Network Engineering

Technical Standards Information Session


November / December 2001

Dene Ward, Gavin Jackson, Joe Frazzetto, Steve Neave

Technical Standards Group

Network Engineering

Purpose of Today
Raise awareness of recent developments in Powercor technical standards
general overview details are in the standards (see the Intranet/Internet) varied audience (high/medium/low users of the standards)

Advise of upcoming changes and initiatives Seek feedback on effectiveness of standards


Technical Standards Group

Network Engineering

Agenda
Introduction Technical Standards changes
New Standards Recent Revisions and Updates Work in Progress Upcoming initiatives

Product show and tell Software Demo Feedback Questionnaire


Technical Standards Group

Network Engineering

Powercor Policy
Where a Powercor Technical Standard exists, it shall be used in lieu of the superseded VESI standard
PCA staff, Contractors, Trainers and Auditors

Material/plant to be used on the Network must be approved and used as defined in the standards
if it is not specified in the standards, it is not approved auditing will identify non-compliance and replacement /rework will be required

Impacts
More reliable, safe, legally compliant and cost effective solutions
Technical Standards Group

Network Engineering

Recent Initiatives
VESI Standards are on the Intranet Work instructions, product brochures and user manuals Powervision information video Use of training CDs Approved materials list on the Internet
high risk areas eg : U/G, P/L, LAs, Insuls, Tx

Non-compliance memos
Technical Standards Group

Network Engineering

Upcoming Initiatives (2002)


Dist. Automation (ACRs, Gas Switches, Regs, etc) Line capacitors Non-conductive pole structures
alt. to wood pole alt. crossarms

Transformers

TT type Rodgers connected

Domestic solar cells connections Fusing


group and/or fuseless

Pole footing redesign Smart Design Conductor guidelines


revised ratings based on localised conditions

Pole rebutting O/H Switch location guidelines Innovations via Eighthgate ETSA technical alignment

2002 Themes : Smart Design and Compliance


Technical Standards Group

Network Engineering

Audit / Compliance Issues


Use of Q lugs & M5DRs Incorrect earthing of crossarms (wood poles) Preformed ties Pit Connectors
Crossarm

Surface logs and bedlogs


Technical Standards Group

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

DC021 - Design Heights & Circuit Separations (Ready Reckoner)


Provides conductor heights above ground for LVABC and 22kV at poles Heights for 12.5, 14, 15.5 & 17m poles Provides circuit separations for a range of wood structures

DC - Clearances

DC141, DC151 & DC201 - Updated to include 66kV clearance information (EK - Subtransmission)

Technical Standards Group

Network Engineering

DE - Connectors
Updated to include connectors for underground applications, including new link standard (DE206) Bonding standard updated (DE303):
Removed bonding on pole-top for intermediate wood pole structures Include additional bonding in some cases in coastal & polluted applications
Technical Standards Group

Network Engineering

DG - Earthing
DG111 - New earthing installation standard for ACRs DG301 - Updated CMEN standard for LVABC DG211 - Kiosk Earthing Assembly
Completion by December 2001 Based on 3.5m x 3.5m reserve for front access kiosks

Earthing standards (part 2 ) - information & installation standards to be completed in 2002


Marker tape requirements - OCEI
Technical Standards Group

Network Engineering

DG - Earthing
Software Example - An Earthing Analysis via MATLAB

Earthing design software to be investigated


EPRI Distribution Engineering Workstation CYME International Power Systems Software plus many others 1 = 2301 ohm/m

Voltage

2 = 344 ohm/m

Depth Below Gnd (m)


Technical Standards Group

Network Engineering

Recently introduced a new HV fuse - S&C Fault Tamer (FT)


improve reliability/ avoid spurious fuse operations and hang-ups FT cost effectiveness compared to Boric Acid Regional training on these items conducted in April/May
Technical Standards Group

DP - Overcurrent Protection (revisit)

Network Engineering

Install Fault Tamers in lieu of BA and PF fuses for all new installations 20A
Selection information in DP011

DP - Overcurrent Protection (revisit) cont..

