Está en la página 1de 112

Fractionation

Task Checklist
X Introduction TOWER SIMULATION
Z Basic Concepts Z Specifications

DEVICE SELECTION
Z Contacting Devices Z Tray Hardware Definitions Z Tray Hydraulics Z Packing Hydraulics Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

Did You Know?


Oldest and most important petrochemical manufacturing process

Equipment accounts for 30% of all investments today

Consumes 70% of all energy at plant

More on Fractionation

Separate feed into products according to boiling point

Products sent to finished product tank or further processed by other units

Multiple products and feeds common

Objective Questions
How can you improve separation efficiency?

How do you decide on the optimum number of trays for a new tower?

What sets a towers operating pressure?

What are my options to increase a towers vapor / liquid handling capacity?

Designers Role
Perform HMB calculations to develop tower loadings New Towers
Select optimum tower size, contacting device, and internals to meet process requirements

Existing Towers
Select optimum contacting device and internals to improve performance or expand capacity Screening - Apply Concepts to Troubleshoot Problems

Prepare Design Package (Consult with Specialist)

Engineers Toolbox
XOM DP Section III (Intranet)

Simulation Tool (PRO/II or HYSIS)

Pegasys ExxonMobil Tower Internals Program - EMoTIP

Fractionation Specialists

Task Checklist
X Introduction

TOWER SIMULATION X Basic Concepts


Z Specifications

DEVICE SELECTION
Z Contacting Devices Z Tray Hardware Definitions Z Tray Hydraulics Z Packing Hydraulics Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

Conventional Tower

R D

Reflux Ratio = R / D

Rules of Thumb

More Reflux

More Trays

More Separation

Lower Pressure

10

BINARY DISTILLATION: MCCABE - THIELE DIAGRAM

11

MINIMUM REFLUX

12

TOTAL REFLUX - MINIMUM STAGES

13

Stages Versus Reflux

14

Optimum Reflux Ratio

15

ESTIMATING ACTUAL REFLUX RATIO AND ACTUAL NUMBER OF STAGES

General Rule of Thumb-R ACTUAL = (1.1 TO 1.35) x R MIN

16

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts

X Specifications DEVICE SELECTION


Z Contacting Devices Z Tray Hardware Definitions Z Tray Hydraulics Z Packing Hydraulics Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

17

Operating Pressure
Factors to consider:
Temperature of available condensing fluid (air, water, etc.) Wheres the overhead product go? Is the overhead totally condensed? Possible Limitations:
+ Bottoms temperature (cracking / color) + Reboiler + Critical Point (poor separation)

How much pressure drop is acceptable?

18

Operating Temperature
Fixed once product specifications and pressure are set

Dew Point Calculation


Overhead temp.

Bubble Point Calculations


Bottoms temp.

Flash Calculations
Reflux temp.

19

Feed Condition

If not specified, start with bubble point feed - Then optimize.

Adjust temp. to balance tower loading

Other Considerations:
Reflux vs. Reboiler Duty / Costs Quenching

20

HIGH FEED TEMPERATURE

RECYCLE GAS COMPRESSOR

PRODUCT

OVERRIDE
A

VAPOR PRESSURE SULFUR

FEED

FUEL GAS CONTROL: FEED RATE PRODUCT VAPOR PRESSURE PRODUCT SULFUR OVERHEAD DRUM LEVEL

21

Simulation Inputs
Feed Rate and Composition VLE Data Method Specifications & Control Variables Operating Pressure Initial Guess (If Required) For Rating:
Plant Test Data
Pressure, Temperature Profile Lab Data (Complete Set of Samples)

Tray Efficiencies
See DP III-I Table 2; Estimates from Past Designs

22

Tower Specifications
Specifications: usually on product quality or temperatures
Can be mathematical Avoid specifying rate. Better to specify % recovery or fraction. Condenser temperature

