Planilla Movimiento de Tierras CONDUCTO RAPACAN - CAMARA DE CARGA KM. 0+000 - KM.. 0+547.05
Planilla Movimiento de Tierras CONDUCTO RAPACAN - CAMARA DE CARGA KM. 0+000 - KM.. 0+547.05
UBICACIN
ELABORACION
FECHA
FINAL
00 + 000.00
00 + 547.05
VOLUMEN TOTAL
VOLUMEN
(m3)
RELLENO
CORTE
315.81
23,329.58
315.81
23,329.58
PROYECTO
UBICACIN
ELABORACION
FECHA
METRADOS DE EXPLANACIONES
CONDUCTO RAPACAN -CAMARA DE CARGA KM. 0+000 - KM.. 0+547.05
PROGRESIVA
DIST.
(m)
AREA (m2)
RELLENO
CORTE
CLASIFICACION
VOL. CORTE (m3)
MAT.
ROCA
ROCA
SUELTO
SUELTA
FIJA
VOLUMEN (m3)
RELLENO
CORTE
00 + 000.00
183.45
00 + 010.00
10.00
130.70
1,570.75
00 + 020.00
10.00
60.97
958.35
00 + 023.40
3.40
0.57
51.10
0.48
190.24
00 + 030.00
6.61
35.90
0.94
287.32
00 + 035.68
5.68
3.62
21.12
5.14
161.94
00 + 040.00
4.32
6.98
17.52
22.90
83.46
00 + 050.00
10.00
3.48
17.51
52.30
175.15
00 + 060.00
10.00
1.17
20.77
23.25
191.40
00 + 070.00
10.00
25.80
2.93
232.85
00 + 080.00
10.00
21.91
238.55
00 + 090.00
10.00
12.23
170.70
00 + 100.00
10.00
9.21
12.37
23.03
123.00
00 + 110.00
10.00
12.52
23.03
124.45
00 + 120.00
10.00
3.91
82.15
00 + 130.00
10.00
1.66
0.95
4.15
24.30
00 + 140.00
10.00
4.44
6.20
30.50
35.75
00 + 150.00
10.00
2.40
14.58
34.20
103.90
00 + 160.00
10.00
7.54
6.00
110.60
00 + 170.00
10.00
1.31
10.90
3.28
92.20
00 + 180.00
10.00
2.90
4.45
21.05
76.75
00 + 190.00
10.00
0.38
16.21
16.40
103.30
00 + 200.00
10.00
11.79
0.95
140.00
00 + 203.87
3.87
6.69
35.76
00 + 210.00
6.13
1.34
5.65
2.05
37.82
00 + 220.00
10.00
1.55
1.50
14.45
35.75
00 + 230.00
10.00
0.21
4.97
8.80
32.35
00 + 240.00
10.00
1.77
4.12
9.90
45.45
00 + 244.25
4.25
1.68
7.67
7.33
25.05
00 + 250.00
5.75
20.55
2.42
81.13
00 + 260.00
10.00
7.86
142.05
00 + 270.00
10.00
6.45
71.55
00 + 280.00
10.00
10.63
85.40
00 + 290.00
10.00
10.92
107.75
00 + 300.00
10.00
9.45
101.85
00 + 310.00
10.00
7.86
86.55
00 + 320.00
10.00
15.07
114.65
00 + 330.00
10.00
19.44
172.55
00 + 340.00
10.00
20.29
198.65
00 + 350.00
10.00
27.51
239.00
00 + 360.00
10.00
27.21
273.60
00 + 370.00
10.00
29.75
284.80
00 + 380.00
10.00
34.91
323.30
00 + 390.00
10.00
33.04
339.75
00 + 400.00
10.00
31.29
321.65
00 + 403.87
3.87
30.83
120.20
00 + 410.00
6.13
29.38
184.54
00 + 420.00
10.00
28.14
287.60
00 + 430.00
10.00
31.34
297.40
00 + 440.00
10.00
26.69
290.15
00 + 450.00
10.00
26.12
264.05
00 + 460.00
10.00
29.35
277.35
PROYECTO
UBICACIN
ELABORACION
FECHA
METRADOS DE EXPLANACIONES
CONDUCTO RAPACAN -CAMARA DE CARGA KM. 0+000 - KM.. 0+547.05
PROGRESIVA
DIST.
(m)
AREA (m2)
RELLENO
CORTE
VOLUMEN (m3)
RELLENO
CORTE
CLASIFICACION
VOL. CORTE (m3)
MAT.
ROCA
ROCA
SUELTO
SUELTA
FIJA
-
00 + 470.00
10.00
57.79
435.70
00 + 480.00
10.00
70.31
640.50
00 + 482.31
2.31
199.01
310.80
00 + 485.00
2.69
205.20
544.07
00 + 490.00
5.00
171.01
940.53
00 + 495.00
5.00
95.77
666.95
00 + 500.00
5.00
139.87
589.10
00 + 505.00
5.00
179.63
798.75
00 + 510.00
5.00
167.34
867.43
00 + 515.00
5.00
339.20
1,266.35
00 + 520.00
5.00
289.44
1,571.60
00 + 525.00
5.00
282.56
1,430.00
00 + 530.00
5.00
230.91
1,283.68
00 + 535.00
5.00
150.73
954.10
00 + 540.00
5.00
92.56
608.23
00 + 545.00
5.00
11.82
260.95
00 + 547.05
2.05
0.69
0.35
6.05
315.81
23,329.58