FTs weight is comparable to BA and less than a PF Reporting of maloperation to the hotline
9683 4151 (24hr)
Technical Standards Group

Network Engineering

New cable head pole arrangement introduced to reduce potential for animal induced flashovers on cable head pole structures (DQ201): Phase-phase flashover - increase phasephase clearance via re-designed bracket
400mm 550mm 750mm (arrester-arrester)
Technical Standards Group

DQ - Overvoltage Protection

Network Engineering

Phase-ground flashover - bushing boot to cover live copper connection bus


Boot is fully insulated & UV stabilised Still provide flag-bolts for operational purposes (not protrude far enough to be a bird perch)
Technical Standards Group

DQ - Overvoltage Protection cont..

750mm

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

DD-Drafting Standard
LV Reticulation Plans - Substation Circuits (DD091) and Town Plans (DD095)
interim standard until GIS takes over

DD041 - Construction Plans DRPs


Changes made to typical new pole description
Old Description HV TERM (EJ152AFAAE) New Description HV TERM (EJ152)S(ST)2.6/125

DD021 - Standard Sheets (templates)


New standards templates are being developed Version controlled and referenced to DD021 ensures uniform and up-to-date information, dwg layout, symbols, drawing approvals etc
Technical Standards Group

Network Engineering

Field Construction Manual


Proposed to issue every 6 month or as required Issue to field personnel only
1 per truck contains construction info only Office staff refer to the Intranet (up to date information)

Old version to be recycled locally Colour coded cover (latest colour is green) Issue number has been included Updates to be inserted into pocket at the back Next issue approx. April 2002

Technical Standards Group

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

EB - Poles
New high-strength wood pole specifically for 66kV construction only (17m/20kN)
Introduced to reduce the amount of stayed poles in 66kV construction Cost analysis completed (versus staying) Standard 12kN footing - concrete and log, but increased setting depth of 3.4m (standard 17m setting depth is 2.5m) Minimum pole diameter @ ground line - 445mm Approximate weight - 2200kg
Technical Standards Group

Network Engineering

EC - Conductors
Removed fixed MES sag and tension tables
EC211 to EC441 Now use variable MES with StringEx

New stringing tension for 66kV construction (EC255) with 19/4.75 AAC
Standard stringing for 19/4.75 AAC Introduced to provide longer spans than EC251 and greater unstayed angles than EC261

Technical Standards Group

Network Engineering

EC - Conductors cont..
New stringing tension (EC255) with 19/4.75 AAC cont.
Cost analysis completed (versus EC251 and EC261), identified 10% cost saving on hypothetical 50km line Based on maximum tension (18% of CBL) before requiring vibration dampers Nominal MES is 95m, maximum MES is 130m May also be used at 22kV StringEx to be updated with EC255
Technical Standards Group

Network Engineering

EE - Crossarms
New intermediate crossarms for 66kV construction
Reduction in weight and cost S(IN)2.6-66 - 100 x 100 x 4 SHS, 32kg S(IN)3.2-66 - 100 x 100 x 4 SHS, 39kg

Use existing VESI strain crossarms for 66kV construction


Technical analysis indicated no benefit in calculated range of new strain crossarms (same sections and length required as SL series)
Technical Standards Group

Network Engineering

EE - Crossarms cont..
New strain crossarm selection charts
19/4.75, 37/3.75 SL series & S(ST) series

Technical Standards Group

Network Engineering

Insulator procurement process

EF - Insulators & Attachments

New contract awaiting CEO signoff 6 month to 16 week initial delivery lead times many new items to be introduced

New 66kV cycloaliphatic post insulators


50% lighter than porcelain Passed 5000hr weatherometer test Tie-top and horizontal clamp-top

Technical Standards Group

Network Engineering

New 66kV strain insulators

EF - Insulators & Attachments cont..