Variables: usually condenser / reboiler duty

23

ProII Condensers
Stage 1, if present Different Types

24

ProII Reboilers
Last Stage(s) Kettle or Thermosiphon
Kettle Thermosiphon specify if have baffle or not

25

KETTLE REBOILER
Advantages: + Additional fractionation stage Disadvantages: - Low NPSH to downstream pump - Very low hold-up - Tubes can dry out - High temperature increase - Large plot space

26

VERTICAL THERMOSIPHON REBOILER


-Advantages: + Partial fractionation stage + Low plot space + Low temperature increase Disadvantages: - Partial fractionation stage - High circulation rate - Pressure drop critical - Limited duty - Difficult to clean

27

HORIZONTAL THERMOSIPHON REBOILER


-Advantages: + Partial fractionation stage + Large duty + Low temperature increase + Lower P than vertical Disadvantages: - Partial fractionation stage - High circulation rate - Pressure drop critical - Large plot space - Large piping

28

Column Stage Summary


Number of Stages
Condenser (1) Theoretical Trays (#)
Can also use Actual Trays * Tray Efficiency Efficiency will be different above and below feed

Reboiler (1 or 2)

29

Simulation Strategy
Optimize Reflux Ratio, Stages, Feed Condition, and Feed Location

30

Simulation Pitfalls
Save / Backup cases often.

Viscosity (high temperature), other properties may need to be verified.

Others?

31

SIMULATION RESULTS

32

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION X Contacting Devices


Z Tray Hardware Definitions Z Tray Hydraulics Z Packing Hydraulics Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

33

Device Categories

Conventional Trays High Capacity Trays


(Proprietary)

Random Packing Structured Packing Baffles, Sheds, and Grid

34

Conventional Trays
Sieve
Most Widely Used 2:1 Turndown Low Cost (Nonproprietary)

Valve
Up to 5:1 Turndown 5-10% higher capacity over sieve Marginally higher cost Not recommended for fouling services

Bubble Cap
Standard until 1950s High Cost Maintenance / Inspection Difficult Excellent Turndown

Jet
hExxon Design for High Liquid Loads Efficiency ~20% less than sieve Mainly used in pumparounds

35

Pumparound Definition
Method to provide tower reflux by cooling tower liquid
Draw-off intermediate liquid Cool liquid by pumping it through heat exchanger Return liquid to tower Use trays/packing to return

Can provide high value heat


Reduces OH condenser duty Reduces furnace duty

Reduces liquid traffic in tower


Can reduce tower diameter Increases tower height since pumparound trays are for heat transfer, not fractionation

36

High Capacity Trays


High Performance Fixed Valves (Increase vapor handling capacity)
Koch-Glitsch
PROVALVE

Sulzer
MVG


37

Directional effect reduces fouling and vapor jetting/entrainment 10-15% jet flood capacity advantage to 1/2 (13mm) sieve trays

High Capacity Trays (Cont.)


Enhanced Downcomer (Increase vapor handling capacity)
Koch-Glitsch
Nye MaxFrac SuperFrac Triton

Sulzer
MVG-T (not shown)

38

High Capacity Trays (Cont.)


Multiple Downcomers
UOP
MD and ECMD

Sulzer
Shell HiFi

~20% higher capacity, but lower efficiency than conventional sieve tray Limited access; not recommended for fouling (Very difficult to clean / inspect)

39

MD and ECMD Tray Unit Cells

40

Want More High Capacity Tray Information?


Read recently released:
EE48E2008, Application Guidelines For Debottlenecking Light Ends Towers With Enhanced Capacity Fractionation Trays

41

Random Packing
3RD Generation
CMR IMTP Nutter Ring Rashig Super-Ring

2ND Generation
Pall Ring Flexirings Ballast Rings Slotted Rings

1ST Generation
Berl Saddle Intalox Saddle Rashig Ring

42

Random Packing (Cont.)


