Está en la página 1de 10

www.ietdl.

org
Published in IET Generation, Transmission & Distribution Received on 18th January 2013 Revised on 6th April 2013 Accepted on 16th April 2013 doi: 10.1049/iet-gtd.2013.0031

ISSN 1751-8687

Comprehensive review of generation and transmission expansion planning


Reza Hemmati, Rahmat-Allah Hooshmand, Amin Khodabakhshian
Department of Electrical Engineering, University of Isfahan, Isfahan, Iran E-mail: reza.hematti@eng.ui.ac.ir

Abstract: Investment on generation system and transmission network is an important issue in power systems, and investment reversibility closely depends on performing an optimal planning. In this regard, generation expansion planning (GEP) and transmission expansion planning (TEP) have been presented by researchers to manage an optimal planning on generation and transmission systems. In recent years, a large number of research works have been carried out on GEP and TEP. These problems have been investigated with different views, methods, constraints and objectives. The evaluation of researches in these elds and categorising their different aspects are necessary to manage further works. This study presents a comprehensive review of GEP and TEP problems from different aspects and views such as modelling, solving methods, reliability, distributed generation, electricity market, uncertainties, line congestion, reactive power planning, demand-side management and so on. The review results provide a comprehensive background to nd out further ideas in these elds.

Introduction

Generally electric power system expansion can be carried out in generation, transmission and distribution sectors. However, since the investment on generation expansion planning (GEP) and transmission expansion planning (TEP) is much more than distribution part and also from the view of stability and reliability, these two parts have more priority for power system engineers. GEP, which is related to the investment on energy production, has always attracted great attention for investors and consumers. The investment planning should consider different aspects of problems, such as sizing, timing, technology of new generation units, investment reversibility, risks and uncertainties to guarantee the prot in this sector and the consumers satisfaction. A classical planning which has been used by researchers for managing the above issues is called GEP problem. In GEP, the objective is to expand the existing power system to serve the growing demand in the future by satisfying the reliability criteria. The GEP determines size, place, technology and the time of installing new plants to satisfy forecasted load within the given reliability criteria over a planning horizon of typically 1030 years. The other important part of long-term planning is TEP. The main objective of TEP is to dene when, where and how many new lines (and substations) should be installed in the electrical network to ensure an adequate level of energy supply to customers, taking into account the load growth and forecasted demand, reliability criterion and new generator capacities, while minimising investment, operation and interruption costs.
IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

TEP and GEP have been widely investigated and analysed from different views and aspects such as: (a) solving method, (b) reliability, (c) electricity market, (d) uncertainty, (e) environmental impact, (f) considering distributed generation (DG), (g) the view of time horizon, (h) modelling, (i) line congestion, (j) reactive power planning, (k) exible AC transmission system (FACTS) devices and (l) demand-side management (DSM). Some of the above issues are considered in both GEP and TEP such as (a) to (e), some are only considered in TEP such as (f) to (k) and some are only dened in GEP such as (l). The proposed issues are reviewed in this paper and their advantages and disadvantages will be studied and compared. Although the reviews of TEP and GEP have already been investigated in [1, 2] and [3, 4], respectively, the current paper is more comprehensive and complete. There are different subjects that either have not been investigated by these references or have been reviewed very briey, while these issues will be thoroughly reviewed in this paper. The issues are TEP modelling such as AC and DC modelling with their advantages and disadvantages, the effect of the line congestion on TEP, uncertainty in TEPGEP and the effect of the environmental emissions on TEPGEP. Also, there are some new issues which have been discussed in recent years such as the effect of DGs on TEP, the application of FACTS devices in TEP and coordinated TEPGEP. These subjects have not been investigated in the above-mentioned papers, while this paper presents a comprehensive review of these issues by also studying their different aspects. It is worth mentioning that for reviewing articles, there are many different criteria for choosing references such as the

& The Institution of Engineering and Technology 2013

955

www.ietdl.org
year of publication, journal and conference categories, the subject and novelty of papers and so on. In this paper, the review is managed based on the subject and novelty of papers. Then, the papers were categorised and managed based on their subjects such as modelling, solving methods, reliability, electricity market, uncertainties and so on. the same time. Thus, in GEP and TEP a multi-objective optimisation problem, which cannot be solved effectively by traditional planning methods, should be used. In this regard, two main mathematical and meta-heuristic optimisation methods have been used to solve the proposed multi-objective optimisation problems. These methods are reviewed in detail in the following subsections. 3.1 From the view of the mathematical modelling, both TEP and GEP can be considered as a large-scale highly constrained mixed-integer non-linear programming and generally contain two parts of objective function and constraints. The exibility of problem is changed by considering different objective functions and constraints. The objective function is mainly dened for costs, such as the costs of new technologies, new lines, reliability, electricity market and so on. The constraints can also be categorised into two sections: mandatory and optional constraints. Mandatory constraints such as load and reliability satisfaction and the limits of transmission lines must be considered in the planning; but the optional constraints such as environmental constraint can be excluded. The optional constraints are used in order to obtain more exibility. As mentioned before, some aspects of planning are mandatory and some others are optional. In this paper, the aspects of planning are reviewed based on the subject and novelty, not based on the mandatory and optional issues. Thus, the paper does not separate the aspects of planning based on mandatory and optional issues and all subjects associated with TEPGEP are presented in separate sections. In this regard, it is worth mentioning that some researches have been carried out without considering reliability and security in the planning. However, considering reliability leads to a exible and reliable planning and is a mandatory issue from the view of many researchers. From another view, in regulated power systems, the objective of GEP and/or TEP is to minimise the cost, but in the deregulated power systems the objective is to maximise the prot for each participant (generation company (GENCO) or transmission company (TRANSCO)). Therefore the GEP and TEP problems in the regulated power systems are modelled as (1), while they are modelled as (2) in deregulated power systems. Min Cost subject to Mandatory constraints and / or Optional constraints (1) Max Profit subject to Mandatory constraints and / or Optional constraints (2) TEP solving methods

TEP and GEP formulation overview


The most popular mathematical and new meta-heuristic optimisation methods that have been used by researchers to solve TEP problem are as follows: 3.1.1 Mathematical optimisation methods: These include linear programming [57], non-linear programming [8, 9], mixed integer programming [10], benders decomposition [1114], branch-bound method [1517], game theory [18, 19], heuristic algorithm based on sensitivity index [20, 21], hierarchical decomposition [22] and dynamic programming [23]. Meta-heuristic optimisation methods: These include ant colony [24], articial immune system [25], articial neural networks [26], bee algorithm [27], Chaos [28], differential evolution [29, 30], expert system [31], frog leaping algorithm [32], fuzzy [33], genetic algorithms (GA) [34 38], decimal-coded GA [39, 40], real-coded GA [41], hybrid GA with fuzzy [42], non-dominated sorting GA [43, 44], greedy randomised search [45], harmony search [46], particle swarm optimisation (PSO) [47, 48], search-based algorithm (grid search algorithm) [49], simulated annealing [50] and tabu search [51, 52]. 3.2 GEP solving methods

