Está en la página 1de 50

S

EN

SI

EM

Tab 5: Wind Integration Operational Impacts

2012 Siemens Industry Inc. All rights reserved

Wind Integration Operational Impacts

Load frequency Control


Governor action and droop control
Wind impacts on frequency regulation
Major Challenges

EM

Load Following Impacts or Economic Dispatch


Definition of economic dispatch
Characteristics of hydro units
Characteristics of wind units
Dispatch of Wind units
Load following
Impact of wind units on assignment of load following units

SI

Unit Commitment Impacts

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

In this section we will explore:


Frequency Control Impacts

5-2

Introduction

SI

now involve different behaviors (than conventional generation)


more variability and uncertainties introduced by wind and other
renewable generation technologies (e.g. solar)
The impact of the variability and uncertainties will increase as
the penetration increases and can lead to substantial integration
costs if not treated properly.
Fortunately there are ways of dealing with this effects.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Voltage control Real Time


frequency control (regulation) Real Time
Load following
Economic dispatch, and
Unit commitment
System Reliability Resource and Capacity Planning

EM

EN

The growth of wind power have complicated the way optimized


power system operation is carried out
The main activities of power system operations:

5-3

EN

Time Line for Operational Control Activities

Impact

Wind reduced
ELCC (Effective
Load Carrying

EM

Capability)

Impact

Wind Variability
& uncertainty

SI

Impact

Wind
uncertainty

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

ELCC

Wind
Source: NERC
IVGTFVariability
Report
Impact

& controllability

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-4

Dispatch of both
energy and capacity
(reserves) services

Ensure sufficient
generation is there
when needed

Initial: Governor
Action seconds
Then: Provided by
generators on AGC

Several minutes to a
few hours

Normally Day Ahead


Hours Ahead provide
adjustments.
Week, Month, Year
Ahead ensure
availability.
Greatest source of
costs. Wind
forecasting crucial to
manage this and the
risk associated with
the uncertainty in the
day-ahead time frame

With wind:

Greater regulation, load-following, and quick-start capability


required from the remaining generators.
Function of balancing area size, the size and geographical
dispersion of Wind Plants, the capabilities of the WTG & the
flexibility of other generators and load.

SI

Scheduling and
Unit
commitment

Short time frames to


maintain system
balance
Seconds - Minutes

EM

Maintain voltage
profiles & Prevent
Voltage collapse

Load following
and Economic
Dispatch

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Real time

Frequency
Regulation

EN

Voltage
Regulation

Time Line for Operational Control Activities


(continued)

5-5

SI

EM

EN

When a generator output is lost the frequency immediately


begins to fall.
The remaining generator governors, to a varying extent, see
the lower frequency and increase the amount of power
generated via governor action
Some loads are naturally frequency dependent. Simple AC
motors slow down and consume less power. For some types of
loads this power reduction is much more than a direct
proportion.
A new equilibrium point is reached, in a few seconds, and the
frequency decline is arrested. The system is off-nominal
frequency
When a block of load is suddenly lost, frequency immediately
begins to rise, governors decrease the generator output,
frequency dependent loads consume more power, and a new
equilibrium is reached.
Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Frequency Events in Power Systems

5-6

Frequency Deviation in the U.S.


For the Northeast interconnected system

EN

Frequency generally remains between 59.85 Hz and 60.15 Hz


During major events the deviation is still small

EM

Loss of the largest single unit in the interconnection (1300 MW)


produces a frequency decline of about 0.04 Hz; No Problem.
Huge Inertia

For the Eastern Interconnection:


Response of about -3300 MW/0.1 Hz, i.e. the loss of 1000 MW of
generation will cause a frequency deviation of -0.0303 Hz.
Usually, rate of frequency change is low: <1% per minute.
Huge Inertia

SI

WECC Frequency Response: -1500 MW/0.1 Hz; still very large


ERCOT Frequency Response: -600 MW/0.1 Hz; smallest of the
interconnected systems.
Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

During the blackout of 2003 frequency only deviated within +/- 0.3 Hz.

5-7

act
p
Im

Frequency Deviation in the U.S.


