Está en la página 1de 29

OptiX OSN 3500&7500&7500 II

V200R013C10SPC100
TMPLS to MPLS-TP Upgrade
Guide


Issue 01
Date 2014-04-11

HUAWEI TECHNOLOGIES CO., LTD.


Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
i

Copyright Huawei Technologies Co., Ltd. 2014. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions
and other Huawei trademarks are trademarks of Huawei Technol ogies Co., Ltd.
All other trademarks and trade names mentioned i n this document are the property of thei r respecti ve
holders.

Notice
The purchased products, services and feat ures are stipulated by the contract made bet ween Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unl ess otherwise specified in the contract, all statements,
informati on, and recommendations in this document are provi ded "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.
The informati on in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.






Huawei Technologies Co., Ltd.
Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
Peopl e's Republic of China
Website: http://www.huawei.com
Email: support@huawei.com


OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide Change History

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
ii

Change History
Issue Date Description
01 2014-04-11 This issue is the first official release.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide Contents

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
iii

Contents
Change History ................................................................................................................................ ii
1 Before You Start............................................................................................................................. 1
1.1 Upgrade Object ive .............................................................................................................................................................1
1.2 Preparing for the Upgrade ................................................................................................................................................1
1.3 Method Introduction..........................................................................................................................................................2
1.4 Impact of the Upgrade.......................................................................................................................................................3
1.4.1 Impact on the System During the Upgrade .........................................................................................................3
1.4.2 Impact on the System After the Upgrade ............................................................................................................3
1.5 Precautions ..........................................................................................................................................................................3
2 Upgrade Process Overview ......................................................................................................... 5
2.1 Upgrade Flowchart ............................................................................................................................................................5
2.2 Running Inspection Scripts ..............................................................................................................................................6
2.3 Checking the Software Version .......................................................................................................................................9
2.3.1 Checking the NE Software Version ......................................................................................................................9
2.3.2 Checking the U2000 Version ...............................................................................................................................10
2.3.3 Upgrading the NE Software.................................................................................................................................10
2.3.4 Upgrading the U2000............................................................................................................................................10
2.4 Checking Feature Coupling............................................................................................................................................10
2.5 Migrating Services...........................................................................................................................................................12
2.6 Replacing the Cross-Connect Board on OptiX OSN 3500.......................................................................................15
2.7 OptiX OSN Replacing the Cross-Connect Board on OptiX OSN 7500.................................................................17
2.8 Switching to Dual-Stack OAM Mode ..........................................................................................................................18
2.9 Switching to MPLS-TP OAM .......................................................................................................................................21

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
1

1 Before You Start
1.1 Upgrade Objective
This document guides you to upgrade the feature TMPLS OAM of the OptiX OSN
3500/7500/7500 II to MPLS-TP OAM. After the upgrade, the OptiX OSN 3500/7500/7500 II
can perform OAM operations with the peers that support MPLS-TP OAM.
1.2 Preparing for the Upgrade
The table below lists the preparations you need to complete before an upgrade.
Table 1-1 Preparations for an upgrade
Item Description
Versions of the U2000 and NE
software
Upgrade the U2000 and NE software to the versions
that support MPLS-TP.
Upgrade the NE software to V200R013C10SPC100.
Upgrade the U2000 to V200R001C00.
Hardware Ensure that the boards on the equipment meet the
following requirements:

The cross-connect board on the OptiX OSN 3500
is SSN3PSXCSA.

The cross-connect board on the OptiX OSN 7500
is SST2PSXCSA.

Ensure that the subrack type of the OptiX OSN
3500/7500 meets the requirements described in
section 2.2 "Running Inspection Scripts."
Personnel Ensure that the upgrade personnel have the basic
network skills, master the common operations on the
U2000, know basics about the transport equipment,
and understand the concepts of MPLS-TP.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
2

Item Description
Feature Before switching Y.1711 to Y.1731, ensure the
following conditions are met.

