ANTAMINA CC-08 TRANSPORTE DE RELAVES Y RECUPERACION DE AGUA

MASTER SCHEDULE
Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
CC-08 TRANSPORTE
TRANSPO DE RELAVES Y RECUPERA 159 0% 07-Mar-11 13-Oct-11 0

Contrato 33 0% 07-Mar-11 21-Apr-11 126


Aker/Antamina 1 0% 07-Mar-11 08-Mar-11 -27
General 1 0% 07-Mar-11 08-Mar-11 -27
General 1 0% 07-Mar-11 08-Mar-11 -27
General 1 0% 07-Mar-11 08-Mar-11 -27
CO0001 Orden de Proceder 0 0% 07-Mar-11* -39 TRRA.PL.000.10
CO0010 Carta Adjudicacion 0 0% 08-Mar-11* -39 TRRA.PL.000.10
Salfa Montajes 8 0% 13-Mar-11 23-Mar-11 0
General 8 0% 13-Mar-11 23-Mar-11 0
General 8 0% 13-Mar-11 23-Mar-11 0
General 8 0% 13-Mar-11 23-Mar-11 0
CO0021 Garantias y Seguros 7 0% 13-Mar-11 19-Mar-11 -39 TRRA.PL.000.10
CO0031 Plan Movilizacion/Desmovilizacion y Proced. SSMM 0 0% 18-Mar-11 -21 TRRA.PL.000.10
CO0041 Procedimientos, Planes, Controles,Programas, Or 0 0% 23-Mar-11* 0 TRRA.PL.000.10
Aker/Salfa Montaj
Montajes 0 0% 21-Apr-11 21-Apr-11 126
General 0 0% 21-Apr-11 21-Apr-11 126
General 0 0% 21-Apr-11 21-Apr-11 126
General 0 0% 21-Apr-11 21-Apr-11 126
CO0011 Firma del Contrato 0 0% 21-Apr-11 176 TRRA.PL.000.10
Hitos Contractuales 153 0% 15-Mar-11 13-Oct-11 0
Aker/Antamina 11 0% 15-Mar-11 29-Mar-11 0
General 11 0% 15-Mar-11 29-Mar-11 0
General 11 0% 15-Mar-11 29-Mar-11 0
General 11 0% 15-Mar-11 29-Mar-11 0
HC0041 Inicio Parada N°1 (4 Hrs) 0 0% 15-Mar-11* 0 TRRA.PL.000.20
HC0051 Fin Parada N°1 (4 Hrs) 0 0% 15-Mar-11* 0 TRRA.PL.000.20
HC0061 Inicio Parada N°2 (96 Hrs) 0 0% 26-Mar-11* 0 TRRA.PL.000.20
HC0071 Fin Parada N°2 (96 Hrs) 0 0% 29-Mar-11* 0 TRRA.PL.000.20
Salfa Montajes 146 0% 23-Mar-11 13-Oct-11 0
General 146 0% 23-Mar-11 13-Oct-11 0
General 146 0% 23-Mar-11 13-Oct-11 0
General 146 0% 23-Mar-11 13-Oct-11 0
HC0011 Inicio de Construcción 0 0% 06-May-11* -29 TRRA.PL.000.20
HC0021 Término Construcción (sin Barcaza 440-ZMZ-660) 0 0% 19-Sep-11* -39 TRRA.PL.000.20
HC0031 Termino Constr. con Barcaza 440-ZMZ-660 0 0% 06-Sep-11 37 TRRA.PL.000.20
HC0081 Inicio Parada N°3 (12 Hrs) 0 0% 13-Jun-11 123 TRRA.PL.000.20
HC0091 Fin Parada N°3 (12 Hrs) 0 0% 13-Jun-11 122 TRRA.PL.000.20
HC0101 Inicio Parada N°4 (12 Hrs) 0 0% 15-Sep-11 29 TRRA.PL.000.20
HC0111 Fin Parada N°4 (12 Hrs) 0 0% 15-Sep-11 28 TRRA.PL.000.20
HC0121 Inicio Parada N°5 (4 Hrs) 0 0% 20-Sep-11 24 TRRA.PL.000.20
HC0131 Fin Parada N°5 (4 Hrs) 0 0% 20-Sep-11 24 TRRA.PL.000.20
HC0141 Inicio Parada N°6 (96 Hrs) 0 0% 30-Aug-11* 0 TRRA.PL.000.20

Actual Work Critical Remaining Work Summ... Page 1 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
HC0151 Fin Parada N°6 (96 Hrs) 0 0% 02-Sep-11 41 TRRA.PL.000.20
HC0161 Termino Instalacion de Faenas 0 0% 20-Apr-11 -14 TRRA.PL.000.20
HC0171 Equipo de termofusion en Obra para cañerias de 5 0 0% 21-Apr-11* 0 TRRA.PL.000.20
