DEAD
ELEMENTO
PESO
ANCHO
PESO DE LADRILLO DE LOSA
80.0 Kg/m2
0.4 m
PESO DE TABIQUERIA
100.0 Kg/m2
0.4 m
PESO DE ACABADOS
100.0 Kg/m2
0.4 m
TOTAL DEAD
TOTAL
32.0 Kg/m
40.0 Kg/m
40.0 Kg/m
112.0 Kg/m
32.0 Kg/m
40.0 Kg/m
72.0 Kg/m
80.0 Kg/m2
100.0 Kg/m2
0.4 m
0.4 m
PESO ESPECIFICO
1800
MUROS PERIMETRALES
ESPESOR
0.15
H
2.6
702.0 Kg/m
PESO ESPECIFICO
1800
PARAPETOS
ESPESOR
0.15
H
1
270.0 Kg/m
ELEMENTO
SOBRECARGA S/C
TOTAL DEAD
LIVE
PESO
250.0 Kg/m2
SOBRECARGA S/C
TOTAL DEAD
100.0 Kg/m2
SOBRECARGA S/C
TOTAL DEAD
400.0 Kg/m2
ANCHO
0.4 m
0.4 m
0.4 m
TOTAL
100.0 Kg/m
100.0 Kg/m
40.0 Kg/m
40.0 Kg/m
160.0 Kg/m
160.0 Kg/m
AZOTEA
2, 3, 4 y 5
AZOTEA
ESCALERAS
Z
U
C
S
Tp
R
PESO POR m2
Area
Peso Nivel 1
Peso Nivel 2
Peso Nivel 3
Peso Nivel 4
Peso Nivel 5
Peso Total
0.4
1
2.5
1.4
0.9
7
PESO DE LA EDIFICACION
1.00
180.29
180.29
180.29
180.29
180.29
90.15
811.32
C=2.50
Tn/m2
m2
Tn
Tn
Tn
Tn
Tn
Tn
CORTANTE EN LA BASE
V = (ZUCS/R)*PESO TOTAL
V=
162.26
DISTRIBUCION DE LA FUERZA SISMICA POR PISO
Piso
5
4
3
2
1
hi (m)
14.65
11.85
9.05
6.25
3.45
Pi (Tn)
90.15
180.29
180.29
180.29
180.29
SUMA
hi*Pi (Tn-m)
1320.65
2136.47
1631.65
1126.83
622.01
3380.49
hi*Pi/(hi*Pi)
0.39
0.63
0.48
0.33
0.18
Fi (ton)
63.39
102.55
78.32
54.09
29.86
ANALISIS DE RESULTADOS
1. DESPLAZAMIENTOS LATERALES
MAX PER:
SISMO X
R=
PISO
1
2
3
3
3
/h 0.007
7
h
345
280
280
280
280
SISMO Y
R=
PISO
1
2
3
4
5
/h 0.007
8
h
345
280
280
280
280
D (cm)
0.3235
0.6463
0.9848
1.2054
1.3294
D*0.75*R
1.6984
3.3931
5.1702
6.3284
6.9794
0.007
VEAMOS LA TABLA DE LOS DESPLAZAMIENTOS EN EL SAP
d (cm)
1.6984
3.3931
5.1702
6.3284
6.9794
d/h
0.0049
0.0121
0.0185
0.0226
0.0249
MAX PERMITIDO
0.0070
0.0070
0.0070
0.0070
0.0070
D*0.75*R
2.7402
5.6286
8.1390
9.9840
11.0862
d (cm)
2.7402
5.6286
8.1390
9.9840
11.0862
d/h
0.0079
0.0201
0.0291
0.0357
0.0396
MAX PERMITIDO
0.0070
0.0070
0.0070
0.0070
0.0070
/h 0.007
7
h
345
280
280
280
280
SISMO Y
R=
PISO
1
2
3
4
5
/h 0.007
8
h
345
280
280
280
280
D (cm)
0.0378
0.1017
0.1742
0.2439
0.3065
D*0.75*R
0.1985
0.5340
0.9147
1.2804
1.6092
0.007
VEAMOS LA TABLA DE LOS DESPLAZAMIENTOS EN EL SAP
d (cm)
0.1985
0.5340
0.9147
1.2804
1.6092
d/h
0.0006
0.0019
0.0033
0.0046
0.0057
MAX PERMITIDO
0.0070
0.0070
0.0070
0.0070
0.0070
D*0.75*R
0.2084
0.5659
0.9878
1.4160
1.8285
d (cm)
0.2084
0.5659
0.9878
1.4160
1.8285
d/h
0.0006
0.0020
0.0035
0.0051
0.0065
MAX PERMITIDO
0.0070
0.0070
0.0070
0.0070
0.0070
OS DESPLAZAMIENTOS EN EL SAP
JOSE LUIS REQUE QUESQUEN
VERIF.
SI CUMPLE
NO CUMPLE
NO CUMPLE
NO CUMPLE
NO CUMPLE
OS DESPLAZAMIENTOS EN EL SAP
VERIF.
NO CUMPLE
NO CUMPLE
NO CUMPLE
NO CUMPLE
NO CUMPLE
OS DESPLAZAMIENTOS EN EL SAP
VERIF.
SI CUMPLE
SI CUMPLE
SI CUMPLE
SI CUMPLE
SI CUMPLE
OS DESPLAZAMIENTOS EN EL SAP
VERIF.
SI CUMPLE
SI CUMPLE
SI CUMPLE
SI CUMPLE
SI CUMPLE
CEL: 979019651