The application of mathematical and meta-heuristic methods has been widely investigated in GEP as follows: 3.2.1 Mathematical optimisation methods: These are analytic hierarchy approach [53, 54], network ow programming [55], decision tree [56, 57], dynamic programming [58, 59], game theory [19], iterative algorithm [60], mixed integer programming [6163], linear programming [64] and benders decomposition [65]. 3.2.2 Meta-heuristic optimisation methods: These include evolutionary programming [66], evolutionary strategy [66], ant colony optimisation [66], tabu search [66], simulated annealing [67], shufed frog leaping algorithm [68], GA and game theory [69], GA and bender decomposition [65], GA [69, 70], honey bee algorithm [71], articial immune system [72], inverse optimisation and bi-level optimisation [73], PSO [74, 75] and expert system and fuzzy [76, 77]. 3.3 Advantages and disadvantages of methods

Solving methods

The planning objectives are mainly in conict with each other and this is an important challenge in GEP and TEP. In traditional planning, the objective is to minimise mainly the investment cost; but, in advanced planning, different objectives are carried out. The proposed objectives are even in conict with each other and they cannot be satised at
956 & The Institution of Engineering and Technology 2013

The advantages and disadvantages of mathematical and meta-heuristic methods given in different papers are now reviewed as follows: 3.3.1 Advantages of mathematical methods: 1. The optimal solution is usually accurate and the solving time is low. 2. A suitable convergence is obtained.
IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

www.ietdl.org
3.3.2 Disadvantages of mathematical methods: 1. Managing power system equations into an optimisation programming model is difcult. 2. To insert a new constraint, the model should be rearranged and new equations should be included. 3. The static studies can only be carried out and dynamical studies such as stability analysis cannot be performed. 3.3.3 Advantages of heuristic methods: 1. These methods are easy to use and very straightforward. 2. In these methods, it is not required to convert power system model to an optimisation programming set. The power system analysis (such as power ow or stability analysis) can be carried out in a power system analyser package (such as DigSILENT power factory) and then the output responses are fed into optimisation method. 3. Implementing these methods is easy and dynamical studies can be carried out. 3.3.4 Disadvantages of heuristic methods: 1. The optimal solution is associated with approximations and simulation time is usually high. 2. It is possible to fall into local minima instead of global minima. 3. The possibility of the divergence is more than the mathematical methods. 4.2 Reliability in GEP In GEP, reliability has been investigated with different forms such as a constraint [6569, 83] or a part of objective function [70]. An index is generally considered for constraint, such as LOLP [68, 71, 72, 74], EENS [68, 72] and LOLE [69, 75, 84, 85]. In some researches [56, 70] the reliability is considered as a part of objective function in order to maximise the reliability index or minimising the outage cost.

Deregulated electricity market

Along with the development of the deregulation of electric power system, GEP and TEP have been changed and their methodologies are recongured. In the regulated systems, the planning aims are at minimising cost, but in the deregulated power systems, each participant tries to maximise its own benet. TEP and GEP in the deregulated markets have been investigated from different views, as discussed in the next subsections. 5.1 TEP in deregulated electricity market

Reliability

The reasonability of a typical power system planning is evaluated in two macro and micro stages. In macro stage the planning from the view of the strategic policy is studied, and it includes adequacy, security and reliability analyses. However, in micro stage the planning from the view of engineering feasibility is examined, and it consists of technical analysis such as fault and stability analyses. In conventional power systems planning the reliability and adequacy analyses are carried out before stability and fault analyses [15]. Thus, reliability evaluation should be incorporated in any long-term planning such as GEP and TEP; otherwise, there is no guarantee of having a trustworthy supply for demands. An expanded plan should satisfy reliability criterion and ensures the reliability requirements. In GEP and TEP problems, reliability has been investigated with different forms. The reliability of the system can include a constraint or a part of objective function. The most commonly reliability indexes such as loss of load expectation (LOLE), energy expected not supplied (EENS), loss of load probability (LOLP) and loss of load cost (LOLC) are used to assess the system reliability. 4.1 Reliability in TEP

In deregulated environment, transmission lines have attracted more attention from the view of stockholders, participants, independent system operator (ISO) and customers [86, 87]. Traditional TEP is no longer viable in a restructured power system. An optimal TEP scheme in this new environment requires new methods and tools. In regulated electricity markets, the objective is to minimise the investment costs of new transmission lines, subject to operational constraints such as demand satisfaction. However, in deregulated electricity markets, the main objective of TEP is to provide a non-discriminatory and competitive environment for all stakeholders by considering power system reliability. TEP problem in traditional systems has a vertical order; but in deregulated electricity market, the order is not vertical and feedback signals are introduced [87]. In deregulated environments, TEP problem has been investigated with different viewpoints such as considering nodal prices [78], load curtailment cost [5], transmission congestion cost [11, 43, 44, 86], social welfare [17, 88] and minimising market risk [89]. Also, the TEP problem has been reported in an imperfect deregulated market in which only the generator sector is deregulated [49]. In [90] TEP is presented in European market, with the allocation of the nancial transmission right to investors. TEP problem in a pool market which aims to select the most effective subset of lines has been reported in [91], and TEP problem considering the demand response in deregulated market is reported in [92]. 5.2 GEP in deregulated electricity market

TEP has been investigated with the consideration of different reliability indexes such as the LOLE [78], hierarchical reliability assessment [79], LOLC [24], EENS [30] and the reliability improvement index [80]. Also, the security can be included in TEP problem. The security analysis is to ensure the performance requirements under one contingency. N 1 contingency [13, 15, 81] and deliberate outages [82] are often used as constraints in TEP problem.
IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

As mentioned before, the main purpose of GEP in deregulated market is to maximise the revenue of generation companies (GENCOs), while the purpose of GEP in regulated system is to minimise the cost. In deregulated power systems, each GENCO tries to maximise their own revenue while satisfying the independent system operator (ISO) criteria such as reliability, reserve margin and load satisfaction [93]. Electricity market in GEP problem has been widely investigated. In electricity market, the GEP scheme is mainly presented in pool market, where GEP is divided into two programming levels: master and slave. In the master level, a game theory is proposed to evaluate the contrast of

