Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Petroleum Upstream
Petroleum Upstream
Petroleum Upstream
API Recommended Practice 575, Inspection of Atmospheric and LowPressure Storage Tanks, Third Edition, April 2014
API Recommended Practice 577 Welding Inspection and Metallurgy,
Second Edition, December 2013
API Standard 650, Welded Tanks for Oil Storage, Twelfth Edition, March
2013 with Addendum 1 (September 2014), Errata 1 (July 2013), and
Errata 2 (December 2014).
API Recommended Practice 651, Cathodic Protection of Aboveground
Petroleum Storage Tanks, Fourth Edition, September 2014.
API Recommended Practice 652, Lining of Aboveground Petroleum
Storage Tank Bottoms, Fourth Edition, September 2014
API Standard 653, Tank Inspection, Repair, Alteration, and
Reconstruction, Fifth Edition, November 2014.
http://independent.academia.edu/CharlieChong1
http://www.yumpu.com/zh/browse/user/charliechong
http://issuu.com/charlieccchong
http://greekhouseoffonts.com/
,
. .
http://cn.bing.com/videos/search?q=Walter+Lewin&FORM=HDRSC3
https://www.youtube.com/channel/UCiEHVhv0SBMpP75JbzJShqw
Q&A Practice 1
Thanks George for your good works!
Q2: Patch plate at critical zone for service temperature >200F for CS,
>100F for SS
Q12: Colum wear plate (key point thickness of plate and fillet weld size = )
Q20: if you want to use A-283 instead of A-36 require purchaser written
approval .
https://law.resource.org/pub/us/cfr/ibr/002/api.620.2002.pdf
Robotic
5.4.5 If specified on the Data Sheet, Line 12, a foundation drip ring shall be
provided to prevent ingress of water between the tank bottom and
foundation. Unless the Purchaser specifies otherwise, the ring shall meet
the following requirements (see Figure 5.5).
Material shall be carbon steel, 3 mm (1/8 in.) minimum thickness.
All radial joints between sections of the drip rings, as well as between the
drip ring and the annular plate or bottom, shall be continuously sealwelded.
The drip ring shall extend at least 75 mm (3 in.) beyond the outer
periphery of the foundation ringwall and then turn down (up to 90) at its
outer diameter.
The top and bottom of the drip ring, and the top of the tank bottom edge
projection beyond the shell, and a portion of the tank shell shall be coated
if specified by the Purchaser.
3 in.min
3in.min
24in.min
3 in.min
http://www.ast-forum.com/ast_forum_tree.asp?master=13099
Q38: Differential aeration corrosion due to hard rock & dirts point contacts
Q46: different plate thicknesses transition with 1:4 for t . 1/8 (3mm)
Q49: acceptance limit for pit & welding at bottom plate critical zone
Q50: Arc-gouging
Arc Gouged
Arc Gouged
Q56:
Q58: Banding & Peaking (New & inservice tank has different acceptance
criteria)
John Denver
http://www.kuwo.cn/mingxing/John+Denver/music.htm
Q70: J value open book t =.5, toughness does not meet API650 7th Ed.
Answer: J = 3
9.9 Alteration of Existing Shell Penetrations
9.9.1 Existing shell penetrations may be altered if the altered details comply
with the requirements of API 650, Section 5.7 including the requirements for
minimum reinforcing area and the requirements for spacing of welds around
connections.
9.9.4 A new bottom may be installed through an existing tombstone
reinforcing plate, provided all weld spacing and reinforcement requirements,
as specified in API 650, are met. One of the following methods shall be used.
a) Remove only that portion of the existing reinforcing plate necessary to weld
and test the new bottom-to-shell weld. The lower edge of the reinforcing plate
shall be cut reasonably straight and horizontal and beveled to facilitate
welding. See Figure 9.10 for weld joint details.
b) Bevel the shell from the inside to allow for a full penetration weld between
the bottom and shell. This method shall only be used on tanks where the
annular plate or bottom sketch plate thickness is equal to or greater than
10 mm (3/8 in.). This weld detail shall be used along the full width of the
reinforcing plate and shall extend a minimum of 25 mm (1 in.) beyond the
edges of the reinforcing plate. Once beyond the reinforcing plate, the full
penetration weld shall tie in to the outside shell-to-bottom fillet weld to
create a water stop and then transition to the typical shell-to-bottom weld
detail. See Figure 9.11 for weld joint details.
