PROGRESS REPORT WITH PHOTOS AS ON 31.07.

2012
PURVA SWANLAKE - KELAMBAKKAM

TOWER ABC - SOUTH SIDE ELEVATION

TOWER - A

All RCC works, block work & ceiling plastering works were completed.
Up to 14th Floor Internal wall plastering work completed. Up to 14th Floor internal water line works, sanitary lines, water proofing & Vermiculite filling works are completed. Up to 8th floor Toilet tiling works were completed excluding (A-103, PPL site office). Above 9th floor works in progress. External plastering work completed. Tiling works are completed up to 8th floor. Above 9th floor in progress. Up to 14th floor 1st coat wall putty 90% & 2nd coat 80% completed.

Kitchen Counter top Granite works up to 9th Floor completed. Above 9th floor works in progress.
In Flat 101 & 102 UPVC doors & windows Fixed. In 101 Door frame fixing in progress. Kota in stair S1 & S2 Up to 14th completed. In 12th,13th & 14th floor CPVC line laying in progress. Electrical wiring works completed up to 8th floor & switch board fixing works were completed in 1st floor (2 flats) & remaining are in progress. DB Box fixing above 9th floor in progress. TOWER- A NORTH SIDE PAINTING WORKS IN PROGRESS

TOWER B

All RCC works, block work & ceiling plastering works were completed . Up to 14th floor Block work completed. Up to 14th Floor Ceiling Plastering completed. Up to 14th completed. Floor Internal wall plastering

Up to 14th Floor internal plumbing & sanitary works, water proofing, Vermiculite filling works completed. Toilet & floor tiling works were completed up to 8th floor. Above 8th Floor tiling works are in progress. 1st coat of wall putty 90% completed up to 8th and 2nd coat completed up to 7th floor. Kitchen Counter top Granite works up to 8th Floor completed. In Flats 101, 103 UPVC doors & windows Fixed. Kota in stair S1 & S2 Up to 8th floor Completed. Above 8th floor works in progress. 9th floor CPVC wall line chipping works in progress. Electrical wiring works are in progress from 1st to 8th floor & 11th floor wall Conduiting works in progress. TOWER - B - NORTH SIDE ELEVATION

TOWER C

All RCC works were completed.

Block works have completed up to 14th floor .


Up to 14th Floor Ceiling Plastering completed. Up to 14th Floor Internal wall plastering completed.13th & 14th floor wall Plastering work in progress. Internal waterline works, sanitary lines, water proofing, vermiculate filling works were completed up to 14th floor. 90% of floor tiling works have completed up to 8th floor & Toilet tiling works have completed except MBT flooring works. Kitchen Counter top Granite works up to 8th Floor completed. 1st coat wall putty 90% completed up to 8th and 2nd coat completed up to 7rd floor.

Kota in stair Completed.

S1&S2

Up

to

8th

floor

TOWER - C NORTH SIDE ELEVATION

TOWER D

All RCC works were completed except OHT wall shuttering works are in progress. Up to 13th floor Block work completed ,14th floor works are under progress Up to 12th completed. Floor Ceiling Plastering

Up to 8th Floor Internal wall plastering completed. 9th Floor work in Progress.

Up to 8th floor Internal waterline & sanitary line, water proofing & vermiculate works were completed.
Toilet tiling up to 8th Floor 90% completed. Floor tiling works were completed up to 4th & from 5th to 8th works Bed room tiling works completed except living & dining areas.

Up to 8th floor 1st coat wall putty 70% completed. In 1st floor 2nd coat of wall putty works are in progress.
Kota in stair S1 & S2 Up to 8th floor works completed.

TOWER - D - NORTH SIDE ELEVATION

TOWER E

All RCC works have completed up to terrace floor. LMR base slab reinforcement, parapet & profile wall works are in progress. Up to 12th Floor Block work completed. 14th floor works are under progress. Up to 10th Floor completed. Ceiling Plastering

Up to 8th Floor Internal wall plastering completed. Internal waterline works, sanitary lines, Water proofing & Vermiculite filling works were completed up to 8th floor. Toilet tiling in 8th Floor 90% completed. Floor tiling works up to 7th floor completed. Up to 8th floor 1st coat wall putty works completed.

TOWER E NORTH SIDE ELEVATION

TOWER F

14th floor RCC works have completed. Up to 9th Floor Block work completed. 10th floor works are under progress. Up to 8th completed. Floor Ceiling Plastering

8th Floor Internal wall plastering completed Internal waterline, sanitary lines, water proofing & vermiculite filling works up to 8th floor completed. 90% of floor tiling works have completed up to 8th floor & Toilet tiling works have completed except MBT flooring works. Floor tiling works were completed up to 7th completed.Toilet flooring in MB toilets up to 1st floor completed remaining are under progress. Up to 8th floor 1st coat wall putty 70% completed. Kota stone flooring 1st to 8th floor in S2 stair case portion completed.

TOWER - F NORTH SIDE ELEVATION

TOWER G

12th Floor slab concrete completed,12th floor Column marking under progress. Up to 8th Floor Block work completed. Up to 8th completed. Floor Ceiling Plastering

Up to 8th Floor Internal wall plastering completed. Staircase plastering woks in progress. Internal water line & sanitary works completed up to 8th floor. Water proofing & vermiculate works up to 8th floor completed. filling

Toilet tiling in 1st Floor 80% completed. Floor tiling works in 1st floor 50%completed. Up to 8th floor 1st coat wall putty 70% completed.