& The Institution of Engineering and Technology 2013

957

www.ietdl.org
GENCOs by ISO and in the slave level, the best solution of each GENCO for decision making of investment is obtained [59, 69, 75, 85]. A model for maximising the expected revenues of a generation company has been presented in [84]. This model aims at maximising the expected revenues of GENCOs while ensuring the safe operation of the power system. In [19, 84], a Cournot model is used to simulate the expansion strategies of generation and transmission enterprises, and the equilibrium is obtained by using the mixed complementarily approach. Another important tool for modelling uncertainty in TEP problem is to use the fuzzy method and fuzzy decision systems. In this regard, the application of fuzzy method in TEP problem has been investigated in [1, 33, 42, 105]. 6.2 Uncertainty in GEP

Uncertainty

The uncertainties always exist and cannot be excluded from power system. Thus, power system uncertainties should be incorporated in any power system planning such as TEP and GEP. Considering uncertainties leads to a robust planning that can satisfy different conditions. Different types of uncertainties have been investigated in GEP and TEP. 6.1 Uncertainty in TEP

GEP problem has been widely investigated, with the consideration of uncertainty in regulated and deregulated market. In [84] some common uncertainties have been considered in GEP, such as price volatility, reliability of generation units, demand evolution, investment and operation costs. The other types of uncertainty such as fuel prices, investment and maintenance costs and electricity price have been considered in GEP by [85]. Dual uncertainty in objective function and constraint has also been presented in GEP [60]. In GEP problem, the commonly used method to deal with uncertainties is MCS method [84]. As mentioned in the previous section, fuzzy method can also be used to deal with the system uncertainties. In this regard, the application of fuzzy method in GEP problem has been investigated in [60, 76].

TEP problem is commonly associated with different uncertainties such as price, power system modelling, input data, load and so on. Also, the uncertainty in deregulated market is more than the regulated electricity markets, because in regulated markets, the planner can obtain all information of the system; but in the deregulated environment, some information about generation, transmission and distribution companies are condential and cannot be obtained by the planner. Some generic uncertainties are as follows: 1. Load and price forecast uncertainty [12, 30, 36, 9498] 2. Availability of power system components [12] 3. Uncertainties due to simplication in modelling and simulation [30] 4. Market uncertainties [36, 9497], energy and its risk [94], fuel availability and cost [96] 5. New technologies of generation such as wind farms and photovoltaic units [99102] 6. Government and political policies [9497] and environmental aspects and their cost [103]. The researchers have shown that considering uncertainty leads to a better and robust TEP. In this regard, a comparison between deterministic and stochastic models in TEP has been reported in [104]. This paper shows that the TEP plans which consider uncertainty perform better than plans with deterministic models. With regard to the proposed uncertainties, TEP is often faced with the risk. Thus, new methods should be incorporated to deal with uncertainties. The most commonly used methods to deal with uncertainties are: 1. Mathematicalstatistical model [30, 99] 2. Monte-Carlo simulation (MCS) [12, 36, 94, 95, 98]. Mathematical method uses probabilistic models for considering uncertainty. But, MCS is a numerical method based on the iterations. Mathematical method takes less computation time, but MCS is easy to be implemented. Both methods have been widely used to deal with uncertainties in TEP problem [98, 99].
958 & The Institution of Engineering and Technology 2013

Environmental impacts

Nowadays, environmental emissions such as carbon, oxide nitrogen and natural gases are limited based on the regulation of environmental protection agency (EPA). The planners are encouraged to install renewable energies instead of conventional energies such as oil. In this regard, the effect of renewable energies and emission on the GEP and TEP has been thoroughly investigated. 7.1 TEP and environmental impacts

Midwest independent transmission system operator (MISO) has reported a transmission expansion plan [103] in which an environmental impact analysis in TEP planning has been considered and the environmental impacts are analysed based on the EPA regulations. 7.2 GEP and environmental impacts and emissions The generation technologies produce environmental emissions and the amount of emission depends on the type of technology. The modern technologies such as nuclear and wind do not produce emission while the old technologies such as gas-turbine and coal-turbine units produce a large amount of air pollutions such as CO2, SO2 and NOx. These air pollutions should be considered in GEP planning in order to reduce their amounts. In all countries, there are some regulations to limit the air pollutions and generally, the EPA has some policies to limit the emissions. The emissions have been considered in GEP problem from different aspects. Some researchers have considered the pollutions as a constraint in their programming [65] and some others have dened a cost for emission and have included it in objective function [60, 62, 64, 106108]. In [109], the impact of some of incentive systems (namely feed-in tariffs, quota obligation, emission trade and carbon tax) on generation planning has been considered and a GEP model with a modied objective function and additional constraints has been presented. Also, in order to reduce the
IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

www.ietdl.org
emission, the renewable energies such as wind have been broadly considered in GEP [102, 106, 110]. 6. Reliability indexes can be consideration of reactive power. 10.3 AC model disadvantages calculated with the

TEP with consideration of DG

The classical centralised generation model is faced with several problems such as high cost, long transmission system, environmental effects, risk and reliability and power losses. In order to solve this drawback, DG systems, which are usually installed near the load centre, are increasingly being used. This property of DG leads to have less power transmission, less losses, less cost and more reliability. However, the penetration of DG will cause signicant changes in the power system, and also it deeply inuences the TEP. For example, DG affects on local demands and changes local marginal prices (LMPs) in electricity market, or changes power losses in transmission lines. Therefore, it is required to consider the effect of DG on TEP problem [111]. The application of DG in practical TEP problems has been investigated in Australia [112] and in UK [113].

1. AC model leads to a large and complex non-linear programming problem. 2. An efcient optimisation technique is required to solve the AC model. 3. AC model handles disconnected systems, a common situation in the initial phase of transmission planning, when generators and loads have not yet been electrically connected to the network.

11

TEP associated with line congestion

TEP from the view of time horizon

From the view of time horizon, TEP problem is classied as static and dynamic planning. In static planning, time horizon is not considered and the optimal plan is determined for a single year. In other words, it is assumed that all new lines should be installed in the rst year of the planning horizon. But, in dynamic planning, the years of horizon are separately studied and new lines for each year are denoted. In fact, it is assumed that each new line should be installed in its relative year of planning horizon. It seems that the dynamic planning leads to a better and cheaper planning, but it is very complex and time-consuming [1].

10

TEP from the view of modelling

There are two general modelling for TEP problem, which are AC model [58, 1520, 22, 23, 3540, 42, 4548, 78, 8689, 91, 92, 9497, 99, 104] and DC model [9, 1114, 21, 24, 26, 2834, 41, 43, 44, 4951, 79, 81, 90, 98, 114, 115]. AC model is a complete and practical one, but it is complex. DC model is simple, but it contains simplications. The advantages and disadvantages of these models can be concluded as follows: 10.1 DC model disadvantages

In the deregulated electricity market, transmission congestion is an important issue that needs to be incorporated in power system operation and network expansion planning. TEP associated with transmission congestion is handled with different objectives that should be considered; such as the operation cost due to congestion [11], the available transfer capability [13], transmission surplus capacity [28] and transmission line loading [48]. Congestion management has also been investigated in a practical case study [90]. In this paper, a trilateral market coupling arrangement among the Netherlands, Belgium and France is investigated. The proposed trilateral market can also be coupled to the other Europes national power markets. In the proposed merchant framework, the system operator allocates nancial transmission rights to investors in transmission expansion based upon their preferences and revenue adequacy. The ISO preserves some proxy nancial transmission rights to manage potential negative externalities that may result from expansion projects. This paper shows that the proposed scheme could help European market in coupling arrangements to attract additional investment. A method for enhancing transmission system capability and having the congestion alleviated using TEP has been reported in [115]. Generally, congestion studies are associated with TEP problem and researchers are interested in this topic [8688, 98, 111].

