Está en la página 1de 14

PREDIMENSIONAMIENTO DE MURO DE CONCRETO CICLOPEO

0.25

2.00

DATOS
h
t
TALUD
H
V

0.30

0.40

0.40

2.5 m
0.3 m

1.20

CALCULO
hz =
B =

ASUMIENDO
0.5
1.875

hz =
B =

0.5 m
1.875 m

t =
H =
PIE =
t2 =
TALON

0.3
3
0.5
0.625
0.75

1
4

2.00

0.25

0.30

0.40

0.40

1.20

MURO DE CONCRETO ARMADO


OBRA:
CONSTRUCCIN DE MURO DE CONCRETO CICLOPEO
EJECUTA GOBIERNO REGIONAL DE PUNO

DATOS :
PESO ESPECIFICO DEL CONCRETO:
PESO ESPECIFICO DEL SUELO:
ANGULO DE FRICCION INTERNA DEL SUELO:
COEFICIENTE DE FRICCION:
CAPACIDAD PORTANTE DEL SUELO:
RECUBRIMIENTO DE ACERO:
LONGITUD DEL MURO
JUNTAS DE CONSTRUCCIN

Yc =
Ys=
=
f=
st=
r=

0.30

Ea
2.00
4
1

0.45
0.05

0.50

0.63

0.75
1.88

2.40
1.44
36.71
0.60
2.72
0.04
46.39
3.75

Tn/m3
Tn/m3

Kg/cm2
m
m
m

CALCULO DEL EMPUJE ACTIVO


Ka = Tg(45-/2) =
Ea = 1/2 .Ka.Ys.(H +Hz ) =
dh = (H + Hz)/3 =
Bt =

0.252
1.133
0.833

1.88 m

VERIFICACION DE ESTABILIDAD
N

1
2
3
4

2.40
2.40
2.40
1.44
R=

Pi

Xi

0.78
1.44
2.25
2.16
6.63

Pi x Xi

0.72
0.98
0.94
1.50
M=

0.56
1.40
2.11
3.24
7.31

Xo = (M-Ea .dh)/R =
e = B/2 - Xo =
B/6 =
3

0.96
-0.02
0.31

< B/6

CHEQUEOS:
A) AL DESLIZAMIENTO:

FSD = f R/Ea =

3.51

> 1.50

7.75

> 1.75

B) AL VOLTEO:

FSV = M/(Ea.dh) =

C) A LOS ESFUERZOS: (kg/cm)

q1 = R/10/B.(1+6.E/B) =

0.33

q2 = R/10/B.(1-6.E/B) =

0.38

<

st =

2.72 Kg/cm2

CALCULO DE ACERO
A) EN PANTALLA

Mu = 1.7 Ka Ys H/6 =

0.82

Tn-m

ZONA INTERIOR:
1. ACERO VERTICAL PRINCIPAL:

As = 0.421 cm2
Asmin = 0.20 d =
As =
11.7 cm2
S=
0.17 m
Asv : 5/8" @

11.70

cm2

0.25

d=

0.59

5/8

"

3/8

"

d=

0.59

5/8

"

1/2

"

2 . ACERO HORIZONTAL:

As' = As/3 =
S=
0.18 m

3.9 cm2

Ast : 3/8" @

0.30

ZONA EXTERIOR:
1. ACERO VERTICAL DE MONTAJE:

Asmin = 0.20 d =
As = 11.70 cm2
S=
0.17 m

11.70

cm2

Asv : 5/8" @

0.25

As'' = 2/3*As =
S=
0.163 m

7.80

cm2

Ast : 1/2" @

0.25

2. ACERO HORIZONTAL:

B) EN TALN POSTERIOR

d=

q' = 10/B.(q1-q2).L2 =
-0.21
q = 10.q2+ q' =
3.59
Wu = 1.4*(Ys.H + 2.4.Hz)=
5.71
Mu = (Wu-14.q2).L2/2 - 1.4 q.L2/6 =

Tn/m
Tn/m
Tn/m
-0.36

0.41

Tn-m

1. ACERO LONGITUDINAL:

Mu = -0.36 Tn/m
As =
-0.26 cm2
Asmin = 0.20 d =
As =
8.20 cm2
S=
0.24 m

8.20

cm2

Asl : 5/8" @

0.20

Asmin = 0.20 d =
As =
8.20 cm2
S=
0.24 m

8.20

cm2

Asl : 5/8" @

0.20

5/8

"