The OptiX OSN 3500 does not support two-slot
boards.

Slots 26 to 31 on the OptiX OSN 7500 do not
support packet boards.

The services that run the IGMP protocol do not
support complex traffic classification.

The PWs configured with the interworking
function (IWF) do not support MPLS-TP OAM.

Switching to the dual-stack mode is not
supported if the number of enabled TMPLS
OAM features exceeds 1024.

1.3 Method Introduction
An upgrade from TMPLS OAM to MPLS-TP OAM includes four procedures.
1. (Optional) Migrate services on the OptiX OSN 7500. Because slots 26 to 31 on the
OptiX OSN 7500 do not support packet boards after the upgrade, the services that are
originally carried by the boards in slots 26 to 31 need to be migrated beforehand.
2. (Optional) Replace cross-connect boards. If the cross-connect boards on the OptiX OSN
3500/7500 do not support MPLS-TP OAM, replace them with proper ones.
3. (Mandatory) Switch the single-stack OAM mode (TMPLS) to the dual-stack OAM mode
(TMPLS+MPLS-TP). The OptiX OSN 3500/7500/7500 II uses the single-stack OAM
mode by default. Therefore, you need to switch the single-stack OAM mode to the
dual-stack OAM mode. The switching is irreversible. That is, you can only switch the
single-stack OAM mode to the dual-stack OAM mode.
4. (Mandatory) Select and switch services to MPLS-TP OAM. You select the desired
services and switch them to MPLS-TP OAM. The switching is reversible.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
3

1.4 Impact of the Upgrade
1.4.1 Impact on the System During the Upgrade
Impact on Services
During the switching to dual-stack OAM mode on the OptiX OSN 3500, services are
interrupted for less than 12 seconds.
During the switching from SST1PSXCSA to SST2PSXCSA on the OptiX OSN 7500, services
are interrupted for less than 2.5 seconds.
During the service migration on the OptiX OSN 7500, services are interrupted until the
migration finishes.
Impact on Network Communications
If the equipment communicates with the U2000 through DCC channels, the communication
will be interrupted for less than 12 seconds during the switching to dual-stack OAM mode on
the OptiX OSN 3500 or for less than 2.5 seconds during the switching from SST1PSXCSA to
SST2PSXCSA on the OptiX OSN 7500.
1.4.2 Impact on the System After the Upgrade
After the switching to dual-stack OAM mode on the OptiX OSN 3500, the services that run
the IGMP protocol do not support complex traffic classification. After the switching from
SST1PSXCSA to SST2PSXCSA on the OptiX OSN 7500, slots 26 to 31 do not support
packet boards.
1.5 Precautions
The switching to dual-stack OAM mode is irreversible. You can return to the
pre-switching condition only by restoring the databases that are automatically backed up
before the switching. If you return to the pre-switching condition through database
restoration, cold reset the cross-connect board to recover services.
Ensure power supply to the equipment where the switching to dual-stack OAM mode is
being performed. If the equipment is powered off before the switching finishes, the
equipment may enter an unexpected state and you can return to the pre-switching
condition only by restoring the databases that are automatically backed up before the
switching.In V200R013C10SPC100, the algorithm PBKDF is added, and three digest
algorithms are supported: MD5, SHA256, and PBKDF. Users can configure a digest
algorithm on the U2000. The security of the three digest algorithms from low to high is
as follows: MD5, SHA256, and PBKDF2. If a stronger digest algorithm is configured
after an upgrade, the digest information of an account added before the upgrade is still
stored in the database. You need to manually delete this account and create another one,
or change the password of the account added before the upgrade.
For example, before an upgrade, digest information is generated using MD5. Suppose
that an administrator account szhw exists, and the digest information of the account
password generated using MD5 is stored in the database. After an upgrade is performed
and the digest algorithm is changed to PBKDF2, the digest information of the szhw
account password generated using MD5 is still stored in the database. You can delete this
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 1 Before You Start