An Example

280

500

210

450

140

400

70

SI

550

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EM

EN

The figure below shows the impact in ERCOT system when WTG (QSE) almost
instantaneously ramp up and down causing frequency deviations and Rapid
Response Reserve (RRS) to be deployed
Eventually, a 10% ramp rate was agreed upon by ERCOT and the wind
community taking into consideration the economical impact a smaller ramp
rate could have on the WTGs (more on this later)

5-8

Frequency Control

EN

When there is disturbance the system responds in


two time frames:
System Inertial Response
Load Response
Prime Mover Governing Response

EM

Primary frequency response (10 sec)


Secondary frequency response (30 sec)

Supplementary Control

SI

Speed changer - local level (Load reference set-point);


Instruction to operators from the control center.
Automatic Generation Control (AGC) - system level

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Primary Control

5-9

Siemens Power Academy TD-NA Power System Studies for Wind Integration

Load can contribute


significantly to arrest the
initial drop in frequency
working together with the
system inertia.

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

Inertia comes from the


large mass in the
rotors and turbines of
conventional
generators.

Initial Line of Defense


Inertial Response / Load Response

5-10

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

Next Line of Defense


Response of Machines Governors

5-11

act
p
Im

But
Frequency Response is Affected by WTG

SI

EM

Increased rate of change of system frequency for the same


disturbance (drop large generator unit)
Need to increase the up-regulation / down-regulation
spinning reserve in the system
More acute for relatively small isolated systems: increased
risk of under-frequency load shedding and cascading
outages
Gets worse for greater levels of penetration

WTG could ramp up and down very rapidly making


the situation worse.
Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

WTG have less inertia and traditionally did not


participate in frequency control: e.g. rotor speed
constant philosophy for the DFIG
This produced:

5-12

Modern Larger WTG

EN

have greater inertia

Solution

However
Modern WTG Generation Addressed This

Deliberately use the control to extract stored inertial energy


by decelerating the machine rotor

EM

Provide incremental energy contribution during the first


several seconds of grid events
Do not go too far down with the rotor speed to avoid stalling a
wind turbine

SI

Can provide Governor like response by spilling wind if this


is the most economic way of providing regulation
Have ramp controls.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

The inertia stored in the rotating mass tends to increase slightly


more than linear with the rated power of the turbine

5-13

Solution

Modern WTG Generation Addressed This


Siemens Netconverter

EN

The output of the WTG is controlled so it is frequency sensitive.


The energy is extracted from both slowing the turbine and the
wind that is spilled.
This gives time for the system to recover.

SI

EM

Turbines at reduced power

Siemens Power Academy TD-NA Power System Studies for Wind Integration

Reduction in turbine output power

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Increase in turbine output power

5-14

ERCOT LOAD SHED LEVELS

EN

Three steps are considered in ERCOT


Frequency Threshold

Load Relief

59.3 Hz

5% of the ERCOT System Load


(Total 5%)

An additional 10% of the ERCOT System Load


(Total 25%)

EM

58.5 Hz

An additional 10% of the ERCOT System Load


(Total 15%)
2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

58.9 Hz

SI

A Typical response shown

Siemens Power Academy TD-NA Power System Studies for Wind Integration

Recorded, Initial, Adjusted


60.3
recorded
initial
adjusted

60.2
60.1
60
59.9

Hz

59.8
59.7
59.6
59.5
59.4
59.3
59.2
0

10

15

20

25

Seconds

5-15

Solution

Modern WTG Generation Addressed This


GE WindINERTIA 1

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

WindInertia increases electric power during the initial stages of


a significant downward frequency event by issuing a command
from the special frequency control
Usually it is enough to provide response within several seconds
until governors of larger conventional machines start their work
WTG electric power drops to allow recovery of rotational speed

Source: N. Miller et al., GE Energy. CanWEA, Vancouver, BC, October 20, 2008

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-16

Solution

Modern WTG Generation Addressed This


Ramp Control

EM

P, MW

Ramp Rate Control

350
300
250
200
150
100
50
0

Curtailment released;
ramp to max power @
10 MW/min

10

15

20

t, min

Available Output

SI

Output

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Curtailment to 100 MW
@ 15 MW/min

EN

ISOs are imposing limits on the ramping of WTG (e.g. 10%/min


for ERCOT)
Modern WTG have the capability to respond.
Below to examples one from Siemens and another from GE

Source: N. Miller et al., GE Energy. CanWEA, Vancouver, BC, October 20, 2008

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-17

Final Line of Defense


AGC

SI

EM

Units on AGC can change output


quickly to track minute by
minute load variations and any
variations in generation.
Units in AGC are usually the
marginal units in the network
(e.g. GTs. CCPs, etc) or storage
hydro.
WTG are never the marginal unit
and would not be on AGC.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

Governor control is proportional and will leave an error in


the frequency.
As shown before the final line of defense after a major
perturbation is the Automatic Generation Control (AGC).

