 KAS
Listen w/press & twist ok ok ok 11-07-2003 pha
Current consumption 1,3 1,4 1,2 11-07-2003 KAS
El./mech. test w/OtiTest ok ok ok 11-07-2003 pha
Visual check slidmrker ved
batteriskuffe
slidmrker ved
batteriskuffe
slidmrker ved
batteriskuffe
11-07-2003 KAS/pha
Svedtest 40C 24 timer Uden batteri i skuffe
Listen w/press & twist ok ok ok 11-08-2003 OT
Current consumption 1,22 1,31 1,14 11-08-2003 OT
El./mech. test w/OtiTest ok ok ok 11-08-2003 OT
Visual check ? ? ? 11-08-2003 OT
Final inspection,
Oticon
Visual inspection Returneret til Oticon
adskilt. MTO switch
klippet af og adskilt.
Returneret til Oticon
adskilt.
ok 28-10-2003 pha
Acoustical measurements Ingen mling, HA adskilt ok ok 28-10-2003
29-10-2003
pha
hlc
Internal visual inspection Stag knkket.
Kompensationssljfe
ls.
Probemrker p
lodninger omkring MTO-
switch. Bat. plus-fjeder
bukket. Stag knkket.
ok 28-10-2003 pha
8 9 10
Cyklus: Bounce -> varme/fugt -> kulde
Initial Acoustical measurements - - -
Current consumption 1,3 1,2 1,4 11-07-2003 KAS
El./mech. test w/OtiTest + A0 ok ok ok 11-07-2003 pha
Listen w/press & twist ok ok ok 11-07-2003 pha
Visual check ok ok ok 11-07-2003 pha
Prconditionering med bounce Med batteri i skuffe, men slukket apparat
Sinus, 7,5g, 16Hz Exposure 15 min ok ok Batteri faldet ud 11-07-2003 KAS
Listen w/press & twist Intet output i T mode ok ok 11-07-2003 pha
Current consumption 1,3 1,2 1,3 11-07-2003 KAS
El./mech. test w/OtiTest ok VC test fail ok 11-07-2003 pha
Visual check slidmrker ved
batteriskuffe
VC trykket, kan ikke
roteres. slidmrker ved
batteriskuffe
slidmrker ved
batteriskuffe
11-07-2003 pha
Listen w/press & twist Intet output i T mode ok ok 07-07-2003 pha/kp/ot
Current consumption 1,2 1,15 1,22 07-07-2003 pha/kp/ot
El./mech. test w/OtiTest ok 07-07-2003 pha/kp/ot
Visual check slidmrker ved
batteriskuffe
07-07-2003 pha/kp/ot
11-08-2003 OT
Listen w/press & twist Intet output i T mode ok ok 11-08-2003 OT
Current consumption 1,18 1,16 1,24 11-08-2003 OT
El./mech. test w/OtiTest ok ok ok 11-08-2003 OT
Visual check
Vame/fugt, kulde ? ? ?
110
11 12 13
Svedtest, prkond. med bounce dato init
Initial Acoustical measurements - - -
Current consumption 1,20 1,17 1,25 08-08-2003 KP
El./mech. test w/OtiTest + A0 ok ok ok 07-08-2003 KP/OT
Listen w/press & twist ok ok ok 07-08-2003 KP/OT
Visual check ok ok ok 07-08-2003 KP/OT
Prconditionering med bounce Med batteri i skuffe, men slukket apparat
Sinus, 7,5g, 16Hz Exposure 15 min ok ok ok 08-08-2003 KP
Listen w/press & twist
Current consumption
El./mech. test w/OtiTest
Visual check Batteri faldet ud,
switche pos. M1,
slidmrker ved
batteriskuffe
Batteri faldet ud,
switche pos. M1,
slidmrker ved
batteriskuffe
Batteriskuffe ben,
switch pos. M1,
slidmrker ved
batteriskuffe
08-08-2003 KP
After bounce Listen w/press & twist ok - ok 11-08-2003 OT
Current consumption 1,20 0,00 1,25 11-08-2003 OT
El./mech. test w/OtiTest ok - teleslynge virker ikke
mere 11-08-2003
OT
Visual check ok ok ok 11-08-2003 OT
Svedtest, 50C Exposure 24 timer
After sved 50 Listen w/press & twist ok Helt dd ok Teleslynge defekt 12-08-2003 OT
Current consumption 1,12 0,08 1,28 13-08-2003 OT
El./mech. test w/OtiTest ok Teleslynge defekt :: ok Teleslynge defekt 12-08-2003 OT
Visual check ok ok ok 12-08-2003 OT
Final inspection,
Oticon
Visual inspection Returneret til Oticon
adskilt.
Returneret til Oticon
adskilt.
Returneret til Oticon
adskilt.
28-10-2003 pha
Acoustical measurements ok Ingen mling, HA adskilt Samlet for akustisk
mling. Fejler lyttetest.
Meget svagt
mikrofonsignal (kontrol
med FB measure).
28-10-2003
29-10-2003
pha
hlc
Internal visual inspection se Delta noter Trd(e) til telespole
knkket. PCB
lederbanet knkket i
bukkezone - set som
markfejl (service).
Se ogs Delta noter
Trde(e) til telespole
knkket. Coating af
PCB revnet i
bukkezone. Stag p
montageskal knkket
af.
28-10-2003 pha
111
14 15 16
Svedtest, prkond. med bounce dato init
Initial Acoustical measurements - - -
Current consumption 1,21 1,22 1,34 08-08-2003 KP
El./mech. test w/OtiTest + A0 ok ok ok 08-08-2003 KP
Listen w/press & twist ok ok ok 08-08-2003 KP
Visual check ok ok ok 08-08-2003 KP
Prconditionering med bounce Med batteri i skuffe, men slukket apparat
Sinus, 7,5g, 16Hz Exposure 15 min ok ok ok 08-08-2003 KP
Listen w/press & twist
Current consumption
El./mech. test w/OtiTest
Visual check Batteriskuffe ben,
switch pos. M1,
slidmrker ved
batteriskuffe
Batteriskuffe ben,
switch pos. M2,
slidmrker ved
batteriskuffe
Batteri faldet ud, swith
pos. M1, slidmrker
ved batteriskuffe
08-08-2003 KP
After Bounce Listen w/press & twist ok ok ok 11-08-2003 OT
Current consumption 1,22 1,23 1,29 11-08-2003 OT
El./mech. test w/OtiTest Tele slynge defekt Tele slynge defekt ok 11-08-2003 OT
Visual check
Svedtest, 60C Exposure 24 timer ok ok ok 14-08-2003 PT OT
After SVED 60 Listen w/press & twist ok ok ok 14-08-2003 OT
Current consumption 1,09 1,14 1,18 14-08-2003 OT
El./mech. test w/OtiTest ok Teleslynge Defekt ok Teleslynge Defekt ok 14-08-2003 OT
Visual check ok ok ok 14-08-2003 OT
Final inspection,
Oticon
Visual inspection ok Returneret til Oticon
adskilt.
Returneret til Oticon
adskilt.
28-10-2003 pha
Acoustical measurements ok ok ok 29-10-2003 hlc
Internal visual inspection Stag p montageskal
ved VC knkket af.