12 TEP associated with reactive power planning


In practical power systems, the reactive loads are supplied by generators. In this case, the reactive power is transferred through transmission lines and transferring such an amount of reactive power may reduce the available transfer capability and this leads to build more new transmission lines. By allocating locally reactive sources close to the loads, it is possible to supply reactive demands and the capacity of transmission lines is thereby increased and also the power losses are reduced. Therefore TEP problem should be associated with reactive power planning and otherwise, the TEP leads to build more new lines [41, 78].

1. In DC modelling, the reactive power cannot be incorporated. 2. The resulted plan from DC model should be reinforced when the AC operation is considered. 3. It is difcult to consider power losses in DC model. 10.2 AC model advantages

1. Considering reactive power in planning. 2. Reactive power planning can be associated with TEP to achieve less new lines. 3. Power losses can be completely included. 4. The other components such as FACTS devices can be included. 5. The other types of studies such as voltage stability can be carried out.
IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

13

TEP with FACTS devices

In TEP problem, network expansion is typically made by adding new transmission lines. Installing new lines

& The Institution of Engineering and Technology 2013

959

www.ietdl.org
increases the transmission system capacity. However, FACTS devices can also increase the transmission system capacity [116] and can be used instead of installing new lines. This issue has been investigated in [117, 118]. of implementation and operation of the used DSM option, including lost revenues as an operational cost. The results in [63] show that considering DSM leads to a better planning with lower cost.

14

GEP with DSM

15

Coordinated TEP and GEP

DSM is a management system in electricity markets that helps the system operator to improve the performance of a system. The DSM programs are usually performed by low level cost, but they have a positive effect on the system performance. DSM programs mainly reduce the operational cost in power systems and considering these programs in GEP problem may lead to a exible programming with optimal results. In [63], the DSM has been considered in GEP. In this paper, the peak clipping is given as a demand-side option in the planning process. The model takes into account the full cost
Table 1 Outline study of researches in TEP problem
Ref. no. Solving method Mathematical [5] [6] [8] [9] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [24] [26] [27] [28] [29] [30] [32] [33] [34] [35] [36] [37] [38] [39] [40] [41] [42] [43] [44] [46] [47] [48] [49] [50] [78] [79] [90] [91] [92] [97] [98] [104] [111] [114] [115] Heuristic Electricity market Uncertainty

In real-power systems, the generation and transmission sectors are not apart from each other. In this regard, transmission expansion planning can be performed associated with GEP. This coordinated TEP and GEP has recently attracted more attention. Many investigations have been carried out to perform coordinated TEP and GEP [12, 14, 18, 49, 79, 81]. The coordinated GEP and TEP have been investigated under both regulated [79] and deregulated [12, 14] electricity markets. In electricity market, coordinated TEPGEP is carried out under ISO supervision. At rst, GENCOs and TRANSCOs

Reliability/ Security

Transmission congestion

Reactive power planning -

DG

Modelling AC DC

960 & The Institution of Engineering and Technology 2013

IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

www.ietdl.org
Table 2 Outline study of researches in GEP problem
Ref. No Solving method Mathematical [53] [56] [57] [58] [59] [60] [61] [62] [63] [64] [65] [66] [67] [68] [69] [70] [71] [72] [73] [74] [75] [76] [84] [85] Heuristic Electricity market Uncertainty Reliability/Security Emission Demand-side management

provide capacity investment decisions to the ISO for approval. GENCOs and TRANSCOs investment decisions are based on individual prot maximisation while considering their respective constraints. The ISO aggregates resource planning proposals and checks the security of transmission network. If the transmission network security is not met, the ISO provides GENCOs and TRANSCOs with capacity signals that represent the added value of generating units or transmission capacity for security. If the transmission network security is met, the ISO calculates LMPs and ow-gate marginal prices based on the proposed investment plan. Accordingly, the projected price signals are provided by the ISO to GENCOs and TRANSCOs for capacity investment planning. The revised optimal transmission and generation capacity planning decisions are submitted iteratively by GENCOs and TRANSCOs to the ISO and the iterative process will continue until a solution is reached for satisfying the stopping criterion. If a cycling pattern emerges during the solution process, the ISO may stop the coordination process and make a nal decision based on pre-specied market rules [14].

published papers were evaluated and investigated. The proposed cited papers showed that GEP and TEP problems should be carried out to satisfy demand and reliability in the future. Besides, in order to achieve a better and exible planning, the problems should be associated with different factors such as uncertainty, market concepts, congestion management, reactive power planning, distributed generation and reliability. However, there is not a unique methodology for GEP and TEP planning and it differs from one system to another. The study of GEP and TEP problems in this paper opens the door for further works in this eld. In general, the GEP and TEP models developed so far have one or more of the following drawbacks: 1. DG has not been properly studied. Application of DG in TEP problem is a new issue and has not been widely considered by researchers. The results of researches show that the application of DG in planning leads to an optimal planning and reducing cost. This issue has been studied in recent years and it can be analysed from different views and aspects in new research works. 2. Reactive power planning has not been thoroughly studied. Reactive power planning is an important issue for considering in TEP and GEP problem. This issue has rarely been investigated by researchers and can be concluded in new research works. Combination of reactive power planning with GEP may lead to a more optimal planning and has not been investigated so far. 3. Uncertainties associated with new generation technologies such as wind farms and photovoltaic have not been properly investigated. In this regard, it is necessary to consider the uncertainties of wind and photovoltaic as probability distribution functions in planning and inserting the uncertainty by using numerical tools such as MCS. 4. Hydro power stations and related effects have not been properly included. Considering the uncertainty and details of hydro power stations such as water limitations leads to a non-linear planning. This issue can be considered as a new research work in this eld.

16

Comparison of researches

Tables 1 and 2 show the outline reviews of the cited papers in TEP and GEP problems. The papers are evaluated from different aspects and a complete comparison is carried out. In TEP problem, the researchers have focused on the market type, uncertainty, reliability and congestion. It seems that the most favourite aspect of TEP problem is to study TEP in a deregulated electricity market considering reliability. Also, it is seen that in GEP problem, the reliability and emission have been considered in planning.