>| dsssa
Q77:
Q78:
Q79:
Discussion
shell plate thickness:
t1 = average thickness
The average plate thickness as determine using L=3.7(Dt2) shall be tmin
t2 = the minimum thickness
The minimum or least thickness as determined when inspection a
corroded area. The t2 shall be 0.6tmin
tmin = the design minimum shell thickness
The tmin = 2.6(H-1)DG/SE for whole course thickness calculation
Pitmaximum = the pitting on a shell plate shall not result in the thickness
<0.5tmin excluding corrosion allowance.
Q82: VT
Q85: W.P.S question joint sketch given but did not mention the grove angle.
Q86: P.Q.R question thickness range qualification .
Q95: Keyword in the exam is experiences with coatings and linings OPEN
BOOK
http://hyperallergic.com/151607/should-the-buddhas-of-bamiyan-rise-again-in-afghanistan/
http://asiasociety.org/blog/asia/are-chinese-miners-destroying-2000-year-old-buddhist-site-afghanistan-images
http://asiasociety.org/blog/asia/are-chinese-miners-destroying-2000-year-old-buddhist-site-afghanistan-images
Q96: Key word is to the maximum liquid level , not shell height in the
examination they mentioned tank height and liquid level and ask us which
one we have to consider for calculating thickness
Q98: Internal corrosion of tank vapor space by (1) H2S (2) H2O (3) O2 (4) any
combination of above.
Q98B: Carbon Steel (Unknown Specification) thickness is .5 and temp 20F- safe for use
API653: 9.1.3 All repair work must be authorized by the authorized inspector
or an engineer experienced in storage tank design, before commencement of
the work by a repair organization.
Authorization for alterations to storage tanks that comply with API 650 may
not be given without prior consultation with, and approved by, an engineer
experienced in storage tank design.
The authorized inspector will designate inspection hold points required during
the repair or alteration sequence and minimum documentation to be
submitted upon job completion.
The authorized inspector may give prior general authorization for limited or
routine repairs as long as the authorized inspector is sure that the repairs will
not require hydrostatic testing or do not require an engineering evaluation.
Q104:
Q105:
Q106:
API650:
5.6 Shell Design
5.6.1 General
5.6.1.2 Unless otherwise agreed to by the Purchaser, the shell plates shall
have a minimum nominal width of 1800 mm (72 in.). Plates that are to be buttwelded shall be properly squared.
API653:
9.2 Removal and Replacement of Shell Plate Material
9.2.2 Minimum Dimensions of Replacement Shell Plate
9.2.2.1 The minimum dimension for a replacement shell plate is 12 in. or 12
times the thickness of the replacement plate, whichever is greater. The
replacement plate may be circular, oblong, square with rounded corners, or
rectangular with rounded corners except when an entire shell plate is
replaced. See Figure 9.1 for typical details of acceptable replacement shell
plates.
API653
9.3 Shell Repairs Using Lap-welded Patch Plates
9.3.1.7 The maximum vertical and horizontal dimension of the repair plate is
48 in. and 72 in., respectively. The minimum repair plate dimension is 4 in.
The repair plate shall be formed to the shell radius.
Discussion
Type of repair plate
1. New plate
Minimum dimension: 72 width
2. Replacement plate
Minimum dimension 12 or 12t whichever greater
3. Patch welded plate
Maximum dimension 48 vertical x 72 horizontal, minimum 4.
Tsingdao Beer
Q&A Practice 2
API 653 PREPARATORY
IMPORTANT CLOSED BOOK QUESTIONS
No.
1
QUESTION
Definition of the Critical zone
CODE
CLAUSE
API653
3.7
API653
3.9
3.
API653
4.2.1.2
4.2.1.2 Roof plates corroded to an average thickness of less than 0.09 in. in any 100 in.2 area or roof plates with any holes through the roof
plate shall be repaired or replaced.
4.
5.
Limits of L
L = 3.7(Dt2), but not more than 40 in.