5-18

EM

EN

Load following takes place in the same time frame as economic


dispatch discussed next, usually defined in the intra-hour time
frame.
Load following is defined as the response to changes in system
load and as we will see to changes in wind output.
The composition of units assigned to load following depend on
both of utility company operational practices, economic
dispatch regime and on the physical capabilities of generators
(such as ramp rates) that follow load.

SI

Larger control areas typically have several units that provide a


fraction of total output and that can be called upon to either
increase or decrease output.
When this load following capability is spread among several units,
the ramp rate becomes less of a constraint than if only a small
number of units adjust to changing load conditions.
It is generally nor economic to use WTG to provide load
following.
WTG is modeled as a reduction in load in operational studies.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Background of Other Operational Concepts


Load Following

5-19

EM

EN

Given a set of generating units, synchronized and under


dispatch control, and given the total net Load demand to be
supplied by the units;
Determine the output of each unit so that the total
production cost is minimized and the sum of the outputs
equals the total net demand. Also

SI

no unit can violate its minimum or maximum dispatch limit.


The flows in the system cannot violate transmission limits and
create potentially unsecure conditions (security constrained
solution)

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Problem Definition

Background of Other Operational Concepts


Economic Dispatch (ED)

5-20

Background of Other Operational Concepts


Generator Models for Economic Dispatch
Thermal Units

Heat Rate (H) Is the amount of heat added, usually in Btu per hour, to produce a unit amount of work kWh. Heat
rate thus has units of Btu/kWh.

Hydro Units

EM

Production function of flow, head and efficiency


Value of water is a function of expected (stochastic) future
production cost savings versus producing today
Value is zero if the plant is spilling water or is a run-of-river
Value is very high if levels are low and it is likely that in the future very
highly priced thermal (or load rationing) would have to be incurred.

Wind Units

SI

Function of the Cp and cube of the wind speed.


Detailed hour by hour mesoscale wind models used to define
production
Modeled usually as a negative load

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

Input-Output characteristics of a thermal generation unit is defined in terms


of gross input: Heat rate (H) in (MBtu/hr) versus net generator MW output
(P).

5-21

Background of Other Operational Concepts


Economic Dispatch Solution

EM

All units are either at its


maximum/minimum output or are
marginal units (within unconstrained
areas)

SI

Tool: Security Constrained Economic


Dispatch (SCED)

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

The goal is to dispatch all the available synchronized units to


meet the load demand at minimum cost.
For a a system with N thermal units, this is achieved under the
condition that at optimal dispatch all units have equal
incremental (marginal cost), where F(Pi) is the Fuel input
power output characteristic of each unit.

5-22

Why Unit Commitment?

Background of Other Operational Concepts


Unit Commitment (UC)

EN

Cyclic nature of power system loads.


Load changes and the operation of an electric power system.
Committing enough units and having them on line is one of
economics and security (reserves)

Tool: Security Constrained Unit Commitment (SCUC)

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Many constraints can be placed on the unit commitment


problem such as;

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-23

Generating unit constraints and status


Reserve constraints
Minimum up-time and down-time
Crew constraints
Ramp rate limits
Transmission Constraints
Generation-Load balance constraint

SI

EM

Background of Other Operational Concepts


Functions of the ISO
The ISOs functions include the administration of the UC
and ED according to various timeframes

EN

Day-ahead security-constrained unit commitment once a


day

EM

Real-time security-constrained economic dispatch every 5


minutes with a 10-minute reaction time
Automatic generation control every 6 seconds
Supplementary, computer-assisted manual intervention as
needed

Other functions of the ISOs are

SI

Operating the high-voltage transmission system and


Administer, monitor, and settle the electricity markets

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Real-time (short-term) security-constrained unit


commitment every 15-minutes with a 30-minute reaction
time

5-24

Background of Other Operational Concepts


Spinning Reserve Constraints

EM

Spinning reserve must be carried so that the loss of one or more


units does not cause too far a drop in system frequency. If one unit
is lost, there must be ample reserve on the other units to make up
for the loss in a specified time period.

Spinning reserve must be allocated to obey certain rules,


usually set by regional reliability councils (in the united States)
that specify, how the reserve is to be allocated to various units.
Typical rules specify

SI

that reserve must be a given percentage of forecasted peak


demand, or
that reserve must be capable of making up the loss of the most
heavily loaded unit in a given period of time.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

Spinning reserve is the term used to describe the total amount


of generation available from all units synchronized (i.e.,
spinning) on the system, minus the present load and losses
being supplied.

