Abstract
Demand of Energy electrics in provinsi Riau and Kepri is supplied by PT. PLN with the Diesel
Power Plant. It is Used all energy attached cause extinction planning for the treatment of
generating machine. By topography of region which is in the form of island, proposed by
alternative of generating mobile of taken as source of power plant emergency utilize to avoid the
extinction. Some generator set with the energy capacities matching with requirement therewith its
supply system is placed at a correct lighter of the size. By using correct service scheduling plan
very conducive to serve the target of some island requiring, So that extinction for the treatment of
avoidable. Pursuant to analysis is done by a investment expense needed compared to smaller than
levying of generator machine set the emergency at every existing island.
Keyword: Power plant emergency
1. PENDAHULUAN
Tujuan
2.
TINJAUAN PUSTAKA
338
1)
2)
3)
4)
5)
6)
7)
Pra Perancangan
Dalam merencanakan ataupun membangun
sebuah kapal/tongkang adalah merupakan
suatu pekerjaan yang sangat komplek, karena
dalam hal in banyak hal yang mesti banyak
diperhatikan, yaitu diantaranya :
1. Segi teknis
Aspek teknis yang dimaksud adalah segala
sesuatu yang berkaitan dengan jaminan
keselamatan selama pelayaran atau
pengoperasian, maka harus mengikuti
peraturan peraturan klasifikasi yang ada
sehingga
PLTD
terapung
yang
direncanakan memenuhi kondisi yang
disyaratkan.
2. Segi ekonomis
Perencanaan pengadaan PLTD terapung ini
merupakan
bentuk
dari
pelayanan
pemenuhan fasilitas yang menunjang
pemerataan pembangunan dan pertumbuhan
perekonomian masyarakat. Selain itu juga
ditinjau dari kemungkinan profit yang
didapatkan dari PLTD terapung yang
direncanakan.
Klasifikasi Tongkang
Berdasarkan cara membawa muatan
Berdasarkan cara membawa muatannya,
tongkang dapat dibedakan menjadi dua
macam, yakni tongkang dengan muatan
didalam palka dan tongkang dengan muatan
METODOLOGI
Metodologi
yang
menyelesaikan masalah
menggunakan metode
metodologi penelitian
baberapa tahap, yaitu:
digunakan
untuk
ini adalah dengan
teoritis.
Dalam
ini dibagi dalam
1) Studi literatur
339
b. Lebar (B)
c. Tinggi (H)
d. Sarat (T)
Parameterparameter diatas merupakan
komponen untuk menentukan berapa
displacement dari tongkang.
5) Merencanakan penempatan mesin
genset beserta sistem penunjang
permesinannya (general arrangement).
Pada tahap ini direncanakan peletakan
genset di atas tongkang, pembagian
ruang
akomodasi,
tangkitangki,
system ballast, system tambat dan
system lainnya.
6) Menganalisa stabilitas dari tongkang
yang didesain dengan menggunakan
sofwer Maxsurf dan Hydromax.
Berdasarkan general arrangement
yang sudah dibuat dilakukan analisa
kestabilan kapal dengan mengunakan
sofwer hydromax versi 11.12 dan
sebelumnya digambarkan terlebih
dahulu pada sofwer maxsurf versi
11.12. Hal ini dimaksudkan agar dapat
memudahkan
dalam
peninjauan
kembali terhadap perencanaan general
arrangement jika dalam analisa
tersebut stabilitasnya tidak baik.
7) Merencanakan
sistem
tambat
(Mooring) yang sesuai untuk tongkang
yang
direncanakan.
Dengan
menggunakan standart BKI dilakukan
perhitungan kebutuhan jangkar yang
sesuai dengan tongkang yang sudah
direncanakan.
8) Merencanakan kabel penghubung dari
pembangkit ke instalasi listrik didarat.
9) Menghitung estimasi investasi yang
diperlukan
untuk
pengadaan
pembangkit listrik terapung yang sudah
direncanakan.
340
4.
