Documentos de Académico
Documentos de Profesional
Documentos de Cultura
208-345-1136
Advanced-Projects.com
Lawrence_leach@hotmail.com
Rev. 4: 2/27/04 1
Objectives
Identify why the critical chain, not the critical path, is often the constraint of a project Exploit the constraint (critical chain) of a project Subordinate everything else to the project goal Define buffers used in Critical Chain Project Management Exploit the multi-project constraint
Rev. 4: 2/27/04
Harris Semiconductor Lucent Technologies Honeywell DAS Israeli Aircraft Company UA Air Force US Navy
PHNSY-FMB Improvements
METRIC BEFORE CCPM AFTER CCPM IMPROVEMENT
ON-TIME (Scheduled Availabilities) Average Cost per Job (incl. overtime) Man-Days Job Completion Rate (same time period) Overtime Customer Backlog
Rev. 4: 2/27/04
40% (8 of 20)
$6,113
$4,700
Rev. 4: 2/27/04
2. Critical Chain
B A B E C
C C D
4. Project Buffer
Time
Resource Leveled Critical (?) Path
Rev. 4: 2/27/04 6
Production Functions
Rev. 4: 2/27/04
Rev. 4: 2/27/04
Resource Leveled CP
Rev. 4: 2/27/04
10
Critical Chain Identified: The longest path through the projectafter resource leveling.
Rev. 4: 2/27/04
11
Frequency
4 3 2 1 0 B in 5
10
20
30
40
50
60
70
8 0 M o re
Rev. 4: 2/27/04
12
Minimum Time/Cost
Rev. 4: 2/27/04
13
Focus On Milestones And Variances Drives Low-risk (90%+) Activity Duration Estimates
1 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0 0 Rev. 4: 2/27/04 0.5 1 1.5 2 2.5
14
Rev. 4: 2/27/04
15
Rev. 4: 2/27/04
Rev. 4: 2/27/04
17
EXPLOIT variation by taking contingency out of each task, and moving it to the end of the chain.
Task 1 Task 2 Task 3 Task 4
Task 1 Task 2
1 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0 0 0.5 1 1 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0 0 1.5 0.5 2 1 1 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0 2.5 0
Task 3 Task 4
1 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0
1.5 0.5 2 1 2.5 0 1.5
Rev. 4: 2/27/04
18
Critical chain differs from critical path by: Resolving resource contentions first (Identify) C Using 50 % probable activity times (Exploit) C D (Smaller) aggregated Buffer at end of chain (Exploit)
Rev. 4: 2/27/04
19
BUFFER
Watch Watch
Plan Plan
Act Act
Rev. 4: 2/27/04
20
1 2/3 1/3 0x x
Act Plan
x x x
x x
Time
Rev. 4: 2/27/04
21
Project Buffer
% Buffer x
Plan
x x
GREEN
GREEN
% Chain
Rev. 4: 2/27/04
22
Project Buffer FB FB
Rev. 4: 2/27/04
23
Rev. 4: 2/27/04
24
Critical chain task gets priority over non critical chain task Priority to task causing greatest project buffer penetration Non-project work lowest priority
Rev. 4: 2/27/04
26
2. Critical Chain
B A B E C
C C D
4. Project Buffer
Time
Resource Leveled Critical (?) Path
Rev. 4: 2/27/04 27
Rev. 4: 2/27/04
28
Rev. 4: 2/27/04
29
Rev. 4: 2/27/04
30
Switching Inefficiency
Task A
Task B
Task C
Rev. 4: 2/27/04
31
Starting each one right away (the sooner you start) each ship is unloaded on the end of the fifth day.
Rev. 4: 2/27/04 32
Put all five resources on ship 1 the first day, ship 2 the second day, etc. Result: Ship New (days) Old (days) Saved 1 1 5 4 2 2 5 3 3 3 5 2 4 4 5 1 5 5 5 0 Nobody loses. Four of five clients done sooner. Cost = $ 0
Rev. 4: 2/27/04 33
IDENTIFY: Multi-project resource constraint EXPLOIT: Prioritize projects (Drum) SUBORDINATE: Stagger project start ELEVATE INERTIA
Rev. 4: 2/27/04 34
Prioritize & Sequence Projects to Accelerate Completion! Individual Project Schedules (Note resource contention) BUFFER BUFFER
Constraint Resource
Rev. 4: 2/27/04 35
Objectives
Identify why the critical chain, not the critical path, is often the constraint of a project Exploit the constraint (critical chain) of a project Subordinate everything else to the project goal Define buffers used in Critical Chain Project Management Exploit the multi-project constraint
Rev. 4: 2/27/04
36
Path Forward
Implement effective process for: Management leadership and behavior Client alignment Resource behavior Buffer Management Organization specific obstacles Potential unintended consequences
Rev. 4: 2/27/04 37
Rev. 4: 2/27/04
38