5/8

"

d=

0.41

5/8

"

5/8

"

2. ACERO TRANSVERSAL:

C) EN TALN ANTERIOR

Wu = 17*q1-0.9*(2.4 Hz) =
Mu = Wu . L1/2 =

4.49
0.56

Tn/m
Tn-m

1. ACERO LONGITUDINAL:

Mu =
0.56 Tn/m
As =
0.41 cm2
Asmin = 0.20 d =
As =
8.20 cm2
S=
0.24 m

8.20

cm2

Asl : 5/8" @

0.20

Asmin = 0.20 d =
As =
8.20 cm2
S=
0.24 m

8.20

cm2

Asl : 5/8" @

0.20

2. ACERO TRANSVERSAL:

0.5
0.0125

MURO DE CONCRETO ARMADO

LONGITUD
ALTURA

46.39
2.00

0.30

pantalla interior
pantalla exterior
5/8" @ 0.25
5/8" @ 0.25

1/2" @ 0.25

3/8" @ 0.30

2.00

5/8" @ 0.25

talon anterior
5/8" @ 0.2

5/8" @ 0.2

0.45

0.05
0.50

0.63

0.75
5/8" @ 0.2

5/8" @ 0.2

Talon posterior

planilla de metrados acero en Muro de Contencion


DESCRIPCION
01.00.00

LONGITUD
(metro)

N DE PIEZAS
x ELEMENTO

N DE
ELEMENTOS

1/4"

3/8"

1/2"

5/8"

3/4"

1"

HABILITAC. DE ACERO CORRUGADO FY=4200 KG/CM2 EN MUROS


pantalla exterior
Fe Horizontal
Fe Vertical

46.39
1/2" @

9.80

1.00

454.62

2.90
5/8" @

185.56

1.00

538.12

pantalla interior
46.39
3/8" @

8.17

1.00

378.85

Fe Vertical

2.90
5/8" @

185.56

1.00

538.12

Fe Vertical

1.32
5/8" @

185.56

1.00

244.32

Fe Horizontal

02.00.00

HABILITAC. DE ACERO CORRUGADO FY=4200 KG/CM2 EN ZAPATA


Fe Horizontal
Fe Vertical

1.29
5/8" @

231.95

1.00

298.64

46.39
5/8" @

6.44

1.00

298.64

Talon posterior
Fe Horizontal
Fe Vertical

2.33
5/8" @

231.95

1.00

539.28

46.39
5/8" @

11.63

1.00

539.28

0.00

0.00

0.00

0.00

378.85

454.62

2,996.41

0.00

0.00

SUB TOTAL

ML

0.25

0.56

1.02

1.55

2.24

3.97

SUB TOTAL

Peso Kg/ml
KG

0.00

212.16

463.71

4,644.43

0.00

0.00

TOTAL

KG

5,320.30

HOJA DE METRADOS
OBRA:
CONSTRUCCIN DE MURO DE CONCRETO CICLOPEO
EJECUTA GOBIERNO REGIONAL DE PUNO
ITEM
01.00.00

02.00.00

03.00.00

04.00.00

DESCRIPCION

UNID.

MEDIDAS
CANT
VECES LARGO (L) ANCHO (B)

ALTO (H)

PARCIAL

TOTAL

TRABAJOS PRELIMINARES
TRAZO Y NIVELES Y REPLANTEO

M2

50.00

1.88

93.75

93.75

LIMPIEZA DE TERRENO EN FORMA MANUAL

M2

50.00

2.53

126.56

126.56

MOVIMIENTO DE TIERRAS
CORTE Y EXCAVACION EN TERRENO SUELTO C/MAQUI. M3

50.00

2.16

123.21

123.21

NIVELACIN Y COMPACTACIN DE TERRENO NATURAL M2

50.00

2.06

103.13

103.13

RELLENO CON MATERIAL COMPACTADO

M3

50.00

0.86

1.67

71.88

71.88

ELIMINACIN DE MATERIAL EXCEDENTE

M3

51.34

66.74

66.74

OBRAS DE CONCRETO SIMPLE


SOLADO DE 4" MEZCLA 1:12 CEMENTO-HORMIGON

M2

93.75

93.75

1.3

CONCRETO CICLOPEO
zapatas
muro

M3

ENCOFRADO Y DESENCOFRADO CARAVISTA

M2

VARIOS
JUNTAS DE DILATAC. RELL. C/MEZCLA ASFALTICA E=1"