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
4

szhw account and create a new szhw account. Then, the new szhw account's digest
information generated using PBKDF2 is stored in the database, and the digest
information generated using MD5 is deleted.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
5

2 Upgrade Process Overview
2.1 Upgrade Flowchart
Figure 2-1 Upgrade flowchart
Running inspection
scripts
(Mandatory) Switching to
dual-stack OAM mode
(Mandatory) Switching to
MPLS-TP OAM
End
(Mandatory) Checking
the software version
(Optional) Migrating
services
(Optional) Replacing
cross-connect boards
(Mandatory) Checking
feature coupling


OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
6

2.2 Running Inspection Scripts
Description
Run inspection scripts to check whether the upgrade conditions are met.
Precautions
Inspection scripts can be used to check:
Whether the cross-connect board on the OptiX OSN 3500 is SSN3PSXCSA
Whether any two-slot packet board is installed on the OptiX OSN 3500
Whether the subrack type of the OptiX OSN 3500 is high-power backplane subrack
(VER.E)
Whether the cross-connect board on the OptiX OSN 7500 is SSST2PSXCSA
Whether slots 26 to 31 on the OptiX OSN 7500 house any packet board
Whether the subrack type of the OptiX OSN 7500 is high-power backplane subrack
(VER.D)
Whether one E-LAN service is configured with complex traffic classification and IGMP
Whether all specifications of TMPLS can be switched to MPLS-TP
Procedure
Step 1 Start the Inspector and add the NEs to be upgraded.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
7

Step 2 Choose Configure > Configure Inspector Template from the Main Menu. In the Configure
Inspection Template window, select Checking whether the NE can be upgraded from the
distributed mode to centralized mode and Checking OAM specifications from the
upgrade from 1711 to 1731, and click Finish.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
8

Step 3 Click in the Inspector window. The inspection starts and endures three to five minutes.
After the inspection finishes, view the results in the Check Result pane.

----End
Verification
Prepare for the upgrade according to the inspection results.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
9

2.3 Checking the Software Version
2.3.1 Checking the NE Software Version
Step 1 In NE Explorer, choose Configuration > NE Attribute from the Function Tree.

----End
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
10

2.3.2 Checking the U2000 Version
Step 1 On the U2000, choose Help > About from the Main Menu.

----End
2.3.3 Upgrading the NE Software
For details on how to upgrade the NE software, see the OptiX OSN 1500&3500&7500&7500
II Intelligent Optical Transmission&Switching System V200R013C10SPC100 Upgrade
Guide-Simulation Package Diffusion and OptiX OSN 1500&3500&7500&7500 II Intelligent
Optical Transmission&Switching System V200R013C10SPC100 Upgrade Guide-Simulation
Package Loading.
2.3.4 Upgrading the U2000
For details on how to upgrade the U2000, see the related upgrade guide.
2.4 Checking Feature Coupling
Description
After the switching to dual-stack OAM mode, the services that run the IGMP protocol does
not support complex traffic classification. Therefore, you need to check whether IGMP
Snooping and complex traffic classification are configured for the same services before the
switching.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
11

Procedure
Step 1 In NE Explorer, choose Configuration > Packet Configuration > Ethernet Protocol
Configuration > IGMP Snooping Configuration from the Function Tree. Check whether
IGMP Snooping is enabled for any service.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
12

Step 2 In NE Explorer, choose Configuration > Packet Configuration > Ethernet Service
Management > E-LAN Service from the Function Tree. In the right pane, click QoS and
check whether the service with enabled IGMP Snooping has any QoS policy.