Rd trd til telespole
knkket ved PCB.
se Delta noter. Coat
revnet i flexzone
ok 28-10-2003 pha
17 18 19
Svedtest, prkond. med bounce dato init
Initial Acoustical measurements - - -
Current consumption 1,24 1,20 1,14 08-08-2003 KP
El./mech. test w/OtiTest + A0 ok ok ok 08-08-2003 KP
Listen w/press & twist ok ok ok 08-08-2003 KP
Visual check ok ok ok 08-08-2003 KP
Prconditionering med bounce Med batteri i skuffe, men slukket apparat
Sinus, 7,5g, 16Hz Exposure 15 min ok ok ok 08-08-2003 KP
Listen w/press & twist ok ok ok 11-08-2003 OT
Current consumption 1,24 1,20 1,27 11-08-2003 OT
El./mech. test w/OtiTest teleslynge defekt teleslynge defekt teleslynge defekt 11-08-2003 OT
Visual check Batteriskuffe lidt ben,
switch pos. M2,
akustisk tilbagekobling,
slidmrker ved
batteriskuffe
Batteriskuffe ben,
switch pos. M1,
slidmrker ved
batteriskuffe
Batteriskuffe ben,
switch pos. M2,
slidmrker ved
batteriskuffe
08-08-2003 KP
Svedtest, 70C Exposure 24 timer ok ok ok 14-08-2003 PT
After sved 70
Listen w/press & twist ok ok ok 15-08-2003 OT
Current consumption 1,13 1,15 1,11 15-08-2003 OT
El./mech. test w/OtiTest teleslynge defekt teleslynge defekt teleslynge defekt 15-08-2003 OT
Visual check ok ok ok 15-08-2003 OT
Final inspection,
Oticon
Visual inspection Returneret til Oticon
adskilt.
ok Returneret til Oticon
adskilt.
28-10-2003 pha
Acoustical measurements ok ok ok 29-10-2003 hlc
Internal visual inspection Stag p montageskal
knkket. Se ogs
Delta noter.
Stag p montageskal
knkket. Flex-flap med
komp.sljfe get fra i
limen p telespolen.
Stag p montageskal
knkket. Flex-flap med
komp.sljfe get fra i
limen p telespolen. Se
ogs Delta noter.
28-10-2003 pha
112
20 21
Svedtest, prkond. med bounce dato init
Initial Acoustical measurements - - -
Current consumption 1,23 1,26 08-08-2003 KP
El./mech. test w/OtiTest + A0 ok ok 08-08-2003 KP
Listen w/press & twist ok ok 08-08-2003 KP
Visual check ok ok 08-08-2003 KP
Prconditionering med bounce Med batteri i skuffe, men slukket apparat
Sinus, 7,5g, 16Hz Exposure 15 min ok ok 08-08-2003 KP
Listen w/press & twist ok ok 11-08-2003 OT
Current consumption 1,03 0,00 11-08-2003 OT
El./mech. test w/OtiTest Er syg Teleslynge
defekt
Eprom test fejler -
Teleslynge defekt
11-08-2003 OT
Visual check Batteriskuffe ben,
switch pos. M1,
slidmrker ved
batteriskuffe
Switch pos. M2,
akustisk tilbakobling,
slidmrker ved
batteriskuffe
08-08-2003 KP
Svedtest, 80C Exposure 24 timer ok ok 15-08-2003 PT
After sved 80 Listen w/press & twist Meget svag Opstn
unknown Var ikke sat
up OT har reloaded
A0Full gain
Meget svag Opstn
unknown Var ikke sat
up OT har reloaded
A0Full gain 15-08-2003
OT
Current consumption 1,15 1,29 Muligt periodisk fejl
?
El./mech. test w/OtiTest Switch Test Failed Programswitch failed 18-08-2003 ot
Visual check ok ok 18-08-2003 ot
Final inspection,
Oticon
Visual inspection Returneret til Oticon
adskilt.
Returneret til Oticon
adskilt.
28-10-2003 pha
Acoustical measurements MTO fejl. M og T pos.
byttet om!?
MTO fejl. M og T pos.
byttet om!?
28-10-2003
29-10-2003
pha
hlc
Internal visual inspection Se Delta noter. Stag knkket ved VC. 28-10-2003 pha
113
22 23 24
Vibrationskarakterisering - bounce
Initial 10 sept 03 Programering A0 FULL Gain ok ok ok 10-09-2003 OT
Acoustical measurements ok ok ok
Current consumption mA@1,3V 1,05 1,07 1,05 10-09-2003 OT
El./mech. test w/OtiTest ok ok ok
Listen w/press & twist ok ok ok
Visual check ok ok ok
Sinus, 7,5g, 16Hz 15
min
Efter danse test Programering A0 FULL Gain ok Virker ikke mere ok 10-09-2003 OT
Acoustical measurements ok ok
Current consumption mA@1,3V 1,30 0,00 1,38
El./mech. test w/OtiTest ok ok
Listen w/press & twist ok ok
Visual check ok ok
40 grader 4 dages sved
16-09-2003 Programering A0 FULL Gain ok Virker stadig ikke mereok 16-09-2003 OT
Acoustical measurements ok ok
Current consumption mA@1,3V 1,16 0,00 1,63
El./mech. test w/OtiTest ok Switch test fail
Teleslynge virker ikke
Listen w/press & twist ok ok
Visual check ok ok
Final inspection,
Oticon
Visual inspection ok ok Returneret til Oticon
adskilt. MTO omskifter
klippet af.
28-10-2003 pha
Acoustical measurements ok Ingen mling, HA adskilt Ingen mling, HA adskilt 28-10-2003
29-10-2003
pha
hlc
Internal visual inspection ok Stag ved VC knkket.
Lederbaner knkket i
bukkezone.
Se Delta noter. 28-10-2003 pha
114
Results of visual inspection of samples from artificial sweat testing
Exposure
temperature
Evaluated samples Results
40C S/N 5, 6 One sample shows cracks in the plastic cover.
No corrosion / migration are observed. Salt residues are
present inside the samples.
50C S/N 11, 12, 13 One or both telecoil connections are broken at the coil
interface. No corrosion of the wires are observed.
In one sample (S/N 12) also the flex PCB is cracked in a
bend area.
No corrosion / migration are observed. Salt residues are
present inside the samples.
60C S/N 15, 16 One telecoil connection is broken at the coil interface in
S/N 15. No corrosion of the wire is observed.
In one sample (S/N 15) also the flex PCB is cracked in a
bend area but conductor elements are still intact.
No corrosion / migration are observed. Salt residues are
present inside the samples.
70C S/N 17, 19 One or both telecoil connections are broken at the coil
interface in both samples. No corrosion of the wire is
observed.
Indications of condensation residues on the gold contact
pins are observed.
No corrosion / migration are observed. Salt residues are
present inside the samples.
80C S/N 20, 21 One or both telecoil connections are broken at the coil
interface in both samples. In one sample one wire is
broken at the PCB. No corrosion of the wire is observed.
Indications of condensation residues on the gold contact
pins are observed.
In one sample (S/N 21) the isolation of one wire is
damaged in a bend area.
No corrosion / migration are observed. Salt residues are
present inside the samples.