TOWER - G NORTH SIDE ELEVATION

TOWER H

12th Floor slab Concrete Completed.13th floor slab shuttering works are in progress. Up to 8th completed. Floor Block work

Up to 8th Floor Ceiling Plastering completed. Up to 8th Floor Internal plastering completed. wall

Internal waterline works up to 5th floor completed, 6th floor in progress & sanitary lines up to 8th floor completed. Water proofing works up to 8th floor completed. Up to 8th floor Vermiculite filling works completed. Up to 8th floor 1st coat wall putty 70% completed.

TOWER H NORTH SIDE ELEVATION

TOWER J

11th Floor slab Concrete Completed.12th floor column shuttering works are in progress. Up to 8th Floor block works completed. Up to 8th completed. Floor Ceiling Plastering

8th Floor Internal wall plastering 90% completed. Internal waterline works up to 4th floor completed, 5th & 6th floor in progress. Water proofing works up to 8th floor completed. Vermiculite filling works up to 6th floor completed.7th & 8th Floor in progress. Up to 8th floor 1st coat wall putty 70% completed.

TOWER - J NORTH SIDE ELEVATION

TOWER K

RCC works are completed up to 9th floor slab. Terrace floor slab shuttering & reinforcement works are in progress. Up to 8th Floor Block works were completed. Up to 8th Floor Ceiling Plastering completed. Up to 8th Floor Internal wall plastering 90% completed. Up to 8th floor internal electrical works completed.

Up to 8th floor internal plumbing works completed.


Up to 7th floor waterproofing works completed, 8th Floor water proofing preparatory works is in progress. Up to 4th floor Putty works completed. Handrail fixing Completed up to 8th floor.

SOUTH SIDE ELEVATION

TOWER L

RCC works are completed up to 9th floor slab.9th floor 25 no of column concrete works in Progress. Up to 8th floor block works were completed. Up to 8th Floor Ceiling Plastering completed. Internal wall plastering completed up to 8th floor 95%. Internal electrical works completed up to 7th floor. Internal plumbing & water proofing works completed up to 7th floor. Up to 3rd completed. floor Putty works

Up to 8th floor Handrail fixing works Completed.

TOWER - L - SOUTH SIDE ELEVATION

TOWER M

RCC works are completed up to 9th floor slab. 10th floor slab shuttering & Reinforcement works in progress. Up to 7th Floor block works completed & 8th Floor. 90% block works completed. Up to 8th Floor Ceiling Plastering completed. Up to 6th Floor Internal wall plastering completed. Up to 6th floor internal electrical works completed. Up to 7th floor internal plumbing works completed. Up to 4th floor waterproofing works completed. Up to 2nd floor Putty works completed. Up to 8th floor Handrail fixing works completed.

TOWER M SOUTH SIDE ELEVATION

TOWER N

RCC works are completed up to 9th floor slab. 9th floor column Concrete and beam shuttering works under progress. Up to 7th Floor block works completed & 8th Floor 90% block works completed. Up to 8th completed. Floor Ceiling Plastering

Up to 5th Floor Internal wall plastering completed. Up to 5th floor internal electrical works in progress. Up to 7th floor internal plumbing works completed. Up to 3rd floor Putty, waterproofing works in progress. Up to 8th floor Handrail fixing works Completed.

TOWER - N SOUTH SIDE ELEVATION

TOWER P

RCC works are completed up to 9th floor slab. 9th floor column concrete in Progress. Up to 7th Floor block works completed & 8th Floor 90% block works completed.

Up to 8th Floor completed.

Ceiling

Plastering

Up to 5th Floor Internal wall plastering completed. Up to 5th floor internal electrical works completed. Up to 6th floor waterline & 1st floor soil line works completed. Up to 1st floor water proofing works completed. Up to 2nd floor wall Putty works completed. Up to 8th floor Handrail fixing works completed.

TOWER P SOUTHSIDE ELEVATION

TOWER Q

RCC works are completed up to 9th floor slab. 9th floor column reinforcement works in progress. Up to 7th Floor block works completed & 8th floor 90% block works completed. Up to 8th Floor Ceiling Plastering completed. Up to 5th Floor Internal wall plastering completed. Up to 6th floor internal electrical works completed.

Up to 6th floor waterline & 1st floor soil line works completed.
Up to 1st floor waterproofing works completed & 2nd floor Putty works completed. Handrail fixing works completed up to 8th floor.

TOWER - Q SOUTH SIDE ELEVATION VIEW

PODIUM & CLUB HOUSE

Podium works 96% completed. Basement tower B preparatory works for plastering under progress. Club house all RCC works were completed. Club house block works are95% completed, internal, External plastering work under progress.

ELEVATION OF CLUB HOUSE

FRONT & NORTH SIDE COMPOUND WALL

Front compound wall feature wall Raft PCC Completed. Raft & RCC wall works in Progress. Security room plinth beams completed, column works in progress. Wall shutter board making and steel reinforcement works are under progress. North side RR masonry works are in progress.

FEATURE WALL FOUNDATION CONCRETE WORKS IN PROGRESS

NORTH SIDE COMPOUND WALL RR MASONRY IN PROGRESS

SOUTH & OSR COMPOUND WALL

South side barrication removal works in progress. Dismantling of RR masonry & OSR portion RR masonry, pointing and Curing under progress. South Side Block Work in Works started. Progress. Plastering

PLASTERING WORKS IN PROGRESS

RR MASONRY WORKS IN PROGRESS

BLOCK WORK IN PROGRESS