Está en la página 1de 49

INSTRUCTION FOR PRODUCT

BTG for Chhattisgarh 4X135 MW CPP, Raigarh

JINDAL STEEL AND POWER LIMITED DESEIN PRIVATE LIMITED

BTG for Chhattisgarh 4 X 135 MW CPP, Raigarh


INSTRUCTION FOR PRODUCT DOCUMENT NO.: 573-1-8601 REV. 0

SHANGHAI ELECTRIC GROUP Co., Ltd., No.8 Xingyi Road,Shanghai,China

SHANGHAI BOILER WORKS LTD. No.250 Huaning Road, Minhang Shanghai,China

DOCUMENT NO.: 573-1-8601

-I-

INSTRUCTION FOR PRODUCT

BTG for Chhattisgarh 4X135 MW CPP, Raigarh

DOCUMENT CONTROL SHEET

PROJECT: CLIENT:

BTG for Chhattisgarh 4 X 135 MW CPP, Raigarh JINDAL STEEL AND POWER LIMITED/ SHANGHAI ELECTRIC GROUP Co., Ltd.,

DOCUMENT TITLE:

INSTRUCTION FOR PRODUCT

DOCUMENT NO.

573-1-8601

REV. NO.

ENDORSEMENTS

2009.3.30

2009.6.8

REV. NO.

DATE

DESCRIPTION

PREP. BY SIGN.(INITIAL)

REVW. BY SIGN.(INITIAL)

APPD BY SIGN.(INITIAL)

DOCUMENT NO.: 573-1-8601

- II -


INSTRUCTION FOR PRODUCT

SG-460/13.7-M573

MODEL OF PRODUCT

460t/h Circulating Fluidized Bed Boiler

NAME OF PRODUCT

SERLES NO.

573-1-8601

DATE

PREPARED BY

2009.6.8

DATE

CHECKED BY

DATE

REVIEWED BY

DATE

APPROVED BY

SHANGHAI BOILER WORKS, LTD.

Catalog
0 1 INTRODUCTION..4 BOILER BASIS AND PERFORMANCE DATA..4

1.1 BOILER MODEL AND TYPE..4 1.2 BOILER TECHNICAL DATA...4 1.3 EXPECTED MAIN PERFORMANCE OF STEAM GENERATOR ( AT B-MCR OF DESIGN COAL..5 1.4 FUEL..5 1.4.1 COAL SPECIFICATION..5 1.4.2 OIL FOR IGNITION AND AUXILIARY FIRING..6 1.5 STEAM AND WATER QUALITY7 1.6 SITE CONDITION.7 1.7 BOILER WORKING CONDITIONS...7 1.8 BOILER WATER VOLUME(M2)....8 2 BOILER OVERVIEW AND CONSTITUENT SYSTEM8

2.1 OVERALL BOILER INTRODUTION.8 2.2 STEAM AND WATER SYSTEM..11 2.2.1 FEEDWATER AND STEAM-WATER RECIRCULATION SYSTEM ( DRAWING 2.2.1; DRAWING 2.2.2)12 2.2.2 SUPERHEATED STEAM SYSTEM ( DRAWING 2.2.3 )13 2.2.3 REHEAT STEAM SYSTEM ( DRAWING 2.2.4 )16 2.3 COMBUSTION SYSTEM17 2.3.1 FUEL CRUSHING SYSTEM17 2.3.2 COAL EXTRACTOR FEEDER AND CHUTE.17 2.3.3 START-UP OIL IGNITOR..18 2.4 GAS AND AIR SYSTEM19 2.5 LIMESTONE AND BED MATERIAL SYSTEM.20 2.6 ASH RECIRCULATION SYSTEM..21 2.7 BOTTOM ASH EXTRACTION SYSTEM.21

2.8 TEMPERATURE CONTROL SYSTEM22 2.8.1 SUPERHEATED STEAM TEMPERATURE CONTROL SYSTEM ( DRAWING 2.8.1 )...23 2.8.2 REHEAT STEAM TEMPERATURE CONTROL SYSTEM23 2.8.2.1 2.8.2.2 EMERGENCY SPRAY WATER..23 GAS TEMPEARATURE CONTROL DAMPER..25

2.9 PIPING SYSTEM25 2.9.1 PIPING FOR DRAINAGE, CHEMICAL FEED, REGULAR BLOWDOWN AND ACID WA S H . 2 5 2.9.2 PIPING FOR VENT, SAMPLING AND NITRIGEN INJECTION..26 2.9.3 CONTINUOUS BLOWDOWN PIPING26 2.9.4 SAFETY VALVE VENT PIPING..27 2.10 MEASURING POINTS ARRANGEMENT..27 2.10.1 2.10.2 2.10.3 STEAM WATER SYSTEM MEASURING POINTS ARRANGMENT..27 GAS AND AIR SYSTEM MEASURING POINTS ARRANGMENT28 THERMAL CONTROL DESIGN DATA..28

2.11 SOOTBLOWING SYSTEM..29 2.11.1 2.11.2 2.11.3 3 SOOTBLOWER ARRANGEMENT OVERVIEW29 SOOTBLOWER PIPING29 PROGRAMED CONTROL OF SOOTBLOWER..29

MAJOR PARTS..30

3.1 STEAM DRUM AND INTERNALS.30 3.2 WATER-COOLING SYSTEM30 3.3 REAR PASS HEAT-ABSORBING SURFACE.31 3.4 CYCLONE AND SEAL POTERROR 3.5 ASH COOLERERROR 3.6 BOILER FRAMWORK AND PLATFORMS & STAIRS33 3.7 SUPPORT AND HANGING FOR PRESSURE PARTS33 4 OTHER SYSTEMS..34

4.1 PROTECTION AGAINST ABRATION.34 4.2 SEALING.35

0.

INTRODUCTION

Circulating fluidized bed (CFB) combustion is a new kind of high efficient, low pollution clean coal combustion technology. The main feature of it is that the furnace contains a large mass of bed materials. In the combustion process, these materials are carried to the upper furnace by gas flow, separated from gas by the cyclones connected to the furnace outlet and conveyed to the bed through non-mechanical return valves. Thus realizes repeatable combustion of these materials. These materials have a high density, large heat capacity and are well mixed and usually each kilo gas can carry several kilo materials. Hence a high thermal coefficient of bed materials, a wide range of boiler load and a large flexibility with respect to fuel quality. CFB technology adopts a higher fluidizing speed than bubbling bed, so there is not an obvious bed plane as is in the bubbling bed. Because of the turbulent flow and recirculation of bed materials inside the bed, which enlarge the residence time of the fuel, CFB has a higher combustion coefficient than the bubbling bed and can run stably under low load without any auxiliary fuel. The working temperature of CFB is usually between 850-900, an ideal range for desulfurisation. In-Furnace Desulfurization technology is adopted. Limestone and desulfurizer are fed into the bed. As the fuel and desulfurizer recirculate, repeating low temperature combustion and desulfurization, at Ca/S circa 2, the desulfurization efficiency can reach 90% and greatly decrease the SO2 emission. On the other hand, CFB technology adopts stepped low temperature air supply combustion which keeps the combustion process going under low excess air condition. Thus the produce and emission of NOx is also greatly reduced. The CFB technology is also advanced in its high combustion efficiency, capability of firing low rank fuel, wide range of boiler load and convenience in ash reuse. So CFB is growing rapidly throughout the world. As the environment protection requirement is getting more and more rigid, it is commonly acknowledged that CFB is, so far, one of the most practical and feasible combustion facilities. Design of boilers of this project is made by SBWL using advanced CFB technology based on the experience of design, manufacture and operation of tens of ultra high

pressure medium reheat CFB boilers. When firing design coal, boiler can operate within 70%~100% rated load at constant pressure and within 50~100% rated load at slide pressure. SH outlet steam can remain at rated parameter. When firing design coal or check coal, boiler can remain stable firing within 30~100% rated load 1. BOILER DESIGN BASIS AND PERFORMANCE DATA This is an island, half-open boiler, with complete steel structure and light steel roof on the top. It is jointly fixed by support and hanging measures. The furnace floor elevation is 9 m above ground. Here is some of the boilers characteristics: single drum natural circulation, confluent downcomer, balance draft, thermal insulated cyclone gas/solids separator, CFB combustion, air and water cooled fluidized bed ash cooler, convection heat- absorbing surface designed in rear pass, superheater with two stages of spray water atteperators, reheater temperature controlled by gas damper and auxiliarily by emergency spray water device. 1.1 BOILER MODEL AND TYPE Model: SG-460/13.7-M573 Type: super-high pressure intermediate reheat, single drum natural circulation, circulating fluidized bed boiler 1.2 BOILER TECHNICAL DATA VWO ITEM SH steam flow SH outlet steam pressure SH steam outlet temperature RH steam flow RH inlet steam pressure RH outlet steam UNIT CONDITION t/h MPa(g) 447.4 13.7 CONDITION 417.9 13.65 T-MCR

t/h Mpa(g) Mpa(g)