Step 3 Delete the QoS policy or disable IGMP Snooping according to the actual requirements.
----End
Verification
No service is configured with IGMP Snooping and complex traffic classification.
2.5 Migrating Services
After the switching from SST1PSXCSA to SST2PSXCSA on the OptiX OSN 7500, slots 26
to 31 do not support packet boards.
If there is any packet board in slots 26 to 31 and the board is configured with services, you
need to migrate the services to the boards in slots 1 to 8 and slots 11 to 18 before the
switching.
After the services are migrated, remove the packet boards in slots 26 to 31 and delete the
corresponding logical boards on the U2000. Service migration can be performed with
Huawei's circuit cutover tool (TCAT).
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
13

To migrate the services that TCAT does not support, you can delete these services and restore
them on the target boards. Considering the complexity of service migration, ask R&D
engineers to assess the feasibility of service migration beforehand.
S
L
O
T
1
S
S
T
1
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
L
O
T
1
S
S
T
1
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
L
O
T
1
7
S
L
O
T
1
8
S
L
O
T
1
7
S
L
O
T
1
8
S
S
N
1
P
E
G
8
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
---
-
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C
S
S
N
1
P
E
G
8
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
---
-
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C
S
S
N
1
P
E
G
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
S
N
1
P
E
G
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
L
O
T
1
7
S
L
O
T
1
8
S
L
O
T
1
7
S
L
O
T
1
8
S
L
O
T
2
6
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
---
-
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C
S
L
O
T
2
6
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
---
-
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C
Before migration, some services are configured on
the boards in slots 26 to 31.
The services are migrated to boards in slots
1 to 8 and slots 11 to 18.
LSP


Description
Migrate the services on the packet boards in slots 26 to 31 to the boards in slots 1 to 8 and
slots 11 to 18.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
14

Precautions
Services may be interrupted during inner-NE migration. To minimize the interruption time of
the services under migration, make the target ports ready and synchronize the DCN and clock
configuration of the source ports to the target ports before you perform service migration. To
prepare for a rollback in case of migration failure, back up the databases.
Procedure
Step 1 Synchronize the Layer 2 and Layer 3 attributes of the source ports to the target ports.
Step 2 Migrate services with the TCAT. (For details, see the help manual related to the TCAT.)
Step 3 Remove the source boards.
Step 4 Delete the logical boards of the source boards.
----End
Verification
For NNI ports, test the connectivity of MPLS tunnels using LSP Ping.
In NE Explorer, choose Configuration > Packet Configuration > MPLS Management >
Unicast Tunnel Management from the Function Tree. In the right pane, click OAM
Parameters. Right-click the migrated tunnels and choose Ping Test from the shortcut menu.
If the number of transmitted packets equals the number of received packets in a ping test, the
migration is successful.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
15

Check the test results.


2.6 Replacing the Cross-Connect Board on OptiX OSN
3500
Description
Replace the SSN2PSXCSA board on the OptiX OSN 3500 with the SSN3PSXCSA board.
S
L
O
T
1
S
S
N
2
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
N
2
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
G
S
C
C
G
S
C
C
S
L
O
T
1
S
S
N
2
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
N
3
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
G
S
C
C
G
S
C
C
S
L
O
T
1
S
S
N
3
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
N
3
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
G
S
C
C
G
S
C
C


OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
16

Precautions
Ensure that services are available during the replacement.
To help you understand the procedure, slot 9 is specified as active slot and slot 10 is specified
as standby slot. The board in slot 9 is the working board and the boards in slots 9 and 10 are
normal.
The board software version of the new cross-connect board should be V200R013C10SPC100.
If the board software version of the new cross-connect board is not V200R013C10SPC100,
update the board software version immediately after the board goes online.
Procedure
Step 1 Remove the SSN2PSXCSA board in slot 10.
Step 2 Delete the logical board SSN2PSXCSA in slot 10.
Step 3 Add a logical board SSN3PSXCSA in slot 10.
Step 4 Install an SSN3PSXCSA board in slot 10 and wait until the board goes online.
Step 5 Issue the active/standby switching command to the cross-connect boards.
Step 6 Remove the SSN2PSXCSA board in slot 9.
Step 7 Delete the logical board SSN2PSXCSA in slot 9.
Step 8 Add a logical board SSN3PSXCSA in slot 9.
Step 9 Install an SSN3PSXCSA board in slot 9 and wait until the board goes online.
----End
Verification
The active and standby cross-connect boards are online and in the normal state. There is no
alarm related to incorrect board types. Services are normal.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
17