HC0181 Term. Precomis. dsde 400-ZMZ-600 hsta720-TKF 0 0% 08-Oct-11 5 TRRA.PL.000.20
HC0200 Cliente Aprueba Plan de Movilizacion y Proced SS 0 0% 23-Mar-11 -21 TRRA.PL.000.20
HC0211 Term. Precomis. 400-ZMZ-660 hsta TKadic.Bbeo 0 0% 08-Oct-11 5 TRRA.PL.000.20
HC0221 Termino Precomisionamiento Sist. Transp. Relave 0 0% 14-Aug-11 60 TRRA.PL.000.20
HC0231 Termino Desmovilizacion 0 0% 13-Oct-11 0 TRRA.PL.000.20
Hitos de Ingeniería 47 0% 04-Apr-11 08-Jun-11 -16
Aker/Antamina 47 0% 04-Apr-11 08-Jun-11 -16
General 47 0% 04-Apr-11 08-Jun-11 -16
General 47 0% 04-Apr-11 08-Jun-11 -16
General 0 0% 05-Apr-11 05-Apr-11 -21
HC0001 Entrega de Ingeniería Aprobada para Construccion 0 0% 05-Apr-11* -29 TRRA.PL.000.30
Civil 0 0% 05-Apr-11 05-Apr-11 -21
HC01CV0 Ingeniería CIVIL Aprobada para Construccion al 1 0 0% 05-Apr-11* -29 TRRA.PL.000.30
Estructuras 0 0% 27-Apr-11 27-Apr-11 -14
HC01ST0 Ingeniería ESTRUCTURA Aprobada para Constru 0 0% 27-Apr-11* -20 TRRA.PL.000.30
Mecanica 0 0% 04-Apr-11 04-Apr-11 -20
HC01MC Ingeniería MECANICA Aprobada para Construcci 0 0% 04-Apr-11* -28 TRRA.PL.000.30
Tuberias 0 0% 12-Apr-11 12-Apr-11 -20
HC01PP0 Ingeniería PIPING Aprobada para Construccion al 0 0% 12-Apr-11* -28 TRRA.PL.000.30
Electrica e Instrumentación
I 0 0% 08-Jun-11 08-Jun-11 -16
HC01EI01 Ingeniería ELECTR/INSTR Aprobada p/Construcc 0 0% 08-Jun-11* -22 TRRA.PL.000.30
Hitos Suministro A
Aker/Antamina 140 0% 07-Mar-11 16-Sep-11 0
Aker/Antamina 140 0% 07-Mar-11 16-Sep-11 0
440-Sistema de Agua
A Recuperada 140 0% 07-Mar-11 16-Sep-11 0
General 140 0% 07-Mar-11 16-Sep-11 0
Estructuras 56 0% 26-May-11 12-Aug-11 0
SC0001 Barcaza 440-ZMZ-600 0 0% 26-May-11* 0 TRRA.PL.440.P.S
SC0071 Barcaza 440-ZMZ-660 0 0% 12-Aug-11* 0 TRRA.PL.440.P.S
Mecanica 98 0% 29-Mar-11 12-Aug-11 0
SC0011 Grúa de Servicio (Barcaza 440-ZMZ-600) 0 0% 26-May-11* 0 TRRA.PL.440.P.M
SC0021 Bombas 440-PPV-700@704) 0 0% 09-May-11* 0 TRRA.PL.440.P.M
SC0081 Grúa de Servicio (Barcaza-ZMZ-660) 0 0% 12-Aug-11* 0 TRRA.PL.440.P.M
SC0091 Bombas 440-PPZ-1310/1311 0 0% 26-May-11* 0 TRRA.PL.440.P.M
SC0131 Bombas PPZ-1312/1313 0 0% 12-Aug-11* 0 TRRA.PL.440.P.M
SC0151 Bombas 440-PPC-606/607/610/611 0 0% 21-May-11* 0 TRRA.PL.440.P.M
SC0161 Tanque 440-TKF-140 (Desmontaje) 0 0% 29-Mar-11* 0 TRRA.PL.440.P.M
Tuberias 140 0% 07-Mar-11 16-Sep-11 0
SC0031 Piping (Linea 36) 0 0% 28-Apr-11* 0 TRRA.PL.440.P.P
SC0041 Piping (Linea 42) 0 0% 28-Apr-11* 0 TRRA.PL.440.P.P
SC0101 Piping (Conexión a Línea Existente) 0 0% 16-Sep-11* 0 TRRA.PL.440.P.P
SC0111 Piping (Linea 28) 0 0% 07-Mar-11* 0 TRRA.PL.440.P.P
SC0171 Piping (Lineas C1E2DU) 0 0% 04-May-11* 0 TRRA.PL.440.P.P
Electrica e Instrumentación
I 113 0% 07-Mar-11 12-Aug-11 0
SC0051 Eléctrico e Instrumentación (Barcaza 440-ZMZ-60 0 0% 26-May-11* 0 TRRA.PL.440.P.E

Actual Work Critical Remaining Work Summ... Page 2 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