Packing can usually provide higher capacity and better efficiency than trays. As size increases, the capacity increases while the pressure drop, cost, and efficiency decrease. Usually not first choice for new designs

Consider for:
Small tower diameter (<3 or 915mm) Low [critical] pressure drop applications (i.e. vacuum distillation, etc.) Need to minimize tower size (offshore) Revamps where acceptable tray design cannot be achieved See DP III-A, p. 34 for others applications

43

Packing Warning

DP III-G (Packing and Grid)

Fire Hazard: Some sites prevent hot work above a packed bed

44

Structured Packing
Conventional
Koch-Glitsch: Flexipac, Intalox Sulzer: Mellapak Montz: Montz-Pak Type B1

High Capacity
Koch-Glitsch: Flexipac HC, Intalox Sulzer: Mellapak Plus Montz: Montz-Pak Type M

45

Structured Packing (Cont.)

Why Structured Packing?


Lowest pressure drop per stage Best capacity / efficiency combination device Less sensitive to liquid maldistribution than random packing Recently, cost is much more competitive with random packing

Why Not Structured Packing?


Not recommended for high pressure towers - above 100 psia (7 kg/cm2) due to poor test results, or where liquid rate exceeds 20 gpm/ft2 (13.6 dm3/s*m2) unless application is high pressure aqueous system.

46

Grid
Used for entrainment removal where fouling is too severe for a crinkle wire mesh screen (CWMS) High Open Area
Prevents plugging

Low Surface Area


Low efficiency

47

Baffles

Large Open Area


Prevents plugging

Low Liquid Residence Time


Prevents coking

48

Practice Tower Internal Type


What type of tower internal would you use for the following?
Desuperheating reactor effluent in bottom of a fractionator? Vacuum fractionator High pressure light ends tower 24 (610mm) diameter absorber Recycle gas absorber (remove H2S from H2) Tail gas absorber (remove H2S from Sulfur Plant effluent) Pumparound section of large fractionator

49

Device Selection Criteria


Fouling Tendency Good Liquid & Vapor Handling Capacity Good Contacting efficiency Acceptable Pressure Drop Predictable Turndown Characteristics Economical

See DP III-A Tables 3-5

50

Device Selection Procedure


New Design
Start with trays, unless pressure drop is critical. If need low dP, consider 2 (50mm) random packing. Calculate optimum tray spacing, diameter, and layout (i.e. bubble area and downcomer dimensions) by trial and error to avoid downcomer and jet flood limitations.
(Use Pegasys / EMoTIP)

Revamp
Rate existing contacting device to identify potential limitations (i.e. downcomer, jet flood, etc.)
(See Table 1 Design Principles in appropriate DP III Section)

Identify new layout and device where all design parameters are satisfied
(Use Pegasys / EMoTIP)

Consider:
Multi-pass Conventional Trays High Performance Fixed Valves Enhanced Downcomer Trays Multiple Downcomer Trays Packing

Then select best device type based on Device Selection Criteria.


(See DP III-A Tables 3&5 Decision Trees)

Dont consider High Capacity Trays for new towers - Instead Increase Diameter, etc.

51

Trays vs. Packing


XOM DP III-A Table 3D -- Fouling Tendencies

52

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION
X Contacting Devices

X Tray Hardware Definitions


Z Tray Hydraulics Z Packing Hydraulics Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

53

Common Pass Arrangements

54

Downcomer Types
Stepped / Sloped: Provide sufficient DC inlet area for adequate vapor / froth disengagement while maximizing bubble area

55

Downcomer Expansion
Can expand downcomer without welding
Commonly called Z-bar or downcomer adapter

Exiting Tray Support Ring

Exiting Downcomer Bolting Bar

Koch-Glitsch supplied Downcomer Adapter

56

Weir Types
Picketing: Can reduce spray regime operation by increasing effective liquid height; Also used to balance multipass designs by making their effective weir lengths the same.

57

Downcomer Seal Techniques


Design should ensure vapor cannot bypass a tray by flowing upward through the DC resulting in poor efficiency.