13.333

1.14

50.00

1.88

50.00
50.00

1.88
0.75

50.00

2.00

200.00

200.00

4.3

57.33

57.33

84.38
0.50

46.88
37.50

HOJA DE METRADOS
OBRA:

CONSTRUCCION MURO DE CONTENCION CONCRETO CICLOPEO

EJECUTAGOBIERNO REGIONAL DE PUNO

ITEM

DESCRIPCION

UNID.

MEDIDAS

CANT

VECES LARGO (L)ANCHO (B) ALTO (H)

PARCIAL

TOTAL

01.00.00 TRABAJOS PRELIMINARES


TRAZO Y NIVELES Y REPLANTEO

M2

50.00

2.53

126.56

126.56

LIMPIEZA DE TERRENO EN FORMA MANUAL

M2

50.00

2.53

126.56

126.56

CORTE Y EXCAVACION EN TERRENO SUELTO M3


C/MAQUI.

50.00

2.16

123.21

123.21

NIVELACIN Y COMPACTACIN DE TERRENO NATURAL


M2

50.00

2.06

103.13

103.13

RELLENO CON MATERIAL COMPACTADO

M3

50.00

0.86

1.67

71.88

71.88

ELIMINACIN DE MATERIAL EXCEDENTE

M3

51.34

66.74

66.74

93.75

93.75

02.00.00 MOVIMIENTO DE TIERRAS

1.3

1.14

03.00.00 OBRAS DE CONCRETO SIMPLE


SOLADO DE 4" MEZCLA 1:12 CEMENTO-HORMIGON
M2

50.00

1.88

zapatas

50.00

muro

50.00

1.88
0.4625

50.00

2.00

04.00.00 OBRAS DE CONCRETO ARMADO


CONCRETO F'C=210Kg/CM2

M3

ENCOFRADO Y DESENCOFRADO CARAVISTA M2


ACERO F'Y=4200 KG/CM2

93.13

0.50

46.88

2.00

46.25
200.00

200.00

KG

5,320.30

M2

200.00

05.00.00 VARIOS
CURADO DE MUROS

JUNTAS DE DILATAC. RELL. C/MEZCLA ASFALTICA


M E=1"13.33333
TUBERIA DE 1" PVC SAP

JUNTAS CON WATER STOP 6"

13.33333

4.3

57.33

57.33

0.46

24.67

24.67
50.00

También podría gustarte

  • Acu Estructuras
    Acu Estructuras
    Documento10 páginas
    Acu Estructuras
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Diseño de Vigas
    Diseño de Vigas
    Documento6 páginas
    Diseño de Vigas
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Memoria de Calculo Vigas
    Memoria de Calculo Vigas
    Documento1 página
    Memoria de Calculo Vigas
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Solucion Vigas
    Solucion Vigas
    Documento26 páginas
    Solucion Vigas
    Alvaro Alexander Muñoz
    Aún no hay calificaciones
  • Acu Estructuras
    Acu Estructuras
    Documento10 páginas
    Acu Estructuras
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Cimiento Corrido
    Cimiento Corrido
    Documento4 páginas
    Cimiento Corrido
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Cimiento Corrido
    Cimiento Corrido
    Documento4 páginas
    Cimiento Corrido
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Analisis de Precios Unitarios
    Analisis de Precios Unitarios
    Documento185 páginas
    Analisis de Precios Unitarios
    Bernabe Quiñones Flores
    75% (4)
  • Clases de Concreto
    Clases de Concreto
    Documento13 páginas
    Clases de Concreto
    Anibal Pilco Villagra
    Aún no hay calificaciones
  • Ho Jade Vida Mia
    Ho Jade Vida Mia
    Documento4 páginas
    Ho Jade Vida Mia
    Anibal Pilco Villagra
    Aún no hay calificaciones