SC0121 Eléctrico e Instrumentación (Barcaza 440-ZMZ-66 0 0% 12-Aug-11* 0 TRRA.PL.440.P.E
SC0181 Eléctrico e Instrumentación (Nueva Est Bombeo 3 0 0% 17-May-11* 0 TRRA.PL.440.P.E
SC0201 Eléctrico e Instrumentación (Sub-Estacion Elect 5 0 0% 17-May-11* 0 TRRA.PL.440.P.E
SC0231 Sala Eléctrica 5MVA 0 0% 17-May-11* 0 TRRA.PL.440.P.E
SC0261 Sala Eléctrica 7.5MVA 0 0% 17-May-11* 0 TRRA.PL.440.P.E
SC0281 Trafos de 5MVA 0 0% 17-May-11* 0 TRRA.PL.440.P.E
SC0311 Trafos de 7.5MVA 0 0% 17-May-11* 0 TRRA.PL.440.P.E
SC0321 Cable de Fibra Optica 0 0% 07-Mar-11* 0 TRRA.PL.440.P.E
420-Sistema de Transporte
T de Relaves 87 0% 07-Mar-11 05-Jul-11 0
General 87 0% 07-Mar-11 05-Jul-11 0
Mecanica 61 0% 07-Mar-11 31-May-11 0
SC0211 Estanque de Relaves (320-SUU-001) 0 0% 07-Mar-11 31 TRRA.PL.420.P.M
SC0241 Cajón de Distribución de Relaves (320-SUU-011) 0 0% 31-May-11* 0 TRRA.PL.420.P.M
Tuberias 0 0% 30-Apr-11 30-Apr-11 0
SC0221 Piping (Línea 52) 0 0% 30-Apr-11* 0 TRRA.PL.420.P.P
SC0271 Piping (Línea 54) 0 0% 30-Apr-11* 0 TRRA.PL.420.P.P
Electrica e Instrumentación
I 53 0% 21-Apr-11 05-Jul-11 0
SC0251 Eléctrico e Instrumentación (Planta Concentradora 0 0% 05-Jul-11* 0 TRRA.PL.420.P.E
SC0291 Eléctrico e Instrumentación (Cajon de Paso N°1) 0 0% 21-Apr-11* 0 TRRA.PL.420.P.E
General 148 0% 22-Mar-11 13-Oct-11 0
Salfa Montajes 148 0% 22-Mar-11 13-Oct-11 0
General 148 0% 22-Mar-11 13-Oct-11 0
General 148 0% 22-Mar-11 13-Oct-11 0
General 148 0% 22-Mar-11 13-Oct-11 0
IF0001 Instalación de Faena 30 0% 22-Mar-11 20-Apr-11 -39 TRRA.PL.000.40
IF0011 Desmovilización 30 0% 14-Sep-11 13-Oct-11 0 TRRA.PL.000.40
Construcción 127 0% 26-Mar-11 20-Sep-11 17
Aker/Antamina 2 0% 26-Mar-11 29-Mar-11 0
440-Sistema de Agua
A Recuperada 2 0% 26-Mar-11 29-Mar-11 0
Nueva Estación
Estació de Bombeo 3B 2 0% 26-Mar-11 29-Mar-11 0
Mecanica 2 0% 26-Mar-11 29-Mar-11 0
CM0160 Desmontaje de Tanque (Parada N°2) 4 0% 26-Mar-11 29-Mar-11 0 TRRA.PL.440.C.G
420-Sistema de Transporte
T de Relaves 2 0% 26-Mar-11 29-Mar-11 0
Planta Concentradora
Concen 2 0% 26-Mar-11 29-Mar-11 0
Tuberias 2 0% 26-Mar-11 29-Mar-11 0
CM0212 Conexion a Brida de 52 ( Parada N°2) 4 0% 26-Mar-11 29-Mar-11 0 TRRA.PL.420.C.G
CM0222 Tie-In N°2 a Línea Existen -Línea 52 (Parada N°2) 4 0% 26-Mar-11 29-Mar-11 0 TRRA.PL.420.C.G
Salfa Montajes 112 0% 17-Apr-11 20-Sep-11 17
440-Sistema de Agua
A Recuperada 112 0% 17-Apr-11 20-Sep-11 17
General 70 0% 17-Apr-11 24-Jul-11 -27
Civil 70 0% 17-Apr-11 24-Jul-11 -27
CM0409 Replanteo Topografico 10 0% 17-Apr-11 26-Apr-11 -10 TRRA.PL.440.C.C
CM0411 Excavacion y relleno en zanjaspara tuberías 60 0% 26-May-11 24-Jul-11 -39 TRRA.PL.440.C.C
Barcaza 440-ZMZ-600
440-Z 80 0% 27-May-11 15-Sep-11 20
Estructuras 11 0% 27-May-11 10-Jun-11 45
CM00010 Armado de estructura Barcaza 440-ZMZ-600 6 0% 27-May-11 01-Jun-11 -20 TRRA.PL.440.C.S