API653
4.3.2.1
API653
4.3.2.2
http://independent.academia.edu/CharlieChong1
7.
8.
What is the reason for the distortion of anchor bolts & excessive cracking of
API653
4.5.3
concrete structures
4.5.3 Anchor Bolts
Distortion of anchor bolts and excessive cracking of the concrete structures in which they are embedded may be
indications of either serious foundation settlement or a tank overpressure uplift condition.
http://independent.academia.edu/CharlieChong1
10.
11.
12.
Tanks fabricated from steels of unknown toughness, thickness less than can API653
5.3.7
be operated at above what minimum shell metal temperature
5.3.5 Step 4If a tank shell thickness is no greater than 0.5 in., the risk of failure due to brittle fracture is minimal,
provided that an evaluation for suitability of service in accordance with Section 4 has been performed. The original
nominal thickness for the thickest tank shell plate shall be used for this assessment.
5.3.6 Step 5No known tank failures due to brittle fracture have occurred at shell metal temperatures of 60 F or
above. Similar assurance against brittle fracture can be gained by increasing the metal temperature by heating the
tank contents.
5.3.7 Step 6Industry experience and laboratory tests have shown that a membrane stress in tank shell plates of at
least 7 ksi is required to cause failure due to brittle fracture.
Interval for routine In-service inspection
API653
6.3.1.2
6.3.1 Routine In-service Inspections
6.3.1.1 The external condition of the tank shall be monitored by close visual inspection from the ground on a routine
basis. This inspection may be done by owner/operator personnel, and can be done by other than authorized
inspectors as defined in 3.4. Personnel performing this inspection should be knowledgeable of the storage facility
operations, the tank, and the characteristics of the product stored.
6.3.1.2 The interval of such inspections shall be consistent with conditions at the particular site, but shall not exceed
one month.
Who shall carry out External Inspection
API653
6.3.2.1
6.3.2 External Inspection
6.3.2.1 All tanks shall be given a visual external inspection by an authorized inspector. This inspection shall be called
the external inspection and must be conducted at least every five years or RCA/4N years (where RCA is the difference
between the measured shell thickness and the minimum required thickness in mils, and N is the shell corrosion rate
in mils per year) whichever is less. Tanks may be in operation during this inspection.
Interval for External inspection
API653
6.3.2.1
As above
http://independent.academia.edu/CharlieChong1
15.
16.
http://independent.academia.edu/CharlieChong1
18.
API653
Table
6-1
a) 0.10 Tank bottom/foundation design with no means for detection and containment of a bottom leak.
b) 0.05 Tank bottom/foundation design with means to provide detection and containment of a bottom leak.
c) 0.05 Applied tank bottom reinforced lining, > 0.05 in. thick, in accordance with API 652.
http://independent.academia.edu/CharlieChong1
20.
21.
API653
7.4
23.
http://independent.academia.edu/CharlieChong1
Insert plate having higher thickness than the shall plate shall be tapered to
API653
9.8.2(c)
9.8.4 The following erection requirements shall be met:
a) if an integral reinforcement design is used, the insert plate at its periphery shall have a 1:4 reduction taper to match
the shell plate thickness when the insert plate exceeds the shell plate thickness by more than 1/8 in. (3mm) ;
Comments:
Taper if t >3mm
25.
Minimum thk. of new roof to be used for repair for a fixed roof shall be
API653
9.11.1.1
9.11.3 Self-supporting Roofs
9.11.3.1 The nominal thickness of new roof plate shall be 3/16 in. (4.7mm) or the required plate thickness given in
API 650, Section 5.10.5 or Section 5.10.6, plus any specified corrosion allowance, whichever is greater.
9.11.3.2 The details of the roof-to-shell junction shall meet the requirements of API 650, Section 5.10.5, Section
5.10.6, or Annex F of this standard, as applicable, for the intended service.
26.
The minimum height of tank liquid above hot tap location shall be at least
API653
9.14.1.2
9.14.1.2 The minimum height of tank liquid above the hot tap location shall be at least 3 ft during the hot tapping
operation.
27
During hot tapping operation welding will be done using which electrodes
9.14.1.3 Welding shall be done with low hydrogen electrodes.
28.
http://independent.academia.edu/CharlieChong1
API653
9.14.2.3
9.14.2.4
30.