17

Conclusions

In this paper, GEP and TEP problems were reviewed by considering different aspects and views. The recently
IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

& The Institution of Engineering and Technology 2013

961

www.ietdl.org
5. Coordinated TEP and GEP have attracted limited attentions. This issue has been investigated in recent years and many aspects of this problem have not been investigated so far. In this regard, many issues such as coordinated TEPGEP associated with reactive power planning, considering different reliability criteria in coordinated TEPGEP and so on, can be viewed as new works. 6. Considering FACTS devices in TEP has not been properly investigated. Therefore, considering the series-type FACTS devices such as TCSC, SSSC, UPFC and IPFC in TEP problem can be investigated and studied. 7. GEP problem is mainly investigated based on single nodal model which is an unreal model. Since in this model the transmission network is not considered, it is assumed that all generation units and loads are installed on a single bus. Therefore, GEP with the consideration of transmission network is closer to practice. In this regard, a security constrained GEP problem can be investigated. 8. Considering demand-side programs such as DSM and interruptible loads can greatly affect the result of planning. This issue has not been adequately investigated in TEP and GEP. 9. With increasing micro-grids in power systems, it is necessary to study GEP and TEP with the consideration of micro-grids in the future.
17 planning using a transportation model, IEE Gener. Transm. Distrib., 2000, 147, (3), pp. 149156 Garcs, L.P., Conejo, A.J., Garca-Bertrand, R., Romero, R.: A bilevel approach to transmission expansion planning within a market environment, IEEE Trans. Power Syst., 2009, 24, (3), pp. 15131522 Hariyanto, N., Nurdin, M., Haroen, Y., Machbub, C.: Decentralized and simultaneous generation and transmission expansion planning through cooperative game theory, Int. J. Electr. Eng. Inf., 2009, 1, (2), pp. 149164 Xiaotong, L., Yimei, L., Xiaoli, Z., Ming, Z.: Generation and transmission expansion planning based on game theory in power engineering, Syst. Eng. Proc., 2012, 4, pp. 7986 Rider, M.J., Garcia, A.V., Romero, R.: Power system transmission network expansion planning using AC model, IET Gener. Transm. Distrib., 2007, 1, (5), pp. 731742 Bustamante-Cedeo, E., Arora, S.: Multi-step simultaneous changes constructive heuristic algorithm for transmission network expansion planning, Electr. Power Syst. Res., 2009, 79, (4), pp. 586594 Romero, R., Monticelli, A.: A hierarchical decomposition approach for transmission network expansion planning, IEEE Trans. Power Syst., 1994, 9, (1), pp. 373380 Dusonchet, Y.P., El-Abiad, A.: Transmission planning using discrete dynamic optimizing, IEEE Trans. Power Appar. Syst., 1973, 92, (4), pp. 13581371 Leite Da Silva, A.M., Rezende, L.S., Da Fonseca Manso, L.A., De Resende, L.C.: Reliability worth applied to transmission expansion planning based on ant colony system, Int. J. Electr. Power Energy Syst., 2010, 32, (10), pp. 10771084 Rezende, L., Leite Da Silva, A., De Mello Honrio, L.: Articial immune system applied to the multi-stage transmission expansion planning. 8th Int. Conf. Articial Immune System (ICARIS07), 2009, pp. 178191 Al-Saba, T., El-Amin, I.: The application of articial intelligent tools to the transmission expansion problem, Electr. Power Syst. Res., 2002, 62, (2), pp. 117126 Kuo, T., Ming, Z., Fan, Y., Na, L.: Chance constrained transmission system expansion planning method based on chaos quantum honey bee algorithm. Power and Energy Engineering Conf. (APPEEC), 2010 Asia-Pacic, 2010, pp. 15 Qu, G., Cheng, H., Yao, L., Ma, Z., Zhu, Z.: Transmission surplus capacity based power transmission expansion planning, Electr. Power Syst. Res., 2010, 80, (1), pp. 1927 Georgilakis, P.S.: Market-based transmission expansion planning by improved differential evolution, Int. J. Electr. Power Energy Syst., 2010, 32, (5), pp. 450456 Zhao, J.H., Dong, Z.Y., Lindsay, P., Wong, K.P.: Flexible transmission expansion planning with uncertainties in an electricity market, IEEE Trans. Power Syst., 2009, 24, (1), pp. 479488 Nasser, F., Silva, A., Araujo, L., Schwabe, D., Pereira, M.V.F., Monticelli, A.: Development of an expert system for long-term planning of power transmission networks. Proc. Second Symp. Experts System Application Power System, 1989, pp. 237242 Eghbal, M., Saha, T.K., Hasan, K.N.: Transmission expansion planning by meta-heuristic techniques: a comparison of shufed frog leaping algorithm, PSO and GA. 2011 IEEE Power and Energy Society General Meeting, 2011, pp. 18 Silva Sousa, A., Asada, E.N.: Combined heuristic with fuzzy system to transmission system expansion planning, Electr. Power Syst. Res., 2011, 81, (1), pp. 123128 Jalilzadeh, S., Kazemi, A., Shayeghi, H., Madavi, M.: Technical and economic evaluation of voltage level in transmission network expansion planning using GA, Energy Convers. Manage., 2008, 49, (5), pp. 11191125 Cadini, F., Zio, E., Petrescu, C.A.: Optimal expansion of an existing electrical power transmission network by multi-objective genetic algorithms, Reliab. Eng. Syst. Safety, 2010, 95, (3), pp. 173181 Yang, N., Wen, F.: A chance constrained programming approach to transmission system expansion planning, Electr. Power Syst. Res., 2005, 75, (2), pp. 171177 Youssef, H.K.M.: Dynamic transmission planning using a constrained genetic algorithm, Int. J. Electr. Power Energy Syst., 2001, 23, (8), pp. 857862 Gil, H., Da Silva, E.L.: A reliable approach for solving the transmission network expansion planning problem using genetic algorithms, Electr. Power Syst. Res., 2001, 58, (1), pp. 4551 Mahdavi, M., Shayeghi, H., Kazemi, A.: DCGA based evaluating role of bundle lines in TNEP considering expansion of substations from voltage level point of view, Energy Convers. Manage., 2009, 50, (8), pp. 20672073 IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