540

540

366.2 2.77 2.63

343.1 2. 6 2.47

pressure RH inlet steam temperature RH steam outlet temperature Feedwater temperature 324 319

540

540

247

245

1.3 EXPECTED MAIN PERFORMANCE OF STEAM GENERATOR (AT T-MCR OF DESIGN COAL) ITEM Designed efficiency (LHV) guaranteed efficiency (LHV) Solid unburnt loss PH outlet dust concentration UNIT % % % g/Nm3 VALUE 81.87 81.5 2.77 50.2

1.4 FUEL 1.4.1 COAL AND ASH SPECIFICATION 135MWe CFB boiler design fuel items description symbol unit design coal

Proximate analysis( As received basis) 1 2 Moisture (Total) Fixed Carbon 3 Ash 4 Volatile Matter 5 Volatile Matter(dry ash free) Vdaf % 41.17 Var % 14.00 Aar % 54.00 Mad % 18.00 Mar % 12.00

6 LHV 7 HHV

Qnet.ar

kJ/kg kcal/kg

8812 2105 9630 2300

Qnet.ar

kJ/kg kcal/kg

Ultimate analysis(As received basis) 1 Carbon 2 Hydrogen 3 Oxygen (by difference) 4 5 6 Nitrogen Sulphur Total Analysis of ash ( Fly ash) 1 Silica 2 Alumina 3 Iron oxide 4 Manganese 5 Titanium oxide 6 Potassium oxide K2O % 0 TiO2 % 1.5 MnO2 % 0.03 Fe2O3 % 8 Al2O3 % 24 SiO2 % 60 % 100 Nar Sar % % 0.7 0.5 Oar % 6.5 Har % 2.3 Car % 24

7 sodium oxide 8 Calcium oxide 9 Magnesium oxide 10 Sulphuric anhydride 11 Phoshorus Pentoxide 12 Others 13 Total Ash Fusion Temp. at oxidizing media 14 Initial deformation temperature 15 Hemi spherical temperature 16 Flow temperature FT Ash Fusion Temp. at reducing media 17 Initial deformation temperature DT 1050 ST DT 1210 % 100 % 0.22 P2O5 % SO3 % 0.25 MgO % 2 CaO % 4 Na2O % 0

1320

1350

1.4.2 OIL FOR IGNITION AND AUXILIARY FIRING This boiler use N0 light diesel oil for ignition and auxiliary firing. The coal specification is as follow:

Sl.No. 1. 2. 3. 4. 5. 6. 7. 8. 9. Flash point

Particulars

Unit Deg. C min. Cst 0C % max. % max. % max. % max. % wt Kcal/kg

(IS : 1593) 66 2.0 - 7 12 0.02% 0.05% 0.1% 1.8%

Viscosity @ 150C Maxi. Pour point Ash content by weight Free Water content by volume Sediments by weight Total sulphur by weight Carbon residence (Rams bottom) Approximate gross calorific value

In the order of 11000

10.

SP gravity at 150C Max.

0.81

1.5

STEAM AND WATER QUALITY

To ensure the boiler outlet steam quality, the boiler water and steam quality must be strictly controlled, especially the feedwater quality. The boiler feedwater, boiler water and steam quality should be accord with GB/T12145-1999, The Standard Of Water And Steam Quality For Power Plant Facilities And Steam Powered Equipments. 1.6 SITE CONDITION The condition as follow: Project 4 x 125 + 20 % MW Thermal Power Plant Owners consultant DESEIN PRIVATE LIMITED, DESEIN HOUSE, GREATER KAILASH II NEW DELHI 110048 Location Village:Dongamahua,Tehsil: harghoda, District Raigarh Longitude:220653to 20713

Latitude:833145to 833226 Site Adjacent to existing coal washery of JSPL. Nearest Airport Domestic Raipur (350 KM) International Kolkata Nearest Seaport Nearest Railway Station Kolkata Raigarh Railway Station on the Mumbai Howrah main line 54 Km way from the site Access to site Metrological data A B I DBT II DBT III Maximum WBT IV Minimum WBT C D I. II E RELATIVE HUMIDITY RAINFALL Annual Rainfall Tropical monsoon WIND VELOCITY AND PRESSURE IS:875-1987] I. Basic wind speed. 50 m/sec at 10M above mean retarding surface. II Wind Direction North East [AS PER 1400 mm to 1600mm Varies from 19% to 85% Temperature, 20.6 Deg C Temperature, 30.8 Deg C Minimum Temperature, 12.41 Deg C Altitude [Observatory] Ambient Temperature Maximum Temperature, 47.2 Deg C 280 m above MSL

June to October

III. F

Terrain classification Seismic Zone

Category II Zone III, as per IS-1893, Part 1

1.7 Boiler working conditions aUnit working mode It can be run following compound slide pressure mode as well as constant pressure mode. bLoad kind of unit The unit is designed to meet the needs of running safely and stably on condition that the minimum steady-state combustion load without oil-feeding is not large than 30% BMCR cUnit annual working mode The annual average working hours is no less than 7500 hours dFeedwater regulation 2 110 electric adjusting speed pumps are set for the unit, one is operating , the other is backup. Feedwater operation desk has no main adjusting valve, the 30% BMCR starting adjusting valve is set to meet the requirement of start and low load condition. eBypass settings Two stage series-connedted bypass system is used to meet the function of quick start and working substance return. The HP bypass flow capacity according to the 60% BMCR of steam flow. The LP bypass flow capacity according to the HP bypass flow adding the HP bypass desuperheater flow. The bargainor shall consider protecting RH against dry-burning. 1.8 BOILER WATER VOLUME (M3) WATER ECO 73.22 DRUM COOLING 30.70 68.90 108.22 107.24 388.28 SH RH TOTAL

2 BOILER OVERVIEW AND CONSTITUENT SYSTEM 2.1 OVERALL BOILER INTRODUTION

The boiler consists of steam drum, suspensory whole-membrane waterwall furnace, thermal insulated cyclone separator, U-type seal pot duct and rear pass convection heat-absorbing furnace. The drum, boiler water wall and rear pass cover wall are all suspended. Cyclone and cyclone outlet duct are laid on steel beams. The primary of economizer pipes are suspended on weight bearing girder by pipe clamps and is laid on the steel beam through economizer frameworks column and ox leg structure. U-type seal pot and tubular air preheater are supported by steel beams. An independent steel structure is settled between column J and column K to support the heavy primary economizer and tubular air preheater. Furnace and rear pass cover superheater expands downward. There is an expansion center designed in boiler waterwall, cyclone and rear pass respectively, the expanding parts are connected by non-metal expansion joints. The figure of the boiler is eudipleural. Secondly span is designed between left and right steel structure, upon which disposed platforms, passages, economizer inlet pipes, main steam pipes, RH inlet pipes and RH outlet pipes. There are 2 water panels and 14 superheater screens on the upper furnace. The panels are disposed symmetrically on left and right sides. Between the furnace and the rear pass are two thermal insulated steel plate cyclones. The hull of the cyclone is made of carbon steel plate. On the inner side of the hull is a layer of thermal insulation material which is between the hull and the abrasion resistant layer. A circular support is disposed between the cyclones column and the cone, laid on the steel beam. Below each cyclone there is a non-mechanical U-type seal pot, at the bottom of which there are fluidizing holes that fluidize the solids and return the solids to the furnace. The rear pass is divided into two gas ducts by partition wall superheater. In the front gas duct disposed the reheater, hung by superheater hanger tubes and other hangers on the furnace top steel beams. In the back gas duct, the high-temperature superheater (HTS) and secondary economizer is disposed successively through the direction of gas flow. The pipes of HTS and secondary economizer are attached to the rear wall superheater and partition wall superheater, which transfer the load to the furnace top steel structure. In the superheater system,