115
Annex 5
Case study
Ultrasound scanner 2120 EXL supplied by B-K Medical A/S
detailed test log
(31 pages)
116
A5.1 Result of cold step stress test
Cassette was initially tested at 20C with Ok result.
Test condition: 0C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,1
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 65%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
Test condition: -10C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,2
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,1
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 66%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
Noise on video out
(Composite) VGA picture
ok
117
Test condition: -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,2
-5V analogue +/- 5% (-4.75 -5.25V) -5,1
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Fail
Doppler on phantom Ok
Doppler noise (gain) 66%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok. (not 3D)
Off/on at 264 VAC, Scanning with 8660 on phantom Ok. (not 3D)
VGA picture unstable (Line
sync? Tear out). Video out
noisy. 3D no picture (Mouse
arrow can be moved, but
picture partly missing).
Unable to go to 3D after
switching off and on again.
It was decided to continue
without the 3D system
Test condition: -30C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,84
3.3V Digital +/- 5% (3.14 - 3.47V) 3,32
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -5
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok, but
picture
unstable
MFI 5.5, 7 and 8 MHz Ok
Capture scan Fail
Doppler on phantom Ok
Doppler noise (gain) 67%
1 element sweep on 8660 0k
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok. (not 3D)
Off/on at 264 VAC, Scanning with 8660 on phantom Ok. (not 3D)
VGA picture very unstable
(Line sync? Tear out and
picture sync. unstable).
Video out noisy. Unable to
go to 3D
118
Test condition: -40C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,92
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,06
-5V analogue +/- 5% (-4.75 -5.25V) -5,04
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital 100mv pp
B-Mode scanning with 8660 on phantom Unreadable
MFI 5.5, 7 and 8 MHz -
Capture scan Fail
Doppler on phantom Doppler is
running
Doppler noise (gain) Unreadable
1 element sweep on 8660 Unreadable
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok. (not 3D)
Off/on at 264 VAC, Scanning with 8660 on phantom Ok. (not 3D)
VGA picture disappeared.
Composite video output
very noisy and unreadable.
Clock is running and the
scanner is able to change
mode (B-mode/ Triplex).
Unable to go to 3D
As the picture was
unreadable it was decided to
increase the temperature to
20C again
At -20C and much less at other temperatures. Doppler is less sensitive during temperature
changes.
At -20 C VGA picture tear out (line sync). Still unable to go to 3D, at -10C VGA Ok, still
unable to go to 3D. At 20C 3D was okay again, everything else also OK.
3D system has a problem when starting at low temperature (<= -20C). Ripple on 5V digital is
approx. 50mV (approx. 3s time period).
The Lower Operating Limit (LOL) was set to -20C, where the entire cassette excl. the 3D
system, was still functioning. The Lower Destruct Limit (LDL) was not found.
119
A5.2 Result of warm step stress test
An initial test was performed at room temperature before starting the warm stress test.
Test condition: 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,06
3.3V Digital +/- 5% (3.14 - 3.47V) 3,27
5V analogue +/- 5% (4.75 5.25V) 5,18
-5V analogue +/- 5% (-4.75 -5.25V) -4,94
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,1
Ripple on 5V digital < 50 mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 80%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
Test condition: 40C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,94
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,16
-5V analogue +/- 5% (-4.75 -5.25V) -5,04
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 81%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
120
Test condition: 50C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,84
3.3V Digital +/- 5% (3.14 - 3.47V) 3,36
5V analogue +/- 5% (4.75 5.25V) 5,16
-5V analogue +/- 5% (-4.75 -5.25V) -5,04
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 81%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
Test condition: 60C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,82
3.3V Digital +/- 5% (3.14 - 3.47V) 3,36
5V analogue +/- 5% (4.75 5.25V) 5
-5V analogue +/- 5% (-4.75 -5.25V) -4,96
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom -
MFI 5.5, 7 and 8 MHz -
Capture scan -
Doppler on phantom -
Doppler noise (gain) -
1 element sweep on 8660 -
Analogue test oscillator -
Off/on at 90 VAC, Scanning with 8660 on phantom -
Off/on at 264 VAC, Scanning with 8660 on phantom -
At 59C. The scanner
picture disappeared. Video
test picture Ok (Video board
Ok) 3D system worked.
Stopped after 'switching
task'
It was decided to lower the temperature to 50C again. At 55C, the picture came back. Scan
converting was not correct. 3D system worked but Freeze button did not work. At 50C
everything Ok again. It was decided to raise the temperature 1C/min to investigate further.
55C scan convertering Ok. Communication sometimes failing (freeze not always understood).
58C.
Scan convertering Ok. Communication sometimes failing (freeze not always understood). 59C
scan converting fails.
It was decided to raise the temperature to 70C to see if other errors appeared.
121
Test condition: 70C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,92
3.3V Digital +/- 5% (3.14 - 3.47V) 3,2
5V analogue +/- 5% (4.75 5.25V) 5
-5V analogue +/- 5% (-4.75 -5.25V) -4,88
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital -
B-Mode scanning with 8660 on phantom -
MFI 5.5, 7 and 8 MHz -
Capture scan Ok
Doppler on phantom -
Doppler noise (gain) -
1 element sweep on 8660 -
Analogue test oscillator -
Off/on at 90 VAC, Scanning with 8660 on phantom -
Off/on at 264 VAC, Scanning with 8660 on phantom -
Coreboard starts, but stops
after 'switching task'.
Master oscillator (120MHz) under suspicion. A local air cooling was placed in that area and it was
decided to repeat the 60C step.
Test condition: 60C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,92
3.3V Digital +/- 5% (3.14 - 3.47V) 3,55
5V analogue +/- 5% (4.75 5.25V) 5,16
-5V analogue +/- 5% (-4.75 -5.25V) -5,1
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -11,9
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 81%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
At 60,1 degree picture
disappeared again, but came
back when the local cooling
(airflow) was started. The
test was performed
successfully.
The temperature was raised to 70C, but the airflow was inadequate to cool master osc. down.
12V fan on 3D system not running! The test was stopped to try to adjust the master oscillator.
122
Master osc. adjusted. Afterwards 3.3V shorted. Coreboard #2001 000 000 (trouble shooting)+
videoboard. Troubleshooting 10/6 showed: 3.3V Ok. U48 (AVG/Peak controller FPGA) is getting
hot (running on 3.3V). Keyboard error -> U51 does not initiate keyboard.
New Coreboard ZD0767 #2001 000 010 installed with new videoboard ZH0743 2002 100 337.
Test repeated at 60C.
Everything worked except the 12V fan on 3D did not start, after switching on at 90V.
The test was then continued at 70C.
Test condition: 70C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,98
3.3V Digital +/- 5% (3.14 - 3.47V) 3,48
5V analogue +/- 5% (4.75 5.25V) 5,26
-5V analogue +/- 5% (-4.75 -5.25V) -4,92
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan
Doppler on phantom Ok
Doppler noise (gain) 82%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
12V fan on PC backend
started during start at 25C.
Stopped at 70 C.
Test condition: 80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,28
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom ok
MFI 5.5, 7 and 8 MHz ok
Capture scan ok
Doppler on phantom ok
Doppler noise (gain) 85%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom ok
Off/on at 264 VAC, Scanning with 8660 on phantom ok
1/5-2003. Air in Doppler
phantom. Flow set to 3l/h
Tested before start.