Process Seal

Mechanical Seals

58

Area Definitions
Also see DP III-A, Figures 12-13

59

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION
X Contacting Devices X Tray Hardware Definitions

X Tray Hydraulics
Z Packing Hydraulics Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

60

Hydraulic Limitations

VAPOR Jet Flooding Ultimate Capacity Flow Regimes Entrainment

LIQUID Downcomer Backup Secondary Limitations:


Liquid Rate per Inch of Weir Downcomer Choking Velocity Under the Downcomer Downcomer Seal

61

FRI VIDEO

62

Jet Flooding
At high vapor rates, liquid is jetted to tray above Vapor handling limitation; sets design in most cases Expressed as Percent; Rigorously Calculated
(See DP III-B / Use Pegasys)

Related to vapor velocity through the free area

Strong function of:


Tower Diameter Tray Spacing

63

Jet Flooding and Efficiency


XOM Jet Flood Limit

85

Late Breaking News: XOM Jet Flood Limit now 80% for new designs

64

Problem Jet Flood


What steps can we take to reduce jet flood, and what are the drawback for each?

65

Ultimate Capacity
Highest vapor rate tower can handle -- Stokes Law Cannot be increased by hardware changes; only way to increase it is by increasing the tower diameter

66

Flow Regimes

To Eliminate Spray Regime:


Use Picket Fence Weirs Increase Open Area Use Smaller Sized Orifices Use Valve Trays

67

Entrainment

Liquid [drops] carried by the vapor to the tray above

Design should limit entrainment to 10% of the tray liquid rate

Function of:
Vapor Rate Liquid Rate Tray Spacing Other Hardware Parameters

68

Downcomer Backup
DC froth height expressed as percent of tray spacing plus the weir height

DC Filling Components:
hi = inlet head; f(inlet & outlet weir) ht = total tray dP hud = head loss under DC; f(DC Clearance) hdc = head loss due to two-phase flow in DC

69

Percent Downcomer Flood


Performance criteria to see how close a tower is to flooding as a result of excessive froth height in the downcomer Represents actual vapor / liquid rates as a percent of the rates which cause 100% DC Backup Rigorously Calculated
(See DP III / Use Pegasys)

70

Flooding Symptoms
Jet Flooding
Tower unstable Liquid entrainment into overhead system; sharp increase in reflux rate with no separation improvement Pressure drop increases sharply with a small incremental increase in vapor rate Separation efficiency gradually decreases

Downcomer Flooding
Tower unstable, surging High pressure drop with a small increase in either vapor or liquid rate Separation efficiency suddenly decreases Loss of tower bottoms liquid level

71

Problem Downcomer Backup


What parameter has a 2x affect on downcomer filling? Name steps we can take to lower downcomer filling, and what drawbacks for each.

72

Secondary Liquid Hydraulic Limitations


Liquid Rate per Inch of Weir
The accuracy of the Jet flood and DC Flood correlations can only be ensured within the range of liquid rates used to develop them.

Downcomer Choking results when the DC inlet area is too small. Velocity Under the Downcomer
If too high, can produce channeling effect leading to vapor / liquid maldistribution on the tray.

Downcomer Seal
If not sealed, vapor can bypass the tray and flow upward through the downcomer resulting in reduced efficiency. Two types:
Mechanical [Static] Process [Dynamic]

73

Tray Hydraulics

DP III-B P.20-22 SIEVE TRAY DESIGN PARAMETERS

74

DP III-B P.20-22 SIEVE TRAY DESIGN PARAMETERS

75

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION
X Contacting Devices X Tray Hardware Definitions X Tray Hydraulics

X Packing Hydraulics
Z Other Process Considerations Z Other Tower Internals Z Tower Revamps

76

Packing Hydraulics

Packing Hydraulics
Flooding -- (Use Pegasys)
Harder to define than tray hydraulics (i.e. no tray spacing or downcomer
to fill with liquid)

As vapor rate increases, liquid accumulates and the pressure drop begins to rise more sharply. With further increases in vapor rate, the pressure drop rises almost vertically and liquid stacks up on top of the packing.