Cost competitive to 2 x 33kV units Multiple suppliers

New 2-disc equivalent 22kV strain insulators


Specifically for maintenance applications

22kV post insulator with integral stud included as a standard item

Technical Standards Group

Network Engineering

EG - Stays & Anchors


New 66kV stay arrangement
2 x GY4 stay insulators connected in series Meets mechanical & electrical performance to ESAA HBC(b)-1 Significantly cheaper than specific 66kV strain long-rod type insulators
Helical Splice

Approx. 2000mm
Technical Standards Group

Network Engineering

New 20m stay coils in SAP

EG - Stays & Anchors cont..

Reduced weight and less potential for waste MI # 351971 Provided in 80% of installations (No 5, 15.5m pole and below) 56m coils still available for longer stay installations

SC/AC stay wire and fittings removed from store


Field confusion (left-hand lay)
Technical Standards Group

Network Engineering

Break

Technical Standards Group

Network Engineering

EK - Subtransmission
Standard structures for 66kV construction
Vertical Insulators

Bridging Bracket

66kV Strain Insulators

Steel Crossarms

Centre- Bracket

Strain
Technical Standards Group

Intermediate

Network Engineering

Poletop Centre-Phase (Intermediate/Angle)


EK - Subtransmission cont..
New design (not 22kV) Mech. tested to 11kN 100 x 100 x 4 SHS Weight - 32kg Bracket Integral M24 nut for insulator mounting

M20 Bolt M24 Kingbolt

Technical Standards Group

Network Engineering

Poletop Bridging (Strain)

EK - Subtransmission cont..

Use 22kV pole top centrephase bracket Two additional holes to mount for bridging
Bracket M12 Bolt M12 x130 Coachscrew
Technical Standards Group

Network Engineering

Horizontal Bridging (66kV and 22kV)


To replace current 22kV arrangement impractical
Bracket

EK - Subtransmission cont..

M24 Welded Nut M16 x 130 Coachscrew

Technical Standards Group

Network Engineering

Update existing effected standards


EK - Subtransmission cont..
EE - Crossarms (new intermediate) EF - Insulators & Attachments (post and strain) EG - Stays & Anchors (new stay arrangement) EB - Poles (new 17m/20kN wood poles) EC - Conductors (new chart - EC255) EJ - Three-Phase Structures (new subsidiary standards)

Target date for release of EK and other existing standards is end Dec
Technical Standards Group

Network Engineering

EA - General Overhead
Raiser bracket design for low conductors
Spreadsheet (EA141 HVRaiser) for determining maximum spans and angles Wood pole 1-phase and 3-phase applications (with or without LV subsidiary)

Technical Standards Group

Network Engineering

EH, EI, EJ - Structures


EJ051, EI051 Design Schedules
Schedules created for single circuit angles & strain structures for
Three phase with 19/3.25 AAC, 3/2.75 Steel & 6/4.757/1.60 ACSR Single phase with 3/2.75 Steel

Technical Standards Group

Network Engineering

EJ401 - Three Phase Raiser Bracket


avoid pole replacements used for wood poles only

EH,EI,EJ - Structures Cont.


Cost effective means of obtaining -Gnd and Cct-Cct clearances Limits calculated via EA141 HVRaiser.XLS spreadsheet
Copies of spreadsheet available from local Design Champions EA141 provides information on use of the spreadsheet

EJ to be amended to include subsidiary const for use with 66kV standards (EK)
Technical Standards Group

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

EL- Transformers
EL101, EL201 - Wood & Concrete Transformer Structures
Split into Single Phase and Three Phase transformer structures EL101, EL201 - Single Phase\SWER transformers EL103, EL203 - Three Phase transformers

Technical Standards Group

Network Engineering

EL- Transformers
EL101, EL201, EL103, EL201, EL301
Include option of ordering LV fuse and mounts Fusing size based on transformer fusing tables (DP021)

Transformer pole loading limits under review by external consultant.


weight limits for transformer / pole combinations
Imperial (A and B) and CCA treated poles Completion by May 2002

Technical Standards Group

Network Engineering

EM- Switches, Fuse Mounts & Isolators


EM191 - Three Phase HV Isolator Assembly
Updated to include 30deg mounting of isolators for use on ACR structures

EM195 - SWER HV Isolator Pole Mount Assembly (WIP)


Mounts single insulator isolator onto pole mount fuse bracket via 135deg conversion bracket (SAP ID# 351882)
Technical Standards Group

Network Engineering

New approved ground mounted design formulated (dwg PCA 17/000001 and PCA 17/000003)
Compatible with 2x1, 3x1 or 1x3 units Allows upgrades from 3MVA (100A) to 10+MVA Operator, maintenance staff and public safety Whole of life costing showed minimal difference Eliminates ESNA Regs clearance issues (highlighted in recent OCEI audit) Currently the only approved design in Powercor
Technical Standards Group

EP - Regulators

Network Engineering

EP - Regulators
Future directions.....
Develop pole mounted 100A solution Investigate alternate regulator makes Investigate in-line ground mounted solution Remote control Develop a comprehensive technical standard
information and installation sections approved products in SAP task lists

Technical Standards Group

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

ER - ACRs, Sectionalisers & Fault Indicators Scope


To develop a Powercor standard that details the approved application, design & construction practices relating to ACRs, Sectionalisers & Fault Indicators. In doing so, opportunities were explored to:
Meet or improve current H&S standards Meet new ESNA regulations Improve customer service through improved system reliability and Achieve cost savings where appropriate

Technical Standards Group

Network Engineering

ER - ACRs
Three Phase ACRs
Standard structures ER101 - Rural (high current, high fault level) - 3 sets of isols ER111 - Rural (low current, low fault level) - 1 set of isols ER121 - Urban - 2 sets of isols

All 3 phase ACRs are remote controlled


Technical Standards Group

Network Engineering

Three Phase ACRs

ER - ACRs cont..

Keep by-pass options for access, testing and H&S reasons esp. in rural areas Nulec - CAPM 2 (CAPM 4 by December)
Cooper ACRs very expensive due to exchange rate CAPM 4 provides more protection options

Technical Standards Group

Network Engineering

ER - Sectionalisers
To be used as part of Network Reliability solution Cost effective method to isolate section of lines
where a new ACR is not financially viable where coordination of fuses and ACR/CBs is difficult avoids spurious operation that can occur with fuses

Technical Standards Group

Network Engineering

ER - Sectionalisers cont..
Utilises mechanical drop out mechanism
avoids incorrect operation found in chemical actuated styles of sectionalisers reset by pushing in lever (No spare actuators needed)

2 types with selectable ratings and no of counts of:


8A to 24A, 40A to 112A 1, 2 or 3 counts to drop out

Technical Standards Group

Network Engineering

ER - Fault Indicators
ER031 - Info Section
Provides guidelines on selection, location, and settings FIs are not for co-gen or 66kV ring lines. Overhead
Pole mount - 22kV single cct (Clean) pole only
Earth, LV, CATV catenaries, other HV circuits provide alternate fault path and may trigger pole mount units

Conductor mount types to avoid these problems


Technical Standards Group

Network Engineering

ER - Fault Indicators cont..


ER031 - Info Section cont. Site selection guidelines
Most effective locations (approx every 500 customers) OR Within 30min (effective) patrol time
Line length patrolled in this time (varies depending on terrain, traffic) Urban (15km), Rural roadside (30km) and Rural difficult (8km) And where combination of distance with No of Customers affected >200

Technical Standards Group

Network Engineering

ER - Fault Indicators cont..


Overhead (ER301, ER311)
Pole mount (SAP ID# 351761)
Clean pole only

Conductor mount (SAP ID# 351831) Flite 110 or Nortroll 110E


Programmable for di of 6A, 12A, 24A, or 60A Selection based on either:
Set di > Capacitive feed back current (approx 1A per km of HV u/g) Set di to approx. min ACR or CB trip rating or EOL fault level (on fused spurs)

Thus, correct operation relies on correct settings


Technical Standards Group

Network Engineering

ER - Fault Indicators cont..


U/G (ER321) 400A
35mm2, 95mm2

600A
185mm2, 240mm2

Very cost effective option (approx $70 each) Use on all outgoing switched HV at kiosks
Technical Standards Group

Network Engineering

ER - Summary & Implications of New Equipment Introduced


ACRs
Nulec ACR (used previously). CAPM 4 will be new control card. Three structures to choose from depending on use

Sectionalisers
New single phase drop out style - mechanical lever Two ratings which are field setable Ratings to be shown in SAP, GIS and on System plans

Fault Indicators
Overhead indicators have limited battery life. All FIs to be in SAP, GIS and on System Plans
Technical Standards Group

Network Engineering

ACRs

ER - Future Investigations

Revisit alternate ACRs & Controllers


alternate communications medium required such as GSM

Sectionalisers
Review other products

Fault Indicators
Review need for SCADA connection as part of Comms and Control strategy Review application of directional fault indicators (approx. $4000 each)

Technical Standards Group

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

F- Public Lighting
Standard to be completed approx. end of Dec 2001 Standard outline:
FA - General Information FB - Poles FC - Cable FE - Brackets & Stays FL - Lanterns FM - Electrical Connections, Fusing & Control FY - General Materials

Technical Standards Group

Network Engineering

F- Public Lighting cont..


FA - General Information and FL - Lanterns currently Work in Progress
New Australian Standards (AS1158 series) required the creation of new spacing tables based on
Cat P - Pedestrian Lighting
Cat P4 used in URD areas and P5 used for areas within o/h LV pole areas

Cat V - Vehicle Lighting

Public lighting equipment reviewed and new tenders in place by Dec 2001 Metal Halides to be reviewed in 2002 Powercor design via software (Perfect Lite) or spacing tables to Council requirements
Technical Standards Group

Network Engineering

ES- Bare LV Structures


ES411 - Multiple In Span Servicing
Used to solve service wire ground clearance or property crossing problems
more cost effective than u/g or service pole option

Catenary supported of up to 4 services Maximum of 70m LV Bare span and 35m service Future review of single in span service via spreader rods to be investigated in 2002
Problem - Long services tend to twist spreader rod and LV and cause uplift/potential failure on LV insulators and reduces clearances

Technical Standards Group

Network Engineering

ES- Bare LV Structures cont..


ES131 - Double strain crossarm installation standard to be developed in 2002
Also update EE Crossarms

In-Span Servicing example

Technical Standards Group

Network Engineering

ET- LV ABC Mains & Services


ET411 - Multiple In Span Servicing
Catenary supported of upto 4 services Maximum of 70m LV ABC span and 35m service span length

ET421 - Single Service Span, In Span Servicing


Direct from LV ABC 20m max service span length

Technical Standards Group

Network Engineering

ET- LV ABC Mains & Services cont..


ET061 - Updated to include information on selection of in span servicing LV Raiser Bracket innovation - to be developed in 2002 to address low services
Attaches to LV crossarms

Technical Standards Group

Network Engineering

EV- Animal Mitigation


Consultant engaged to complete standard by June 2002 Materials to be investigated in Dec 2001
Vinny bushing covers - under trial in Port Fairy ABB Rulle Tape Raychem fuse mount covers (alternative to the Pheonix covers) Salisbury conductor cover (alternative to Pheonix covers) and other products
Technical Standards Group

Network Engineering

EV- Animal Mitigation cont..


Scope of project
Information standards to cover Bird Mitigation - EV011
Review concrete polymer covers Fuse covers Appropriate air gap Aerial markers or noise making products to ward off birds Swan (open delta) construction Insulated raiser bracket for HV insulators
Technical Standards Group

Network Engineering

EV- Animal Mitigation cont..


Scope of project - cont.
Possum mitigation - EV021
Pole guards Stay and service cable guards, LVABC and HVABC rotating covers - currently under trial in the You Yangs HV bushing covers Use of insulation eg polytube covered droppers, insulated & screened droppers, wood poles (no earthing)
Technical Standards Group

Network Engineering

Change Speaker...