12V fan Ok again!
123
Test condition: 90C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,27
5V analogue +/- 5% (4.75 5.25V) 5,14
-5V analogue +/- 5% (-4.75 -5.25V) -4,9
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom ok
MFI 5.5, 7 and 8 MHz ok
Capture scan ok
Doppler on phantom ok
Doppler noise (gain) -
1 element sweep on 8660 -
Analogue test oscillator
Off/on at 90 VAC, Scanning with 8660 on phantom
Off/on at 264 VAC, Scanning with 8660 on phantom
Doppler flow changed to
6l/h.
Composite out unstable.
After 8 min. the screen got
black (power disappeared).
Temperature was lowered.
Started normal again when
temperature was 25C.
A complete test was done at 20C.
Test condition: 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,06
3.3V Digital +/- 5% (3.14 - 3.47V) 3,27
5V analogue +/- 5% (4.75 5.25V) 5,18
-5V analogue +/- 5% (-4.75 -5.25V) -4,94
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,1
Ripple on 5V digital < 50 mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 80%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
It was decided to stop the high temperature test at this temperature. The Upper Operating Limit
(UOL) was set to 80C. The Upper Destruct Limit (UDL) was not found.
124
A5.3 Result of temperature cycling step stress test
The temperature cycling test was set in the interval from 20C to +80C. At each end
temperature there was a dwell time of 10 min. where the test could be performed.
Test condition: -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,32
5V analogue +/- 5% (4.75 5.25V) 5,16
-5V analogue +/- 5% (-4.75 -5.25V) -5
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 80%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
prior to the Off/On test as it
was unable to start again at
low temperature
Test condition: +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,02
3.3V Digital +/- 5% (3.14 - 3.47V) 3,3
5V analogue +/- 5% (4.75 5.25V) 5,26
-5V analogue +/- 5% (-4.75 -5.25V) -5,08
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 85%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
after the Off/On test as it did
not start again after having
being stressed with the low
temperature from the
previous cycle.
Fan on 3D system (12VDC)
stopped. Backflow from air
inlet!
Flow on Doppler a little
weaker (colours). Composite
video a little unstable.
Doppler ok later. Some
elements are weaker during
1-element sweep
(transmitters??)
125
Test condition: -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,02
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,04
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 80%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
prior to the Off/On test as it
was unable to start again at
low temperature
Test condition: +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,02
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -4,98
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 85%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
after the Off/On test as it did
not start again after having
being stressed with the low
temperature from the
previous cycle.
126
Test condition: -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,00
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -4,98
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 79%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
prior to the Off/On test as it
was unable to start again at
low temperature
1 element sweep has weak
elements. Not completely
reset after leaving 1 element
sweep (Test osc. not turned
off!!). Ok after off/on.
Test condition: +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,28
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -4,96
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan
Doppler on phantom Ok
Doppler noise (gain) 86%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
after the Off/On test as it did
not start again after having
being stressed with the low
temperature from the
previous cycle.
Some week elements in 1
element sweep
127
Test condition: -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,88
3.3V Digital +/- 5% (3.14 - 3.47V) 3,28
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -5
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital <50 mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 79%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
prior to the Off/On test as it
was unable to start again at
low temperature
Some week elements in 1
element sweep
Test condition: +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,92
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 87%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
after the Off/On test as it did
not start again after having
being stressed with the low
temperature from the
previous cycle.
Some week elements in 1
element sweep
128
Test condition: -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,88
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,02
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 80%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
prior to the Off/On test as it
was unable to start again at
low temperature
Some week elements in 1
element sweep
Test condition: +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,88
3.3V Digital +/- 5% (3.14 - 3.47V) 3,4
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,06
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan
Doppler on phantom Ok
Doppler noise (gain) 86%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
The 3D system was tested
after the Off/On test as it did
not start again after having
being stressed with the low
temperature from the
previous cycle.
Some week elements in 1
element sweep
1.5 cycles more were performed during lunch, where there are no results recorded. After the
cycling the chamber was brought back to 20 degree and a final test was performed.
129
Test condition: 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,88
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,06
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 80%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
130
A5.4 Result of vibration step stress test
Prior to starting the vibration the harddrive for the 3D system was removed from the system and
placed in 2 strings hanging down from the ceiling of the chamber, to avoid problems with the
harddrive during test.
The vibration step stress test started with 5G, but the cassette stopped working when vibration
started! After removing vibration and powered up again the message Keyboard error popped up
on the screen. From the Coreboard ZD0767 2002 000 010 no response was received from the
keyboard during initialisation. The error followed the Coreboard. (Troubleshooting 10/6-2003
showed that U51 was defective (Latch for HW programming and reset of the keyboard)). Passed
the PCB test system in P4 030811/HED)
Coreboard was changed and the test continued at 5G.
Test condition: 5G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,3
5V analogue +/- 5% (4.75 5.25V) 5,14
-5V analogue +/- 5% (-4.75 -5.25V) -5
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 200mVPP
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 77%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
Doppler is less sensitive.
Test osc. noise at the
boarders. Video signal
noisy. Ripple on power
supply is steady even though
power is off
131
Test condition: 10G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,9
3.3V Digital +/- 5% (3.14 - 3.47V) 3,3
5V analogue +/- 5% (4.75 5.25V) 5,26
-5V analogue +/- 5% (-4.75 -5.25V) -5,08
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 200mVPP
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Unable to
start
Doppler on phantom Ok
Doppler noise (gain) 66%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom OK
3D system locked up.
Mouse arrow could be
moved until it was turned
off.
Very long time starting up
(Coreboard ?) showed KDB
on = K 2001 and waited for
approx. 30 sec. Before
proceeding. This happened
at both 90 and 264 V. 3D
was unable to start under the
test. After test the Coreboard
started up at normal speed
and the 3D system was
working again.
Test condition: 15G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,12
3.3V Digital +/- 5% (3.14 - 3.47V) 3,26
5V analogue +/- 5% (4.75 5.25V) 5,26
-5V analogue +/- 5% (-4.75 -5.25V) -5,06
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital < 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom No doppler
information
Doppler noise (gain) 55%
(vibration in
table)
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok (80 sec.
start up
time)
Off/on at 264 VAC, Scanning with 8660 on phantom Ok (start up
time 75 sec.)
3D system on during start.
OK at 10G. Switched to 2 D
-> ok. Back to 3D but
locked. Scanner off/on.
Start-up takes a very long
time. Slow reaction on a
keypress. Scanner stopped
during test. Off/on -
>Scanner continued. (Long
start-up time) and 3D got up
and running again
Tape was put on trackerball on the keyboard to prevent interrupts. Start-up at 15G was faster.
Scanner stopped when triplex should be tested. Off/on -> long startup time. Stopped again when
selecting Triplex. Off/on -> start-up 100 sec.
132
Test condition: 20G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,15
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital <50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Not running
Doppler on phantom -
Doppler noise (gain) -
1 element sweep on 8660 Ok
Analogue test oscillator Ok. Noisy
picture.
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
Scanner stopped 4 times
when trying to run triplex.
Vibration removed. Still a problem when entering triplex mode. 3D system was running when
vibration was removed.