2.7 OptiX OSN Replacing the Cross-Connect Board on
OptiX OSN 7500
Description
Replace the SST1PSXCSA board on the OptiX OSN 7500 with the SST2PSXCSA board.
S
L
O
T
1
S
S
T
1
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
1
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
L
O
T
1
7
S
L
O
T
1
8
S
L
O
T
1
S
S
T
1
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
2
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
L
O
T
1
7
S
L
O
T
1
8
S
L
O
T
1
S
S
T
2
P
S
X
C
S
A
S
L
O
T
2
S
L
O
T
3
S
L
O
T
4
S
L
O
T
5
S
L
O
T
6
S
L
O
T
7
S
L
O
T
8
S
S
T
2
P
S
X
C
S
A
S
L
O
T
1
1
S
L
O
T
1
2
S
L
O
T
1
3
S
L
O
T
1
4
S
L
O
T
1
5
S
L
O
T
1
6
S
L
O
T
1
7
S
L
O
T
1
8
S
L
O
T
2
6
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
----
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C
S
L
O
T
2
6
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
----
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C
S
L
O
T
2
6
S
L
O
T
2
7
S
L
O
T
2
8
S
L
O
T
2
9
S
L
O
T
3
0
S
L
O
T
3
1
S
L
O
T
1
9
S
L
O
T
2
0
S
L
O
T
2
1
S
L
O
T
2
2
S
L
O
T
2
3
P
I
U
A
----
P
I
U
B
S
L
O
T
3
4
S
L
O
T
3
5
S
L
O
T
3
6
S
L
O
T
3
7
S
L
O
T
3
8
G
S
C
C
G
S
C
C


Precautions
During the replacement, services are interrupted for 2.5 seconds. To help you understand the
procedure, slot 9 is specified as active slot and slot 10 is specified as standby slot. The board
in slot 9 is the working board and the boards in slots 9 and 10 are normal. The board software
version of the new cross-connect board should be V200R013C10SPC100. If the board
software version of the new cross-connect board is not V200R013C10SPC100, update the
board software version immediately after the board goes online.
Procedure
Step 1 Remove the SST1PSXCSA board in slot 10.
Step 2 Delete the logical board SST1PSXCSA in slot 10.
Step 3 Add a logical board SST2PSXCSA in slot 10.
Step 4 Install an SST2PSXCSA board in slot 10 and wait until the board goes online.
Step 5 Issue the active/standby switching command to the cross-connect boards. (Services are
interrupted for 2.5 seconds during the switching.)
Step 6 Remove the SST1PSXCSA board in slot 9.
Step 7 Delete the logical board SST1PSXCSA in slot 9.
Step 8 Add a logical board SST2PSXCSA in slot 9.
Step 9 Install an SST2PSXCSA board in slot 9 and wait until the board goes online.
----End
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
18

Verification
The active and standby cross-connect boards are online and in the normal state. There is no
alarm related to incorrect board types. Services are normal.
2.8 Switching to Dual-Stack OAM Mode
The switching to dual-stack OAM mode can be performed after the operations on software,
hardware, and services are completed. The switching duration varies depending on the
number of services and the maximum duration is ten minutes. The switching causes service
interruption of 12 seconds on the OptiX OSN 3500 and the OAM and APS alarms on the peer
NE of the OptiX OSN 7500/7500 II. The switching only enables the equipment to support
MPLS-TP and does not affect services.
Description
Switch the single-stack OAM mode to the dual-stack OAM mode on the OptiX OSN
3500/7500/7500 II.
Precautions
During the switching, do not make any configuration and ensure the power supply to the
equipment. If the equipment is powered off during the switching, you can return to the
pre-switching condition only by restoring the databases automatically backed up before the
switching.
The U2000 interface is locked during the switching. Do not configure the equipment using
other tools.
If the LSP/PW APS is configured, ensure that the involved services are running on the
working trails. Otherwise, these services may be interrupted for over 12 seconds.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
19