Ultimate Capacity -- (Use Pegasys)


Similar to tray hydraulics

77

Packing Hydraulics

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION
X Contacting Devices X Tray Hardware Definitions X Tray Hydraulics X Packing Hydraulics

X Other Process Considerations


Z Other Tower Internals Z Tower Revamps

78

Packing Hydraulics

Tray Efficiency
Overall Efficiency, EO, is a measure of the effectiveness of an entire tower or tower section. Allows designer to determine the number of actual trays to provide and sets the tower height.

Actual Trays = Theoretical Stages / EO


Calculated Rigorously - Use Pegasys
(See DP III-I)

Factors affecting EO:


Weir Height Flow Path Length and Number of Passes (i.e. Residence Time) Weeping or Vapor Recycle VLE Properties and Tower Loading

79

Other Process Considerations

Calculation of Tray And Packing Efficiency


# of theoretical trays = # of actual trays x tray efficiency Screening Estimates - See DPM III-I Table 2 for historical efficiencies Figure 8 for heavy hydrocarbons Rigorous Methods - DPM III-G (Packing) & DPM III-I (Trays) Plot y* vs x for light key and heavy key y* = vapor mole fraction in equilibrium with liquid x = liquid mole fraction Input slope into PEGASYS tray program

80

Estimating Tray Efficiency

81

Estimating Tray Efficiency, Heavy Hydrocarbons

82

Packing Height
To specify correct packing height, designer must calculate height equivalent to a theoretical plate (HETP)

Packing Height = Theoretical Stages x HETP


HETP must be calculated rigorously - Use Pegasys
(See DP III-G)

Other methods for packing efficiency exist, but HETP applies to most systems Factors affecting HETP:
Distributor Design Packing Size / Geometry VLE Properties and Tower Loading

83

Other Process Considerations

Turndown
Defines range of loadings for acceptable device performance Excessive Weeping Decreases Efficiency

84

Other Process Considerations

Dry Tray Pressure Drop, hed


Dry tray dP is important because:
If its too high --- Entrainment If its too low --- weeping at turndown

Calculated based on vapor flow through device with no liquid present

hed (Vapor Velocity )


Function of:
Vapor Rate Open Area / Device

85

Other Process Considerations

Foaming
Foaming Mechanisms:
Presence of surface active materials or solids HC entrainment or condensation in aqueous systems

Compensate design by using:


Lower percent of Jet and Downcomer Flood Low dry tray dP Low DC entrance velocity and filling Radial tips (shaped lips) and large DC clearance Provide antifoam injection facilities (Since degree of foaminess varies and is generally unpredictable, experience in similar towers may be used instead - Contact a Fractionation Specialist)

Known Foamers
Amine and Glycol Absorbers Caustic Towers Ethylene Demethanizers Sour Water Strippers

86

Other Process Considerations

EXISTING T-2851 RE-DISTRIBUTOR


509

20" Manway

Top Bed, 5334 deep (17.5') 2" Pall rings

254

74

357

180

Redistributor
100

20" Manway
800

480

Top of Packing
25

Bed Limiter

Bottom Bed, 5334 deep (17.5') 2" Pall rings

87

286

Bed Support

This FLEXSORB absorber tower foams. What changes would you make to improve it? Units are in mm (25mm=1) unless stated.

650

396

110

1830

Design Contingency

To insure 90% chance of successful operation, safety margins should be adhered to and are built into EMoTIP.