primary spray water attemperator is set between the cold end and the hot end of the superheater screen while secondary spray water attemperator is set between superheater screen hot end and HTS. As CFB is characterized in its little gas temperature difference, it is unnecessary to cross and combine the pipes from left and right, and this arrangement is more practical. Gas temperature control damper is disposed at reheater and secondary economizer outlet to control the gas flow passing the reheater and thus control the outlet steam temperature. Emergency spray water system is disposed on both sides of the reheater inlet ducts. When the steam turbine high pressure cylinder outlet temperature goes above designed parameter, the emergency spray water system will be actuated to ensure the reheater working safely. Two stages of air supply are used in the boiler. Primary air goes through the bed plate at furnace bottom and fluidizing holes into the furnace. Secondary air goes from combustion chambers cone into the furnace. There are six coal-feed holes and six limestone feed holes symmetrically disposed before furnace. At furnace bottom, the steel plate made primary air chamber is hung on the lower header of waterwall. Onbed start-up ignition is used and four (2 on either side wall) powerful torch oil guns are disposed on the bed. And there is 4 drum ash cooler at the bottom of combustion chamber. Circulating fluidized bed combustion is used in this boiler. Under circa 880 bed temperature, the fuel, air and limestone mix in the dense-phase zone. Fluidized coal particles burns and gives heat. Heat transfers from high temperature bed materials and gas to waterwall surface. Limestone is calcinated into CaO and CO2. CaO combines with SO2, which is a product of fuel combustion, and realizes in-furnace desulfurization. The gas containing a large mass of bed materials goes tangentially into the two cyclones from the furnace back wall outlet and is separated from the solids by the cyclones. Then the clean gas leaves the center cylinder of the cyclone and passes HTS (RH), ECO in the rear pass and the air preheater and is finally released to air with its temperature drops to about 140. The solids collected by the separators are returned to the furnace through the vertical pipes and the U-type seal pots, hence the solids recirculated combustion. Because the solids (ash, unburnt

carbon, CaO and CaSO4) are repeatedly fired during the recirculation, the availability of desulfurizer is greatly increased. The bottom ash (bottom ballast) is cooled in the ash cooler disposed on both sides of the furnace and is discharged when its temperature is below 150. The mean elevation of the drum is 48220 mm. The distance from column G to K is 37200 mm. The main span width is 21000mm and the secondary span width is 5000 mm.

2.2 Steam Water System The steam water circulation system includes back pass economizer, drum, generating surface (boiler water wall and water wall panels), back pass enclosure SH, cold and hot platen SH, high temperature SH and RH.

2.2.1 Feedwater and Steam Water Circulation System (drawing 2.2.1, drawing2.2.2) There are 2 electric adjusting feed pumps, and the capacity is designed according to 100%BMCR. The total 2 circuits are set for feed water: a DN225 main feedwater duct with an electric gate valve and a non-return valve; a DN100 bypass feedwater duct with an adjusting valve and 2 shut-off valves. When the boiler load is within the 30-100%BMCR, use the adjusting feed pump to control the feedwater; when the boiler load is lower than 30%BMCR, switch to the bypass feedwater duct and use the feed adjusting valve to control the feedwater.

Fig 2.2.1 feed water system C1drum E1ECON inlet tube E2Low temp. ECON inlet header E3Low temp. ECON E4Low temp. ECON outlet header E5ECON duct connection E6: High temp, ECON inlet header E7High temp. ECON E8High temp. ECON outlet header E10ECON riser tube E11ECON recirculating tube

fig. 2.2.2 steam water circulating system C1drum C2collective downcomer C3C4C5C6water wall lower header C7C8C9C10water wall tubes of furnace C11rear wall outlet ring header C12C13water wall upper headerC14water wall downcomer C15water wall inlet header: C16water wall tubesC17water wall outlet heade

C18C19water wall steam-water riser tube

Firstly the feedwater flows from one side of the boiler into the primary economizer inlet header. Secondly it flows upstream through 2 horizontal-arranged economizer ducts. Thirdly after it is heated, it flows into the second stage economizer ducts. Finally it converges at the economizer outlet header, and then flows through 2 connecting ducts into the drum. One economizer recycle duct with 1 electric shut-off valve and 1non-return valve is set between the drum and the header at the primary economizer inlet. When the boiler is starting up, turn on the electric shut-off valves in the duct. A natural circulation circuit is established between the economizer and drum, which prevents the dead water evaporation in the economizer and assures the safety of the economizer when the boiler is starting up. When the feedwater is enough, the electric shut-off valves in the duct can be shut off. The recycle duct capacity is designed according to 5%BMCR. The steam water circulation system includes drum, big diameter downpipes, water wall panel downpipes, water wall, water wall panels and lead-out ducts. The 4 356 big diameter downpipes leaded from the water space of the drum are connected with the lower headers of water wall at the front, left and right furnace walls separately. According to the combustion characteristics of CFB, the heat load distribution in the furnace is very homogeneous. So the separating circuit is not set in the water wall design, and the tee junction is used to connect the lower headers of water wall into a ring circuit and the inside medium is connected. The water wall is made of membrane wall containing 63.5bare tube and flat iron. The boiler water is continuously heated when it flows up along the membrane waterwall, and the steam-water mixture is formed gradually. The steam-water mixture flows from the headers at the upper outlet, and then it flows through 36 168 steam-water lead-out pipes to the drum. At the same time, the water is supplied from 2 219water wall panel downpipes leaded from the water space of the drum to 6 water wall panels at the upper of the furnace. The steam-water mixture formed in the water wall panel flows through 4 168 steam-water lead-out pipes to the drum. The steam-water mixture is well separated in the drum by cyclone and corrugated plate. The separated water goes into the drum and water circulation again, and the purified steam goes into the SH system by steam-water lead-out pipes at the furnace roof.

The circuits of water wall and water wall panels are two separated parallel ones, and the flow distribution between them depends on their own surfaces, furnace heat load and water circulation coefficient. Once the flow distribution is determined, specifications and quantities of downpipe and lead-out pipe can be selected according to the outcome of water circulation calculation. Thus, the reasonable water circulation coefficient is guaranteed, and the water circulation is stable and reliable.

2.2.2 Superheated Steam System (drawing 2.2.3) The saturated steam leads out from the top of the drum, and it flows through 8 168 connecting ducts into the header above the left and right side enclosure SH. Secondly it flows into the header under the side enclosure SH. Thirdly it converges through header at the header under the front enclosure SH. Fourthly it flows through front enclosure SH, roof enclosure SHrear enclosure SH, parallel-arranged pendant tube SH and division wall enclosure SH. Fifthly it converges at the header above the division wall enclosure SH. Sixthly it flows through 2 273 connecting ducts into the header at the inlet of cold panel SH. Seventhly it is heated when it flows along the heating surface and then flows into the primary attemperator. Eighthly it flows into the hot panel SH, and then it is attempered by the second stage attemperator. Ninthly, it flows through 2 324 connecting ducts into the high temperature SH in the back pass and is heated to the required temperature. At last it flows through the main steam duct from the header at the outlet of the high temperature SH into the high-pressure tank of the steam turbine. The flow of steam is as flows: saturated steamleft and right side enclosure SHfront enclosure SHroof enclosure SHrear enclosure SHdivision wall enclosure SH, pendant tube SH cold panel SHprimary attemperatorhot panel SH rear panel second stage attemperatorhigh temperature SHmain steam outlet

fig. 2.2.3 SH steam system S1saturated steam riser tube S17primary SH inlet header S2clad side wall upper header S18primary SH panel tube S3clad side wall tube S19primary SH panel middle header S4clad side wall low header S20primary SH panel tube S5clad front wall low header S21primary SH panel outlet S6clad front wall tube S22primary desuperheater S7clad front wall upper ring header S23secondary SH panel inlet header S8S9clad roof & rear wall tube S24secondary SH panel tube S10clad rear wall low header S25secondary SH panel middle header S11connecting pipe S26secondary SH panel tube S12partition low header S27secondary SH panel outlet header S13partition tube S28secondary SH outlet header tee S14hanger tube S29secondary desuperheater S15partition wall upper header S30high temp. SH inlet header S16connecting pipe S31high temp. SH tube S17primary SH panel inlet header S32high temp. SH outlet header

S33high temp. SH outlet connecting pipe

2.2.3 Reheated Steam System (drawing 2.2.4)

The steam discharged from the high-pressure tank of the steam turbine flows through 2 426connecting ducts into the RH. The RH is arranged in one stage,

which comprises 4 sets of tube. All sets are arranged in the front duct of back pass and are suspended on the SH pendant tube. The reheated steam is heated and flows through 2 457 connecting ducts into the inter median cylinder of turbine. An

emergency attemperator is set on the duct of RH inlet. When the temperature of the exhausted steam from HP cylinder of turbine is higher than the design value, the emergency attemperator will be started to lower the temperature of reheated steam and thus guarantee the safe operation of RH. The temperature of reheated steam is attempered by flue gas baffle at the outlet of back pass.

