Activity Codes:
LVL1 LEVEL 01
01 START UP 1
02 IMPORTANT DATES 2
03 ENGINEERING 3
04 CONSTRUCTION WORKS 4
05 HANDING OVER 5
06 REVENUE 6
LVL2 LEVEL 02
04 KEY DATES 1
01 PRELIMINARIES 2
02 MOBILIZATION 2
05 TOWER CRANES & HOISTS 5
06 MOCK - UP REQUIREMENTS 6
07 CLEARANCE / CONNECTION DATES OF MAIN SERVICES 7
08 SUBCONTRACTORS / SUPPLIERS APPOINTMENT 8
09 SHOPDRAWINGS SUBMITTALS & APPROVALS 9
10 MATERIALS APPROVALS &PROCUREMENT 10
11 METHOD STATEMENTS SUBMITTALS AND APPROVALS 11
12 TOWER FOOTPRINT 12
13 PODIUM 13
14 EXTERNAL WORKS 14
15 OTHER WORKS 15
16 SNAGGING & CLEANING 16
LVL3 LEVEL 03
CONT CONTRACTUAL MILESTONES 1
INCRN INTERNAL CRANES 1
INTER INTERMEDIATE MILESTONES 1
CLEAR CLEARANCE & CONNECTION DATES OF MAIN SERVICES 2
EXCRN EXTERNAL CRANES 2
HOIST HOISTS 3
PILES FOUNDATION - PILES 4
LP2&4 FOUNDATION - LIFT PIT 2-4# 5
RAFT RAFT FOUNDATION 6
RAFT1 RAFT FOUNDATION PART 1 7
RAFT2 RAFT FOUNDATION PART 2 8
RAFT3 RAFT FOUNDATION PART 3 9
RAFT4 RAFT FOUNDATION PART 4 10
B5 BASEMENT 5 11
B4 BASEMENT 4 12
B3 BASEMENT 3 13
B2 BASEMENT 2 14
B1 BASEMENT 1 15
GF GROUND FLOOR 16
MEZZ MEZZANINE 17
1STF 1ST FLOOR OFFICES 18
2NDF 2ND FLOOR OFFICES 19
3RDF 3RD FLOOR OFFICES 20
4THF 4TH FLOOR OFFICES 21
5THF 5TH FLOOR OFFICES 22
6THF 6TH FLOOR MECHANICAL FLOOR 1 23
7THF 7TH FLOOR MECHANICAL FLOOR 2 24
8THF 8TH FLOOR OFFICES 25
9THF 9TH FLOOR OFFICES 26
10THF 10TH FLOOR OFFICES 27
11THF 11TH FLOOR OFFICES 28
12THF 12TH FLOOR OFFICES 29
13THF 13TH FLOOR OFFICES 30
14THF 14TH FLOOR OFFICES 31
15THF 15TH FLOOR OFFICES 32
16THF 16TH FLOOR OFFICES 33
17THF 17TH FLOOR OFFICES 34
18THF 18TH FLOOR OFFICES 35
19THF 19TH FLOOR OFFICES 36
20THF 20TH FLOOR OFFICES 37
21STF 21ST FLOOR OFFICES 38
22NDF 22ND FLOOR OFFICES 39
23RDF 23RD FLOOR OFFICES 40
24THF 24TH FLOOR OFFICES 41
--------------------------------------------------------------------------------
PRIMAVERA PROJECT PLANNER
LVL4 LEVEL 04
CIVIL CIVIL SYSTEM 1
MEP MEP SYSTEM 2
LIFTS VERTICAL TRANSPORTATION SYSTEMS 3
OTHER OTHER SPECIAL SYSTEMS 4
LVL5 LEVEL 05
STRUCTURAL STRUCTURAL 1
ARCHITECT ARCHITECTURAL 2
DEWATERING DEWATERING WORKS 2
SUBSTRUCT SUB-STRUCTURE 3
STEEL STEEL STRUCTURE 4
SUPER SUPER-STRUCTURE 4
BLOCK BLOCK WORKS 5
WP WATER PROOFING SYSTEM 5
PLASTERING PLASTERING WORKS 6
TILING TILING WORKS 6
FALSE FALSE CEILING WORKS 7
FINISHS FINISHES WORKS 7
PART PARTITIONS 7
VANITY VANITIES 7
CURTAIN CURTAIN WALL WORKS 8
--------------------------------------------------------------------------------
PRIMAVERA PROJECT PLANNER
Activity ID Codes:
Alias Codes: