Documentos de Académico
Documentos de Profesional
Documentos de Cultura
The gas turbines are of the 9001 E type; they operate on natural gas or on BFO. The gas turbine exhaust is fitted with two duplex flap isolators, one at the inlet of the by-pass stack and one on the inlet of the HRSG. Each gas turbine exhausts into its own HRSG. The heat recovery steam generators are single pressure type. The water circulation in the boiler vaporizer is ensured by HP circulating pumps. The advantage of forced circulation boilers is their start-up speed. With this type of boiler, circulation is ensured before start-up of the gas turbines, allowing the tubes to cool down and following advantages. No problem of water hammer No flow unbalance in the tubes Small diameter tubes, thus low thermal inertia, Fast start-up.
To maintain the very high availability of the HRSG, two HP circulating pumps are installed on normal/stand by operation, with automatic start-up of the second pump if there is an incident on the first. The HRSG's are provided with soot-blowers for the blowing of exchanger's tubes.
2.
123456789-
10- HP steam outlet 11- HP Steam temperature at superheater outlet 12- HP Steam pressure at superheater outlet 13- HP feedwater temperature
3.
PLANT DESCRIPTION
The boiler is a vertical duct in which the various heat exchanger tube banks are arranged horizontally. The gas turbine exhaust flue gas successively passes through. The HP superheater, The HP evaporator, The HP economizer, The LP evaporator.
The HP circulating pump takes suction from the HP drum and feeds the HP evaporator. The HP drum is fed by three HP feedwater pumps, two on duty, the other on stand-by. At the top of each HRSG, a LP evaporator feeds the feedwater tank with LP steam. The LP evaporator pumps take suction from the feedwater tank and feed the LP evaporator. The LP evaporators are fed by three evaporator pumps, two on duty, the other on stand-by. The LP steam produced by the LP evaporators is discharged in the feedwater tank for heating and deaerating of the feedwater. A LP separator tank is installed between evaporator outlet and deaerator. From the deaerator water is returned to the HP drum by up to 3 50 % HP boiler feed pumps. The feedwater tank also supplies 3 50 % LP evaporator pumps, which deliver water to the LP evaporator. From the condenser, condensate is delivered to a single deaerator by either of 2 100 % condensate extraction pumps.
4.
STEAM DRUMS
The drum volumes are determined in accordance with the volume of tube banks in order to monitor the water level during start-ups or rapid load swings without undue blowdown. An inside plate concentric to the shell is fitted in the drum to guarantee good temperature uniformity in the outside housing, taking into account the temperature rises and very rapid load swings. The steel and the drum thickness are chosen as to obtain an acceptable temperature gradient in the wall thickness for a very high number of cycles. The drums incorporate steam dryers to the form of corrugated plate assemblies. The drums are put on the boiler structural steel above the tube banks in order to avoid accidental drainage of the economizer into the drum.
5.
HP CIRCULATING PUMP
Pump assisted circulation successfully manage fast start-up, transient operation, reliable operation and high availability. To maintain the very high availability of the HRSG, two pumps (2 100%) are installed on normal/stand by operation with automatic start-up of the second pump if there is an incident of the first.
6.
Ducts are provided to direct the turbine exhaust gases from bypass stack to the boiler and from the boiler to the top stack. A flexible expansion below allows free expansion of ducts and boiler blocks. Ducts are bottoms supported on two lubricating piles. A stack is located downstream of the boiler, at its summit. This self-supporting stack is fixed into the upper part of the boiler by means of transformation pieces. Deflectors are installed in the stack to avoid rainfalls into the boiler.
7.
SOOTBLOWERS
Sixteen rake sootblowers with a translation stroke are provided per boiler as furnace oil is burnt in the gas turbine. One sequence each 8 hours is enough when GT is continuously operating with furnace oil. Necessary steam used by the sootblowers is taken at the superheater outlet. But the sootblowers can be used to waterwash the exchangers during shutdown. Sootblowers are electrically driven units.
8.
One vent duct to atmosphere. One cooling water circuit. One discharge to sewer. One condensate from sootblowing system. All drain from the HP economizer, the LP evaporator, the boiler flash tank, the superheater and the emergency blowdown.
9.
The water steam mixture coming from LP separator arrives in the separator. The steam goes to the deaerator and the water to feedwater tank. The separator is equipped with a steam dryer of corrugated plate type. The steam outlet line is equipped with a manual-isolating valve. The water outlet line is equipped with a manual-isolating valve.
B) -
ON LP CIRCUIT
Downstream of the LP evaporator a relief safety valve is installed to protect the evaporator against over pressure.
OPERATION PROCEDURE
This part describes the different operations, which are
1.