Fig 2.2.4 RH steam system

R1R2RH emergency spray R5RH outlet header R3RH steam inlet pipeRH inlet header R6: RH steam outlet pipe R4RH tube

2.3 Burning System 2.3.1 Fuel Crushing System Raw coal is crushed through two stage crushers. The requirement of grain size at the outlet of the last-stage crusher is seen in Drawing 2.3.1. Raw coal with the eligible final grain size goes into the big coal bunker, and is conveyed by a coal feeder to the above of coal chute. The sweeping air is set under each coal chute so that the coal can be fed into the furnace homogeneously.

2.3.2 Coal Feeder and Coal Chute Six coal feeders are arranged in front of furnace. They connect the big coal bunker and coal chute and convey the crushed coal to the inlet of coal chute according to the boiler load requirement. Considering the repair of coal feeder and fuel change, the feeder design capacity should have 100% reserve margin. In the coal chute, the coal arrives at the feed port of furnace by gravity, and finally goes from the front water wall into the furnace. The sweeping air is provided at the feed port of furnace so that the air cushion can be formed in the duct and at the turning corner of duct. It makes coal flow fluently, have some kinetic energy and distribute evenly, and it prevents coal local piling. The material of coal chute is stainless steel tube material of 45710mm, and the lower part of it is the ceramic lining tube of internal diameter 433mm, which prevents coal clogging. Expansion joint is set on the perpendicular section of coal chute. It absorbs the heat displacement of water wall and the heat displacement is as follows:
Item Feed Unit port#1 port#2 port#3 port#4 port#5 port#6 Feed Feed Feed Feed Feed

Down mm Front of Furnace Left mm mm 140 20 28 140 20 18 140 20 7 140 20 / 140 0 20 /

14

20 /

Right mm / / / 7 18 8

-2

Note: The feed ports are numbered from left to right, and the expansion center of boiler takes the symmetrical centerline of boiler as origin. To prevent backflow of gases from the furnace to the coal feeder, a cold air, used as sealing air to protect the coal feeder, should be leaded from the cold air duct at the outlet of primary air fan to the coal feeder and coal chute. The inlet of coal feeders sealing air is set at the inlet of coal feed, and the inlet of coal chutes sealing air is set under the sluice valve.

2.3.3 Start-up Oil Burner There are 4 above-bed start-up burners (the capacity is 43000kg/h) in the boiler. The oil gun is the one with pressure air atomization, center return flow oil, wide control band and convenient operation. The pressure of main line feeding oil is 1.8MPa and the flow is 12t/h. The oil system at the front of furnace takes the pressured air as the sweeping medium, and the sweeping pressure is 0.75MPa and the temperature is 250. The ignition oil gun is the advance and retreat type one and there is some space between gun and anti-abrasion sheet surface inside the furnace. When the boiler operates normally, the above-bed ignition oil gun can be retreated to the outside of furnace. At the same time, certain amount of cold air is maintained, which prevents burners burnout. The high energy arc ignition device and flame detector are supplied with the above-bed ignition oil gun.

When the boiler starts up coldly, the start-up bed material is put into the CFB. Firstly turn on the primary air fan and make bed material little fluidized. Secondly turn on the secondary air fan, put the ignition oil gun into use and heat bed material according to the start-up chart. Thirdly after the bed temperature increases to 620C and keeps stable, feed the coal to guarantee the reliability of ignition. During the coal feeding, small amount of coal is fed at interval at first. And after the coal is fired, feed more coal and start the feed device continuously.

2.4 Flue Gas and Air System The boiler is a balance draft one, and the pressure zero point is set at the inlet flue gas duct of cyclone. The circulation of material in CFB is started and maintained by FD fan (including primary and secondary air fan) and ID fan. The combustion air from the primary air fan goes through the air heater and primary air preheater in line and then splits in three parts: the 1st one is as fluidizing air that goes into the air plenum at the furnace bottom and through the furnace capped nozzles, and it fluidizes the material on the bed and forms the upward solid circulation; the 2nd one is as sweeping air extracted through a trunk duct from the air plenum to the front of furnace and then 6 branch ducts from the trunk duct to the coal chute, and the total flow is 18600Nm3/h; the 3rd one is a high pressure cold air extracted from the cold air duct behind the outlet of the primary air fan as sealing air for coal feeder and coal chute, and the total flow for coal feeder is 2520Nm3/h and the total flow for coal chute is 672Nm3/h. The secondary air is heated when going through the air heater and primary air preheater in line, and then it is leaded to the front of furnace. Several branch ducts leaded from the air plenum goes from the upper of front, rear wall and emulsion zone of furnace to the furnace firing chamber. It is also used as cooling air for oil gun. When the boiler load is 100%B-MCR, the proportion between primary air and secondary air is about 55:45. When the boiler load decreases gradually, the proportion between primary air and secondary air changes accordingly and the proportion of primary air increases gradually. The details are seen in Collection Chart of Boiler Thermal Calculation. The flue gas with solid particles goes through the inlet duct of cyclone from the furnace into 2 cyclones tangentially. In the cyclone, coarse particles are separated from flue gas, and the flue gas goes through the cyclone into the back pass. The flue

gas is cooled by the convection heating surface. Then it goes through the tubular air preheater into the dust collector and fine particles are left out of flue gas. Finally it is sent into the stack by ID fan and discharged to the atmosphere. One portion of high pressure fluidizing air is used as fluidizing air for U seal pot; the other one is used as greasing air for erect duct and return duct of seal pot. One portion of FBAC fluidizing air is used as fluidizing air for FBAC; the other one is leaded to the outlet of furnace slag-drip opening and used for sweeping tapered valve hood at the top of slag-drip valve shaft. It assures the smooth feeding of FBAC. 2.5. Bed material system Start-up bed material feed-hole is designed at anabatic vertical pipe of two U-type seal pots, start-up bed material bin is arranged in boiler proper structure, the height of strat-up bed material bin shall be above the level of start-up bed material feed-hole, to ensure bed material can flow into seal pot of itself. Start-up bed material bin is also arranged at front of furnace and connected with feeder, bed material is filled into furnace by using feeder and feed chute. Start-up bed material is usually adopt sand, or adopt coal ash is burned off, grain requirement of bed material see 2.5.2 bed material grain distribution.

Bed material injection quality is 13600kg before boiler start-up, including bed material for furnace, seal pot and ash cooler. If CFB slag as bed material in furnace, the height is about 880mm; if bed material is sand, the height is about 760mm.

2.6 Ash circulation system Ash circulation system is composed of furnace, cyclone and U-type seal pot. Primary air enter into emulsion zone at furnace bottom through nozzle arranged at water-cooled air distributor, to make material in furnace fluidize, HT material, coal and limestone mix completely, and complete burn and desulfurize in emulsion zone. Large grain material flow into emulsion zone along boiler water wall after it is fluidized and suspend at certain height; small grain material leave furnace carried by flue gas, tangential enter into cyclone with high speed through nonprismatic cyclone inlet duct. Flue gas rotate with high speed in cyclone, solid grain that its quality is

large is thrown cyclone inside wall because of centrifugal force effect and flow into seal pot along inside wall, but small solid grain enter into boiler back pass by flue gas through vortex at cyclone upper. Cyclone design is adopted ALSTOM company mature and advanced technology, separate rate is more than 99.5%, can separate HT solid material from gas flow, then enter into furnace through seal pot to maintain high grain concentration in furnace and ensure large heat surface heat-transfer rate, ensure that fuel and desulfurizing agent can completely burn off and chemical react in multi-circulation. Truly materialize CFB boiler high efficient and clean combustion technology. Ash circulation ratio is about 30, bed pressure in furnace emulsion zone can reflect furnace ash concentration indirectly, control ash concentration at reasonable level by ash discharge at furnace bottom. 2.7 Tapping slag and ash discharge system Ash content of coal is discharge as slag at furnace bottom and as fly ash at boiler back-end. The quotient of each kind of ash content is different according to coal granularity, ashing feature. Based on this boiler design coal and coal granularity into furnace, slag is 45% in total ash, mean granularity is about 500um, fly ash is 55% in total ash, mean granularity is about 30um. Four ash coolers is arranged in this boiler, set at the furnace bottom and arranged at 0m layer, adopt water cool as main cooling form. The total ash of boiler is . 16091kg/h, The designed ash discharge amount of each ash cooler is 50% in total ash. Only one ash cooler can meet the needs of normal operation for boiler. The feed slag temperature is 880, and the tapping spout temperature is 110. 2.8 Attemperation system 2.8.1 SH steam attemperation system

