Pre Supuesto Client e Resume N
Pre Supuesto Client e Resume N
Pgina
Presupuesto
Presupuesto
Cliente
Lugar
0302026
"MEJORAMIENTO DE LAS CALLES Y PASAJES DEL ASENTAMIENTO HUMANO TECHO PROPIO, DISTRITO DE YANACANCHA PASCO - PASCO"
Costo al
MUNICIPALIDAD DISTRITAL DE YANACANCHA
23/05/2012
PASCO - PASCO - YANACANCHA
Item
Descripcin
01
01.01
Und.
Precio S/.
Parcial S/.
38,150.43
TRABAJOS PRELIMINARES
23,540.70
01.01.01
01.01.02
TRAZO Y REPLANTEO
m2
01.01.03
01.01.04
01.02
Metrado
1.00
939.24
939.24
17,088.50
0.71
12,132.84
glb
1.00
4,000.00
4,000.00
m2
363.61
17.79
6,468.62
2,765.67
01.02.01
1.00
336.30
336.30
01.02.02
1.00
336.30
336.30
01.02.03
47.00
38.88
1,827.36
1.00
265.71
265.71
01.02.04
01.03
11,844.06
01.03.01
8.00
01.03.02
01.03.03
02
02.01
54.62
436.96
1,550.00
6.84
10,602.00
10.00
80.51
805.10
PAVIMENTO DE CONCRETO
956,503.96
MOVIMIENTO DE TIERRAS
300,243.70
02.01.01
m3
5,112.18
18.84
96,313.47
02.01.02
m2
7,888.93
4.96
39,129.09
02.01.03
m3
1,321.50
6.00
7,929.00
02.01.04
m3
5,324.34
7.49
39,879.31
m2
7,888.93
14.83
02.01.05
02.02
02.02.01
116,992.83
556,081.21
m2
1,424.37
16.79
23,915.17
02.02.02
m3
1,577.79
300.35
473,889.23
02.02.03
kg
7,399.57
5.94
43,953.45
02.02.04
3,002.80
4.77
14,323.36
7,121.83
4.31
30,695.09
7,121.83
8.97
63,882.82
m2
7,888.93
0.71
02.03
02.03.01
02.03.02
02.04
02.04.01
03
03.01
03.01.01
03.01.02
03.02
JUNTAS
94,577.91
OTROS
CURADO DE LOSA DURANTE 8 DIAS INC. ARROZERA
5,601.14
CUNETAS DE CONCRETO
5,601.14
103,937.32
MOVIMIENTO DE TIERRAS
18,109.95
m3
391.55
24.94
m2
873.79
9.55
CONCRETO SIMPLE
9,765.26
8,344.69
82,336.43
03.02.01
m2
792.15
15.74
12,468.44
03.02.02
m3
234.71
255.98
60,081.07
03.02.03
m2
1,155.48
8.47
9,786.92
389.18
8.97
03.03
03.03.01
04
04.01
04.01.01
JUNTAS
JUNTAS ASFALTICAS EN CUNETAS DE 1"
3,490.94
m
VEREDAS
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO SEMIROCOSO P/VEREDAS
3,490.94
370,825.03
127,795.92
m3
1,309.32
24.94
32,654.44
04.01.02
04.01.03
04.02
04.02.01
04.02.02
04.03
04.03.01
05
05.01
m3
1,702.12
7.49
m2
7,929.99
10.39
CONCRETO SIMPLE
12,748.88
82,392.60
228,366.57
m2
792.91
15.12
11,988.80
m2
5,987.21
36.14
216,377.77
1,634.62
8.97
VARIOS
JUNTAS ASFALTICAS EN VEREDAS DE 1"
14,662.54
GRADERIAS
MOVIMIENTO DE TIERRAS
14,662.54
174,595.97
43,935.42
05.01.01
m3
1,032.59
29.09
30,038.04
05.01.02
m3
1,302.72
10.44
13,600.40
05.01.03
m3
39.65
7.49
296.98
05.02
CONCRETO SIMPLE
05.03
130,660.55
05.03.01
m3
490.08
241.99
05.03.02
m2
946.36
12.75
06
06.01
SARDINELES
118,594.46
12,066.09
428,777.71
MOVIMIENTO DE TIERRAS
24,126.00
06.01.01
m3
621.37
29.09
18,075.65
06.01.02
m3
807.79
7.49
6,050.35
06.02
CONCRETO ARMADO
357,268.78
06.02.01
m3
890.95
254.31
226,577.49
06.02.02
m2
3,413.32
17.23
58,811.50
kg
12,245.28
5.87
71,879.79
06.02.03
06.03
06.03.01
06.04
06.04.01
06.05
06.05.01
07
07.01
29,544.98
m2