18

19

20

21

22

23

24

25

18

References

26

1 Latorre, G., Cruz, R.D., Areiza, J.M., Villegas, A.: Classication of publications and models on transmission expansion planning, IEEE Trans. Power Syst., 2003, 18, (2), pp. 938946 2 Lee, C.N., Simon, K., Zhong, J., Wu, F.F.: Transmission expansion planning from past to future. IEEE Power Systems Conf. and Exposition, PSCE06, 2006, pp. 257265 3 Jia, D.X., Cheng, H.Z.: Review of generation expansion planning in market environment, Proc. Chin. Soc. Univ. Electr. Power Syst. Autom., 2007, 19, (5), pp. 5865 4 Zhu, J., Chow, M.Y.: A review of emerging techniques on generation expansion planning, IEEE Trans. Power Syst., 1997, 12, (4), pp. 17221728 5 Leou, R.C.: A multi-year transmission planning under a deregulated market, Int. J. Electr. Power Energy Syst., 2011, 33, (3), pp. 708714 6 Alguacil, N., Motto, A.L., Conejo, A.J.: Transmission expansion planning: a mixed-integer LP approach, IEEE Trans. Power Syst., 2003, 18, (3), pp. 10701077 7 Villasana, R., Garver, L.L., Salon, S.J.: Transmission network planning using linear programming, IEEE Trans. Power Appar. Syst., 1985, 104, (2), pp. 349356 8 Youssef, H.K., Hackam, R.: New transmission planning model, IEEE Trans. Power Syst., 1989, 4, (1), pp. 918 9 Al-Hamouz, Z.M., Al-Faraj, A.S.: Transmission-expansion planning based on a non-linear programming algorithm, Appl. Energy, 2003, 76, (1), pp. 169177 10 Bahiense, L., Oliveira, G.C., Pereira, M., Granville, S.: A mixed integer disjunctive model for transmission network expansion, IEEE Trans. Power Syst., 2001, 16, (3), pp. 560565 11 Tor, O.B., Guven, A.N., Shahidehpour, M.: Congestion-driven transmission planning considering the impact of generator expansion, IEEE Trans. Power Syst., 2008, 23, (2), pp. 781789 12 Roh, J.H., Shahidehpour, M., Wu, L.: Market-based generation and transmission planning with uncertainties, IEEE Trans. Power Syst., 2009, 24, (3), pp. 15871598 13 Akbari, T., Rahimikian, A., Kazemi, A.: A multi-stage stochastic transmission expansion planning method, Energy Convers. Manage., 2011, 52, (8), pp. 28442853 14 Roh, J.H., Shahidehpour, M., Fu, Y.: Market-based coordination of transmission and generation capacity planning, IEEE Trans. Power Syst., 2007, 22, (4), pp. 14061419 15 Choi, J., Mount, T.D., Thomas, R.J.: Transmission expansion planning using contingency criteria, IEEE Trans. Power Syst., 2007, 22, (4), pp. 22492261 16 Haffner, S., Monticelli, A., Garcia, A., Mantovani, J., Romero, R.: Branch and bound algorithm for transmission system expansion 962 & The Institution of Engineering and Technology 2013