NOTE :
LOAD INCREASE
The HP by-pass valve may eventually open according to the loading rates to limit the positive pressure gradient at 4-bar/mm maxi.
LOAD DECREASE
Only normal load decreases (between 0 and 10 %) are considered here. In this case, the steam turbine valves may operate in limitation mode in order to limit the HP steam negative pressure gradient or to prevent the HP steam pressure from falling below 20-bar abs. (4 bar /mm maxi). The HP steam by-pass remains closed.
2.
The combined cycle block start-up is automatic when the plant is ready to start. On boilers, "plant ready to start" means that all circuits must be filled, the drums levels adjusted, all circulating pumps ready to start and flop isolators ready. This preparation for start-up must be done before the combined cycle start-up.
At boiler inlet, motorized and manual shut-off valves are open. At drum inlet, the level control valve is OPENED (LCV 050). At steam outlet, the condensate pot-draining valve is OPENED. Be sure that following are in service:
Pressure transmitters, Level switches on drain pots, Level indicators on drum, Level transmitters on drum and boiler flash tank. The indications of level transmitters on HP drum are correct only if the connection pipes between transmitter and drum are filled up with cold water. It is necessary to fill them before the first filling of boilers.
NOTE :
Fill the boiler up to reach the filling level into the drum Check the indications of drum level Complete the filling of economizer by opening manual vent valves inlet economizer, close then when air free water passes through Adjust (if necessary by acting on intermittent blowdown) the level at the filling level
Mechanical seal housing (HV 161 and HV 261) Pump body and bearing box (HV 181 and HV 281) Cooler of mechanical seal (HV 156, 155 and HV 256, 255) FSR HV 162 and HV 262 FSR HV 175, 176 and HV 275, 276
2.3.2
HP Drum level adjusted below the swelling level and the low level. One HP feedwater pump is in operation. One condensate extraction pump is started and the level in the condenser is kept constant by the control valve. One LP evaporator pump is in operation. Piping drains closed. START-UP OF FIRST GT
At the start-up order The boiler inlet is fully open, the by-pass blast stack is also fully open (about 30% of the gas turbine rated low is discharged in the HRSG in order to limit the boiler thermal stresses). The isolating valves are open: 2.3.3 The steam isolating valves on the HP header is open, if the isolating valve associated with the other boiler is closed. To supply steam to the steam turbine gland sealing system and the piping heating up to the steam turbine. The piping drain valves open as soon as the boiler inlet damper starts to open. The HP drum pressure increases naturally and when the HP drum level reaches the swelling level, the HP feedwater control valve is put under automatic control. The LP evaporator begins to produce steam and feed the deaerator. At 12-bar abs of HP steam pressure, the steam turbine gland seal system is put in operation. As soon as the condenser vacuum is < 0.35 bar abs, the HP by pass is available. The HP by-pass controls the boiler pressure gradient < 4 bar/min. At 15 % steam turbine load, the HRSG load increases by closing step by step of the by-pass flap. At 20 % steam turbine load, the ST drain valves receive a closing order. SECOND HRSG START-UP The second GT and HRSG can be started at any time. The start-up of the second HRSG is the same than the first one but with the condenser already under vacuum. The HP by-pass limits the HRSG pressure gradient and then stabilizes the HP steam pressure at the sliding pressure set point. When the pressure at the second HRSG is slightly higher than the other, and when there is no more saturation detection, there is an automatic opening of the HP steam header value. As soon as both HP steam-isolating valves are open, both HP by-pass receivers the same sliding pressure set point values depending on the total steam flow. When both HP by-pass valves are closed, the unit operates in sliding pressure made with HP control valve fully open if the steam flow is sufficient or at minimum pressure of 20 bar abs controlled by the turbine HP control valves. The HP steam pressure follows the natural sliding pressure curve. The HP bypasses receive a set point value, which is slightly higher than the sliding pressure curve.
3.
The combined cycle block automatic system ensures complete shutdown of the steam plant. As for start-up sequence, the operator may decide to stop all or part of the plant. The normal shutdown of a combined cycle block is scheduled to maintain the boiler. Steam turbine plant in the hottest possible conditions and is as follows; The steam turbine load is reduced to a minimum value.
During this load reduction sequence, the HP by-pass follows the sliding pressure curve. As far as the boiler inlet damper is kept open during the ST load reduction, the steam flow remains at its initial value so that the sliding pressure set point is maintained at its higher value. The turbine drains open when ST load < 20 %. Then, the by-pass blast stack is open and the boiler inlet damper is closed. The HRSG's are maintained at the steam pressure existing before the shutdown and isolated on the same side (drains and vents are closed). The HRSG's and common feedwater plant auxiliaries are shutdown where applicable. The gas turbines are shutdown.
4.