CM00010 Montaje Estruct. Soporte Grúa (incluye plataform 5 0% 02-Jun-11 06-Jun-11 64 TRRA.PL.440.C.S

Actual Work Critical Remaining Work Summ... Page 3 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
CM00010 Instalacion barandas y Grating Barcaza -ZMZ-600 4 0% 07-Jun-11 10-Jun-11 64 TRRA.PL.440.C.S
Mecanica 17 0% 11-Jun-11 05-Jul-11 46
CM0011 Montaje Grúa de Servicio 440-CNZ-054 4 0% 11-Jun-11 14-Jun-11 64 TRRA.PL.440.C.M
CM00211 Montaje de Bomba 440-PPZ-1310/1311 5 0% 01-Jul-11 05-Jul-11 64 TRRA.PL.440.C.M
CM00217 Montaje de Bomba 440-PPV-700 5 0% 15-Jun-11 19-Jun-11 64 TRRA.PL.440.C.M
CM00217 Montaje de Bomba 440-PPV-701 5 0% 19-Jun-11 23-Jun-11 64 TRRA.PL.440.C.M
CM00217 Montaje de Bomba 440-PPV-702 5 0% 23-Jun-11 27-Jun-11 64 TRRA.PL.440.C.M
CM00217 Montaje de Bomba 440-PPV-703 5 0% 27-Jun-11 01-Jul-11 64 TRRA.PL.440.C.M
CM00217 Montaje de Bomba 440-PPV-704 5 0% 01-Jul-11 05-Jul-11 64 TRRA.PL.440.C.M
Tuberias 74 0% 05-Jun-11 15-Sep-11 20
CM0031 Montaje Piping 440-RWU-36-MDEOH-24707 a TK 50 0% 05-Jun-11 24-Jul-11 -39 TRRA.PL.440.C.P
CM0041L Montaje Piping 440-RWU-42-C1E2DU-24736 35 0% 20-Jun-11 24-Jul-11 26 TRRA.PL.440.C.P
CM0041L Montaje Piping 440-RWU-42-MDEOH-24745 26 0% 20-Aug-11 14-Sep-11 0 TRRA.PL.440.C.P
CM0041L Montaje Piping 440-RWU-42-MDEOH-24737 50 0% 01-Jul-11 19-Aug-11 0 TRRA.PL.440.C.P
CM0041L Montaje Piping 440-RWU-42-C!E2DU-24738 20 0% 25-Jul-11 13-Aug-11 60 TRRA.PL.440.C.P
CM0042 Conexión Línea 42 a Tanque exist. (Parada N°4) 1 0% 15-Sep-11 15-Sep-11 28 TRRA.PL.440.C.P
Electrica e Instrumentación
I 10 0% 09-Jul-11 25-Jul-11 40
CM0061 Aterramiento 1 0% 09-Jul-11 10-Jul-11 56 TRRA.PL.440.C.E
CM0071 Armado de acometida a bombas 2 0% 10-Jul-11 12-Jul-11 56 TRRA.PL.440.C.E
CM0091 Cableado y Conexionado Bomba 440-PPV-700 1 0% 12-Jul-11 13-Jul-11 56 TRRA.PL.440.C.E
CM0131 Cableado y Conexionado Bomba 440-PPV-701 1 0% 12-Jul-11 13-Jul-11 56 TRRA.PL.440.C.E
CM0141 Cableado y Conexionado Bomba 440-PPV-702 1 0% 13-Jul-11 14-Jul-11 56 TRRA.PL.440.C.E
CM0151 Cableado y Conexionado Bomba 440-PPV-703 1 0% 13-Jul-11 14-Jul-11 56 TRRA.PL.440.C.E
CM0171 Cableado y Conexionado Bomba 440-PPV-704 1 0% 14-Jul-11 15-Jul-11 56 TRRA.PL.440.C.E
CM0231 Cableado y Conexionado Bomba 440-PPZ-1310 / 1 0% 14-Jul-11 15-Jul-11 56 TRRA.PL.440.C.E
CM0261 Bandejas y conduits 1 0% 15-Jul-11 16-Jul-11 56 TRRA.PL.440.C.E
CM0281 5 Interruptores de Vibracion :440-XSH-28900, 440 1 0% 16-Jul-11 17-Jul-11 56 TRRA.PL.440.C.E
CM0451 5 Interruptores de Flujo Termico 440-FSL-28900, 1 0% 17-Jul-11 18-Jul-11 56 TRRA.PL.440.C.E
CM0461 5 Manometros Bourdon: 440-PI-28900, 440-PI-28 1 0% 18-Jul-11 19-Jul-11 56 TRRA.PL.440.C.E
CM0471 1 Sensor Transmisor de Nivel Capacitivo: 440-LIT 1 0% 19-Jul-11 20-Jul-11 56 TRRA.PL.440.C.E
