Aibel has built a new Krst testing facility for Statoil which is designed to test subsea compressors. This week the pilot compressor was hoisted into place in the test pool.
The compressor was supplied by Aker Solutions. It was set in a frame in Egersund before it came to Krst and was hoisted into place in the test pool on Tuesday photo! Statoil".
&'es, it #as lifted into place on Tuesday morning% (t #eighs )* tons, and represents an important milestone for the pro+ect,, says Ole Kristian Hal orsen, Pro+ect -anager in Aibel%
Historical significance
A total of about 1*! Aibel employees ha3e been in3ol3ed in the #or4 on the test facility% The contract is #orth about $5. 6!! million% The ne# test facility is attached to the ./rst0 metering and technology laboratory, the .7lab% And no# the first compressor is in place%
-ow that the compressor is in place in the test pool+ Aibel has ./ days to complete the hook$up work. Then /0 days of tests follow photo Aibel".
'n all, four compressors will be made to start with. The first one is &ust a pilot, and will remain at ()rst* to be used for further testing. 't#s the ne+t three that will be going out onto the field. The first of these will come to ()rst* in ,anuary -./0. The offshore testing will begin early in -./1,! e1plains 2al3orsen, and continues8 The subsea compressors on sgard are a very important pro&ect in 2orwegian oil history. Today ma&or rebuilding often has to be done on platforms to make room for more powerful compressors. 'f they can be placed on the seabed in the future, it will be a milestone for the industry.! Krst Tysvr, Norway