Procedure
Step 1 Check whether the services involved in LSP/PW APS are running on the working trails. In
NE Explorer, choose Configuration > Packet Configuration > APS Protection
Management from the Function Tree. Check whether the services involved in LSP/PW APS
are running on the working trails.


OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
20

Step 2 Choose Configuration > NE Batch Configuration > MPLS OAM Configuration from the
Main Menu.

Step 3 Select the desired NE and click Switch to Dual-Stack Mode (TMPLS+MPLS-TP). The
switching endures a maximum of ten minutes.

----End
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
21

Verification
The U2000 displays a successful switching message and no unexpected OAM alarm is
reported.
2.9 Switching to MPLS-TP OAM
To ensure that the OAM can work properly after the switching to MPLS-TP OAM, you need
to perform the switching on each node of the OAM-enabled line. Therefore, the switching
should be performed with the U2000 in end-to-end mode.
Description
Switch the TMPLS OAM to the MPLS-TP OAM.
Precautions
The OAM detection intervals supported by Y.1711 are not consistent with those supported by
Y.1731. When the system encounters the detection interval inconsistencies, related alarms are
reported and persist until the switching finishes. You can query the updates in detection
intervals on the U2000.
Detection
Interval
Supported by
Y.1711
Detection
Interval
Supported by
Y.1731

Detection
Interval
Supported by
Y.1731
Detection
Interval
Supported by
Y.1711
FFD 3.3 ms 3.33 ms

3.33 ms FFD 3.3 ms
FFD 10 ms 10 ms

10 ms FFD 10 ms
FFD 20 ms 10 ms

100 ms FFD 100 ms
FFD 50 ms 100 ms

1 s CV 1s
FFD 100 ms 100 ms

10 s CV 1s
FFD 200 ms 100 ms

1 min CV 1s
FFD 500 ms 1 s

10 min CV 1s
CV 1s 1 s


For the OptiX OSN 3500/7500/7500II in dual-stack mode, the number of supported
TMPLS-TP OAM specifications is different from the number of supported MPLS-TP OAM
specifications. To be specific, the OptiX OSN 3500/7500 supports 2k MPLS-TP OAM
specifications; the OptiX OSN 7500II supports 4k MPLS-OAM specifications, with slots 1 to
8 supporting a maximum of 2.5k and slots 11 to 18 supporting a maximum of 2.5k. Therefore,
the switching from TMPLS OAM to MPLS-TP OAM will fail if the number of supported
TMPLS-TP OAM specifications is larger than the number of supported MPLS-TP OAM
specifications.
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
22

Procedure
Step 1 In NE Explorer, choose Configuration > Packet Configuration > MPLS Management >
Unicast Tunnel Management from the Function Tree. Click Static Tunnel in the right pane.

OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
23

Step 2 Select the desired tunnel, right-click, and choose Switch to Y.1731 from the shortcut menu.

----End
OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
24

Verification
There is no alarm related to MPLS-TP tunnel OAM or MPLS-TP PW OAM. An LB test
initiated on the MEP is successful. In NE Explorer, choose Configuration > Packet
Configuration > MPLS Management > Unicast Tunnel Management from the Function
Tree. In the right pane, click MPLS-TP OAM. In the MEP tab page, select the desired tunnel,
right-click, and choose Start LB from the shortcut menu. If the LB response packets are
received correctly, the switching is successful.


OptiX OSN 3500&7500&7500 II
TMPLS to MPLS-TP Upgrade Guide 2 Upgrade Process Overview

Issue 01 (2014-04-11) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
25

Check the test results.