31.
http://independent.academia.edu/CharlieChong1
What alternative methods are used to inspect the integrity of the welded
API653
12.1.7.1
bottom joint
API653: 12.1.7 Bottoms
12.1.7.1 Upon completion of welding on a tank bottom, the plates and the entire length of new welds for tank bottom
plates shall be examined visually for any potential defects and leaks. Particular attention shall apply to areas such as
sumps, dents, gouges, three-plate laps, bottom plate breakdowns, arc strikes, temporary attachment removal areas,
and welding lead arc burns. Visual examination acceptance and repair criteria are specified in API 650, Section 8.5.
In addition, all new welds, including the weld attaching a patch plate to the bottom, the areas of bottom plate restored
by welding, and the restoration of welds found with defects during an internal inspection shall be examined by one of
the methods specified in API 650, Section 7.3.3. Leaking areas shall be repaired by grinding and rewelding as
required, and the repaired area shall be retested.
API650: 7.3.3 Examination and Testing of the Tank Bottom
Upon completion of welding of the tank bottom, the bottom welds and plates shall be examined visually for any
potential defects and leaks. Particular attention shall apply to areas such as sumps, dents, gouges, three-plate laps,
bottom plate breakdowns, arc strikes, temporary attachment removal areas, and welding lead arc burns. Visual
examination acceptance and repair criteria are specified in 8.5.
In addition, all welds shall be tested by one of the following methods.
a) A vacuum-box test in accordance with 8.6.
b) A tracer gas test in accordance with 8.6.11.
c) After at least the lowest shell course has been attached to the bottom, water (to be supplied by the Purchaser)
shall be pumped underneath the bottom. A head of 150 mm (6 in.) of liquid shall be maintained using a temporary
dam to hold that depth around the edge of the bottom. The line containing water for testing may be installed
temporarily by running it through a manhole to one or more temporary flange connections in the bottom of the tank, or
the line may be installed permanently in the subgrade beneath the tank. The method of installation should be
governed by the nature of the subgrade. Reasonable care shall be taken to preserve the prepared subgrade under
the tank.
http://independent.academia.edu/CharlieChong1
Areas of bottom plate repaired by welding in addition to MT/PT are any other API653
12.1.7.3
testing done.
12.1.7.3 In addition to the requirements in 12.1.7.1, areas of bottom plate repaired by welding shall be examined by
the magnetic particle method or the liquid penetrant method. In addition, the repaired area shall also be tested using
a vacuum box and solution or a tracer gas and detector.
34.
35.
For penetration installed using insert plates , butt weld between the insert
API653
12.2.1.8
plate & shell plate shall be radiographed to what extent
12.2.1.8 For penetrations installed using insert plates as described in 9.8.6, the completed butt welds between the
insert plate and the shell plate shall be fully radiographed.
36.
Hydrostatic test of a reconstructed tank shall be held for how long time.
API653
12.3.1.1
12.3.1 When Hydrostatic Testing is Required
A full hydrostatic test, held for 24 hours, shall be performed on the following.
a) A reconstructed tank.
b) Any tank that has undergone major repairs or major alterations (see Section 3) unless exempted by 12.3.2 for the
applicable combination of materials, design, and construction features.
c) A tank where an engineering evaluation indicates the need for the hydrostatic test due to an increase in the
severity of service. Examples of increased service severity are an increase in operating pressure (such as storing a
product with a higher specific gravity), lowering the service temperature (see Figure 5.2), and using tanks that have
been damaged.
http://independent.academia.edu/CharlieChong1
API653
12.2.1.7
38.
http://independent.academia.edu/CharlieChong1
API653
Fig. B-2
http://independent.academia.edu/CharlieChong1
What is the NDT Inspector Qualification requirement for carrying out UT during API653
F 4.3
tank repair?
API650: U.4 Personnel Qualifications and Training U.4.1 Personnel QualificationsPersonnel performing and
evaluating UT examinations shall be qualified and certified in accordance with their employers written practice. ASNT
SNT-TC-IA or CP-189 shall be used as a guideline. Only Level-II or Level-III personnel shall perform UT
examinations, analyze the data, or interpret the results.
