Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Contents
MATERIALS .............................................................................................................................................................. 2
3.1
3.2
4
5
CONCRETE ............................................................................................................................................................. 2
REINFORCING STEEL .............................................................................................................................................. 3
DURABILITY ............................................................................................................................................................. 3
ANALYSIS & VERIFICATION ............................................................................................................................... 3
5.1
5.2
5.3
5.4
ANALYSIS .............................................................................................................................................................. 3
LIMIT STATE VERIFICATION (DESIGN) .................................................................................................................... 3
THE FOLLOWING SECTIONS .................................................................................................................................... 3
FLOATING .............................................................................................................................................................. 3
GEOMETRY ............................................................................................................................................................ 4
ACTIONS ................................................................................................................................................................ 4
6.2.1
6.2.2
6.3
6.3.1
6.3.2
6.4
6.5
6.6.1
Walls ............................................................................................................................................................. 5
Slab ............................................................................................................................................................... 5
6.5.1
6.6
Introduction
The following structures are to be designed according to EC1992 part 1 and part 3.
Due to its functionality (liquid retaining structure) water tightness is of primary concern. On this report, a brief description is given of the considerations we have taken into account.
2.1
The requirements for this particular structure are outlined below. The structure is required to:
Action
Liquid (Waste water)
see 6.2.2
see 6.2.2
2.2
10~12kN/m3
see 6.2.2
Load Acting
Combination coefficients
2.3
Favourable
1.10
0.90
1.50
1.50
1.35
1.00
1.50
1.50
1.35
1.15
1.50
1.50
Name
Main combination
01ULS
Pressure on Ground
02ULS
1.5LLliq + 1.0DL
03ULS
1.5LLwp + 0.9DL
Materials
3.1
Concrete
The basic concrete strength class used for this structure is C30/37. The strength and deformation characteristics for concrete are taken by the following table
Concrete
C30/37
fck
fck,cube
fcm
MPa
MPa
MPa
MPa
MPa
MPa
GPa
30
37
38
2.9
3.8
33
c1
cu1
c2
cu2
2.2
3.5
3.5
3.2
Reinforcing steel
For the present calculation is made reference to reinforcement steel of class C according to Eurocode, with the mechanical and physical characteristics as per the following table.
Class
C
Es
200GPa
Durability
The elements of the structural system of building belong to the classes as shown on the table below. The covers are obtained for a structure with design working life of 50 years
Element
Slabs
Walls
Foundation mat
Str. Cls.
+/-
Struct. Cls.
+/-
S4
S4
XS2
S4
XS2
S4
Cover (mm)
cmin.dur
cnom =cmin+cdev
Str.
Cls.
S4
35
45
S4
S4
35
45
S4
S4
35
45
The Class designation is in accordance with EN 206-1, where XS2 refer to concrete surfaces subjected to long-term water
contact, parts of marine structures or subject to sea water
5
5.1
Etabs 9.2.01, was used to model and analyse the structure. A three dimensional space model was build and analysed using
finite element linear analysis with frame elements and shell elements.
Hand calculations were also done to verify the above finite element analysis.
5.2
The structure was verified/checked for both ULS and SLS limit state designs. SLS was found to be the governing limit
state on most of the elements due to the water tightness requirement.
5.3
The following sections deals with the limit state design (SLS or ULS) and detailing of each element of the structure.
Where workability is effecting the design of the structure, comments and recommendations are given accordingly.
5.4
Floating
The structure was checked for floating. Walls and slab thickness were adjusted accordingly to overcome any possible
floating. The total dead weight of the structure was found to be higher than the uplift from water.
Assumptions made:
Etabs is three-dimensional FE analysis software, mainly for building systems. Etabs is a registered trademark of
Computers and Structures Inc. www.csiberkeley.com
3
Ground water level is assumed to raise all the way to the top of the ground level
A safety factor of 1.1 is considered
Reinforced concrete unit weight is taken as 24kN/m3
Groundwater unit weight is taken as 10kN/m3
6.1
Geometry
Description / dimension
Length
Width
Planar area
Construction volume
92 and 112 m3
Note: there are two final settling tanks, and the figures given on the table above are only for one.
6.2
6.2.1
Actions
Properties and assumptions
Load cases
6.3
The design of the walls is SLS governed due to the water tightness requirement. Therefore the verification is done for the
SLS and checked for the ULS.
6.3.1
Walls
The most onerous case is the wall dividing the basin in two areas.
Moment at the intersection of the wall with the base of the basin goes up to 106kNm (serviceability un-factored). This
is the case when only one side of the basin is filled with water.
Considering the thickness of the wall 300mm, than the 106kNm flexure resistance for a 0.3mm flexure crack can be resisted by reinforcing with fi16/125mm (which resists 116kNm).
6.3.2
Slab
The most onerous case is the slab starting from greed line C up to Greed line D. Not only this part of the slab is the widest of all the sections but at this slab part the dead loads are at the maximum as well.
Several combinations were considered in obtaining the maximum moments on the slab and base of the structure. The
combination giving the highest flexural moment is shown below.
Considering combination of loads (1.35DL + 1.1Uplift Water Pressure) yields the following moments:
Figure 3: flexural moments on wall and slab
The reinforcement required to resist the ULS forces is much lower than then the reinforcement required to prevent cracking of the walls. Therefore the reinforcement provided is satisfactory for this as well.
6.4
Grit removal chamber is design as a liquid retaining structure, therefore a minimum crack width is considered according
to EN EC1992-3 (0.2mm for pure tension and 0.3mm for flexure)
6.5
6.5.1
Foundation
Differential settlement
The structure has a considerable length, therefore the potential for differential settlement is assessed and designed for,
especially at the point of join between the raft foundation and the pad foundations.
6.6
6.6.1
Base slab
External restrained cracking due to early thermal cracking
The slab is prone to early thermal cracking. It shrinks toward its center, and is restrained from external factors leading to
concrete cracking. By external factors is meant the friction of the slab base with the blinding layer. This friction however
can be eliminated by introducing a polymer sheet and fine finish blinding layer.
Wall and base construction joints are recommended to contain water-stops.
In order to eliminate early age thermal cracking for the slab base, it will have to be casted over a polymer layer over
which it can shrink freely unrestrained. Blinding has to be leveled and finely finished, so the layer of polymer can slide
on it when the slab will shrink, and therefore no cracks will form.