S10
Hoja resumen
Obra
0801055
Localizacin
030101
Fecha Al
10/10/2015
Presupuesto base
001
4,596.19
002
003
GUARDIANIA Y SS.HH
61,162.00
004
23,961.53
005
FLETE TERRESTRE
185,042.84
1,000.00
(CD)
S/.
COSTO DIRECTO
275,762.56
275,762.56
18,751.85
================
294,514.41
SUPERVICION 3%
8,835.43
EXPEDIENTE TECNICO 2%
5,890.29
IMPACTO AMBIENTAL
1,500.00
=================
TOTAL PRESUPUESTO
310,740.13
S/.
38,928.83
MATERIALES
S/.
226,647.69
EQUIPOS
S/.
10,186.18
SUBCONTRATOS
S/.
10/10/2015
S/.
275,762.70