41
API653
F 4.4
Definitions:
RT=Radiographic Testing
VB =Vacuum-Box Testing
VE =Visual Examination
Acceptance Standards:
MT: ASME Section VIII, Appendix 6 (Paragraphs 6-3, 6-4, 6-5)
UT: For welds examined by UT in lieu of RT, acceptance standards are in Annex U.6.6. For UT when RT is used
for the requirements of 7.3.2.1, the acceptance standard is as agreed upon by the Manufacturer and Purchaser.
http://independent.academia.edu/CharlieChong1
RT:ASNT SNT-TC-1A Level II or III. Level-I personnel may be used under the supervision of a Level II or Level III
with a written procedure in accordance with ASME Section V, Article 2.
UT:For welds examined by UT in lieu of RT, the inspector must be ASNT-TC-1A or CP-189 Level II or Level III
per
API Std 650 Annex U.4.1. For UT when RT is used for the requirements of 7.3.2.1, the required qualifications are
ASNT-TC-1A Level II or Level III. A Level I may be used with restrictions, see API Std 650, Section 8.3.2.
RT: A procedure is not required. However, the examination method must comply with ASME Section V, Article 2.
Acceptance standards shall be in accordance with ASME Section VIII, Paragraph UW-51(b).
UT: For shell welds examined by UT in lieu of RT, ASME, Section V, Article 4 and API Std 650 Annex U.3.5. For
welds when RT is used for the requirements of 7.3.2.1, ASME Section V.
VB: API Std 650, Sections 8.6.2, 8.6.5, 8.6.6, 8.6.7, and 8.6.8
VE: None
http://independent.academia.edu/CharlieChong1
Q&A Practice 3
API 653 PREPARATORY
IMPORTANT OPEN BOOK QUESTIONS
QUESTION
CODE
CLAUSE
API653
4.3.3.1
a) When determining the minimum acceptable thickness for an entire shell course, tmin is calculated as follows:
b) When determining the minimum acceptable thickness for any other portions of a shell course (such as a locally thinned area or any other
location of interest), tmin is calculated as follows:
Where:
tmin is the minimum acceptable thickness, in inches for each course as calculated from the above equation;
however, tmin shall not be less than 0.1 in. for any tank course;
D is the nominal diameter of tank, in feet (ft);
H is the height from the bottom of the shell course under consideration to the maximum liquid level when
evaluating an entire shell course, in feet (ft); or
is the height from the bottom of the length L (see 4.3.2.1) from the lowest point of the bottom of L of the
locally thinned area to the maximum liquid level, in feet (ft); or
is the height from the lowest point within any location of interest to the maximum liquid level, in feet (ft);
G is the highest specific gravity of the contents;
http://independent.academia.edu/CharlieChong1
Y is the specified minimum yield strength of the plate; use 30,000 lbf/in.2 if not known;
T is the smaller of the specified minimum tensile strength of the plate or 80,000 lbf/in.2; use 55,000 lbf/in.2 if not known;
E is the original joint efficiency for the tank. Use Table 4.2 if original E is unknown. E = 1.0 when evaluating the retirement thickness in a
corroded plate, when away from welds or joints by at least the greater of 1 in. or twice the plate thickness.
What is the maximum allowable stress for bottom & second course
API653
4.3.3.1
3.
To change the service of the tank to above 200F what requirements are to be met
API653
4.2.4.4
http://independent.academia.edu/CharlieChong1
API653
4.3.3.1
NOTE 6 The allowable stresses for reconstructed tanks are tabulated in API 650, Table 5-2a or 5-2b or calculated per
8.4 of this standard.
5.
API653
4.3.4.1
4.3.4.1 The minimum acceptable thickness for riveted tank shells shall be calculated using the equation in 4.3.3.1
except that the following allowable stress criteria and joint efficiencies shall be used:
S is 21,000 lbf/in.2;
E is 1.0 for shell plate 6 in. or more away from rivets. See Table 4.3 for joint efficiencies for locations within 6 in. of
rivets.
6.
Table 4.5Annular Bottom Plate Thicknesses (in.) (Product Specific Gravity < 1.0)
http://independent.academia.edu/CharlieChong1
API653
Table 4-4
API653
Fig. 5.2
8.