CM0481 1 Sensor Transmisor de Presion Diafragma: 440-L 1 0% 20-Jul-11 21-Jul-11 56 TRRA.PL.440.C.E
CM0491 Cableado de señales al tablero 440-DCS-691 1 0% 21-Jul-11 22-Jul-11 56 TRRA.PL.440.C.E
CM0501 Cableado de señales de status de arrancadores, 1 0% 22-Jul-11 23-Jul-11 56 TRRA.PL.440.C.E
CM0511 Interconectar medidores de MCCS 1 0% 23-Jul-11 24-Jul-11 56 TRRA.PL.440.C.E
CM0521 Instalar Gabinetes en SE 440-ER-611 1 0% 24-Jul-11 25-Jul-11 56 TRRA.PL.440.C.E
Barcaza 440-ZMZ-660
440-Z 42 0% 25-Jul-11 20-Sep-11 17
Estructuras 9 0% 13-Aug-11 25-Aug-11 -15
CM00710 Armado de estructura Barcaza 440-ZMZ-660 5 0% 13-Aug-11 17-Aug-11 -21 TRRA.PL.440.C.S
CM00710 Montaje Estruct. Soporte Grúa (incluye plataform 5 0% 18-Aug-11 22-Aug-11 -21 TRRA.PL.440.C.S
CM00710 Instalacion barandas y Grating Barcaza -ZMZ-660 3 0% 23-Aug-11 25-Aug-11 -21 TRRA.PL.440.C.S
Mecanica 8 0% 26-Aug-11 06-Sep-11 -17
CM0081 Montaje Grúa de Servicio 440-CNZ-055 4 0% 26-Aug-11 29-Aug-11 -21 TRRA.PL.440.C.M
CM0090 Desmontaje de Bombas (Parada N°6) 4 0% 30-Aug-11 02-Sep-11 -25 TRRA.PL.440.C.M
CM00910 Montaje de Bomba 440-PPV-031 4 0% 03-Sep-11 06-Sep-11 -25 TRRA.PL.440.C.M
CM00910 Montaje de Bomba 440-PPV-032 4 0% 03-Sep-11 06-Sep-11 -25 TRRA.PL.440.C.M
CM00911 Montaje de Bomba 440-PPZ-1312/1313 2 0% 05-Sep-11 06-Sep-11 -25 TRRA.PL.440.C.M
Tuberias 42 0% 25-Jul-11 20-Sep-11 17

Actual Work Critical Remaining Work Summ... Page 4 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
CM0101 Piping Conexión Línea Existente (Parada N°5) 4 0% 17-Sep-11 20-Sep-11 23 TRRA.PL.440.C.P
CM0111 Montaje Piping 440-RWU-28-MDECOH-24710 a T 25 0% 25-Jul-11 18-Aug-11 -39 TRRA.PL.440.C.P
CM0111L Tie In 001 2 0% 19-Aug-11 20-Aug-11 54 TRRA.PL.440.C.P
CM0111L Montaje Piping440-RWU-28-MDECOH-24712 a T 15 0% 19-Aug-11 02-Sep-11 -39 TRRA.PL.440.C.P
CM0111L Montaje Piping 440-RWU-30-MDECOH-24744 de 15 0% 03-Sep-11 17-Sep-11 -39 TRRA.PL.440.C.P
CM0112 Tie-In 002 2 0% 18-Sep-11 19-Sep-11 -39 TRRA.PL.440.C.P
Electrica e Instrumentación
I 7 0% 27-Aug-11 06-Sep-11 27
CM0121 Monteje Eléctrico e Instrumentación 11 0% 27-Aug-11 06-Sep-11 30 TRRA.PL.440.C.E
CM0531 Apoyo en desconexionado de bombas (Parada N° 1 0% 29-Aug-11 29-Aug-11 45 TRRA.PL.440.C.E
CM0541 Conexionado Bomba 440-PPV-031 1 0% 06-Sep-11 06-Sep-11 37 TRRA.PL.440.C.E
CM0551 Conexionado Bomba 440-PPV-032 1 0% 06-Sep-11 06-Sep-11 37 TRRA.PL.440.C.E
CM0561 Conexionado Bomba 440-PPZ-1312 / 1313 1 0% 06-Sep-11 06-Sep-11 37 TRRA.PL.440.C.E
Nueva Estación
Estació de Bombeo 3B 98 0% 26-Apr-11 08-Sep-11 25
Civil 78 0% 26-Apr-11 11-Aug-11 45
CM0189 Replanteo Topografico 6 0% 26-Apr-11 01-May-11 -25 TRRA.PL.440.P.C
CM0191 Excavaciones, rellenos y plataformas 35 0% 02-May-11 05-Jun-11 -25 TRRA.PL.440.P.C
CM0381 Concreto, armado en losas,pedestales, cimentaci 55 0% 06-Jun-11 30-Jul-11 35 TRRA.PL.440.P.C