Examples
Jet Flooding (Trays) Downcomer Filling Packing Flooding Tray efficiency Packing HETP 80-90% of predicted 35-50% 80-85% of predicted Point efficiency debited 10% Predicted divided by 0.85

88

Other Process Considerations

Trayed Tower Thoughts


Review all designs with Fractionation Specialist Use EMoTIP as starting point
Will not optimize open area or downcomer slope

Design for vacuum if can occur


Check vapor pressure of contents if reduced to ambient temperature

Try high capacity designs instead of packing for revamps Prevent water from entering tower
#1 cause of refinery tray damage

Specify additional static pressure drop for design pressure


Use water filled basis if not high cost

Consider if can condense water on top tray BEWARE of foaming


A well designed tower for non-foaming service will still flood if it foams

89

CONTACTING DEVICE PROBLEM

90

Other Process Considerations

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION
X Contacting Devices X Tray Hardware Definitions X Tray Hydraulics X Packing Hydraulics X Other Process Considerations

X Other Tower Internals


Z Tower Revamps

91

Other Tower Internals

Tray Internals

92

Other Tower Internals

Perforated Pipe Distributors


Usually directed against a downcomer
Use baffle to prevent downcomer boiling

Hole/Slot Area should give 0.25-0.5 psi (0.018-0.035 kg/cm2) pressure drop
(See Fluid Flow Equations, DP III-H)

Four common types:

93

Other Tower Internals

Tower Internals Details (DP III-H)


Pay special attention to tower inlets and outlets
Follow directions in DP III-H Leave extra tray spacing for distributors and manways
Figure out where the manways will be Distributors will create high velocity areas where flooding can start

Insulate baffle to prevent vaporization in downcomer 0.25-0.5 psi (0.02-0.04 kg/cm2) for distributor hole/slots Chimneys
Long rectangular lowest cost, then round, last square

Size CWMS for 100% Vc, unless foaming service Useful fluid flow equations hidden in DP III-H Some drawoffs require self venting flow (eq 13)
Chance that vapor can enter drawoff line
Low residence time Lack of seal in drawoff pan (coking or fouling services)

See also Distillation Operations, p. 89-94 (Kister)


94

Packing Internals

95

Other Tower Internals

Packing Liquid Distributors


Gravity Type
Most important packing internal Trough type preferred, but high cost Design details by vendor but must meet DP III-G, Appendix A criteria Must be installed level

96

Other Tower Internals

Packing Distributor

97

Packing Spray Nozzles


Provide poor liquid distribution Plug easily; strainers required upstream Low cost, but often require demister above

Sprays in action: Water Test of BTRF PS 8 VPS Wash Oil Distributor at Turndown Rate - 2003

98

Other Tower Internals

Distribution Quality

All packing distributors should be tested at vendor shop

Distributor should be fully assembled during test

Area samples and individual random sample are compiled to verify performance

99

Other Tower Internals

Packing Supports
Located at bottom of packed bed Open Area sized for at least 100% of tower cross section to prevent flooding Design details by vendor

100

Other Tower Internals

Bed Limiters
Restrain packing during upsets - keep out of draw nozzles, etc. Fastened to clips welded to shell or suspended from distributor

101

Other Tower Internals

Packed Tower Details


First, dont use packed tower unless necessary
Low pressure drop (vacuum or atmospheric pressure tower) Very small diameter tower (3 ft or 915mm or less) Possibly foaming, but still try trays first Revamp where high capacity trays still cant provide necessary capacity/efficiency

Specify liquid distributor to meet criteria in DP-III-G Appendix A


3/8 (10mm) minimum orifice desired, but can reduce to (6mm)
Smaller holes may plug, resulting in poor fractionation

Be careful of high turndown requires small orifices

Specify liquid distributor to meet flow test criteria in Appendix B


Copy both appendices and give to vendor

Provide dual strainers on liquid feed to prevent plugging


No bypass recommended SS piping downstream of strainers (especially if at grade)

102

Liquid Draws - Trays and Packing


Two types:
Downcomer (Sump) Chimney Tray

Either type may be a partial or total draw Reboiler Draws are unique (see DP III-H)