API653
6.8.1
http://independent.academia.edu/CharlieChong1
API653
7.3.2
http://independent.academia.edu/CharlieChong1
Shell design for a reconstructed tank, with materials whose allowable stresses are not given
in Table 3-2 of API 650, what allowable stresses are to be taken
API653
8.4.2
http://independent.academia.edu/CharlieChong1
After the valve has been installed on the flange at what pressure the pressure test shall be
performed
API653
9.14.5.3
9.14.5.3 After the reinforcing plate has been welded to the shell and NDE performed, the pad shall be pneumatically
tested by the procedure described in API 650, Section 7.3.4. After the valve has been installed on the flange, a
pressure test at least 1.5 times the hydrostatic head shall be performed on the nozzle prior to mounting the hot tap
machine, which shall be bolted to the valve. The required pressure for the pressure test shall be at least the value
computed by the following equation:
where
H2 is the height of tank shell in inches (in.);
G is the specific gravity of product stored, as specified by purchaser. The specific gravity shall not be less than 1.0;
w is the density of water in pound force for cubic inch (lbf/in.3).
12.
In tank reconstruction, new vertical joints in adjacent shell courses shall be offset by what
minimum distance
API653
10.4.2.1
10.4.2 Welding
10.4.2.1 Provisions shall be made during the reconstruction of a tank to ensure that weld spacing requirements of
Figure 9.1 are maintained. New vertical joints in adjacent shell courses, made in accordance with 10.3.3.1, shall not
be aligned but shall be offset from each other a minimum distance of 5t, where t is the plate thickness of the thicker
course at the point of the offset.
13.
During tank reconstruction / repair what is the maximum allowed undercutting for vertical
joints
API653
10.4.2.5
10.4.2.5 The edges of all welds shall merge with the surface of the plate without a sharp angle. Maximum permissible
weld undercut shall be in accordance with API 650, Section 7.2.1.4 and Section 8.5.1 b).
http://independent.academia.edu/CharlieChong1
http://independent.academia.edu/CharlieChong1
API653
Table 10-1
In completed horizontal butt joints, the upper plate shall not project beyond the lower plate
by how much
API653
10.4.4.2
10.4.4 Shells
10.4.4.1 Plates to be joined by butt welding shall be matched accurately and retained in position during welding.
Misalignment in completed vertical joints over 5/8-in. thick shall not exceed 10 % of the plate thickness, with a
maximum of 1/8 in. Misalignment in joints 5/8-in. thick or less shall not exceed 1/16 in. Vertical joints shall be
completed before the lower horizontal weld is made.
10.4.4.2 In completed horizontal butt joints, the upper plate shall not project beyond the face of the lower plate at any
point by more than 20 % of the thickness of the upper plate, with a maximum projection of 1/8 in., except that a
projection of 1/16 in. is acceptable for upper plates less than 5/16-in. thick.
10.4.4.3 For horizontal and vertical joints in tank shell courses constructed of material over 1 1/2-in. thick (based on
the thickness of the thicker plate at the joint), multi-pass weld procedures are required, with no pass more than 3/4-in.
thick permitted. A minimum preheat of 200 F is required of these welds.
16.
API653
B.3.3
API653
Fig B-10
Tanks with larger edge settlements are to be repaired, or have detailed analysis of bottom, and bottom-to-shell
Junction Welds in tanks with settlement greater than or equal 75 % of Bew, and larger than 2 in., are to be examined
with magnetic particle or liquid penetrant methods
http://independent.academia.edu/CharlieChong1
API650
2.8
7.2.1.11 Low-hydrogen electrodes shall be used for all manual metal-arc welds in annular rings and shell
courses, including the attachment of the first shell course to bottom or annular plates, as follows.
a) Where the plates are thicker than 12.5 mm (1/2 in.) (based on the thickness of the thicker member being
joined) and made of material from Groups IIII.
b) For all thicknesses when the plates are made of material from Groups IV, IVA, V, and VI.
http://independent.academia.edu/CharlieChong1
Reading4
POINTS TO RECALL
Day 1
1. API 653 is code used for inspection, repair, and alteration for the
aboveground storage tanks which are placed in Service. API 650 is the
basic construction code for making New Tanks.
