Planilla Movimiento de Tierras Acceso Laclan As BUILD
Planilla Movimiento de Tierras Acceso Laclan As BUILD
UBICACIN
ELABORACION
FECHA
: 28 SETIEMBRE 2013
PROGRESIVA
INICIO
FINAL
00 + 000.00
00 + 541.24
VOLUMEN TOTAL
VOLUMEN
(m3)
RELLENO
CORTE
ROCA
1,526.54
14,058.18
1,475.74
1,526.54
14,058.18
1,475.74
PROYECTO
UBICACIN
ELABORACION
FECHA
: 28 SETIEMBRE 2013
PROGRESIVA
INICIO
FINAL
00 + 000.00
00 + 541.24
VOLUMEN TOTAL
VOLUMEN
(m3)
RELLENO
CORTE
ROCA
1,526.54
14,058.18
1,475.74
1,526.54
14,058.18
1,475.74
PROYECTO
: CENTRAL HIDROELECTRICA RIO CHANCAY
UBICACIN
: KM. 73 CARRETERA HUARAL - CERRO DE PASCO
ELABORACION : TOPOGRAFIA & METRADO
FECHA
: 28 SETIEMBRE 2013
METRADOS DE EXPLANACIONES
ACCESO LACLAN KM. 0+000 - 0+541.24 SEGN CONSTRUIDO
PROGRESIVA
DIST.
(m)
AREA (m2)
RELLENO
CORTE
ROCA
CLASIFICACION
VOL. CORTE (m3)
MAT.
ROCA
ROCA
SUELTO SUELTA
FIJA
VOLUMEN (m3)
RELLENO
CORTE
ROCA
00 + 000.00
12.09
00 + 010.00
10.00
12.13
121.10
00 + 020.00
10.00
18.91
155.20
00 + 030.00
10.00
19.96
194.35
00 + 040.00
10.00
18.43
191.95
00 + 050.00
10.00
27.66
230.45
00 + 060.00
10.00
38.39
330.25
00 + 070.00
10.00
44.00
411.95
00 + 080.00
10.00
33.41
387.05
00 + 090.00
10.00
24.84
291.25
00 + 100.00
10.00
22.52
236.80
00 + 110.00
10.00
34.54
285.30
00 + 120.00
10.00
57.95
462.45
00 + 130.00
10.00
140.89
994.20
00 + 140.00
10.00
83.97
1,124.30
00 + 150.00
10.00
34.96
594.65
00 + 160.00
10.00
12.36
236.60
00 + 170.00
10.00
14.29
133.25
00 + 180.00
10.00
0.49
13.33
1.23
138.10
00 + 190.00
10.00
13.04
9.51
67.65
114.20
00 + 200.00
10.00
15.35
9.93
141.95
97.20
00 + 210.00
10.00
0.99
12.51
81.70
112.20
00 + 220.00
10.00
11.11
2.48
118.10
00 + 230.00
10.00
16.39
137.50
00 + 240.00
10.00
17.56
169.75
00 + 250.00
10.00
4.05
9.87
7.39
10.13
137.15
18.47
00 + 260.00
10.00
8.85
7.96
14.72
64.50
89.15
110.53
00 + 270.00
10.00
37.77
10.56
27.67
233.10
92.60
211.94
00 + 280.00
10.00
32.15
7.07
23.19
349.60
88.15
254.30
00 + 290.00
10.00
3.72
2.78
3.88
179.35
49.25
135.35
00 + 300.00
10.00
34.19
9.30
184.85
9.70
00 + 310.00
10.00
33.21
337.00
00 + 320.00
10.00
34.48
338.45
00 + 330.00
10.00
30.36
324.20
00 + 340.00
10.00
19.05
247.05
00 + 350.00
10.00
15.04
170.45
00 + 360.00
10.00
13.68
143.60
00 + 370.00
10.00
12.45
130.65
00 + 380.00
10.00
11.51
119.80
00 + 390.00
10.00
45.33
284.20
00 + 400.00
10.00
68.57
569.50
00 + 410.00
10.00
42.33
554.50
00 + 420.00
10.00
34.41
383.70
00 + 430.00
10.00
27.79
311.00
00 + 440.00
10.00
16.43
221.10
00 + 450.00
10.00
9.66
6.27
24.15
113.50
PROYECTO
: CENTRAL HIDROELECTRICA RIO CHANCAY
UBICACIN
: KM. 73 CARRETERA HUARAL - CERRO DE PASCO
ELABORACION : TOPOGRAFIA & METRADO
FECHA
: 28 SETIEMBRE 2013
METRADOS DE EXPLANACIONES
ACCESO LACLAN KM. 0+000 - 0+541.24 SEGN CONSTRUIDO
00 + 460.00
10.00
23.05
24.15
146.60
CLASIFICACION
VOL. CORTE (m3)
MAT.
ROCA
ROCA
SUELTO SUELTA
FIJA
-
00 + 470.00
10.00
20.62
218.35
00 + 480.00
10.00
20.96
207.90
00 + 490.00
10.00
18.60
197.80
00 + 500.00
10.00
21.66
201.30
00 + 510.00
10.00
5.93
8.81
4.54
14.83
152.35
11.35
00 + 520.00
10.00
12.26
12.45
18.07
90.95
106.30
113.03
00 + 530.00
10.00
16.09
25.07
39.48
141.75
187.60
287.73
00 + 540.00
10.00
1.19
27.76
16.13
86.40
264.15
278.03
00 + 541.24
11.24
11.00
PROGRESIVA
DIST.
(m)
AREA (m2)
RELLENO
CORTE
ROCA
VOLUMEN (m3)
RELLENO
CORTE
ROCA
3.34
217.83
45.32
1,526.54
14,058.18
1,475.74