2,057.45
14.36
m2
2,057.45
6.21
544.80
9.29
PINTURA
PINTURA ESMALTE EN SARDINELES
12,776.76
VARIOS
JUNTAS ASFALTICAS EN SARDINELES DE 1"
29,544.98
12,776.76
5,061.19
JARDINERIA
5,061.19
92,927.51
MOVIMIENTO DE TIERRAS
6,634.36
07.01.01
m3
170.87
29.09
4,970.61
07.01.02
m3
222.13
7.49
1,663.75
m3
132.73
254.31
07.02.02
m2
664.14
17.23
11,443.13
07.02.03
kg
2,931.54
5.87
17,208.14
07.02
07.02.01
07.03
07.03.01
07.04
07.04.01
07.05
CONCRETO ARMADO
62,405.84
3,815.60
m2
265.71
14.36
m2
265.71
6.21
PINTURA
PINTURA ESMALTE EN SARDINELES
33,754.57
3,815.60
1,650.06
OTROS
1,650.06
18,421.65
07.05.01
m3
387.24
23.88
9,247.29
07.05.02
m2
709.00
4.80
3,403.20
07.05.03
m2
709.03
3.46
2,453.24
07.05.04
178.00
18.64
3,317.92
839.30
2.38
1,997.53
16,771.05
08
SEALIZACION
22,122.79
08.01
MARCAS EN EL PAVIMENTO
m2
08.02
SEALES INFORMATIVAS
45.00
372.69
SEALES PREVENTIVAS
9.00
372.69
08.03
09
09.01
MURO DE CONTENCION
3,354.21
58,979.14
MOVIMIENTO DE TIERRAS
5,690.80
09.01.01
m3
263.67
8.00
2,109.36
09.01.02
m3
336.32
10.44
3,511.18
09.01.03
m3
9.38
7.49
70.26
09.02
09.02.01
09.03
09.03.01
9,103.69
m2
270.38
33.67
CONCRETO ARMADO
9,103.69
44,184.65
ZAPATAS
44,184.65
09.03.01.01
m3
86.52
278.09
09.03.01.02
kg
3,387.93
5.94
20,124.30
10
10.01
m3
94.58
291.40
116,810.59
27,560.61
10.02
m2
709.38
23.91
16,961.28
10.03
kg
5,908.35
5.94
35,095.60
10.04
393.38
12.06
398.00
72.72
398.00
8.81
10.04.01
10.05
10.05.01
10.06
10.06.01
11
24,060.35
4,744.16
CARPINTERIA METALICA
BARANDA METALICA CON TUBOS REDONDOS DE 2"
28,942.56
PINTURA
PINTURA EN BARANDAS METALICAS
4,744.16
28,942.56
3,506.38
OTROS
3,506.38
87,638.86
11.01
INSTALACIONES ELECTRICAS
11.02
pto
69.00
76.40
5,271.60
11.03
m3
63.00
21.82
1,374.66
11.04
236.25
8.70
2,055.38
11.05
m3
63.00
10.44
657.72
11.06
500.00
19.53
9,765.00
11.07
FAROLES
11.08
m3
14.90
19.02
283.40
11.09
m3
14.90
10.44
155.56
11.11
m3
14.90
0.23
3.43
11.12
m3
14.90
355.96
5,303.80
11.13
m2
82.80
29.48
2,440.94
11.14
69.00
263.50
18,181.50
11.15
TACHO DE BASURA
11.16
TACHO DE BASURA
40.00
170.00
6,800.00
11.17
BANCAS
11.18
20.00
290.00
5,800.00
11.19
IMPACTO AMBIENTAL
19,309.27
11.19.01
glb
1.00
5,042.01
5,042.01
11.19.02
glb
1.00
4,296.39
4,296.39
11.19.03
glb
1.00
567.83
567.83
11.19.04
glb
1.00
1,344.54
1,344.54
11.19.05
glb
1.00
567.00
567.00
11.19.06
glb
1.00
500.00
500.00
11.19.07
glb
1.00
1,701.00
1,701.00
11.19.08
glb
1.00
4,728.00
4,728.00
11.19.09
PROGRAMA DE FORESTACION
glb
1.00
562.50
562.50
11.20
VARIOS
10,236.60
11.20.01
glb
48.00
48.00
2,304.00
11.20.02
glb
46.00
32.00
1,472.00
glb
1.00
6,460.60
11.20.03
COSTO DIRECTO
GASTOS GENERALES (10%)
UTILIDADES (8%)
6,460.60
2,451,269.31
245,126.93
196,101.54
-----------------------------------SUB TOTAL
IMPUESTO (IGV) 18%
2,892,497.78
520,649.60
-------------------------------------
TOTAL PRESUPUESTO
3,413,147.38