Delayboard ZE0772 sn 000 004 changed and an extra keyboard was set externally to avoid
interrupts from the trackball.
Doppler stopped with new delay board and B-picture was not updated, during ramp from 0 to 20G
within 5 min. It stopped at 0.3G. It was decided to change the delay board.
ZE0772 000 001 was inserted instead. Knocking on the cassette caused the scanner to stop. An
error was found on the Coreboard (rework on U117).
The original delay board was therefore tested and found ok. Original delay board ZE0772
(000 004) was inserted again and test continued. First ramping from 10G to 20G, then continuing
at 20G.
133
Test condition: 20G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,16
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,3
Ripple on 5V digital 150mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan .
Doppler on phantom .
Doppler noise (gain) approx. 60%
(noise from
movement)
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
3D does not start.
The start speed was normal
after keyboard disconnected
and external keyboard
attached.
External keyboard attached during further testing.
Test condition: 25G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -5,06
12V analogue +/- 5% (11.4 12.6V) 12,2
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 150mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) approx.
55-60%
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
3D does not start.
134
Test condition: 30G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -5,06
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) Approx.
55% noisy
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom OK
3D does not start. Vibration
removed and system was
able to start and perform a
scan.
Test condition: 35G @ 20 C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,94
3.3V Digital +/- 5% (3.14 - 3.47V) 3,28
5V analogue +/- 5% (4.75 5.25V) 5,2
-5V analogue +/- 5% (-4.75 -5.25V) -5,12
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,3
Ripple on 5V digital 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok!!
Doppler on phantom Ok
Doppler noise (gain) ?? Noisy
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
3D is running again!
135
Test condition: 40G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,2
-5V analogue +/- 5% (-4.75 -5.25V) -5,12
12V analogue +/- 5% (11.4 12.6V) 12,2
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 50mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) ?? Noisy
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
3D does not start.
Picture is noisy. Some
stribes in ultrasound picture
(with 8660 transducer).
Vibration removed and
scanner turned off and on
again. 3D system was
running
Test condition: 45G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,96
3.3V Digital +/- 5% (3.14 - 3.47V) 3,24
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -5,06
12V analogue +/- 5% (11.4 12.6V) 12,2
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 50mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok, but
noisy
Doppler noise (gain) ?? Noisy
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
3D system worked at 40G,
when vibration was started
after 3D was up and
running. Stopped after 6
min. @ 45G
136
Test condition: 50G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,98
3.3V Digital +/- 5% (3.14 - 3.47V) 3,28
5V analogue +/- 5% (4.75 5.25V) 5,08
-5V analogue +/- 5% (-4.75 -5.25V) -5,08
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,4
Ripple on 5V digital 50mV pp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) ?? Noisy
1 element sweep on 8660 Ok
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
3D not running. Vibration
stopped and system
restarted. 3D was running.
Vibration started after 3D
was restarted. After 8 min.
3D was still working. Lines
appeared on the captured
image. Went to 2D -> lines
in picture. Size was changed
and lines disappeared. Back
to 3D still -> ok. After 13
min. the capture stopped
(unresponsive). System
restarted. The 2D system
started, but stopped when
scanning was started
(possible watchdog
shutdown).
After the test, Dornier logo has now changed to BK logo and date/time was not correct. A RAM
checksum error must have occurred and the Coreboard must have set the contents to default value
(a possible battery problem).
Composite video output was very noisy.
Vibration removed and system restarted -> ok. Vibration on again -> 40G. 2D system started up
but crashed as scanning was started. Lines on composite video out. Possible bad connection on
videoboard (As the videocard was a Prototype card without number it was checked and one
capacitor seemed loose, but no further troubleshooting was performed).
Vibration was removed and everything was running again.
Keyboard in chamber was checked. TGC potmeters and trackball worked, but keyboard was
unresponsive.
After changing the front-end board (ZE0724) sn 000 013 to sn 000 109 vibration was started again
ramping from 40 to 50G. The scanner did not stop this time, but after 5 min. the scanner stopped
as the power supply failed. It turned out to be a screw from one of the fans that had gone loose and
short circuited the power supply filter. The filter was changed.
After the filter had been changed no doppler information could be found. Front-end board was
changed (ZE0724 #000 102) to the old board #000 109.
Further troubleshooting showed that the 2 front-end boards were not working (no doppler
information / Transmitter errors).
137
A5.5 Result of combined temperature cycle and vibration step stress test
The test was performed 29/9 2003 with. SW version 0.140 24-09-2003 (Improved doppler).
Initial pretest:
Test condition: 0G @ 20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,02
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,26
-5V analogue +/- 5% (-4.75 -5.25V) -5,18
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mvPP
B-Mode scanning with 8660 on phantom ok
MFI 5.5, 7 and 8 MHz ok
Capture scan Ok
Doppler on phantom ok
Doppler noise (gain) 65%
1 element sweep on 8660 -
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on
phantom
Ok
Off/on at 264 VAC, Scanning with 8660 on
phantom
Ok
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
During the initial temperature cycling test from -20 t0 +80 deg the cassette stopped at 61C
The master osc. was adjusted. 1/8 Rp counter-CW. Seemed a little better as it was ok to 70C
Adjusted 1/8 more. Ferrite defective.
Therefore a new coreboard was inserted. It was decided to continue the test even though the
cassette stops.
The new coreboard was equipped with SW dated 14/5-2003.12.13
A quick test was done to determine the state of the master oscillator:
@60C Ok still functioning.
@70C Ok still functioning.
@80C Ok still functioning.
Back to 20C test start at -20 to 80 deg and vibration 10G.
138
Test condition: 10G @ -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,4
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,12
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on
phantom
Ok
Off/on at 264 VAC, Scanning with 8660 on
phantom
Ok
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
Doppler could not be
tested with stress as it was
too noisy during tempera-
ture changes with
vibration
Doppler did not work when stress was removed. Doppler board ZD0758 sn 000 264 inserted
instead of sn 000 104. Jumper J5 almost off. New board tested ok. Test continued.
139
Test condition: 20G @ -20C to 80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V digital +/- 5% (3.14 - 3.47V) 3,4
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,18
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mvPP
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz OK
Capture scan Can be
selected
but not
operated
Doppler on phantom ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on
phantom
1)
Off/on at 264 VAC, Scanning with 8660 on
phantom
2)
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
Doppler could not be
tested with stress as it was
too noisy during tempera-
ture changes with
vibration.
1) KBD on =K 2001.
Stops here without
getting further. When
vib removed ok. Error
is related to keyboard.
Keyboard removed
and test ok. TGC line
visible always
(Indicates that the
keyboard is active)
2) At -20 deg 20G See
1) Works at -20C
without vib.
To avoid interruptions from the keyboard during the test the keyboard was removed and the test
continued.
140
Test condition: 20G @ ~50C rising
temperature
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 4,98
3.3V Digital +/- 5% (3.14 - 3.47V) 3,34
5V analogue +/- 5% (4.75 5.25V) 5,24
-5V analogue +/- 5% (-4.75 -5.25V) -5,18
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on
phantom
Ok
Off/on at 264 VAC, Scanning with 8660 on
phantom
Ok
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
Doppler could not be
tested with stress as it was
too noisy during tempera-
ture changes with
vibration.