CM0391 Conformacion de accesos 12 0% 31-Jul-11 11-Aug-11 63 TRRA.PL.440.P.C
Mecanica 14 0% 16-Jul-11 04-Aug-11 50
CM01516 Montaje de Bomba 440-PPC-606 5 0% 16-Jul-11 20-Jul-11 35 TRRA.PL.440.C.M
CM01516 Montaje de Bomba 440-PPC-607 5 0% 21-Jul-11 25-Jul-11 35 TRRA.PL.440.C.M
CM01516 Montaje de Bomba 440-PPC-610 5 0% 26-Jul-11 30-Jul-11 35 TRRA.PL.440.C.M
CM01516 Montaje de Bomba 440-PPC-611 5 0% 31-Jul-11 04-Aug-11 35 TRRA.PL.440.C.M
CM0161 Montaje de Tanque 440-TKF-140 12 0% 24-Jul-11 04-Aug-11 70 TRRA.PL.440.C.M
Tuberias 26 0% 29-Jul-11 03-Sep-11 29
CM0171L Montaje Linea 36 -C1E2DU-24708 7 0% 29-Jul-11 04-Aug-11 40 TRRA.PL.440.C.P
CM0171L Montaje Linea 48 -C1E2DU-24714 21 0% 05-Aug-11 25-Aug-11 40 TRRA.PL.440.C.P
CM0171L Montaje Linea 24 -C1E2DU-24715 3 0% 26-Aug-11 28-Aug-11 40 TRRA.PL.440.C.P
CM0171L Montaje Linea 24 -C1E2DU-24717 3 0% 29-Aug-11 31-Aug-11 40 TRRA.PL.440.C.P
CM0171L Montaje Linea 24 -C1E2DU-24719 3 0% 01-Sep-11 03-Sep-11 40 TRRA.PL.440.C.P
CM0171L Montaje Linea 24 -C1E2DU-24721 3 0% 02-Aug-11 04-Aug-11 46 TRRA.PL.440.C.P
CM0171L Montaje Linea 24 -C1E2DU-24723 3 0% 05-Aug-11 07-Aug-11 61 TRRA.PL.440.C.P
CM0171L Montaje Linea 20 -C1E2DU-24725 2 0% 08-Aug-11 09-Aug-11 61 TRRA.PL.440.C.P
CM0171L Montaje Linea 20 -C1E2DU-24726 2 0% 10-Aug-11 11-Aug-11 61 TRRA.PL.440.C.P
CM0171L Montaje Linea 20 -C1E2DU-24727 2 0% 12-Aug-11 13-Aug-11 61 TRRA.PL.440.C.P
CM0171L Montaje Linea 20 -C1E2DU-24728 2 0% 03-Aug-11 04-Aug-11 45 TRRA.PL.440.C.P
CM0171L Montaje Linea 20 -C1E2DU-24729 2 0% 05-Aug-11 06-Aug-11 45 TRRA.PL.440.C.P
CM0171L Montaje Linea 42 -C1E2DU-24730 20 0% 07-Aug-11 26-Aug-11 45 TRRA.PL.440.C.P
CM0171L Montaje Linea 42 -C1E2DU-24734 3 0% 27-Aug-11 29-Aug-11 45 TRRA.PL.440.C.P
Electrica e Instrumentación
I 73 0% 31-May-11 08-Sep-11 25
CM0571 Armado de acometida a bombas 2 0% 05-Aug-11 06-Aug-11 64 TRRA.PL.440.C.E
CM0581 Cableado y Conexionado Bomba 440-PPC-606 1 0% 07-Aug-11 07-Aug-11 64 TRRA.PL.440.C.E
CM0591 Cableado y Conexionado Bomba 440-PPC-607 1 0% 08-Aug-11 08-Aug-11 64 TRRA.PL.440.C.E
CM0601 Cableado y Conexionado Bomba 440-PPC-610 1 0% 09-Aug-11 09-Aug-11 64 TRRA.PL.440.C.E
CM0611 Cableado y Conexionado Bomba 440-PPC-611 1 0% 10-Aug-11 10-Aug-11 64 TRRA.PL.440.C.E
CM0621 Aterramiento 1 0% 31-May-11 01-Jun-11 100 TRRA.PL.440.C.E
CM0631 4 Interruptores de Vibracion 1 0% 05-Aug-11 05-Aug-11 35 TRRA.PL.440.C.E

Actual Work Critical Remaining Work Summ... Page 5 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
CM0641 4 Interruptores de Flujo Termico 1 0% 06-Aug-11 06-Aug-11 35 TRRA.PL.440.C.E
CM0651 4 Manometros Bourdon 1 0% 07-Aug-11 07-Aug-11 35 TRRA.PL.440.C.E
CM0661 1 Sensor Transmisor de Presion Diafragma 1 0% 08-Aug-11 08-Aug-11 35 TRRA.PL.440.C.E
CM0671 1 Sensor Transmisor de Flujo Ultrasonico 1 0% 09-Aug-11 09-Aug-11 35 TRRA.PL.440.C.E