PEMBAHASAN
Berdasarkan
pengumpulan
data
yang
dilakukan didapat data kapasitas pembangkit
untuk tiap pulau sebagai berikut :
Table 2.
Perencanaan konfigurasi mesin genset
Kapasitas
Merk
3 x 1000 Kw
Caterpil
lar
Table 1.
Kapasitas pelayanan PLTD terapung
Spesifikasi /
Type
1500 Rpm,
50
Hz,
11000 V
Berat
3 x 14424
kg
Engine
Merk
Type
: Caterpillar
: 3512 TA, 4-stroke-cycle
watercooled diesel
Bore
: 170 mm (6,69 inchi )
Stroke
: 190 mm (7,48 inchi )
Displacement : 51,80 L
Comp. Ratio : 13,5 : 1
Fuel System : Direct unit injection
Governor type : Woodward
Generator
Merk
Type
Output
Frame size
Exitation
Pole
Cos
: Caterpillar
: SR4B HV Generator
: 1000 eKw, 50 Hz, 3 phase,
11000 volt, 1500 rpm
: 2730
: Permanent magnet
:4
: 0,85
Dimensi genset
- Panjang
- Lebar
- Tinggi
: 5544,8 mm
: 2073,1 mm
: 2367,2 mm
341
Kondisi
I
II
III
IV
100%
100%
0%
25%
100%
50%
100%
25%
0%
75%
50%
50%
Rencana Umum
Berikut ini gambar rencana umum dari PLTD
terapung
yang
direncanakan
dengan
mempertimbangkan keperluan ruangan yang
minimal .
Kondisi II
Gambar 3.
Rencana Umum PLTD terapung
Gambar 10.
Grafik stabilitas kondisi II
342
Kondisi III
Gambar 11.
Grafik stabilitas kondisi III
Kondisi IV
Gambar 12.
Grafik stabilitas kondisi IV
Gambar 15.
Instalasi kelistrikan koneksi ke darat
343
Tabel 5.
Jadwal pelayanan PLTD terapung periode Juli
Desember.
Tabel 4.
Jadwal pelayanan PLTD terapung periode Januari
Juni.
DAERAH/ PULAU
RUPAT
BENGKALIS
SUNGAI PAKNING
KAPASITAS MESIN
Januari
Februari
1
2 3 4 1 2 3
kW
kW 72A
kW
kW
72A
72B
x 500 kW
72C
x 250 kW
72B
x 100 kW
72A
x 400 kW
72A
x 100 kW
120A
x 1000 kW
120B
120C
120C
x 800 kW
120B
120A
120A
x 500 kW
2
7
x 250 kW
X 1000 kW
1
1
1
2
3
3
2
3
1
3
4
SELAT PANJANG
x
x
x
x
3 x 1000 kW
1 x 1000 kW
x 2000 kW
1 x 2000 kW
1 x 2000 kW
2 x 500 kW
5
x 500
kW
1 x 2000 kW
2 x 500 kW
1 x 2000 kW
1 x 500 kW
MORO
4
5
x 250 kW
x 1480 kW
4 x 250 kW
2 x 1480 kW
2 x 1480 kW
1 x 1480 kW
4
x 1000 kW
1 x 1000 kW
3 x 1000 kW
x 3000 kW
2 x 3000 kW
TANJJUNGPINANG
2 x 3000 kW
1 x 3000 kW
4
x 500
x 2000 kW
kW
4 x 500 kW
1 x 2000 kW
1 x 2000 kW
1 x 2000 kW
1 x 2000 kW
LINGGA
2
1
Mei
2 3
Juni
2 3
120B
3 x 1000 kW
500
100
55
1000
x 1000 kW
x 670 kW
2 x 1000 kW
1 x 670 kW
120C
120A
120B
120C
120A
120B
72C
72A
72B
120C
120A
120B
120C
120A
120B
72C
72A
72B
168C
x 1480 kW
2 x 1480 kW
72A
72B
72C
2 x 1480 kW
72A
72B
72C
1 x 1480 kW
72A
72B
72C
x 1000 kW
x 3000 kW
1 x 1000 kW
3 x 1000 kW
120A
120B
120C
72A
72B
72C
72A
72B
72C
2 x 3000 kW
TANJJUNGPINANG
72A
72B
72C
72A
72B
72C
2 x 3000 kW
1 x 3000 kW
48A
48B
48C
48A
48B
x 500
x 2000 kW
kW
48A
48B
48A
48C
48A
48B
4 x 500 kW
1 x 2000 kW
1 x 2000 kW
1 x 2000 kW
48A
48C
192A
192B
192C
1 x 2000 kW
LINGGA
2
1
x 1000 kW
x 670 kW
2 x 1000 kW
1 x 670 kW
November
2 3 4
Desember
2 3 4
72A
72B
72C
72A
72B
72C
72A
72B
72C
120A
120B
120C
72A
72B
72C
72A
72B
72C
72A
72B
72C
72A
72B
72C
48A
48B
48C
48A
48B
48A
48B
48A
48C
48A
48B
48A
48C
192A
192B
192C
344
Tabel 6.