3D unable to start during
stress
Keyboard is interrupting all the time (hourglass) even though only an external keyboard is
attached (No keyboard in the chamber).
This might indicate a bad connection either to the supply voltage or to the reset line. Doppler gate
is moving during vibration, when keyboard is connected (absolutely no movement on trackball)
the gate is ok when vibration is removed.
141
Test condition: 30G @ ~-15C falling
temperature
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,34
5V analogue +/- 5% (4.75 5.25V) 5,2
-5V analogue +/- 5% (-4.75 -5.25V) -5,16
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -18
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator OK
Off/on at 90 VAC, Scanning with 8660 on
phantom
Ok
Off/on at 264 VAC, Scanning with 8660 on
phantom
Ok
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
Doppler could not be
tested with stress as it was
too noisy during tempera-
ture changes with
vibration.
3D unable to start during
stress
Test condition: 30G @ ~50 C rising
temperature
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,36
5V analogue +/- 5% (4.75 5.25V) 5,22
-5V analogue +/- 5% (-4.75 -5.25V) -5,16
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan
Doppler on phantom Ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on
phantom
1)
Off/on at 264 VAC, Scanning with 8660 on
phantom
1)
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
Doppler could not be
tested with stress as it was
too noisy during
temperature changes with
vibration.
3D unable to start during
stress
1) Unable to start. Stops
after switching task
Keyboard error. Unable to start. Stops after switching task. Coreboard (ZD0767 sn 000 002 )
was inserted to see if the Coreboard was the problem.
142
The new coreboard was OK, but the hourglass still occurred during vibration.
U51 changed on coreboard, but the coreboard had to be reset (setting NVRAM to default) to
enable power up.
143
Test condition: 30G @ -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,24
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,04
-5V analogue +/- 5% (-4.75 -5.25V) -5,18
12V analogue +/- 5% (11.4 12.6V) 11,9
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mvPP
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on
phantom
Ok
Off/on at 264 VAC, Scanning with 8660 on
phantom
Ok
1 element sweep could
not be tested as the Com
port on the attached PC
was not functioning.
Doppler could not be
tested with stress as it was
too noisy during
temperature changes with
vibration.
3D unable to start during
stress
Test condition: 30G @ +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5.04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,22
-5V analogue +/- 5% (-4.75 -5.25V) -5,2
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mvpp
B-Mode scanning with 8660 on phantom NA
MFI 5.5, 7 and 8 MHz NA
Capture scan NA
Doppler on phantom NA
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator NA
Off/on at 90 VAC, Scanning with 8660 on
phantom
Ok 1)
Off/on at 264 VAC, Scanning with 8660 on
phantom
Ok 1)
Test at +80C was
impossible as master osc.
on the new coreboard
stopped.
1) Until after switching
task
As a complete functional test could not be performed because the master oscillator stopped, the
temperature was set to 20 C and the functional test performed.
144
Test condition: 30G @ +20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5.04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,18
-5V analogue +/- 5% (-4.75 -5.25V) -5,16
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,5
Ripple on 5V digital 25mV
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok
Doppler on phantom Ok
Doppler noise (gain) 68%
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
1 element sweep could not
be tested as the Com port on
the attached PC was not
functioning.
Doppler could not be tested
with stress as it was too
noisy during temperature
changes with vibration.
As the result was satisfying it was decided to continue the test at 40G.
Test condition: 40G @ -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 5,22
-5V analogue +/- 5% (-4.75 -5.25V) -5,14
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
1 element sweep could not
be tested as the Com port on
the attached PC was not
functioning.
Doppler could not be tested
with stress as it was too
noisy during temperature
changes with vibration.
3D unable to start during
stress.
Composite video out is
flickering
145
Test condition: 40G @ +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,34
5V analogue +/- 5% (4.75 5.25V) 5,28
-5V analogue +/- 5% (-4.75 -5.25V) -5,14
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mV
B-Mode scanning with 8660 on phantom NA
MFI 5.5, 7 and 8 MHz NA
Capture scan NA
Doppler on phantom NA
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator NA
Off/on at 90 VAC, Scanning with 8660 on phantom Ok 1)
Off/on at 264 VAC, Scanning with 8660 on phantom Ok 1)
Test at +80C was
impossible as master osc. on
the new coreboard stopped.
1) Until after switching task
Stress was removed shortly to make a functional test
Test condition: 0G @ +20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,38
5V analogue +/- 5% (4.75 5.25V) 4,96
-5V analogue +/- 5% (-4.75 -5.25V) -5,14
12V analogue +/- 5% (11.4 12.6V) 12,1
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan Ok 1)
Doppler on phantom Ok
Doppler noise (gain) 69%
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
1 element sweep could not
be tested as the Com port on
the attached PC was not
functioning.
Doppler could not be tested
with stress as it was too
noisy during temperature
changes with vibration.
1) The 3D system did not
respond the first time
(Windows regenerating. But
was Ok after windows had
restarted.
146
The test was continued at 50G.
Test condition: 50G @ -20C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,04
3.3V Digital +/- 5% (3.14 - 3.47V) 3,4
5V analogue +/- 5% (4.75 5.25V) 5,22
-5V analogue +/- 5% (-4.75 -5.25V) -5,16
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom Ok
MFI 5.5, 7 and 8 MHz Ok
Capture scan -
Doppler on phantom Ok 1)
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator Ok
Off/on at 90 VAC, Scanning with 8660 on phantom Ok
Off/on at 264 VAC, Scanning with 8660 on phantom Ok
1 element sweep could not
be tested as the Com port on
the attached PC was not
functioning.
Doppler could not be tested
with stress as it was too
noisy during temperature
changes with vibration.
3D unable to start during
stress
Composite video flickering.
Language switched during
test!! (after power down).
1) Doppler stopped. Power
down and up again. Doppler
ok.
Test condition: 50G @ +80C
Test description Result Remark
5V digital +/- 2% (4.9 5.1V) 5,06
3.3V Digital +/- 5% (3.14 - 3.47V) 3,36
5V analogue +/- 5% (4.75 5.25V) 5,26
-5V analogue +/- 5% (-4.75 -5.25V) -5,14
12V analogue +/- 5% (11.4 12.6V) 12
-12V analogue +/- 5% (-11.4 -12.6V) -12,6
Ripple on 5V digital 25mVpp
B-Mode scanning with 8660 on phantom NA
MFI 5.5, 7 and 8 MHz NA
Capture scan NA
Doppler on phantom NA
Doppler noise (gain) NA
1 element sweep on 8660 NA
Analogue test oscillator NA
Off/on at 90 VAC, Scanning with 8660 on phantom Ok 1)
Off/on at 264 VAC, Scanning with 8660 on phantom Ok 1)
At 60C the master osc
stopped. Only partial test
performed
Composite video flickering.
1) until switching task
As the functional test could not be completed at +80C the stress was remove after 10 min. to
make a functional test at +20C.
However, when the stress was removed the scanner was unable to start. The trouble shooting
showed that one transmitter module (ZE0728) was defective, a fuse on the motherboard was
damaged and the power supply had 2 errors.
The fan did not run (had to be changed).
Transformer on the filter board had a loose connection.