CM0681 1 Sensor Transmisor de Nivel Ultrasonico 1 0% 10-Aug-11 10-Aug-11 35 TRRA.PL.440.C.E
CM0691 1 Valvula de Control Bola Vee 1 0% 11-Aug-11 11-Aug-11 35 TRRA.PL.440.C.E
CM0701 Cableado de señales al tablero 1 0% 12-Aug-11 12-Aug-11 35 TRRA.PL.440.C.E
CM0711 Cableado de señales de status de arrancadores, 1 0% 13-Aug-11 13-Aug-11 35 TRRA.PL.440.C.E
CM0721 Interconectar medidores de MCCS 1 0% 14-Aug-11 14-Aug-11 35 TRRA.PL.440.C.E
CM0731 Instalar Gabinetes en SE 440-ER-612 1 0% 15-Aug-11 15-Aug-11 35 TRRA.PL.440.C.E
CM0741 DISTRIBUCION ELECTRICA -Tendido de Postes 10 0% 16-Aug-11 25-Aug-11 35 TRRA.PL.440.C.E
CM0751 Sala Electrica 7.5 MVA 14 0% 05-Aug-11 18-Aug-11 49 TRRA.PL.440.C.E
CM0761 Trafos de 7.5 MVA 7 0% 19-Aug-11 25-Aug-11 49 TRRA.PL.440.C.E
CM0771 Caja Terminal para los Bornes de baja tension 1 0% 26-Aug-11 26-Aug-11 35 TRRA.PL.440.C.E
CM0781 Resistencia de puesta a tierra 400A, 10 seg 1 0% 27-Aug-11 27-Aug-11 35 TRRA.PL.440.C.E
CM0791 Bus bar 4.16 KV 1200 A 2 0% 28-Aug-11 29-Aug-11 35 TRRA.PL.440.C.E
CM0801 Alumbrado 2 0% 30-Aug-11 31-Aug-11 35 TRRA.PL.440.C.E
CM0811 Pararrayos 1 0% 01-Sep-11 01-Sep-11 35 TRRA.PL.440.C.E
CM0821 Tendido de Fibra Optica - Postes y Fibra 7 0% 02-Sep-11 08-Sep-11 35 TRRA.PL.440.C.E
Subestación Eléctrica
E 5 MVA 98 0% 21-Apr-11 05-Sep-11 28
Civil 73 0% 21-Apr-11 01-Aug-11 53
CM0359 Replanteo Topografico 8 0% 21-Apr-11 28-Apr-11 -22 TRRA.PL.440.C.C
CM0361 Relleno y Conformación de Plataforma y excavacio 60 0% 29-Apr-11 27-Jun-11 -22 TRRA.PL.440.C.C
CM0371 Concreto, armado en losas y pedestales 40 0% 08-Jun-11 17-Jul-11 -22 TRRA.PL.440.C.C
CM0401 Conformacion de accesos 15 0% 18-Jul-11 01-Aug-11 73 TRRA.PL.440.C.C
Electrica e Instrumentación
I 42 0% 08-Jul-11 05-Sep-11 28
CM0351 DISTRIBUCION ELECTRICA -Tendido de Postes 30 0% 08-Jul-11 06-Aug-11 -22 TRRA.PL.440.C.E
CM0831 Sala Electrica 5 MVA 12 0% 08-Jul-11 19-Jul-11 38 TRRA.PL.440.C.E
CM0841 Trafos de 5 MVA 12 0% 20-Jul-11 31-Jul-11 38 TRRA.PL.440.C.E
CM0851 Caja Terminal para los Bornes de baja tension 6 0% 01-Aug-11 06-Aug-11 38 TRRA.PL.440.C.E
CM0861 Resistencia de puesta a tierra 400A, 10 seg 6 0% 07-Aug-11 12-Aug-11 38 TRRA.PL.440.C.E
CM0871 Bus bar 4.16 KV 1200 A 6 0% 13-Aug-11 18-Aug-11 38 TRRA.PL.440.C.E
CM0881 Alumbrado 9 0% 19-Aug-11 27-Aug-11 38 TRRA.PL.440.C.E
CM0891 Pararrayos 6 0% 28-Aug-11 02-Sep-11 38 TRRA.PL.440.C.E
CM0901 Tendido de Fibra Optica - Postes y Fibra 3 0% 03-Sep-11 05-Sep-11 38 TRRA.PL.440.C.E
420-Sistema de Transporte
T de Relaves 72 0% 21-Apr-11 31-Jul-11 54
Planta Concentradora
Concen 72 0% 21-Apr-11 31-Jul-11 40
Civil 57 0% 21-Apr-11 09-Jul-11 30
CM0209 Replanteo Topografico 8 0% 21-Apr-11 28-Apr-11 -39 TRRA.PL.420.C.C
CM0211 Modificación Estanque de Relaves (320-SUU-010) 20 0% 05-May-11 24-May-11 -28 TRRA.PL.420.C.C