fig 2.8.1 SH steam attemperation system

SH steam attemperation system is divided into two stages. Primary spray desuperheater is arranged between cold end outlet and hot end inlet of platen superheater to control steam temperature into hot end inlet of platen superheater. Primary desuperheater is one, proper size is32428, material is SA335-P12, spray tube adopt flute-type structure. Secondary spray desuperheater is arranged at connection pipe between hot end outlet of platen superheater and HT superheater inlet to control steam temperature of HT superheater outlet, and make SH steam

temperature attain design value. Secondary desuperheater is two, proper size is324 28, material is SA335-P12, spray tube adopt flute-type structure. Water source of desuperheated water is introduced to the front of HP heater and feedwater operation platform, the max. spray water amount in this system has been considered desuperheated water amount needed in high preesure heater out of servicedrawn point temperature of desuperheated water is 172, pressure is about 16Mpa(g) under B-MCR condition. See drawing 820573-E1-06 (superheater desuperheated water pipeline), the interface position of desuperheater water pipeline and design institute is at the front of column G. adopt reducing tee to divide into three branch pipe at the end of desuperheated water manifold, one cutout valve is set at each branch pipe, this valve can be closed under boiler emergency condition to separate electric control valve behind it. Set another cutout valve behind electric control valve, close this valve when control valve is maintained. Set one drainage (backwash) pipeline between cutout valve and control valve, can termly check cutout valve is leakage under closed condition or not. Spray water control valve adopt imported produce, can meet the requirement under various conditions of boiler. Flow nozzle is set at each branch pipe of desuperheated water pipeline. 2.8.2 RH steam attemperation system Gas tempering damper is main in RH steam attemperation, emergency spray water is only used at non-normal condition, and viz. emergency spray water is used when RH steam inlet temperature is higher than design value to ensure reheater safety 2.8.2.1 Emergency spray water Two emergency spray water devices are apart arranged at left and right side pipe of heater inlet, water source comes from pump pigtail, the pressure is about 6.0Mpa(g), temperature is 172 under B-MCR condition. At desuperheated water manifold, adopt reducing tee to divided pipeline into two parallel circuits, and apart enter into emergency desuperheated spray water desuperheater at two sides of boiler. One cutout valve is set at each branch pipe; this valve can be closed under boiler emergency condition to separate electric control valve behind it. Set another cutout

valve behind electric control valve, close this valve when control valve is maintained. Set one drainage (backwash) pipeline between cutout valve and control valve, can termly check cutout valve is leakage under closed condition or not. Spray water control valve adopt imported produce, can meet the requirement under various conditions of boiler. Flow nozzle is set at each branch pipe of desuperheated water pipeline This system sees drawing 2.8.2.

Fig 2.8.2 RH spray desuperheater system 2.8.2.2 Gas tempering damper

Gas tempering dampers are apart arranged below reheater duct and HT superheater duct, gas damper in every duct is divided into left and right group, 4 groups in all, the type is separating-chamber. Damper of every group at reheater side is composed of 7 pieces of blade; at superheater side is 3 pieces of blade, and combined by the tie rod. The tie rod is laid upon the damper to avoid abrasion. The damper is controlled by the electric actuator via the tie rod; Control the damper according to the following suggestions: (1) Limiting position protection: the limiting inclination () of the damper and level is 15. (damper close completely is 0 ) (2) Operation with normal load: the damper regulates the temperature of the reheated steam. When regulating, the damper of the RH flue gas duct and SH flue gas duct should be turning at the same time but in the opposite direction, and the sum of these two dampers angle should be always kept as 90. Gas quotient of duct of reheater side under various load condition sees boiler heat calculation data sheet. (3) The blow stage before the boiler start-up: The dampers of gas flue are completely opened. (4) The start-up stage: is 15at the RH side and 75at the SH side, so most flue gas flow through the cold SH. This can not only protect the RH, but also increase the temperature of the superheated steam quickly, and then reduce the start-up time. 2.9 piping system Boiler piping system is mainly composed of drainage, blowdown, vent, exhaust, etc. pipeline with related pipe and valve. 2.9.1 Drainage, periodic blowdown chemical feed , acid wash pipeline 17 lines are set in boiler drainage pipeline in all, viz. economizer inlet pipe 1, economizer outlet header 2, ring lower header under enclosure front wall 2, both ends of lower header under enclosure rear wall 2, medium header of platen superheater cold end 1, medium header of platen superheater hot end 1, HT superheater inlet header 2, pipe at superheater outlet 2, reheater inlet 2, reheater outlet 2, connected to boiler operation layer. 4 periodic blowdown lines are arranged at water wall ring lower header, one 2 cutout valves are set in each pipeline in series, valve adopt DN20. all drainage pipeline is

periodic blowdown pipeline is set at every water wall panel lower header. Every pipeline is arranged with 1 imported electric periodic blowdown valve, in series with one cutout valve before it, can close cutout valve under boiler emergency condition to isolate electric periodic blowdown valve. Finally, above 6 periodic blowdown pipeline converge in periodic blowdown manifold header, manifold header outlet is arranged with high pressure difference throttling valve and electric periodic blowdown valve in series to reduce inlet and outlet pressure difference of blowdown valve, to improve the condition at operation, and to extend its life. The quality of the steam and water in operation is controlled by continuous blowdown. Only when the boiler first start-up or start-up after overhaul, or the continuous blowdown cannot maintain the quality of the steam and water by some reasons, the periodic blowdown system will be turned on. The support and suspender of the periodic blowdown duct should be designed properly and meet the requirements of the expand displacement and the periodic blowdown duct wont oscillate when it is turned on. Besides above normal drainage, another emergency drainage pipeline is set in boiler, introduced boiler operation layer from drum bottom. Pipeline is arranged with two DN3 electric cutout valves, immediately open this valve when drum water level exceed normal level, after reach normal level, close the valve. Chemicals feed pipeline is arranged at the front of boiler, connected to drum front of bottom, one non-return valve and one cutout valve are arranged in series in this pipeline. One acid wash pipeline is set at waterwall front and rear wall header.

2.9.2 Vent, nitridation ,samplingpipeline 10 vent pipelines are set between economizer and HT superheater, 2 vent pipelines are set at reheater outlet, and 2 cutout valves in series for every pipeline. There is 10 nitrogen injections in all set at economizer outlet pipe, saturated steam riser tube, the connection pipe between clad SH and platen SH, primary stage desuperheater, connection pipe between platen superheater and HT superheater and reheat outlet pipe, nitridation pipeline is set between two cutout valves of vent pipeline, 1 cutout valve is arranged at each pipeline. Shall open vent valve and drainage valve before boiler ignition, close vent valve and part drainage after having certain pressure, dont close superheater vent valve until unit is on-line, avail to control main steam temperature and pressure, close reheater vent valve and drainage valve before condenser in vacuum.

Nitridation pipeline is for boiler shutoff for long time (exceed one month), boiler adopt nitridation or other method. Boiler shall be draughty when filling nitrogen or in nitridation maintenance period. It is 8 lines for boiler sampling, viz. sampling of feedwater, boiler water, saturated steam, SH steam and RH steam. Feedwater sampling is set at feedwater manifold, boiler water sampling is set at continuous blowdown pipe at drum both ends, 2 points are set at steam riser pipe for saturated steam sampling, 2 points of SH steam is set at HT SH outlet pipe, two cutout valve are arranged at each pipeline.2 points are set at RH inlet pipe for RH steam sampling, one cutout valve is arranged at each pipeline. 2.9.3 Continuous blowdown pipeline The continuous blowdown converge in one line after it is connected from the downside of the drum both ends, mainly for controlling and keeping boiler water quality, the capacity of blowdown shall accord to boiler water chemical analysis. Continuous blowdown pipeline is arranged with one imported air-operated valve, another high pressure difference control valve in series to reduce the pressure difference of the periodic inlet and outlet of the air-operated valve, to improve the condition at operation, and to extend the life. The front and back of air-operated valve are also arranged with one electric cutout valve while set bypass for air-operated valve service 2.9.4 Safety valve discharging pipe Overpressure protection of boiler pressure part is realized by setting certain safety valve. There are 3 safety valves for SH steam system, thereinto 2 valves for drum, one for superheater outlet pipe, additionally set 2 EBV valves in series at superheater outlet pipe (each for left and right). pipe. There are 4 safety valves for RH steam system, thereinto 2 valves for reheater inlet pipe, 2 valves for reheater outlet pipe. There are 9 silencers in all according to connection meeting minutes requirement to design silencer and discharging pipe, thereinto 2 silencers for drum safety valve, one for superheater safety valve, two for superheater EBV valve, 2 for reheater inlet safety valve, 2 for reheater outlet safety valve. All discharging pipes are connected from safety valve to boiler roof upper side. 2.10 Measuring point 2.10.1 Measuring point arrangement for steam-water system Whole steam-water system is arranged with various function instrument measuring points according to different part and requirement. Besides local