27

28

29

30

31

32

33

34

35

36

37

38

39

www.ietdl.org
40 Shayeghi, H., Jalilzadeh, S., Mahdavi, M., Hadadian, H.: Studying inuence of two effective parameters on network losses in transmission expansion planning using DCGA, Energy Convers. Manage., 2008, 49, (11), pp. 30173024 41 Rahmani, M., Rashidinejad, M., Carreno, E.m., Romero, R.: Efcient method for AC transmission network expansion planning, Electr. Power Syst. Res., 2010, 80, (9), pp. 10561064 42 Chung, T.S., Li, K.K., Chen, G.J., Xie, J.D., Tang, G.Q.: Multi-objective transmission network planning by a hybrid GA approach with fuzzy decision analysis, Int. J. Electr. Power Energy Syst., 2003, 25, (3), pp. 187192 43 Foroud, A.A., Abdoos, A.A., Keypour, R., Amirahmadi, M.: A multi-objective framework for dynamic transmission expansion planning in competitive electricity market, Int. J. Electr. Power Energy Syst., 2010, 32, (8), pp. 861872 44 Maghouli, P., Hosseini, S.H., Buygi, M.O., Shahidehpour, M.: A multi-objective framework for transmission expansion planning in deregulated environments, IEEE Trans. Power Syst., 2009, 24, (2), pp. 10511061 45 Binato, S., De Oliveira, G.C., De Arajo, J.L.: A greedy randomized adaptive search procedure for transmission expansion planning, IEEE Trans. Power Syst., 2001, 16, (2), pp. 247253 46 Verma, A., Panigrahi, B.K., Bijwe, P.R.: Harmony search algorithm for transmission network expansion planning, IET Gener. Transm. Distrib., 2010, 4, (6), pp. 663673 47 Yi-Xiong, J., Hao-Zhong, C., Jian-Yong, Y., Zhang, L.: New discrete method for particle swarm optimization and its application in transmission network expansion planning, Electr. Power Syst. Res., 2007, 77, (34), pp. 227233 48 Shayeghi, H., Mahdavi, M., Bagheri, A.: Discrete PSO algorithm based optimization of transmission lines loading in TNEP problem, Energy Convers. Manage., 2010, 51, (1), pp. 112121 49 Motamedi, A., Zareipour, H., Buygi, M.O., Rosehart, W.D.: A transmission planning framework considering future generation expansions in electricity markets, IEEE Trans. Power Syst., 2010, 25, (4), pp. 19871995 50 Cortes-Carmona, M., Palma-Behnke, R., Moya, O.: Transmission network expansion planning by a hybrid simulated annealing algorithm. 15th Int. Conf. Intelligent System Applications to Power Systems, 2009. ISAP09, 2009, pp. 17 51 Sadegheih, A., Drake, P.R.: System network planning expansion using mathematical programming, genetic algorithms and tabu search, Energy Convers. Manage., 2008, 49, (6), pp. 15571566 52 Wen, F., Chang, C.S.: Transmission network optimal planning using the tabu search method, Electr. Power Syst. Res., 1997, 42, (2), pp. 153163 53 Meza, J.L.C., Yildirim, M.B., Masud, A.S.M.: A model for the multiperiod multiobjective power generation expansion problem, IEEE Trans. Power Syst., 2007, 22, (2), pp. 871878 54 Clarke, R.R.: Choosing an integrated resource plan for electric utilities: an analytic hierarchy approach. Proc. 31st Intersociety Energy Conversion Engineering Conf., 1996. IECEC96, 1996, pp. 15921597 55 Li, C., Jap, P.J., Streiffert, D.L.: Implementation of network ow programming to the hydrothermal coordination in an energy management system, IEEE Trans. Power Syst., 1993, 8, (3), pp. 10451053 56 Farghal, S., El-Dewieny, R.M., Roshdy Abdel Aziz, M.: Generation expansion planning using the decision tree technique, Electr. Power Syst. Res., 1987, 13, (1), pp. 5970 57 Ryan, Y.F.S.M.: Scenario construction and reduction applied to stochastic power generation expansion planning, Comput. Oper. Res., 2013, 40, (1), pp. 923 58 Karaki, S.H., Chaaban, F.B., Al-Nakhl, N., Tarhini, K.A.: Power generation expansion planning with environmental consideration for Lebanon, Int. J. Electr. Power Energy Syst., 2002, 24, (8), pp. 611619 59 Moghaddas, T.S.M., Saliminia Lahiji, A., Aghaei, J., Rabiee, A.: Reliable generation expansion planning in pool market considering power system security, Energy Convers. Manage., 2012, 54, (1), pp. 162168 60 Hu, Q., Huang, G., Cai, Y., Huang, Y.: Feasibility-based inexact fuzzy programming for electric power generation systems planning under dual uncertainties, Appl. Energy, 2011, 88, (12), pp. 46424654 61 Bakirtzis, G.A., Biskas, P.N., Chatziathanasiou, V.: Generation expansion planning by MILP considering mid-term scheduling decisions, Electr. Power Syst. Res., 2012, 86, (1), pp. 98112 62 Tekiner, H., Coit, D.W., Felder, F.A.: Multi-period multi-objective electricity generation expansion planning problem with Monte-Carlo simulation, Electr. Power Syst. Res., 2010, 80, (12), pp. 13941405 IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031 63 Antunes, C.H., Martins, A.G., Brito, I.S.: A multiple objective mixed integer linear programming model for power generation expansion planning, Energy, 2004, 29, (4), pp. 613627 64 Delgado, F., Ortiz, A., Renedo, C.J., Prez, S., Maana, M., Zobaa, A. F.: The inuence of nuclear generation on CO2 emissions and on the cost of the Spanish system in long-term generation planning, Int. J. Electr. Power Energy Syst., 2011, 33, (3), pp. 673683 65 Sirikum, J., Techanitisawad, A., Kachitvichyanukul, V.: A new efcient GA-benders decomposition method: for power generation expansion planning with emission controls, IEEE Trans. Power Syst., 2007, 22, (3), pp. 10921100 66 Kannan, S., Slochanal, S.M.R., Padhy, N.P.: Application and comparison of metaheuristic techniques to generation expansion planning problem, IEEE Trans. Power Syst., 2005, 20, (1), pp. 466475 67 Yildirim, M., Erkan, K., Ozturk, S.: Power generation expansion planning with adaptive simulated annealing genetic algorithm, Int. J. Energy Res., 2006, 30, (14), pp. 11881199 68 Jadidoleslam, M., Bijami, E., Amiri, N., Ebrahimi, A., Askari, J.: Application of shufed frog leaping algorithm to long term generation expansion planning. Proc. Int. Conf. Electrical Energy and Networks (ICEEN), 2011, pp. 16 69 Shayanfar, H., Lahiji, A.S., Aghaei, J., Rabiee, A.: Generation expansion planning in pool market: a hybrid modied game theory and improved genetic algorithm, Energy Convers. Manage., 2009, 50, (5), pp. 11491156 70 Murugan, P., Kannan, S., Baskar, S.: NSGA-II algorithm for multi-objective generation expansion planning problem, Electr. Power Syst. Res., 2009, 79, (4), pp. 622628 71 Hejrati, Z., Hejrati, E., Taheri, A.: Optimization generation expansion planning by HBMO, Optimization, 2012, 37, (7), pp. 99108 72 Chen, S.L., Zhan, T.S., Tsay, M.T.: Generation expansion planning of the utility with rened immune algorithm, Electr. Power Syst. Res., 2006, 76, (4), pp. 251258 73 Zhou, Y., Wang, L., Mccalley, J.D.: Designing effective and efcient incentive policies for renewable energy in generation expansion planning, Appl. Energy, 2011, 88, (6), pp. 22012209 74 Kannan, S., Slochanal, S., Subbaraj, P., Padhy, N.P.: Application of particle swarm optimization technique and its variants to generation expansion planning problem, Electr. Power Syst. Res., 2004, 70, (3), pp. 203210 75 Moghddas-Tafreshi, S.M., Shayanfar, H.A., Saliminia Lahiji, A., Rabiee, A., Aghaei, J.: Generation expansion planning in Pool market: a hybrid modied game theory and particle swarm optimization, Energy Convers. Manage., 2011, 52, (2), pp. 15121519 76 Su, C.T., Lii, G.R., Chen, J.J.: Long-term generation expansion planning employing dynamic programming and fuzzy techniques. Proc. IEEE Int. Conf. Industrial Technology, 2000, pp. 644649 77 David, A.K., Zhao, R.D.: Integrating expert systems with dynamic programming in generation expansion planning, IEEE Trans. Power Syst., 1989, 4, (3), pp. 10951101 78 Hooshmand, R.A., Hemmati, R., Parastegari, M.: Combination of AC transmission expansion planning and reactive power planning in the restructured power system, Energy Convers. Manage., 2012, 55, pp. 2635 79 Alizadeh, B., Jadid, S.: Reliability constrained coordination of generation and transmission expansion planning in power systems using mixed integer programming, IET Gener. Transm. Distrib., 2011, 5, (9), pp. 948960 80 Chanda, R.S., Bhattacharjee, P.K.: A reliability approach to transmission expansion planning using fuzzy fault-tree model, Electr. Power Syst. Res., 1998, 45, (2), pp. 101108 81 Samarakoon, H., Shrestha, R.M., Fujiwara, O.: A mixed integer linear programming model for transmission expansion planning with generation location selection, Int. J. Electr. Power Energy Syst., 2001, 23, (4), pp. 285293 82 Alguacil, N., Carrin, M., Arroyo, J.M.: Transmission network expansion planning under deliberate outages, Int. J. Electr. Power Energy Syst., 2009, 31, (9), pp. 553561 83 Dhanalakshmi, S., Baskar, S., Kannan, S., Mahadevan, K.: Generation scheduling problem by intelligent genetic algorithm, Comput. Electr. Eng., 2013, 39, (1), pp. 7988 84 Pereira, A.J.C., Saraiva, J.T.: A decision support system for generation expansion planning in competitive electricity markets, Electr. Power Syst. Res., 2010, 80, (7), pp. 778787 85 Pereira, A.J.C., Saraiva, J.T.: Generation expansion planning (GEP) a long-term approach using system dynamics and genetic algorithms (GAs), Energy, 2011, 36, (8), pp. 51805199 963