CM0301 Excavaciones y relleno en tubería 0+000 a 0+980 65 0% 06-May-11 09-Jul-11 -39 TRRA.PL.420.C.C
CM0321 Muro de Contencion 20 0% 05-May-11 24-May-11 68 TRRA.PL.420.C.C
CM0331 Estructura Concreto By Pass inicio y final 20 0% 25-May-11 13-Jun-11 68 TRRA.PL.420.C.C
Tuberias 17 0% 13-May-11 06-Jun-11 77
CM0221 Montaje de Piping 420-TL-52-L1EOU-24501A 11 0% 13-May-11 23-May-11 -28 TRRA.PL.420.C.P
CM0224 Montaje de Piping BYPASS 420-TL-52-L1EOU-24 14 0% 24-May-11 06-Jun-11 55 TRRA.PL.420.C.P
CM0225 Montaje de Piping a Cajon 1 420-TL-54-MCEOHU 15 0% 16-May-11 30-May-11 114 TRRA.PL.420.C.P

Actual Work Critical Remaining Work Summ... Page 6 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Schedule % Start Finish Total WBS 2011
Duration Complete Float
Mar Apr May Jun Jul Aug Sep Oct Nov
Electrica e Instrumentación
I 10 0% 17-Jul-11 31-Jul-11 40
CM0251 Monteje Eléctrico e Instrumentación 15 0% 17-Jul-11 31-Jul-11 55 TRRA.PL.420.C.E
Cajon de Distribucion
Distr de Relaves 320-SUU-011 31 0% 15-Jun-11 27-Jul-11 56
Civil 29 0% 17-Jun-11 27-Jul-11 56
CM0239 Excavacion 10 0% 17-Jun-11 26-Jun-11 109 TRRA.PL.420.C.C
CM0241 Concreto en cajon 25 0% 27-Jun-11 21-Jul-11 55 TRRA.PL.420.C.C
CM0341 Relleno estructural 6 0% 22-Jul-11 27-Jul-11 78 TRRA.PL.420.C.C
Tuberias 16 0% 15-Jun-11 06-Jul-11 71
CM0223 Montaje de Piping 420-TL-54-MCOHU-24507 7 0% 15-Jun-11 21-Jun-11 99 TRRA.PL.420.C.P
CM0233 Montaje de Piping 420-TL-54-MCOHU-24509 15 0% 22-Jun-11 06-Jul-11 99 TRRA.PL.420.C.P
Cajon de Paso N°1 (420-SUU-022) 31 0% 20-May-11 01-Jul-11 74
Civil 25 0% 30-May-11 01-Jul-11 74
CM0311 Excavacion 8 0% 30-May-11 06-Jun-11 107 TRRA.PL.420.C.C
CM0421 Concreto en cajon 20 0% 07-Jun-11 26-Jun-11 55 TRRA.PL.420.C.C
CM0431 Relleno estructural 5 0% 27-Jun-11 01-Jul-11 104 TRRA.PL.420.C.C
Tuberias 17 0% 20-May-11 13-Jun-11 88
CM0270 Montaje de Piping Subterranea 420-TL-52-L1EOU 7 0% 02-Jun-11 08-Jun-11 112 TRRA.PL.420.C.P
CM0271 Montaje de Piping a Cajon N°2 420-TL-54-MCEOH 25 0% 20-May-11 13-Jun-11 107 TRRA.PL.420.C.P
CM0272 Conexión definitiva (en sector de Tie-in N°1) 1 0% 12-Jun-11 12-Jun-11 123 TRRA.PL.420.C.P
Electrica e Instrumentación
I 11 0% 14-Jun-11 28-Jun-11 77
CM0291 Monteje Eléctrico e Instrumentación 15 0% 14-Jun-11 28-Jun-11 107 TRRA.PL.420.C.E
Pre-Commissioning 50 0% 31-Jul-11 08-Oct-11 0
Salfa Montajes 50 0% 31-Jul-11 08-Oct-11 0
General 50 0% 31-Jul-11 08-Oct-11 0
General 50 0% 31-Jul-11 08-Oct-11 0
General 50 0% 31-Jul-11 08-Oct-11 0
PM0011 Precomis. Sist. Balsa 600 hasta 720-TKF-005 20 0% 19-Sep-11 08-Oct-11 0 TRRA.PL.440.U
PM0021 Precomis. Sist. Balsa 660 hasta est. bbeo 3B 22 0% 17-Sep-11 08-Oct-11 0 TRRA.PL.440.U
PM0031 Precomis. Sist. Transporte de Relaves 15 0% 31-Jul-11 14-Aug-11 55 TRRA.PL.420.U

Actual Work Critical Remaining Work Summ... Page 7 of 7 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.