Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Project Status
Project is moving forward with cost saving measures
incorporated into the P3 RFP
Right-of-Way offers and property settlements are ongoing
Selection of Purple Line Transit Partners (PLTP)
announced on March 2, 2016
Board of Public Works approved P3 Concessionaire
Contract on April 6, 2016. Six years of final
design/construction and 30-year O&M period
MTA issued Limited Notice To Proceed to PLTP in April
2016
2
Typical Cross-Section
Except at Key Intersections
County will remain involved in issues regarding design and operation of the
roads, on-street parking regulations, pedestrian crossings and intersection
operations
PLTP to assume maintenance responsibility once construction is completed
11
TPSS Rendering
12
13
Project Delivery
Benefits of the P3
Project Delivery
15
16
17
18
19
21
22
Start
End
Fall 2017
Summer 2018
Summer 2018
Spring 2019
Spring 2019
Winter 2019
Spring 2019
Fall 2020
Fall 2020
Spring 2022
Utility Relocations
Stage 1 Roadway Work - Traffic Shifted to South Side
Continued utility relocations
Roadway widening / Track construction
SSIMS retaining walls and parking lot (Summer 18)
Dale Drive Station
Wayne Avenue Bridge
23
25
26
28
Next Steps
Financial Close June 2016
FTA Full Funding Grant Agreement July 2016
CATs Kick-off Meetings Fall 2016
Commence Construction Late 2016
Begin Revenue Service 2022
29
Questions?
Please contact Lesli Leath, Public Outreach at:
443-451-3706
outreach@purplelinemd.com
www.purplelinemd.com
Mike Madden
Purple Line Deputy Project Director
443-451-3718
MMadden@mta.maryland.gov
Lnea telefnica en espaol:
443-451-3705
Like us on Facebook facebook.com/marylandpurpleline
Follow us on Twitter twitter.com/PurpleLineMD
30