2. API 650 and API 653 are used for aboveground storage tanks at
atmospheric pressure (maximum 2.5 psi above atmospheric) and
temperatures not exceeding 90C. (200F)
3. Design metal temperature of tank is assumed to be 8C (15 F) above the
lowest one day mean temperature of tank site.
4. Where necessary, as per Fig. 2-1 (API 650), the tank materials shall be
checked against brittle failure by conducting impact testing. Acceptance
criteria shall be as per Table 2-4.
Where:
D
= Tank Diameter m (ft)
H
= Height shell course from top liquid level in m (ft)
G
= Specific Gravity of liquid to be stored
Sd / St = Allowable stress for design and hydrostatic conditions in Mpa (psi)
C.A. = Corrosion allowance in mm (in)
7. Shell thickness calculated above (point no. 6) shall not be less than that
required by Diameter Thickness table in API 650. (3.6.1.1)
8. Values of Sd and St are taken from Table 3-2 of API 650. For unlisted
material:
Sd = Lower of 2/3 (Y.S) or 2/5 (T.S.) and
St = Lower of (Y.S) or 3/7 (T.S.)
9. Minimum nominal thickness excluding corrosion allowance for roof plate
shall be 5 mm (3/16) and for bottom plate shall be 6 mm (1/4).
10. All nozzles, manholes and other openings shall have dimensions
thickness, reinforcement plates and weld sizes as per tables 3-6 and 3-7
of API 650.
11. Radiography inspection is required for all shell butt welds and annular
plate butt welds and insert plates for manhole and nozzles.
10. For shell plates the number of radiographs required depend on whether
the plate thickness is up to 10 mm (3/8), or above 10 mm to 25 mm (3/8
1) or above 25 mm (1). (Fig. 6-1 of API 650).
13.Radiography is also required on: 100% length of butt welds joining insert
plate to shell, and Annular bottom plate radial joints (1 spot on 10% of radial
welds if double butt welded and 1 spot on 50% of radial welds if single welded
with backing strip.)
Day 2
Critical zone means portion of tank bottom within 3 inches of shell inside
and measured radically inwards.
Repair organization means any of the following who carries out repairs /
alterations according to API 653.
Owner-user
Subcontractor to owner-user
Subcontractor authorized or approved by jurisdiction
Tank roof plates which are so corroded that there are through holes or the
average thickness is less than 0.09 inch in any 100 sq. inch area, then
plates must be repaired or replaced, i.e., tank cannot be permitted to
continue operation.
Min. thickness in critical zone is smaller of:(but not less than 0.1)
Half of original bottom thickness in critical zone, and
Half of tmin for first shell course.
Tanks designed prior to API 650 (7th edition, 1980) may be assessed for
brittle failure as per Fig. 5.2.
Tanks are not likely to fail in brittle failure if thickness is not more than
or shell temperature is not less than 60 F or stress level is less than
7,000 psi.
Day 3
New materials for repair/alteration/ reconstruction: All plate material used for
shell and the bottom plates welded to shell shall be identified.
Thickness of shell plates to be used for checking the tank design shall be
within 180 days before relocation.
The strength values Sd and St for reconstructed tank shall be on the basis of
allowable stress as per table 3-2 of API 650.
The replacement shell plate thickness thickness of the shell course where
replacement is proposed and dimensions and spacing shall be as per Figure
9-1.
All shell plate defects like the cracks, gauges, tears, widely scattered .pits and
corroded areas shall be evaluated case by case as per chapter 4 of API 653.
New reinforcements can be added to existing unreinforced nozzles as per Fig.
9-3a and 9-3b.
Repairs within critical zone of the bottom require additional precautions like
Tombstone type patch and additional PT or MPI testing after visual
examination of patch welds, and weld shall be made by minimum 2 passes.
If impact test was not done on original tank material, the hot taps shall be
limited to NPS 4 (max).
Toe-to-toe minimum spacing between hot tap and adjacent nozzle shall be =
(RT)
where R= tank shell radius in inches T is shell plate thickness in inches.
Day 4
For tank relocation, the bottom, shell or roof may be cut in any size from
existing tank so that the pieces are suitable for transportation.
