EXPEDIENTE TECNICO: MEJORAMIENTO DE LA INFRAESTRUCTURA DE

ALMACENAMIENTO Y DISTRIBUCION DE AGUA PARA EL FUNDO AVO PERU SAC

CALCULOS DE VOLUMENES - POZA DE IMPULSION A RESERVORIO

Progresiva
0+000
0+010

Areas m2
Corte
Relleno
62.88
0
38.05

Distancia
m.

Volumen de Corte m3
Volumen de Relleno m3
Parcial
Acumulado
Parcial
Acumulado

10.00

504.650

504.650

0.000

0.000

10.00

346.550

851.20

0.000

0.000

10.00

315.800

1,167.00

0.000

0.000

10.00

295.300

1,462.30

0.000

0.000

10.00

288.050

1,750.35

0.000

0.000

10.00

249.750

2,000.10

0.000

0.000

10.00

177.050

2,177.15

0.000

0.000

10.00

153.450

2,330.60

0.000

0.000

10.00

188.450

2,519.05

0.000

0.000

10.00

338.600

2,857.65

0.000

0.000

10.00

445.650

3,303.30

0.000

0.000

4.00

295.160

3,598.46

0.000

0.000

0+020

31.26

0+030

31.9

0+040

27.16

0+050

30.45

0+060

19.5

0+070

15.91

0+080

14.78

0+090

22.91

0+100

44.81

0+110

44.32

0+114

103.26

INGENIERIA Y SERVICIOS INTEGRALES CASTINO SAC

AVO PER SAC

EXPEDIENTE TECNICO: MEJORAMIENTO DE LA INFRAESTRUCTURA DE


ALMACENAMIENTO Y DISTRIBUCION DE AGUA PARA EL FUNDO AVO PERU SAC

CALCULOS DE VOLUMENES - POZA DE IMPULSION A RESERVORIO

Progresiva
0+000

Areas m2
Corte
Relleno
26.45
43.3

0+005

25.81

41.61

0+010

26.87

38.85

0+015

31.07

36.19

0+020

37.61

34.88

0+025

40.56

33.58

0+030

45.87

31.1

0+035

49.08

27.83

0+036

49.34

27.28

Distancia
m.

Volumen de Corte m3
Volumen de Relleno m3
Parcial
Acumulado
Parcial
Acumulado

5.00

130.650

130.650

212.275

212.275

5.00

131.700

262.35

201.150

413.425

5.00

144.850

407.20

187.600

601.025

5.00

171.700

578.90

177.675

778.700

5.00

195.425

774.33

171.150

949.850

5.00

216.075

990.40

161.700

1111.550

5.00

237.375

1,227.78

147.325

1258.875

1,227.78

13.778

1272.653

0.50

INGENIERIA Y SERVICIOS INTEGRALES CASTINO SAC

AVO PER SAC

EXPEDIENTE TECNICO: MEJORAMIENTO DE LA INFRAESTRUCTURA DE


ALMACENAMIENTO Y DISTRIBUCION DE AGUA PARA EL FUNDO AVO PERU SAC

CALCULOS DE VOLUMENES - RESERVORIO

Progresiva
0+000
0+005

Areas m2
Corte
Relleno
10.474
389.59
20.4

Distancia
m.

Volumen de Corte m3
Volumen de Relleno m3
Parcial
Acumulado
Parcial
Acumulado

5.00

77.185

77.185 1634.625

1634.625

5.00

150.850

228.04

1059.025

2693.650

5.00

258.525

486.56

664.875

3358.525

5.00

295.250

781.81

547.425

3905.950

5.00

141.750

923.56

593.750

4499.700

5.00

169.585

1,093.15

647.350

5147.050

5.00

245.010

1,338.16

748.650

5895.700

5.00

140.900

1,479.06

929.350

6825.050

5.00

103.850

1,582.91

1109.100

7934.150

5.00

71.575

1,654.48

1191.850

9126.000

5.00

43.650

1,698.13

1194.050

10320.050

5.00

21.850

1,719.98

1231.825

11551.875

5.00

6.600

1,726.58

1315.075

12866.950

5.00

0.375

1,726.96

1416.225

14283.175

5.00

0.000

1,726.96

1548.200

15831.375

5.00

0.000

1,726.96

1707.900

17539.275

5.00

0.000

1,726.96

1731.975

19271.250

5.00

0.475

1,727.43

1543.150

20814.400

5.00

23.075

1,750.51

1248.700

22063.100

5.00

48.400

1,798.91

1097.825

23160.925

5.00

30.150

1,829.06

1176.650

24337.575

5.00

7.075

1,836.13

1325.475

25663.050

5.00

4.225

1,840.36

1479.975

27143.025

5.00

2.400

1,842.76

1486.950

28629.975

5.00

1.150

1,843.91

1431.925

30061.900

264.26

0+010

39.94

159.35

0+015

63.47

106.6

0+020

54.63

112.37

0+025

2.07

125.13

0+030

65.764

133.81

0+035

32.24

165.65

0+040

24.12

206.09

0+045

17.42

237.55

0+050

11.21

239.19

0+055

6.25

238.43

0+060

2.49

254.3

0+065

0.15

271.73

0+070

294.76

0+075

0.00

324.52

0+080

358.64

0+085

334.15

0+090

0.19

283.11

0+095

9.04

216.37

0+100

10.32

222.76

0+105

1.74

247.90

0+110

1.09

282.29

0+115

0.6

309.70

0+120

0.36

285.08

0+125

0.1

287.69

INGENIERIA Y SERVICIOS INTEGRALES CASTINO SAC

AVO PER SAC

EXPEDIENTE TECNICO: MEJORAMIENTO DE LA INFRAESTRUCTURA DE


ALMACENAMIENTO Y DISTRIBUCION DE AGUA PARA EL FUNDO AVO PERU SAC

0+130

0.98

277.07

0+135

1.65

255.07

0+140

3.43

204.39

0+145

20.56

162.87

0+150

17.85

249.38

0+155

12.49

316.03

0+156
5.21
PRESED
LONG. DE TALUD
10
10
65
65

5.00

2.700

1,846.61

1411.900

31473.800

5.00

6.575

1,853.18

1330.350

32804.150

5.00

12.700

1,865.88

1148.650

33952.800

5.00

59.975

1,925.86

918.150

34870.950

5.00

96.025

2,021.88

1030.625

35901.575

5.00

75.850

2,097.73

1413.525

37315.100

1.13

10.001

2,107.73

460.023

37775.123

498.17
5.5902
55.902
55.902
363.363
363.363

RESERVORIO
LONG. DE TALUD
175
175
62
62

11.1803
1956.5525
1956.5525
693.1786
693.1786

FONDO
CAMINO

300
356

FONDO
CAMINO

8580
1044

TOTAL

1494.53

TOTAL

14923.4622

INGENIERIA Y SERVICIOS INTEGRALES CASTINO SAC

AVO PER SAC