5-25

Background of Other Operational Concepts


Spinning Reserve Constraints (continued)

quick-start diesel or
gas-turbine units
hydro-units
pumped-storage hydro-units

EM

that can be brought on-line, synchronized, and brought up to full


capacity quickly.
As such, these units can be counted in the overall reserve assessment,
as long as their time to come up to full capacity is taken into account;
Rapid Response Reserves (RRS)
Finally, Reserves must be spread around the power system;

SI

to avoid transmission system limitations (often called bottling of reserves)


and
to allow various parts of the system to run as islands, should they become
electrically disconnected.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

These include:

EN

Beyond spinning reserve, the unit commitment problem may involve


various classes of scheduled reserves or off-line reserves.

5-26

Background of Other Operational Concepts


Resource Adequacy

EM

One key component to represent the value of a unit is its ELCC or


Expected Load Carrying Capability.
For conventional generation it is approximately equal to Maximum
Demonstrated Capacity (MW) * (1-FOR)
For WTG we will see later.

SI

Yearly the ISO must ensure that there is enough capacity in the
network including firm imports less firm exports.
Now we will see how WTG affects all of this!

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

This refers to the procurement of enough installed generation in


the system to be able to attend the forecasted peak load,
schedule the required maintenances and account for forced
unavailability while maintaining a desired level of reliability;
usually measured in LOLP in % or LOLE in days per ten years

5-27

act
p
Im

The Nature of WTG


Variability & Uncertainty

Solution

SI

EM

Wind mesoscale models demonstrate that it is not credible that in a


large area all wind speed will experiment the same variation.
The larger the geographical dispersion of Wind Plants the smaller the
variability of the generation

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

Variability are changes in the WTG output due to weather


patterns and are unavoidable, but can be mitigated.
Geographic Dispersion reduces Variability

Source: DOE 2008 Report

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-28

The Nature of WTG


Variability
The size of the Wind Generation reduces the variability

Solution

EN

More WTG imply that it is less likely that they all see simultaneously
the same change in wind speed resulting in soothing effects
More WTG generation is likely to also imply greater geographical
diversity.

SI

EM

Sudden changes in wind speed are less likely and thing localized.

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Also, shorter time frames are subject to less variability.

Source: DOE 2008 Report

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-29

The Nature of WTG


Variability (continued)

EN

Based on the observations above we conclude that making


the balancing areas larger reduce variability and as we will
see also the uncertainty.

Solution

Virtual arrangements though reserve sharing, ACE sharing and


dynamic scheduling of wind plants from smaller to larger areas.
Cost is reduced as
the Balancing Areas
increases (larger
areas.

Increase in
Geographical
diversity

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

Wind resources were evaluated in the Columbia Basin, in Eastern Montana, as a 50%/50% mix of Columbia Basin and Eastern
Montana wind, and as a multi-state diversified mix with many smaller sites combined.

Source: Avista Wind Integration Study

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-30

act
p
Im

The Nature of WTG


Uncertainty

EN

Uncertainty are errors in the estimation of production due to


error in the wind speed forecast
The errors in wind speed are magnified in the power output due
to the cube dependency.
10% error in wind speed results in 33% error in power.

SI

EM

Level of
Penetration

Siemens Power Academy TD-NA Power System Studies for Wind Integration

Source: Avista Wind Integration Study

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Costs can be substantial, particularly for over commitments of capacity.

5-31

act
p
Im

The Nature of WTG


Uncertainty (continued)

SI

EM

This has an impact on


markets, the sooner the
day ahead closes the
greater the error in the
forecast and the higher the
cost
Same applies for hour
ahead and
This is a case for late
closing of day ahead
markets and intra-hour Solution
markets.
Siemens Power Academy TD-NA Power System Studies for Wind Integration

Source: NERC IVGTF Report 041609

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

The errors in wind speed are magnified as the time horizon


increases. This means that on one extreme day ahead unit
commitment it has the greatest impact and on the other load
following has the least.

5-32

The Nature of WTG


Uncertainty (continued)

Solution

SI

EM

Better data collection / larger areas / faster computers


Use of multi-model approaches for forecast; statistical models using for
example Artificial Neural Networks, mixture of experts, nearest neighbor
search and support vector machines
Use of mutischeme forecasting based on different assumptions/methods in
numerical weather models

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

Wind forecasting technology has improved substantially over the


years, lead by countries like Germany that have large levels of
wind integration.