monitoring pressure gauge, other pressure measuring points of steam-water system shall be arranged with primary valve, the owner can set control instrument according to requirement, 5 pressure measuring points for drum, two of these for local monitoring. SBWL supply whole set of valve and pressure gauge, other pressure measuring point is supplied with primary valve, the owner can introduce to anywhere according to checking, protection, adjustment etc. requirement. It is necessary condition that keep boiler normal water level for natural circulation boiler safe operation. Usually set certain number water gauge for monitoring method. This boiler adopt dual-color water gauge arranged at drum both end head as for water level local monitoring, the visual height of water gauge is 550mm, one TV monitor is set prior to each water gauge, can interlaced monitor water level of drum both ends by switching device. One electric connecting point water gauge set at drum left head is for water level monitoring and alarm. Boiler phase-down automatically (see sheet 2.10.1) when water level exceed protection limit value. Additionally one high level electric connecting point water gauge is arranged at drum right side head, besides have effect as water gauge at left side head, also can meet drum full water level checking requirement when boiler shutoff. Sheet 2.10.1protection limit value for drum water level control Level mm Below drum Centerline 150 Measuring point Thermal control interlock 4 water level balance vessels is set at head of drum both ends for checking, protection and adjustment under boiler operation. for Normal water level Allowable water level Audible alarm Emergency discharge Phasedown Phasedown 50 100 150 175 230

Drum is very important pressure part for boiler; boiler start-up and shutdown speed will affect drum thermal stress amplitude, so affect drum life breakage, and so

control start and shutdown speed according to the requirement of boiler start-up and shutdown curve strictly. 4 couples outside wall temperature measuring points and 2

couples inside wall temperature measuring points are arranged along drum axes direction, avail to monitor drum wall temperature difference under boiler start and shutdown. The temperature difference between drum upper wall and below wall is not less than 50 and same as to inside wall and outside wall when boiler cold start. 2.10.2 measuring point arrangement for gas and air system Besides gas temperature, pressure, sampling measuring point as same as pulverized fuel boiler are arranged at CFB boiler, also set a lot of furnace pressure difference, bed temperature, fluidizing air pressure, air flow measuring point to provide needed monitoring method and protection measure, and to ensure boiler safety operation. 6 couples gas pressure difference measuring point are apart set furnace below, medium upper and primary air box, pressure transmitter convert pressure signal into electric signal, connect with slag valve actuator at ash cooler inlet. Slag valve actuator will operate; quicken tapping slag to make furnace bed pressure keep in regulated range when furnace pressure difference exceeds set value. Additionally set 4 pressure measuring points and 8 pressure switches interface in furnace, furnace pressure set value is +20.8KPa, -8.7KPa, subatmospheric pressure zero is set at furnace outlet. 2 gas pressure measuring points are set in cyclone outlet duct, can measure cyclone resistance loss. 2 pressure measuring points for material level are set every seal pot vertical pipe to monitor material level in vertical pipe and alarm when material level is too high or too low. 22 gas temp. measuring points are set in furnace, 8 gas temp. measuring points are set in cyclone inlet duct and outlet duct in all, these measuring points are in HT, high speed and high ash concentration zone, so shall select wear-resisting thermocouple to ensure certain service life. Temp. and pressure measuring point is set at all convection heat surface in rear pass, additionally, 2 oxygen measuring points and 14 gas sampling points are set at primary economizer outlet, 5 gas sampling points are set at air preheater outlet duct,

design institute confirm its position. Set enough material temp. and pressure measuring points in seal pot to ensure material fluidize well and return to furnace successfully, and need to monitor HP fluidizing air flow. set air flow gauge in all HP fluidizing air branch pipe and air-filled pipe, to control air injection in design range. 2.10.3 thermal control design information SBWL supply following information. Confirm position, range, number, use, supply range of thermal control measuring points and alarm value and protection

value of boiler operation in these information for design institute thermal control speciality: P&ID drawing for boiler system hole measuring point layout drawing thermal control measuring point arrangement position and description boiler control system information information for start burner oil system at front of furnace information for electric actuator of steam-water system valve 2.11 Sootblowing system Reasonably set soot-blower is important auxiliary method for boiler safety and reliable operation and to prevent heat-transfer effect due to heat surface fouling. Sootblowing system is composed of pressure-reduction station, soot-blower, sootblowing pipe and drainage pipe, sootblowing steam source come form platen superheater cold end outlet pipe prior to primary desuperheater, steam pressure drop to design value through pressure-reduction station is sent to each soot-blower. Sootblowing steam come form auxiliary steam source system in boiler start stage, require that steam temp260, pressure is 0.5~0.7MPa, flow 2m3/h, design institute take charge of auxiliary steam source design. 2.11.1 soot-blower arrangement Because boiler water wall of CFB boiler has strong capacity to clean ash by itself, so not set soot-blower in furnace. Only install soot-blower at convection heating surface of boiler rear pass ,

thereinto 2 pieces of long-length retracting type steam soot-blower are installed at under first layer tube group inlet of superheater, 2 pieces of long-length retracting type steam soot-blower are installed at secondary economizer topper tube group inlet, 2 pieces of semi-retracting type steam soot-blower are installed at under tube group inlet of secondary economizer. 6 pieces of long-length retracting type steam soot-blower are installed at the topper three layer tube group inlet of reheater , 2 pieces of half retracting type steam soot-blower are installed at under tube group inlet of reheat ; 16 pieces of land-rotary steam soot-blower are installed at under & upper tube group inlet and front & rear wall inlet of primary economizer. 12 pieces of half-retracting type steam soot-blower are installed at each tube group inlet of tubular preheater. 2.11.2 Sootblowing pipe sootblowing pipe include all equipments and pipe between superheater extraction opening and all soot-blower, steam pressure drop regulated value through pressure-reduction station, then enter into each soot-blower, auxiliary steam source is connected behind pressure-reduction station. Sootblowing pipe is supplied by soot-blower manufactory. 2.11.3 Sootblowing program control Soot-blower program control can be realized by PLC. System can operate automatically, remote operate and simulated operate in control room; can realize local manual operation on site. soot-blower operate in couple according to gas flow direction, first upstream then downstream, the longest working time of single soot-blower is about 5min.

3. Main part 3.1. Drum and internals drum inside diameter is 1600mm, wall thickness is 145mm, material is SA299, straight length of shell is around 14200mm, total length including head length is about 16000mm, 4 couples measuring socket for outside wall temp. and 2 couples measuring sleeve for inside wall temp. are set in drum wall for controlling temp.

difference of upper and below wall in hydraulic test and operation. Drum normal water level is set 150mm under drum centerline, the distance between highest and normal water level is +50mm, and the distance between lowest and normal water level is -50mm. Drum internals is composed of separator, feedwater washing orifice plate, top uniform flow orifice plate. Separator diameter is315mm, number is 54, connect with each connection box, deflector is installed at separator inlet to improve steam separation effect. The capacity of single separator is about 9t/h under B-MCR condition. Washing orifice plate is arranged above separator, it is keep 30~40mm thickness water at washing orifice plate, separated steam through washing orifice plate cleaned by 50% feedwater came form economizer, part salt dissolve in washing water, washed steam take uniform flow through top multi-orifice plate, finally clean steam introduced into superheater system by saturated steam riser pipe. Steam-water mixture is introduced from water wall and water panel into drum by 36 pieces pipes which diameter is 168. 4 pieces downcomer which diameter is356 come form drum supply water to boiler water wall, in addition 2 pieces downcomer which diameter is219 supply water to 2 pieces of water panel at furnace upper. Boiler feedwater is introduced from economizer outlet header into drum by 2 connection pipe which diameter is219, 12 branch pipe which diameter is108, thereinto 50% feedwater flow through washing orifice plate, another 50% is directly introduced into drum water room. Saturated steam is educed from top of drum, then is introduced into enclosure wall superheater upper header at rear pass both sides by 4 pieces of pipe which diameter is168. Two spring safety valves is arranged at drum both ends, also some needed nozzles for continuous blowdown, chemicals feed, emergency discharge, recirculation of start and shutdown, water gauge and balance vessel are arranged at drum. Boiler steam and water quality shall accord with the requirement of GB/T12145-1999water and steam quality standard for heat power unit and steam