103

Other Tower Internals

Reboiler Draw and Return Design


11"

1 1/2"

11" 4"

1' - 0" 71

4" 15

2' - 10"

4' - 10"

1' - 6"

2"

4" 1' - 4" 6"

9" 4" 2" 2"

2' - 0"

1' - 3" 8"

1' - 9" 5' - 0"

3' - 3"

104

8"

1' - 12"

4"

3' - 10"

Task Checklist
X Introduction

TOWER SIMULATION
X Basic Concepts X Specifications

DEVICE SELECTION
X Contacting Devices X Tray Hardware Definitions X Tray Hydraulics X Packing Hydraulics X Other Process Considerations X Other Tower Internals

X Tower Revamps

105

Tower Revamps

Tower Revamps
Always consider process alternatives first!!!
(e.g. increase tower pressure, etc.)

Revamp Strategy: Rate existing tower to identify limitations


Vapor Handling Limitation? Liquid Handling Limitation? Poor Separation Efficiency? Different Service?

Explore high capacity tray options discussed previously before considering packing Fundamental design concepts remain the same. However, sometimes design criteria are too conservative - consult with a Fractionation Specialist.

106

Tower Revamps

Options Guide
Revamp Objective: Increased capacity at constant separation efficiency
(XOM DP III-A Table 4A)

107

Tower Revamps

Debottleneck Examples
Cheap Operational changes Reduce weir height, increase DC clearance or add a shaped lip to lower DC filling Change tray decks Packed Towers:
Increase Packing Size Install Structured Packing Replace liquid distributor(s)

Expensive Install sloped or mod. arc downcomers Increase number of liquid passes Install high capacity trays Changing tray spacing Install packing Change amine type or concentration

108

Tower Revamps

Packing Selection

Can easily compare different packing types using this chart


(see DP III-G, Figure 3)

109

Tower Revamps

Expansion Example
What consider for expansion?
Top Trays Jet Flood Limit Base Expansion <85% 42% 45% DC Flood <85% 90% 95% DC Choke <100% 150% 160%

Bottom Trays Jet Flood Limit Base Expansion <85% 29% 31% DC Flood <85% 62% 66% DC Choke <100% 97% 103%

Preheat: 6.1 MBtu/hr (6.4 M.kJ/h) Base, 6.5 MBtu/hr (6.9 M.kJ/h) Expansion Reboiler: 60% of capacity

110

Tower Inspection
All vessels need technical inspection Inspect every tray, every pass, recording dimensions
DC clearance, DC rise, weir heights, number of holes (within reason) Verify bolts are tight Make sure internals are put together correctly Levelness of weirs Helmet mounted and hand held flashlights (explosion proof recommended) Rechargeable spotlight for large vessels/furnaces Knee pads, and maybe seating pad Wrench (to check bolts) Ruler, tape measure, and wooden blocks cut to measurement tolerances Water bottle Level (consider laser type) Hardhat, gloves, clear safety glasses, pool FRCs Marker or paint pen Shoulder bag

Tools

Do not enter vessel without signing in through hole watch


Do not even put head inside vessel without permission Gas test required to make sure safe Sign out through hole watch when leaving

111

NEW T-2851 RE-DISTRIBUTOR


509

20" Manway

Top Bed, 5334 deep (17.5') Cascade Minirings #3


649 112

Bed Support

Replace packing with one with higher capacity. Newer packings can give similar performance with higher capacity (at lower % jet flood).

Old Redistributor (removed)

396

20" Manway

New Redistributor Old Bed Limiter Old Top of Packing


152

Velocity through chimneys was 21.5 ft/sec (6.6 m/s), with only 3 (76 mm) gap between top of chimney and bed support. Chimneys were missing hats. Lower distributor and install hats on chimneys.

633

825

New Bed Limiter (supported by clips) New Top of Packing

Bottom Bed, 5182 deep (17.0') Cascade Minirings #3


1830

112

También podría gustarte