Source: Predicting the Wind, IEEE

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-33

The Nature of WTG


Uncertainty (continued)

Solution

SI

Source: Predicting the Wind, IEEE

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EM

EN

These methods and efforts have resulted in a continued


reduction in the forecasting error

5-34

The Nature of WTG


Uncertainty (continued)

Solution

Larger areas result in a reduced forecasting error for the region.

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

This results in less impact on scheduling and therefore lower integration


costs,

Source: Predicting the Wind, IEEE

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-35

Modeling Wind as a Load Resource


for System Operations

EN

WTG is normally treated as a negative load resource and the net


load forecast is used to commit and dispatch non-wind
generation:

EM

Load and WTG are independent and the combination of errors is :


2
total load
2wind generation

SI

Example if the load forecast error for a 5,000 MW peak load is 2% = 100 MW
and the WTG error for a total of say 1000 MW, with an output of 500 MW
during the peak is 25% = 125 MW, then the total expected error is 160 MW..

Wind forecast error and variability increases ancillary services for


regulation control
Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Since wind has no fuel cost per se, it is always called to run, whenever
available in the dispatch; same as load
It is treated as non dispatchable unit by most utilities and electricity markets;
same as loads
Wind generation is variable and has errors in its forecast; same as loads

5-36

Wind adds variability to


the to the ramping
requirements.

SI

EM

The figure to the left


shows the increase in
requirements for Xcel
energy North, with and
without wind

Source: Grid Impacts of Wind Power Variability: Recent


Assessments from a Variety of Utilities in the United
States
B. Parson et. al.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

Ramp up
requirements
increased by
wind

Ramp down
requirements
increased by
wind

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

Wind generation can


have significant Impact
on load following.

Wind Impacts on Load Following

act
p
Im

5-37

Unit Commitment of Wind Generation

act
p
Im

EN

The use of wind generation, due to the variable nature of wind,


can lead to operational uncertainty:
How much generation will be necessary to serve the net load (load
WTG)?

EM

What load following reserves and ramping capabilities are


required?

SI

To allow regulation, i.e. the minute by minute changes in


system load
Some utilities when committing or dispatching wind
generation, use a generation output that is discounted by a
certain percentage of the forecast value to hedge against
uncertainties in wind forecasting.
Remember that errors in the forecast have maximum impact the
longer the time are maximum in the day ahead unit
commitment.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

How much spinning reserve will be necessary to maintain reliability


levels?

5-38

Solution

Effect of the Nature of Other Generation

act
p
Im

Impact

Very inflexible slow to change

Run-of-river hydro

Limited flexibility without wasting water

Large Coal Fired

Slow to start and ramp, better at base


load

Combined Cycle
Plants

Faster to start, fast to ramp; high


efficiency at close to nominal

Conventional CT

Fast to start and ramp; costly

Advanced CCP

Fast to start and ramp; very efficient at


many load levels FlexPlant 10

SI

EM

Nuclear Power
Plants

Pump storage

Faster to start, fast to ramp; need low


cost energy

Storage Hydro

Fast to start and ramp; can virtual


store

Siemens Power Academy TD-NA Power System Studies for Wind Integration

worst

better

Best

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Technology

EN

The impact of the variability and uncertainty of wind generation is minimized


when the rest of the generation is flexible and the LOAD!

5-39

act
p
Im

Summary of Impacts and Solutions

Impact

Mitigation

- WTG Controls
- WTG Controls
- Flexible Generation
- Flexible Generation - Geographical Diversity
- Large Balancing Areas

- Flexible Generation
- Flexible Generation
- Geographical Diversity
- Geographical Diversity
- Large Balancing Areas
- Large Balancing Areas
- Flexible Markets
- Flexible Markets
- Improved forecasting

High

Improving

SI

Effectiveness

Unit Commitment
Day Ahead

High
Low
Medium
Significant errors in
Smaller errors in forecast Some errors in forecast
forecast
Subject to Variability
Important Variability
Important Variability

EM

Very Low
Smallest errors in
forecast
Limited Variability

Activity
Load following
Unit Commitment
Economic Dispatch
short term

High

Need to improve

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Regulation

EN

The table below summarizes the main operation impacts and their
mitigations/solutions
Not all systems are the same with respect of the quality of the WTG,
the flexibility of the generation and the level of penetration but this is a
good indication