Jadwal pelayanan untuk tiap bulan periode 1 tahun
sebagai brikut :
Bulan Januari
Kegiatan
Pulau/Daerah
1
Minggu ke-1
3 4 5 6
Rupat
( 48,6 mil, 5 knots = 9,62 jam )
Bengkalis
( 16,2 mil, 5 knots = 3,21 jam )
Januari
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
P
P
E
E
N
N
G
G
I
I
S
S
I
I
A
A
N
N
29 30
P
E
N
G
I
S
I
A
N
S. Pakning
B
B
M
B
B
M
B
B
M
Tabel 7.
Estimasi biaya investasi dan opersional periode 1 tahun
Bulan Februari
Kegiatan
Pulau/Daerah
1
Minggu ke-1
3 4 5 6
Selat Panjang
( 76,9 mil, 5 knots = 15,22 jam )
Tjg. Balai Karimun
P.
B
B
M
Februari
Minggunke-2
Minggu ke-3
Minggu ke-4
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
P.
P.
P.
B
B
B
B
B
B
M
M
M
No
Bulan Maret
Kegiatan
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke Moro
Pulau/Daerah
Minggu ke-1
1 2 3 4 5 6
B
Tjg. Balai Karimun
B
M
( 32,4 mil, 5 knots = 6,41 jam )
Maret
Minggunke-2
Minggu ke-3
Minggu ke-4
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
B
B
B
B
M
M
Bulan April
Kegiatan
Pulau/Daerah
1
Minggu ke-1
3
4 5
P.
Moro
( 68,4 mil, 5 knots = 12,82 jam )
Tjg. Pinang
B
B
M
April
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
P.
P.
B
B
B
B
M
M
Bulan Mei
Kegiatan
Suply listrik ke darat
Minggu ke-1
3 4 5 6
Mei
Minggunke-2
Minggu ke-3
Minggu ke-4
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Minggu ke-1
3
4 5
Pulau/Daerah
Biaya
( Rupiah )
Uraian
Tanjung Pinang
26,555,562,884.00
397,200,000.00
531,111,257.00
265,555,628.00
87,674,572.80
1,512,000.00
1,590,458,188.80
35,571,840.00
3,456,000,000.00
32,920,646,370.60
Bulan Juni
Kegiatan
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke Lingga
Persiapan koneksi instalasi di Lingga
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke Rupat
Maintenance Genset & Tongkang
Persiapan koneksi instalasi di Rupat
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke Bengkalis
Persiapan koneksi instalasi di Bengkalis
Suply listrik ke darat
Pulau/Daerah
Tanjung Pinang
6
P.
B
B
M
Juni
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
P.
B
B
M
P.
B
B
M
Kegiatan
pembelian
genset
pembangkit
Pulau / Wilayah
Bulan Juli
Pulau/Daerah
1
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke Sungai Pakning
Persiapan koneksi instalasi di S. Pakning
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke Selat Panjang
Persiapan koneksi instalasi di S. Panjang
Suply listrik ke darat
Tabel 8.