Technical Standards Group

Network Engineering

G - Underground
GA - General Underground GB - Underground HV Cable & Accessories GC - Conduits & Cable Pulling GE - Cable Head Poles GL - Kiosk Substations GS - Underground LV & Servicing GV - Equipment Bases & Enclosures

Technical Standards Group

Network Engineering

GA - General U/G
GA070 - HV Network Design Guidelines (revisit)
Residential switching zones based on number of customers at risk, not the number of substations Consistent and smart approach to HV U/G design
technical and commercial

Technical Standards Group

Network Engineering

GB - HV Cable & Acc.


Cable/Conductor Procurement
Joint process with ETSA Completion date Dec 01

GB011 - Cable Information Standard


Cable characteristics Physical data Application guidelines Current ratings Short circuit ratings

Technical Standards Group

Network Engineering

Joints and Terminations Procurement


Cold applied indoor & outdoor HV terminations Cold applied HV straight joints

GB - HV Cable & Acc. cont..

Cold applied trification kits


Technical Standards Group

Network Engineering

Joints and Terminations Procurement cont..


Advantages of cold applied products:
No flame required in flame sensitive situations Range taking - unlike heatshrink they continue to apply pressure to accommodate expansion and contraction with thermal cycling One piece - with built in stress control More forgiving of poor cable preparation Sheds on terminations are automatically located

GB - HV Cable & Acc. cont..

Technical Standards Group

Network Engineering

Joints and Terminations Procurement cont..


Loadbreak elbows and accessories, standard for 200Amp applications Deadbreak pin type contact elbows and accessories, standard for 400Amp applications Deadbreak bolted type contact elbows for limited 630Amp applications
Technical Standards Group

GB - HV Cable & Acc. cont..

Network Engineering

Joints and Terminations Procurement cont..


Separable HV tee joints

GB - HV Cable & Acc. cont..

Roll-out (including training) in March 02

Technical Standards Group

Network Engineering

Conduit Procurement

GC - Conduit & Cable Pulling

Contract placed with Iplex Large $$ savings achieved, now all SAP items Continuous polyethylene conduit
approved for use at 750mm depth only (at this stage) 63mmOD (351691) and 110mmOD (351692) Currently negotiating with OCEI to classify as equivalent to HD conduit for mechanical protection

Corrugated (flex) conduit


32mmOD (351693) - 25m roll with draw wire
Technical Standards Group

Network Engineering

GE - Cable Head Poles


New CHP assembly
New surge diverter bracket (increase - ) New copper bus arrangement (surge diverter to droppers) New insulated bushing boot (- G protection) Flag-bolt still available 630mm2 assembly to be developed
Technical Standards Group

Network Engineering

GL - Kiosk Substations
New tender in progress New design & layout Rotary in-oil switches Load break/make fuses Smaller land reserve Front access only Provision to fit loggers Generator connection Slab provided ( 500kVA)

Slab Pr

ovide d

Technical Standards Group

Network Engineering

GL-Kiosk Substations cont..

Technical Standards Group

Network Engineering

GL-Kiosk Substations cont..


Prototypes built in Aug 01 Design finalised in Sep 01 Negotiate terms & pricing (Sep / Oct) Recommendation to CEO and Board (Nov) Await first delivery (Nov + 12-16 weeks)
field training to occur

Indicative costs
315kVA RMU : was $27K, now $20K* (-25%) 315kVA Loop : was $21K, now $18K* (-15%)
* includes slab
Technical Standards Group

Network Engineering

GS - U/G LV & Servicing


Joints and Terminations Procurement
Cast resin LV straight joints
No flame

Heatshrink LV straight joints


Immediate backfilling of trench (1hr for cast resin to cure)
Technical Standards Group

Network Engineering

Service Pit Assembly Pillar Assembly Kiosk Bases and Vaults

GV - Equipment Bases & Enclosures


Investigating appropriate means of cable access to new Kiosk transformers

Technical Standards Group

Network Engineering

The End
Thankyou
1. Satisfaction Survey 2. Raiser Bracket Software Demo

Technical Standards Group

Network Engineering

Software Demo...