& The Institution of Engineering and Technology 2013

www.ietdl.org
86 Aguado, J.A., De La Torre, S., Contreras, J., Conejo, A.J., Martnez, A.: Market-driven dynamic transmission expansion planning, Electr. Power Syst. Res., 2012, 82, (1), pp. 8894 87 Xu, Z., Dong, Z., Wong, K.P.: Transmission planning in a deregulated environment, IEE Gener. Transm. Distrib., 2006, 153, (3), pp. 326334 88 De La Torre, S., Conejo, A.J., Contreras, J.: Transmission expansion planning in electricity markets, IEEE Trans. Power Syst., 2008, 23, (1), pp. 238248 89 Rodriguez, R.D., Latorre-Bayona, G.: HIPER: interactive tool for mid-term transmission expansion planning in a deregulated environment, IEEE Power Eng. Rev., 2000, 20, (11), pp. 6162 90 Kristiansen, T., Roselln, J.: Merchant electricity transmission expansion: a European case study, Energy, 2010, 35, (10), pp. 41074115 91 Lu, W., Bompard, E., Napoli, R., Jiang, X.: Heuristic procedures for transmission planning in competitive electricity markets, Electr. Power Syst. Res., 2007, 77, (10), pp. 13371348 92 Kazerooni, A.k., Mutale, J.: Transmission network planning under a price based demand response program. 2010 IEEE PES Transmission and Distribution Conf. and Exposition, 2010, pp. 17 93 Cerda, P., Larrain, M., Rudnick, H.: Identication of generation expansion plans in competitive markets, IEEE Latin Am. Trans., (Revista IEEE America Latina), 2011, 9, (5), pp. 774784 94 Buygi, M.O., Shanechi, H.M., Balzer, G., Shahidehpour, M., Pariz, N.: Network planning in unbundled power systems, IEEE Trans. Power Syst., 2006, 21, (3), pp. 13791387 95 Buygi, M.O., Balzer, G., Shanechi, H.M., Shahidehpour, M.: Market-based transmission expansion planning, IEEE Trans. Power Syst., 2004, 19, (4), pp. 20602067 96 Linares, P.: Multiple criteria decision making and risk analysis as risk management tools for power systems planning, IEEE Trans. Power Syst., 2002, 17, (3), pp. 895900 97 Fang, R., Hill, D.J.: A new strategy for transmission expansion in competitive electricity markets, IEEE Trans. Power Syst., 2003, 18, (1), pp. 374380 98 Akbari, T., Heidarizadeh, M., Siab, M.A., Abroshan, M.: Towards integrated planning: Simultaneous transmission and substation expansion planning, Electr. Power Syst. Res., 2012, 86, (0), pp. 131139 99 Yu, H., Chung, C.y., Wong, K.p., Zhang, J.h.: A chance constrained transmission network expansion planning method with consideration of load and wind farm uncertainties, IEEE Trans. Power Syst., 2009, 24, (3), pp. 15681576 100 Moeini-Aghtaie, M., Abbaspour, A., Fotuhi-Firuzabad, M.: Incorporating large-scale distant wind farms in probabilistic transmission expansion planningPart I: theory and algorithm, IEEE Trans. Power Syst., 2012, 27, (3), pp. 15851593 101 Moeini-Aghtaie, M., Abbaspour, A., Fotuhi-Firuzabad, M.: Incorporating large-scale distant wind farms in probabilistic transmission expansion planningPart II: case studies, IEEE Trans. Power Syst., 2012, 27, (3), pp. 15941601 102 Gu, Y., Mccalley, J.D., Ni, M.: Coordinating large-scale wind integration and transmission planning, IEEE Trans. Sust. Energy, 2011, 3, (4), pp. 652659 103 Midwest ISO Transmission Expansion Plan 2011, 2011, Midewest ISO 104 Cedeo, E.B., Arora, S.: Performance comparison of Transmission Network Expansion Planning under deterministic and uncertain conditions, Int. J. Electr. Power Energy Syst., 2011, 33, (7), pp. 12881295 105 Braga, A.S.D., Saraiva, J.T.: A multiyear dynamic approach for transmission expansion planning and long-term marginal costs computation, IEEE Trans. Power Syst., 2005, 20, (3), pp. 16311639 106 Alishahi, E., Moghaddam, M.P., Sheikh-El-Eslami, M.K.: A system dynamics approach for investigating impacts of incentive mechanisms on wind power investment, Renew. Energy, 2012, 37, (1), pp. 310317 107 Santisirisomboon, J., Limmeechokchai, B., Chungpaibulpatana, S.: Impacts of biomass power generation and CO2 taxation on electricity generation expansion planning and environmental emissions, Energy Policy, 2001, 29, (12), pp. 975985 108 Chen, Q., Kang, C., Xia, Q., Zhong, J.: Power generation expansion planning model towards low-carbon economy and its application in China, IEEE Trans. Power Syst., 2010, 25, (2), pp. 11171125 109 Careri, F., Genesi, C., Marannino, P., Montagna, M., Rossi, S., Siviero, I.: Generation expansion planning in the age of Green Economy, IEEE Trans. Power Syst., 2011, 26, (4), pp. 22142223 110 Farghal, S., Abdel Aziz, M.r.: Generation expansion planning including the renewable energy sources, IEEE Trans. Power Syst., 1988, 3, (3), pp. 816822 111 Zhao, J.H., Foster, J., Dong, Z.Y., Wong, K.P.: Flexible transmission network planning considering distributed generation impacts, IEEE Trans. Power Syst., 2011, 26, (3), pp. 14341443 112 Zhao, J., Foster, J.: Investigating the impacts of distributed generation on transmission expansion cost: an Australian case study, Energy Econom. Manage. Group Working Pap., 2010, 2, pp. 108115 113 Strbac, G., Ramsay, C., Pudjianto, D.: Integration of distributed generation into the UK power system. Summary report, DTI Centre for Distributed Generation and Sustainable Electrical Energy, 2007, pp. 6674 114 Padiyar, K.R., Shanbhag, R.S.: Comparison of methods for transmission system expansion using network ow and DC load ow models, Int. J. Electr. Power Energy Syst., 1988, 10, (1), pp. 1724 115 Wang, Y., Cheng, H., Wang, C., et al.: Pareto optimality-based multi-objective transmission planning considering transmission congestion, Electr. Power Syst. Res., 2008, 78, (9), pp. 16191626 116 Hooshmand, R.-A., Banejad, M., Isazadeh, G.: Management of power ow of transmission lines in disturbed conditions using UPFC. Australian Universities Power Engineering Conf., Australia, 2007, pp. 3341 117 Blanco, G.A., Olsina, F.G., Ojeda, O.A., Garcs, F.F.: Transmission expansion planning under uncertainty: the role of FACTS in providing strategic exibility. 2009 IEEE PowerTech, Bucharest, 2009, pp. 18 118 Blanco, G.A.: Optimal transmission expansion planning with FACTS, in Electrical Engineering (National University of San Juan, Argentina, 2010)

964 & The Institution of Engineering and Technology 2013

IET Gener. Transm. Distrib., 2013, Vol. 7, Iss. 9, pp. 955964 doi: 10.1049/iet-gtd.2013.0031

También podría gustarte