power equipment . 3.2. Water-cooling system furnace heightwidthdepth is 35400mm14795.5mm7683.4mm, boiler water wall tube all adopt diameter is63.56.5, material is SA-210C tube, bare tube and flat steel compose membrane wall, the pitch of tube is 88.9mm, arrange 166 pieces of front wall as same as rear wall, 86 pieces of tube for left side wall as same as right wall. The excellence of membrane wall is: good sealing performance, reducing furnace leakage, and increasing economical efficiency, wall setting structure and support is easy and can adopt light wall setting. Multi-layer buckstay are arranged along the height direction of boiler water wall, increase whole furnace stiffness and keep water wall from deformity due to positive pressure combustion in furnace. Pressure capacity of buckstay of combustion zone under furnace isnt less than +20800KPa,-8700KPa, upper pressure capacity isnt less than 8700KPa. Tube below rear wall is loosed, thereinto 84 pieces of tube form fluidization bed air distributor at furnace bottom, air distributor incline is 2, another 82 pieces of

tube enter into rear wall below header. Wearing layer of air distributor level is 8200, the pitch of water wall tube at air distributor is 177.8mm, arrange 1150 bell-type nozzle in flat steel between water wall tube, nozzle pitch is 355.6mm and arrange in alternation. Nozzle adopt heat-resistant and wearing stainless steel cast, can operate at 1100, has high service life. Front and rear water wall form cone at the angle of 75 degree apart in direction of front and rear, form combustion space emulsion zone. Open any special hole needed by CFB boiler at below water wall in this zone, include 6 coal injection at front wall (6 limestone injection, use one hole as coal feed) , 2 start burner for left side wall as same as right side wall, 2 seal pot material return hole at rear wall, 1 access door for overhauling at right side wall, one furnace slag notch and one ash cooling air-return porthole at right side wall as same as left wall, two layer that it is 18 secondary air injection in all are arranged at front and rear wall. At same time arrange enough temperature, pressure and sampling measuring porthole in this zone. Arrange water wall panel and platen superheater along width direction at furnace

upper, transverse pitch is 711.2mm and 889mm, 14 pieces of platen superheater are arranged in medium, one pieces of water wall panel are arranged in left side as same

as right side. Cold heating surface of platen superheater is composed of 38 pieces of tube which diameter is 44.5 5, material is SA213-T12, longitudinal pitch is 60.3mm, aggregately arrange 7 pieces. Hot heat surface of platen superheater is composed of 38 pieces of tube which diameter is44.55.5, material is SA213-T23, longitudinal pitch is 60.3mm, aggregately arrange 7 pieces. Every piece of water wall panel is composed of 28 pieces of tube which diameter is63.56.5, material is SA-210C, longitudinal pitch is 88.9mm. Front wall turn to furnace rear and form furnace roof. Steam and water mixture come from front wall and rear wall whole enter into rear water wall upper header. Flue gas discharge from two ring headers arranged at rear wall upper, enter into cyclone. For wearing, spud which diameter is1025 welded at cone under furnace bottom, water panel and its bottom, rear part of furnace roof and some area of furnace outlet. The pitch between upper and down row spud is 30mm, angle staggers 15 degree; wearing layer thickness is around 60mm (water wall centerline). Butt-welding bead at gas side of water wall tube above wearing layer shall be worn flat, welding bead remnants height shall be not less than 1mm. 3.3. Back pass heating surface Back pass heating surface includes high temperature superheater, enclosure superheater, economizer, hanger tube and tubular air preheater. The back pass upper part is divided into front and rear gas duct by division wall enclosure superheater. Front gas duct has reheater inside while rear gas duct has high temperature superheater and second grade economizer in sequence inside. The cross-section of back-end convection ductwork is 12243.8 width 6400.8 depth.The pipes used for front and rear enclosure wall are of 45 5 tube. The enclosure division wall adopt 516 tube, with pitch equal for 114.3mm, membrane wall type structure. Both front and rear enclosure wall has 107 tubes; both left and right enclosure side wall have 57 tubes; enclosure division wall have 108

tubes. The upper part of enclosure front wall has 2 annular headers, which connect to cyclone separator flue gas duct outlet, and thus form the flue gas duct inlet. All the headers at enclosure wall are 273 36. High temperature superheater tube bundle adopts in-line arrangementthe two ends of heating surface piping are rested upon enclosure division wall and enclosure rear wall. The welding between supporting devices and enclosure tubes is to be performed in the shop. The specification of high temperature superheater is 51 5.5mm tubes, double tubing loop tube coil bundles, with pipe transverse pitch for 114.3mmlongitudinal pitch for 102mmtransverse direction row number 106 portrait direction row number 72low temperature segment material SA213-T22 medium temperature segment material SA213-T22 high temperature segment material SA213 - T91. In order to ensure site welding are carried out to the same class steel, a SA335-T91 tube with length of about 100mm is to be connected to the SA213 - T91 tube, which belongs to high temperature superheater outlet segment and is outside the flue gas duct. The specification of high temperature superheater inlet header is 324 55, material SA335-P12while outlet header specification is 324 40, material SA335-T91.The specification of the primary desuperheater header is 32428mm material SA335-P12 the secondary desuperheater Header specification is 324 28, material SA335-P12. All the reheater tube bundles are of in-line arrangementadopting superheater hanger tube hanging mode.The reheater heating surface piping adopts 63.5 tubes, twosome tubing loop tube coils, pipe transverse pitch for 114.3mm, longitudinal pitch for 114mmtransverse direction row number 106, portrait direction row number 72 altogether 4 tube groupsand materials of them are SA210A1SA213-T12SA213-T2
and SA213-T91. In order to ensure site welding are carried out to the same class steel, a

SA335-P22 tube with length of about 100mm is to be connected to the SA213 - T91 tube, which belongs to reheater outlet section and is outside the flue gas duct. The specification of reheater inlet header is 426 16, material SA-106B; The specification of reheater outlet header is 45735, material SA335-P22 Feedwater is lead into primary economizer inlet header from one side of the

boiler by 273 25 feed water pipes. The specification of the primary economizer pipes is 51 5mmmaterial SA210A1with pipe transverse pitch for 90mm transverse direction row number 70longitudinal pitch for 102mmportrait row number 52arranged into 2 groups. And then feedwater is lead into second stage economizer through a 273 25 connecting pipe. The specification of the secondary economizer pipe is 515 material SA210A1, pipe transverse pitch for 114.3mmtransverse direction row number 106longitudinal pitch for 102mm portrait row number 48arranged into 2 groups. Finallyfeedwater leaving from the second stage economizer is to be lead into the drum, through 2 219 20 connecting pipes and 12 108 10 branch pipes. The air preheater is arranged in the back pass. Because the blast pressures of the primary and secondary air are greatly differentthe channel boxe is divided into 2 independent air duct primary air channel box is located at the right side of the boiler while secondary air channel box is located at the left side of the boiler. Both of them have 3 layers of channel boxes, with tube bundle of horizontal in-line arrangement. The entire load of air preheater is laid upon a layer of boiler frame transverse beam. Both Primary and Secondary air air preheater are three-pass, of in-line arrangement transverse pitch for 75mmlongitudinal pitch for 75mmprimary air air preheater transverse direction row number for 104secondary air air preheater transverse direction row number for 72. 3.4 Cyclone separator and return device See the 573-1-8609 3.5 Ash cooler See the documents of provider 3.6. Boiler framework as well as platforms and stairways Boiler framework is full-steel structure, a pair-column type, and the boiler roof has light steel boiler house cover. The distance of boiler framework column from G to K row is 37200mm with main span width for 21000mm both left and right sub-span width for 5000mm, 5 layer of rigid platforms arranged in the vertical direction, the