147
Annex 6
Case study
Modules for BeoSound 1 and BeoSound 3000
supplied by Bang & Olufsen A/S
detailed test log
(7 pages)
148
DELTA/KAS Oversigt over testemner
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Eksponering
Dato Nr. 1 Nr. 2 Nr. 3 Nr. 4 Nr. 5 Nr. 1 Nr. 2 Nr. 3
Kulde 14-apr x x
Varme 14-apr x x
Temperaturcycling 14-apr x x
Vibration optil 15 grms 15-apr x x
Vibration optil 25 grms 15-apr x x
Vibration ved 25 grms 15-apr x (x) x x
Vibration ved 30 grms 15-apr x x
Ekstra temperaturtest 15-apr x
Vibration ved 35 grms 15-apr x
Vibration optil 65 grms 15-apr x
Kombineret vibration og temperatur 16-apr x
med ny
metal vinkel
Bemrkninger:
Overvgning lavet vha. komplette B&O apparater F-test inkluderer power off/on
Test overvget af: Turi Bach Roslund
Mogens Agger
Unit ID
PCB 12 (Input-select til
BeoSound 3000)
SMPS (til BeoSound 1)
149
DELTA/KAS Kuldeeksponering
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Aktivitet Dato Tid Init. SMPS PCB 12 Bemrkning
Initial F-test 14-apr 11:30 B&O OK OK
F-test ved +10C 14-apr 11:38 B&O OK
Ingen lyd (hverken fra CD
eller Radio)
PCB 12 kan tilsyneladende
ikke lide temperaturtransienter
F-test ved +17C 14-apr 11:46 B&O N/A Stopper af og til
F-test ved +25C 14-apr 11:50 B&O N/A Verifikation af opstilling
Rampe ned med 1/min 14-apr 12:02 B&O N/A
OK ved 20C, OK ved
17C,
F-test ved +15C 14-apr 12:41 B&O N/A OK
Rampe ned med 1/min 14-apr B&O
F-test ved +10C 14-apr 12:59 B&O OK
Funktion ustabil (skifter
mellem lyd eller display)
Rampe ned med 1/min 14-apr B&O Rampe hastighed passer ikke !
F-test ved 0C 14-apr 13:22 B&O OK OK
Rampe ned med 2/min 14-apr B&O
F-test ved -10C 14-apr 13:33 B&O OK
OK, dog funktion ustabil af
og til
Rampe ned med 2/min 14-apr B&O
F-test ved -20C 14-apr 13:46 B&O OK
OK, dog funktion ustabil af
og til
Rampe ned med 2/min 14-apr B&O
F-test ved -30C 14-apr 14:04 B&O OK OK
Rampe ned med 2/min 14-apr B&O
Radio begynder at
"knase" ved -35C
F-test ved -40C 14-apr 14:14 B&O OK
Radio-del nsten
ubrugelig, grn LED tndt
Grn LED hrer til "Timer
funktionen"
Rampe ned med 2/min 14-apr 14:24 B&O
F-test ved -50C 14-apr 14:35 B&O OK Grn LED tndt
Rampe ned med 2/min 14-apr 14:36 B&O
Stj ved skift mellem
programkilder ved -55C
F-test ved -60C 14-apr 14:43 B&O Gr ud engang imellem
Tilbage til ambient 14-apr B&O
F-test ved +25C 14-apr 14:56 B&O OK Display ustabilt ellers OK
Ekstra test ved -55C 15-apr 14:15 KAS N/A
Med nr. 3. Knaser ved ca. -
38C
Efter at P20 testledning var
repareret
Lower Operational Temperature Limit LOTL -55C -35C
Lower Destruct Temperature Limit LDTL Ikke fundet Ikke fundet
Resultat
150
DELTA/KAS Varmeeksponering
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Aktivitet Dato Tid Init. SMPS PCB 12 Bemrkning
Initial F-test 14-apr 14:56 B&O OK Display ustabilt ellers OK
Rampe op med 5/min
F-test ved +40C 14-apr 15:09 B&O OK OK
Rampe op med 5/min
F-test ved +50C 14-apr 15:17 B&O OK OK
Rampe op med 5/min
F-test ved +60C 14-apr 15:26 B&O OK
OK (dog lidt problemer med
display)
Rampe op med 5/min
F-test ved +70C 14-apr 15:51 B&O OK OK
Rampe op med 5/min
F-test ved +80C 14-apr 16:00 B&O OK OK
Rampe op med 5/min
F-test ved +90C 14-apr 16:07 B&O OK OK
Rampe op med 5/min
F-test ved +100C 14-apr 16:15 B&O OK OK
Rampe op med 5/min
F-test ved +110C 14-apr 16:22 B&O OK OK
Stoppet ved +110C
for ikke at beskadige
testledninger
Rampe ned med 50/min
F-test ved +25C 14-apr 16:31 B&O OK OK
Upper Operational Temperature Limit UOTL Ikke fundet Ikke fundet
Upper Destruct Temperature Limit UDTL Ikke fundet Ikke fundet
Resultat
DELTA/KAS Temperaturcycling
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Aktivitet Dato Tid Init. SMPS PCB 12 Bemrkning
Start cycling 14-apr 16:33
Temperaturcycling KAS OK OK
10 cykles med 30 min dwell time.
Tlow = -55C, Thigh = +110C.
F-test 15-apr 08:09 B&O OK OK
Visuel inspektion 15-apr 08:15 B&O
Begyndende
stresssymptomer ved
lodning af tunge
komponenter (endnu ikke
kritisk)
Begyndende
stresssymptomer ved
lodning af tunge
komponenter (endnu ikke
kritisk)
Resultat
151
DELTA/KAS Vibrationseksponering
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Aktivitet Dato Tid Init. SMPS PCB 12 Bemrkning
Initial F-test 15-apr 09:44 B&O OK
Nr. 1. virker ikke rigtigt
(brummer og reagerer
langsomt). Skiftet til nr. 2
inden vibrationstest
Random 5 grms 15-apr 09:52 KAS OK OK Ca. 15 minutter
Random 10 grms 15-apr 10:06 KAS OK OK Ca. 15 minutter
Random 15 grms 15-apr 10:20 KAS OK Slr fra engang imellem Ca. 10 minutter
Fejlsgning 15-apr 10:32 B&O N/A
Ser ud til at vre omkring
stik P20 (data, clock
mm.). P20
testledningsstik ustabilt
F-test 15-apr 10:58 B&O N/A
Skiftet til nr. 3 +
testledningstik P20 skiftet
F-test 15-apr 11:16 B&O OK OK
Random 15 grms 15-apr 11:18 KAS OK OK Ca. 5 minutter
Random 20 grms 15-apr 11:24 KAS OK OK Ca. 15 minutter
Random 25 grms 15-apr 11:38 KAS
C1 + RT1 falder af efter ca.
1 minut
OK Ca. 2 minutter
F-test 15-apr 11:58 B&O
Skiftet til nr.2 hvor C1 og
RT1 er stttelimet
OK
Random 25 grms 15-apr 11:58 KAS
C55 falder af og C54 ls
efter ca. 12 minutter
OK
Pause efter ca. 1 minut, i alt ca.