Estimasi Investasi
emergency didarat.
Minggu ke-1
3
4
5
S
Juli
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
S
S
S
I
I
I
A
A
A
N
N
N
S. Pakning
B
B
M
B
B
M
B
B
M
Rupat
Bengkalis
Selat Panjang
Sungai Pakning
Tjg. Balai Karimun
Moro
Tjg. Pinang
Lingga
Kapasitas
Mesin Emergency
500 Kw
1000 Kw
1000 Kw
400 Kw
2000 Kw
250 Kw
3000 Kw
1000 Kw
Jumlah
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Harga Satuan
Per KW
5,600,000.00
5,600,000.00
5,600,000.00
5,600,000.00
5,600,000.00
5,600,000.00
5,600,000.00
5,600,000.00
Jumlah
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
2,800,000,000.00
5,600,000,000.00
5,600,000,000.00
2,240,000,000.00
11,200,000,000.00
1,400,000,000.00
16,800,000,000.00
5,600,000,000.00
51,240,000,000.00
Bulan Agustus
Kegiatan
Pulau/Daerah
1
Minggu ke-1
3
4 5
Selat Panjang
( 76,9 mil, 5 knots = 15,22 jam )
Tjg. Balai Karimun
P.
B
B
M
Agustus
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
P.
P.
B
B
B
B
M
M
Bulan September
Kegiatan
Pulau/Daerah
1
Minggu ke-1
3
4
5
September
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
B
B
M
Bulan Oktober
Kegiatan
Pulau/Daerah
1
2
P.
Minggu ke-1
3
4 5
Moro
B
( 68,4 mil, 5 knots = 12,82 jam )
M
Tjg. Pinang
M
Oktober
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
P.
B
B
M
P.
B
B
M
P.
B
B
M
Bulan Nopember
Kegiatan
Pulau/Daerah
1
Minggu ke-1
3
4
5
Nopember
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Kegiatan
Desember
Minggunke-2
Minggu ke-3
Minggu ke-4
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Kapasitas
Dimensi Genset
Mesin Emergency
( PxLxT) m
500 Kw
4 x 1.5 x 2.2
1000 Kw
5.55 x 2.1 x 2.4
1000 Kw
5.55 x 2.1 x 2.4
400 Kw
3.8 x 1.1 x 2.2
2000 Kw
6.3 x 2.3 x 2.4
250 Kw
3.8 x 1.1 x 2.1
3000 Kw
7 x 2.5 x 2.7
1000 Kw
5.55 x 2.1 x 2.4
Jumlah
Jumlah Total
* Pembebasan lahan Rp 70.000,- / M^2
** Harga proyek pengadaan gedung Rp 4.000.000,- / M^2
Pulau / Wilayah
Rupat
Bengkalis
Selat Panjang
Sungai Pakning
Tjg. Balai Karimun
Moro
Tjg. Pinang
Lingga
Pembebasan Lahan
Pengadaan Gedung
( Rp )
( Rp )
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
16,100,000.00
390,000,000.00
128,800,000.00
3,120,000,000.00
3,248,800,000.00
Tanjung Pinang
Bulan Desember
Pindah ke Lingga
Persiapan koneksi instalasi di Lingga
Suply listrik ke darat
Pelepasan koneksi instalasi
Pindah ke PT. Patra Dok Dumai
Maintenance Genset & Tongkang
Pindah ke Rupat
Persiapan koneksi instalasi di Rupat
Tabel 9.
Estimasi Pengadaan gedung untuk menempatkan genset
didarat
Pulau/Daerah
Minggu ke-1
1 2
3
4 5
( 76,9 mil, 5 knots = 15,22 jam )
5.
KESIMPULAN
Lingga
( 235 mil, 5 knots = 46,47 jam )
Dumai
( 12,1 mil, 5 knots = 2,4 jam )
Rupat
Estimasi Investasi
Perkiraan dana yang diperlukan untuk
merealisasikan PLTD terapung ini dilakukan
dengan mengkelompokan dalam dua bagian
345
DAFTAR PUSTAKA