For dismantling the tank the bottom may be cut 12 away from shell to bottom
weld, if entire bottom plates are to be used.
Alternatively cut the bottom and shell at 1/2 from toe of shell to bottom weld
and discard the weld portion.
For rest of the bottom, de-seaming of welds or cutting 2 away from weld may
be done.
Shell plates thk may be dismantled by cutting through weld without
removing HAZ. If shell plate thk > , discard welds + HAZ.
Alternatively, shell plates may be cut 6 away from existing welds.
Based on Fig. B-10, and B-11 maximum allowable edge settlement is worked
out depending on settled area being approximately parallel or perpendicular
to shell.
As per API RP 575, the grounding connection inspection shall be included is
external visual inspection. Total resistance from tank to soil should not
exceed approximately 25 ohms.
Ultrasonic thickness measurements as a minimum must be made on at least
one TML on each shell course. TMLs also shall be established on top
uncoated portion of shell for floating roof tanks.
For internal inspection of tank bottoms, a preliminary random thickness
scanning survey is carried out in X pattern across the tank and along the
circumference. If significant corrosion is detected, entire bottom shall be
scanned.
For internal inspection of shell, the major areas of focus shall be the vapour
space, liquid-vapour interface and the bottom area.
Day 5
API651: 11.4.7
Records sufficient to demonstrate the need for corrosion control measures
should be retained as long as the facility involved remains in service.
Records related to the effectiveness of cathodic protection should be
retained for a period of five years unless a shorter period is specifically
allowed by regulation.
Day 6
GENERAL:
ASME Sec. V is NDT procedure/methods code and is applicable only if it is
referenced by the relevant construction code. The extent of NDT and
acceptance standards is given in relevant construction code.
NDT equipment and their calibration shall be as per ASME Sec. V.
Examiner is NDT person in employment of fabricator or repair organization.
Inspector means Authorized Inspector who finally accepts/rejects NDT results.
FOR RT:
Satisfactory radiograph shall meet requirements of density and IQI image (2T
hole for hole type and designated wire for wire type).
Backscatter:
Light image of B on dark background - Unacceptable
Density Limitations:
Min 1.8 for X Ray / 2.0 for G-Ray
Max 4.0 for X / G Ray
Density Variation = -15 % to + 30%
Double wall viewing (DWDI) - Up to 3.5 outside diameter
Charlie Chong/ Fion Zhang
FOR PT:
Control of Contaminants: Sulphur (for Nickel alloys) shall not exceed 1% of
residue. Chlorine + Fluorine (for S.S. and Titanium) shall not exceed 1% of
residue.
Temp. shall be between 10oC to 52oC, for standard procedures.
Penetrants are colour (visible) type and fluorescent type. Each of these have:
water washable
post emulsifying
solvent removable
Thus, total 6 categories of penetrant are available.
Emulsifier is applied after applying penetrant and required dwell time is
completed.
Lipopholic emulsifier is applied without pre-rinsing.
Hydropholic emulsifier is applied after pre-rinsing.
For dwell time for penetrant and developer refer Table T-672.
After applying developer, interpretation shall be done within 10 to 60 minutes.
All penetrant materials should be from same manufacturer.
FOR MT:
Prod Technique:
Use direct (rectified) current for magnetization
Prod spacing 3 to 8
Useful for surface and sub-surface defects.
Yoke Technique:
Use D.C. or A.C. or permanent magnet
Suitable for surface defects only.
Calibration:
Equipment Ammeter to be calibrated once a year comparing with standard
Ammeter, take 3 readings. Deviation shall not exceed 10% of full scale.
Lifting Power of Yokes
AC shall have lifting power of at least 4.5 kg (10 lbs.)
DC shall have lifting power of at least 18.1 kg (40 lbs.)
Minimum two examinations on each area, the second is perpendicular to first
SE-797 UT MEASUREMENT:
Pulse-echo method can be adopted up to 200F
Apparatus: 3 types
CRT read out
CRT + direct read out
Direct thickness read out
Search Units: 3 types
- Straight beam contact type
Delay line type (delay block to minimize dead zone)
Dual element type. There are two crystals set at
a small range. Low roof angle used for higher
range and higher angle for low range.
Good Luck!