elevation of them are EL.9000EL.21200EL.33200EL.45200 and EL.52700, ensuring the stability of the whole boiler framework. Besides bearing the load of boiler proper, the boiler framework can also bear the loads of the Pipes for steam and water, gas, air, coal, oil and limestone, and also loads of soot-blowing equipment, light boiler house roof cover, anti-wear and heat insulating materials, as well as some load brought by the elevator (including wind force, earthquake force). Boiler framework is designed for operation at ZoneIS-1893Part 1area, and the basic wind press 50m/smain components are connected by the friction-type torsion shear type high-strength boltnormal components are connected by welding. The design of the platform, footpath and staircase has enough strength and hardness. The live load of the platform is 10kPa (excluding the platform deadweight); the live load of the maintenance platform is 4kPa; the live load of the other platforms is 2.5kPa; the live load of the staircase is 2kPa. Boiler operation floor is designed at elevation 9m, Adopting checkered steel platform drum water control chamber platform is laid with checkered stee; plate, and the other passage platform adopts zincification grid plates. 3.7. Hangers and supports for pressure parts Except the primary economizer is laid upon the support beam of boiler

structure , the other pressure parts are supported by the boiler roof steel frame through hangers and supports. In order to decrease the bending press born by the hanger rod root during boiler operation, each heating surface lifting point is to preset offset in every expansion direction according to different expansion capacity. Because the drum has great load and large vertical height, U type hanger rod is used to install the drum. 2 hanger rods are arranged at both side of the drum. The expansion capacity during drum hot-condition operation has been taken into consideration to decide the distance between centers of installation location in cold condition. The hanger rod upper end is laid upon the support beam of the drum by screw nut. During installation, for the purpose of adjusting the drum's height, hydraulic jacks are placed at both ends of the supporting beam. Waterwalls front wall is hung upon the boiler roof steel structure by rigid hanger and lifting eye, which are

welded to the pipe. While all the other 3 walls and waterall panel are hung upon the boiler roof steel structure by rigid hanger on the header. High coronet sealed supporting structure is used to hang the platen superheater. This structure can be seen in 502573 - E1 01 furnace and down comer arrangement drawing, as well as 502573 - E1 - 04 boiler roof lifting point and piping arrangement drawing. The load of curtain panel are laid upon The middle transition beam through small hanger rod, every 7 curtain panels' transition beams form the frame structure altogether 4 transition beam frame structure then they are hung to the boiler roof steel structure by spring hangerensuring this hanger always on strained condition during boiler hot-condition operation. One end of high temperature superheater tube group and second stage economizer tube group is laid upon the enclosure rear wall, while the other end is laid upon the division wall. The high temperature superheater inlet/outlet header is laid upon the enclosure rear wallaround back pass enclosure wall and division wall are hung to the boiler roof steel structure by rigid hanger. Each row of pendant tube hang 2 reheater tube-row. Both pendant tube and reheater tube-row are assembled by corrugated plate and tightening in the shop. The load of the whole reheater tube group is hung to the boiler roof steel structure through the rigid hanger and the lifting eye at upper part bend of the pendant tube. reheater inlet/outlet header is laid upon the enclosure front wall. The

4. Others 4.1. Anti-wear measures Because the boiler adopts circulating fluidized burning mode, plentiful circulation materials are existed in the firing system. Furthermore, the material circulating ratio attains 30. Therefore the anti-wear measures for firing system and tail heating surface are of great importance. To select furnace cross-sectional area per flue gas volume generated by firing, and to control the flue gas velocity within the prescribed range of performance standard, can greatly decrease the wearing at furnace heating surface. In the back pass convection gas duct, Although the ash content in the gas is low, the rigidity of the gas

increases as the gas temperature decrease, so to choose a suitable gas velocity is a good way to wearing on convection surface. Furnace air distributors are poured over by about 200mm thick antifriction pouring material. The waterwall pipes at the furnace cone segment are welded by pin bolt, and laid with 70mm thick distance to the center of the pipe high temperature fireproof anti-wear layer. At the transition part between cone segment and vertical segment, Waterwall pipe are bended towards outside the boiler, ensuring the falling material within the furnace can fall over the anti-wear layer. In addition, The weld seam of the gas side pipes above the anti-wear layer shall be grinded smooth, and the residual height of weld seam shall be no more than 1mm. For both platen superheater and waterwall panel at the upper furnacethe pipes at the lower part surface and wall-penetrating area are welded by the pin bolt, and laid with 70 mm thick (distance to the centerline of the pipe) high temperature fireproof anti-wear layer to prevent pipe form wearing by the ascending gas. At furnace upper rear wall gas outlet, 70mm thick, 1000mm wide annular high temperature fireproof anti-wear layer are laid upon the waterwall pipe surface, to prevent the wearing to these pipes as changing gas flow. The inner wall of cyclone separator inlet gas duct,cyclone separator and cyclone separator outlet gas duct adopts anti-wear castable material, and is fixed by high density pin bolt, guaranting anti-wear material firm and reliable. When laying the

114mm thick high temperature anti-wear layer the surface of the anti-wear layer shall be flat, and transition shall be smooth. The center pot of the separator adopts high temperature high strength anti-wear austenitic stainless steel. Within the U type material return leg, FBAC and its connecting pipeline, all the internal surfaces of gas duct, which contact with high temperature high concentration ash particles, shall be laid with a layer of high temperature anti-wear pouring material and a layer of fireproof insulation pouring material, and fixed by Y type pin bolt. For the heating surface of tail convection gas duct such as high temperature superheater, reheater, economizer and air preheater, anti-wear cover shall be added to the first row of pipe windward at flue gas inlet, to prevent pipe from abrading.

Both the ingredient and performance index of the anti-wear refractory material shall meet the requirements raised by Shanghai Boiler Works, Ltd, details refer to <<furnace wall, insulation and anti-wear refractory material>>. 4.2. Sealing CFB's furnace pressure is barotropic during operationand the operation pressure at the lower furnace dense-phase region can reach about 10kPa. Through excellent sealing design, SBWL can prevent gas leakage and ash leakage, and therefore provide a clean and easeful work environment for the boiler user. The boiler has 3 expansion centers, namely, in furnace, in cyclone separator and in back pass. Among them, 3 layers of expansion center are designed on boiler waterwall (elevation for EL.16700, EL.32500 and EL.41500), a layers of expansion center is designedon on cyclone separator EL.33200, 3 layers of expansion center is designed on back pass enclosure wall (elevation for EL.33800, EL.40800 and EL. 47200 ). This design can boiler heating parts can freely expand in order in a certian direction during operation. Every sealing structure has determinate expansion direction and capacity, which can provide definite reference value and reliable basis for the sealing design. The furnace adopts the membrane wall structure, which is formed by welding bare tube and flat iron together. This membrane wall structure have good airtightness, and can be laid with light refractory furnace wall to decrease boiler deadweight. Boiler roof pipes are formed by the bending of front wall waterwall, so their expansion is the same as of the about waterwall. This enable boiler roof sealing design to be simplethe boiler roof pipe can be seal welded with the 2 sides waterwalls. Upper furnace has wide pitch waterwall and platen superheater, whose Transverse pitch are larger than 600mm. Therefore this is easy for site welding and can guarantee the installation quality. Waterwall panel and boiler roof pipe directly adopt comb type steel plate welding, And the platen superheater adopts metal expansion joint for sealing, which can absorb the expansion difference between platen superheater and waterwall. At the lower header tube seat of waterwall, sealing box is used for sealing, while At the tube seat of annular header, flanged plate is used for

sealing. Waterwall has Positive pressure manhole door . The inner surface of manhole door is laid with refractory material and thermal insulating material, which can effectively prevent flue gas leakage raised by heating distortion. At the connecting points between furnace and cyclone separator inlet gas duct, between cyclone separator and inlet gas duct, between cyclone separator and outlet gas duct, between cyclone separator and material return device, between cyclone separator outlet gas duct and back pass, and between back pass and air preheater inlet, metal/non-metal expansion joints are placed to absorb heat displacement. The expansion joint itself is anti-wear and high temperature resistant. Compression

amount of the expansion joint shall reserve suitable allowance, in order to guarantee certain service life. The around enclosure wall of back pass adopts the membrane type wall structure, which are formed by welding between bare tube and flat iron. Because all the enclosure walls are steam cooling type, all the expansion values are the same, so the sealing design can be simplified. The connecting points between back pass boiler roof pipe and enclosure front wall/rear wall has no header, but pipes for direct connection. This guarantees the sealing in structure. Boiler roof pipe are directly welded to the enclosure sidewall, without any expansion joint. The tube seats of enclosure front Sealing box is used at high

wall annular header adopts flanged plate for sealing.

temperature superheater inlet/outlet, reheater inlet/outlet, and pipe penetrating area between enclosure front wall and enclosure rear wall. The sealing box has metal expansion joints at its upper and lower parts, which can absorb the heat displacement in width direction.

También podría gustarte