12 minutter
Skift til nyt emne 15-apr 12:17 B&O
Skiftet til nr. 3 hvor C55,
C54, C21, C22, C1 og RT1
er stttelimet. Nr. 3 virker
ikke i opstillingen. Skiftet til
nr. 4 der er stttelimet p
samme mde
OK
F-test 15-apr 12:37 B&O OK OK
Random 25 grms 15-apr 13:09 KAS OK Ustabil
Ca. 3 minutter (i alt ca. 15
minutter ved 25 Grms).
Accelerometer nr. 4 faldet af
Random 30 grms 15-apr 13:15 KAS
L7 knkket halvt af efter
ca. 15 minutter. Repareret
og stttelimet
OK Ca. 15 minutter
Random 30 grms 15-apr 14:02 KAS OK OK
Ca. 3 minutter. Accelerometer #
4 sat p igen
Random 35 grms 15-apr 14:05 KAS Fejler OK Ca. 6 minutter
Herefter lav temperatur af PCB 12
# 3
Random 35 grms 15-apr 14:18 KAS (ikke med) OK
Accelerometer # 2 og # 4 falder
af. Ca. 10 minutter i alt
Random 40 grms 15-apr 14:29 KAS (ikke med) OK Ca. 10 minutter
Random 45 grms 15-apr 14:39 KAS (ikke med) OK Ca. 12 minutter
Random 50 grms 15-apr 14:52 KAS (ikke med) OK Ca. 10 minutter
Random 55 grms 15-apr 15:02 KAS (ikke med) OK Lidt ustabilitet i lys
Random 60 grms 15-apr 15:12 KAS (ikke med) OK Ca. 10 minutter
Random 100% ! 15-apr 15:22 KAS (ikke med)
OK (frste produkt p
100% !!!)
Ca. 61-64 grms. Ca. 10 minutter
Visuel inspektion 15-apr 15:37 B&O
C97 og C107 faldet af.
Monteringsvinkel p
netstiksskinne ved
netskinne knkket
25 Grms (C1, C21, C22,
C54, C55, RT1)
30 Grms (L7)
Vibration Destruct Level KAS 35 Grms
ca. 65 grms
(kondensatorer)
Resultat
Operational Vibration Level Ikke fundet KAS
Eksponering udfrt med random vibration i 6 akser. 10-15 minutter ved hvert niveau. 5 grms step
152
DELTA/KAS Kombineret vibrations- og temperatureksponering
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Aktivitet Dato Tid Init. Bemrkning
Initial F-test SMPS PCB 12
Kombineret vibration
og temperatur
cycling
16-apr 08:11 KAS
Ustabilitet efter ca. 8
minutter ved -55C.
CD afspilning virker
ikke efter ca. 10
minutter. Dr helt
efter ca. 7 minutter
ved +110C
"Sdvanlig knas" p vej
ned i temperatur. Vil
ikke starte op efter
power off ved -55C.
Kan ikke spille CD ved
slutningen af T = 110C
1 cykle med 15 min dwell time.
Tlow = -55C, Thigh = +110C.
Vibrationsniveau 20 grms.
Funktionstest 16-apr 08:50 B&O OK OK
Kombineret vibration
og temperatur
cycling
16-apr 08:53 KAS
CD afspilning
stopper efter ca. 5
minutter ved -55C.
Stttelim (Hot-melt)
svigter ved den hje
temperatur
Radio "dr" efter ca. 4
minutter ved -55C
1 cykle med 15 min dwell time.
Tlow = -55C, Thigh = +110C.
Vibrationsniveau 30 grms.
Funktionstest 16-apr 09:36 B&O
Virker ikke (C55
knkket af)
OK
Kombineret vibration
og temperatur
cycling
16-apr 09:36 KAS
Er med, men virker
ikke
Stadig problemer
undervejs (men ingen
"nye")
1 cykle med 15 min dwell time.
Tlow = -55C, Thigh = +110C.
Vibrationsniveau 40 grms.
Funktionstest 16-apr 10:16 B&O
Virker ikke (flere
komponenter der er
stttet limet
knkket af)
OK
Kombineret vibration
og temperatur
cycling
16-apr 10:19 KAS
Er med, men virker
ikke
Stadig problemer
undervejs (men ingen
"nye")
1 cykle med 10 min dwell time.
Tlow = -55C, Thigh = +110C.
Vibrationsniveau 50 grms.
Visuel inspektion +
funktionstest
16-apr 10:57 B&O
C11 og U2 knkket
af
Funktion OK, men C89
knkket af.
Antennestik knkket.
Monteringsvinkel p
netskinne knkket
Resultat
153
DELTA/KAS Resume
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
SMPS PCB 12 Bemrkning
LOTL -55C -35C
Lower Operational
Temperature Limit.
LDTL Ikke fundet Ikke fundet
Lower Destruct Temperature
Limit
Svaghed Stj ved skift af programkilder Radio "knaser" i lyden
UOTL Ikke fundet Ikke fundet
Upper Operational
Temperature Limit.
UDTL Ikke fundet Ikke fundet
Upper Destruct Temperature
Limit
Svaghed
(stoppet ved +110C pga.
testledninger)
(stoppet ved +110C pga.
testledninger)
OVL
25 grms (5 komponenter)
30 grms med L7)
Ikke fundet Operational Vibration Level
VDL ca. 35 grms ca. 65 grms Vibration Destruct Level
Svaghed
Montering af C1, C21, C22,
C54, C55, RT1 og L7
Montering af C97 og C107.
Moneringsvinkel p netskinne
Temperatur cycling
(-55C/+110C, 30 min.dwell
10 cycles)
Svaghed
Begyndende stresssymptomer
ved lodning af tunge
komponenter (endnu ikke
kritisk)
Begyndende stresssymptomer
ved lodning af tunge
komponenter (endnu ikke
kritisk)
Kombineret vibration og
temperatur
10, 20, 30, 40 og 50 grms,
-55C og +110C
Svaghed
Problemer med CD afspilning
ved lav temp. Montering af C11
og U2.
Montering af C89.
Monteringsvinkel p netskinne,
Antennestik knkket i ene
side
Bemrkning: Der br udfres en detaljeret visuel inspektion af alle emner for at afdkke eventuelle andre svagheder
Eksponering
Kulde
Varme
Vibration
154
DELTA/KAS Konklusioner efter overordnet visuel inspektion udfrt p DELTA
HALT test af moduler til BeoSound 1 og BeoSound3000 udfrt for Bang & Olufsen a/s
DELTA sag nr. E501018 A
Forml At finde de svage punkter for SMPS til BeoSound 1
Her er der plads til
kundens's kommentarer
Mulig rsag Aktion
Fundne svagheder Ja Nej (evt. henvisning til fejlrapport etc.) Ja Nej
Stj ved skift mellem programkilder
RT1 falder af
C21, C22, C54 og C55 falder af
L7 falder af
C11 falder af
U2 knkker af
CD afspilning stopper ved kav temp./vibration
Forml At finde de svage punkter for PCB12 til BeoSound 3000
Mulig rsag Aktion
Fundne svagheder Ja Nej (evt. henvisning til fejlrapport etc.) Ja Nej
Radio "knaser" i lyden (ved lav temp.)
C97 og C107 falder af
C89 knkker af
Monteringsvinkel p netskinne knkker af
Antennestik knkker af
Relevant RE-HALT
Relevant RE-HALT
De testede moduler br underkastes en detaljeret visuel inspektion