CALENDARIO VALORIZADO DE EJECUCION DE OBRA

OBRA

MEJORAMIENTO DE PISTAS DE LAS CALLES DE LA URBANIZACION TUNGASUCA, DISTRITO DE CARABAYLLO - LIMA LIMA.

REGION

LIMA

PROVINCIA

LIMA

DISTRITO

CARBAYLLO

PLAZO (d.c.)

: 120 DIAS CALENDARIOS

ITEM

SUB TOTAL

DESCRIPCIN

VALOR
REFERENCIAL

MES 1

MES 2

MES3

MES 4

S/.66,558.03

33,279.02

33,279.02

0.00

0.00

DEMOLICION

S/.186,237.91

62,079.30

62,079.30

62,079.30

0.00

03

MOVIMIENTO DE TIERRAS

S/.289,317.74

96,439.25

96,439.25

96,439.25

0.00

04

PAVIMENTO

S/.1,160,983.66

0.00

348,295.10

580,491.83

232,196.73

05

SEALIZACION

S/.80,848.43

0.00

0.00

40,424.22

40,424.22

06

VARIOS

S/.39,932.09

0.00

0.00

19,966.05

19,966.05

S/.1,823,877.86

S/.191,797.57

S/.540,092.66

S/.799,400.64

S/.292,586.99

01

OBRAS PRELIMINARES

02

S/.

GASTOS GENERALES

10%

S/.182,387.79

S/.19,179.76

S/.54,009.27

S/.79,940.06

S/.29,258.70

UTILIDAD

10%

S/.182,387.79

S/.19,179.76

S/.54,009.27

S/.79,940.06

S/.29,258.70

TOTAL

S/.

S/.2,188,653.44

S/.230,157.09

S/.648,111.20

S/.959,280.76

S/.351,104.39

IGV

18%

S/.393,957.62

S/.41,428.28

S/.116,660.02

S/.172,670.54

S/.63,198.79

MONTO CONTRACTUAL
MONTO CONTRACTUAL ACUMULADO

S/.2,582,611.06
S/.0.00

S/.271,585.37
S/.271,585.37

S/.764,771.22

S/.1,131,951.30

S/.414,303.18

S/.1,036,356.59

S/.2,168,307.89

S/.2,582,611.07

POCENTAJE AVANCE MENSUAL

0.00%

10.52%

29.61%

43.83%

16.04%

% AVANCE MENSUAL ACUMULADO

0.00%

10.52%

40.13%

83.96%

100.00%

CRONOGRAMA DE DESEMBOLSOS
MEJORAMIENTO DE PISTAS DE LAS CALLES DE LA URBANIZACION TUNGASUCA, DISTRITO
DE CARABAYLLO - LIMA LIMA.

OBRA
REGION

LIMA

PROVINCIA

LIMA

DISTRITO

CARBAYLLO

PLAZO (d.c.)

: 120 DIAS CALENDARIOS

Valor Referencial

2582611.06

CRONOGRAMA DE DESEMBOLSOS
CONCEPTO

30

60

90

120

MES 1

MES 2

MES 3

MES 4

TOTAL

271585.37 764771.22

1131951.30

414303.18

2582611.06

516522.21
1033044.42
1821152.00 764771.22

1131951.30

414303.18

4132177.71

ADELANTO PARA MATERIALES

54317.07 152954.24
108634.15 305908.49

226390.26
452780.52

82860.64
165721.27

1033044.43

SUB TOTAL

162951.22 458862.73

679170.78

248581.91

1549566.64

1658200.78 305908.49

452780.52

165721.27

2582611.06

EJECUCION DE OBRA
ADELANTO EN EFECTIVO (20.00%)
ADELANTO PARA MATERIALES (40%)
SUB TOTAL
DESCUENTOS
ADELANTO EN EFECTIVO

TOTAL

516522.21