INCREASING COSTS

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-40

Summary of Impacts and Solutions


(continued)

act
p
Im

Wind
Regulation Load
Unit Gas Supply Tot
Capacity
Cost
Following CommitCost
Oper.
Penetration ($/MWh)
Cost
ment
($/MWh)
Cost
(%)
($/MWh)
Cost
Impact
($/MWh)
($/MWh)
3.5
0
0.41
1.44
na
1.85
15
0.23
na
4.37
na
4.60
20
10
15
14.8

SI

May 03 Xcel-UWIG
Sep 04 XcelMNDOC
2005
PacifiCorp
April 06 Xcel-PSCo
April 06 Xcel-PSCo
Jul 07
APS

0
0.20
0.20
0.37

INCREASING COSTS

Siemens Power Academy TD-NA Power System Studies for Wind Integration

1.6
na
na
2.65

3.0
2.26
3.32
1.06

na
1.26
1.45
na

4.60
3.72
4.97
4.08

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Study

EM

Date

EN

The table below summarizes the results of various integration studies


to date.
It is largely in agreement with the observations made

5-41

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

A larger number of Studies

5-42

Using Economic Dispatch Simulation to Evaluate


the Cost Impact of Wind Generation

EN

The costs impacts of sub hourly load following that include


dispatched wind generation can be evaluated by running a
Security Constrained Economic Dispatch (SCUD) simulation
software .

EM

Run the SCUD and calculate the dispatch for other units and reserves.
For comparison purposes a case with uniform capacity and energy equal to
that produced by the wind resources can be assessed.

This cost incurred due to using wind during this period, is


largely due to factors such as;
Sudden loss or increase of wind power

SI

Slow changes in wind power output (i.e. ramp rates)

Units at their minimum.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

With wind profiles / mesoscale models / forecasts calculate wind production


by plant in 15 minutes increments and its expected error (introduced as
probability)

5-43

Using Unit Commitment Simulation to Evaluate the


Economic Impact of Wind Generation (continued)

With wind profiles / mesoscale models / forecasts calculate


wind production by plant in hourly increments. Expected
case can be used or historical series. Account for errors in
the forecast.

EM

Run the SCUC and calculate the commitment for other units
and reserves. Calculate the cost.

SI

This cost can be compared with a benchmark case that has a


unit commitment with no wind capacity scheduled, but
instead an uniform block of generation that produces the
same energy of the wind is included.
A case where wind and corresponding load is removed from
the runs.

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

EN

The economic impact of wind generation in the unit


commitment can be done as follows;

5-44

EN

Carrying of additional reserves, both spinning and


non spinning to meet intra hour load following.
Additional energy costs incurred for intra hour load
following due to greater variability
Possible additional costs of frequency regulation
resources or regulation reserves

EM

Found by evaluating the impact of wind fluctuations on the


standard measures such as area control error etc.
Increased reserves for safe operation.
Important for older WTG less so with new designs

SI

Additional cost for Unit commitment costs due to


forecast inaccuracies in Wind generation outputs
The cost of rescheduling generation to account for short fall
of wind output

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

Summary of Operational Impacts of Wind Integration

5-45

A Case Study of a WPG in High Penetration Denmark


(19.3%)

EM

EN

Plant spilling wind


so it has spinning
reserve available

SI

Fast Reduction
to counteract
frequency
increase

Manual orders
to reduce
output

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

A typical day on the Horns Rev Offshore wind plant in Denmark

Source: European Balancing Act, IEEE

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-46

The Capacity Value of Wind

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

While wind is largely an energy resource it does have some


capacity value; i.e. Effective Load Carrying Capability (ELCC)
There are several methods for determining this value for WTG

Source: M. Milligan and K. Porter, Determining the capacity value of wind: A survey of methods and implementation,

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-47

The Capacity Value of Wind (continued)

Source: Wind Plant Integration- Cost Status & Issues IEEE

Siemens Power Academy TD-NA Power System Studies for Wind Integration

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

As can be observed in the figure below in average about 25%


ELCC is assigned to WTC across different companies.

5-48

The Capacity Value of Wind (continued)

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

However, this value may change season to season as Avista


found:

Source: Avista Wind Integration Study

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-49

The Capacity Value of Wind (continued)

2012 Siemens Industry Inc., Siemens Power Technologies International (Siemens PTI)

SI

EM

EN

At the end of the day the ELCC of wind is the additional load
that one can serve when wind is added without degrading the
target reliability level

Source: Avista Wind Integration Study


Source NREL The Capacity Value of Wind

Siemens Power Academy TD-NA Power System Studies for Wind Integration

5-50

También podría gustarte