Está en la página 1de 2

ALCANTARILLADO TRAMO 1

TRAMO

P24

COTA NIVEL
TERMINADO

LONGUITUD

DELTA

H
ENTRADA

2846

1
13.87

P18

2846

P17

2846

P16

2846

P15

2846

P14

2842

P13

2842

P12

2842

BLOQUE I y H
P23

2846

20.22
26.1
23.5
5
21.05
21

14.5
P17

2846

BLOQUE G y I
P22

2846
14.5

P16

2846

BLOQUE F y G
P20

2845
14.5

P13

PENDIENTE

2.0%
3.0%
3.0%
3.0%
33.0%
3.0%
3.0%

3.0%

3.0%

16.0%

COTA POZO
LLEGADA
2845

DIAMETRO
(mm)

RESALTO

0.28

2845

1.28

2844.72

0.2

1.89

2844.11

0.2

2.67

2843.33

0.2

3.38

2842.62

0.2

1.03

2840.97

0.2

1.66

2840.34

0.2

2.29

2839.71

0.2

1.45

2844.55

2844.27

1.48

2843.61

2.09

2842.83

2.87

2842.12

3.58

2840.47

1.23

2839.84

1.86

2839.21

2.49

2844.55

1.45

2843.86

1.89

2843.77

2.23

2843.08

2.67

2842.77

2.23

2840.2

1.55

300

0.78

300

0.71

300

1.65

300

0.63

300

0.63

300

0.44

250
1.89

2844.11

2.23

2843.77

0.44

250
2.67

2843.33

2.23

2842.77

2.32

250
1.55

2840.45

174.24

57.37 M
116.87 M

ESPESOR
VOLUMEN
CAMA DE
CAMA DE
ARENA (M3) ARENA(M3)

H
VOLUMEN
DESCONTADO DE RELLENO
TUBERIA (M)
(M3)

1.24

13.87

0.8

13.76

0.05

0.55

0.94

10.43

1.79

20.22

0.8

28.96

0.05

0.81

1.44

23.29

2.48

26.1

0.8

51.78

0.05

1.04

2.13

44.47

3.23

23.5

0.8

60.72

0.05

0.94

2.88

54.14

2.41

0.8

9.64

0.05

0.2

2.06

8.24

1.55

21.05

0.8

26.1

0.05

0.84

1.2

20.21

2.18

21

0.8

36.62

0.05

0.84

1.83

30.74

1.67

14.5

0.8

19.37

0.05

0.58

1.37

15.89

2.45

14.5

0.8

28.42

0.05

0.58

2.15

24.94

1.89

14.5

0.8

21.92

0.05

0.58

1.59

18.44

TOTAL

TUBERIA 250
300

VOLUMEN
EXCAVACION
(M3)

250

0.61

2842

H
A
COTA POZO
LONGUITUD
H SALIDA PROMEDIO
ANCHO
SALIDA
(M)
(M)
(M)

297.29

6.96

250.79

ALCANTARILLADO TRAMO 2
TRAMO

P12

COTA NIVEL
TERMINADO

LONGUITUD

DELTA

H
ENTRADA

2845

1.3
11.14

P6

2845

P5

2845

P3

2844

P2

2844

P1

2841

BLOQUE C y D
P11

2845

22.2
40.4
21.5
19.2

11.5
P5

2845

BLOQUE CC y B
P3

2845
12

P9

2845

BLOQUE A y B
P8

2842
11

P2

PENDIENTE

3.0%
3.0%
3.0%
4.0%
8.0%

2.0%

2.0%

2.0%

COTA POZO
LLEGADA

2843.7

DIAMETRO
(mm)

RESALTO

0.33

2843.7

2842.92

1.83

2842.25

2.5

2840.99

2.71

2841.13

2.57

2837.59

3.11

2843.5

1.5

2842.82

1.93

250
1.63

2843.37

0.2

2.3

2842.7

0.2

2.51

2841.49

0.2

2.37

2841.63

0.2

2.91

2838.09

0.2

1.5

2843.5

0.67

250

1.21

300

0.86

300

1.54

300

0.23

250
1.73

2843.27

0.2

2843

0.24

2843

2.24

2842.76

0.2

2.2

2839.8

2842.31

2.44

2839.8

2.2

2839.33

2.42

250
2.42

2839.58

148.94

67.84 M
81.1 M

ESPESOR
VOLUMEN
CAMA DE
CAMA DE
ARENA (M3) ARENA(M3)

H
VOLUMEN
DESCONTADO DE RELLENO
TUBERIA (M)
(M3)

1.42

11.14

0.8

12.66

0.05

0.45

1.12

9.98

2.17

22.2

0.8

38.54

0.05

0.89

1.87

33.21

2.61

40.4

0.8

84.36

0.05

1.62

2.26

73.04

2.64

21.5

0.8

45.41

0.05

0.86

2.29

39.39

2.84

19.2

0.8

43.62

0.05

0.77

2.49

38.25

1.72

11.5

0.8

15.82

0.05

0.46

1.42

13.06

2.22

12

0.8

21.31

0.05

0.48

1.92

18.43

2.31

11

0.8

20.33

0.05

0.44

2.01

17.69

TOTAL
TUBERIA 250
300

VOLUMEN
EXCAVACION
(M3)

250

0.22

2842

H
A
COTA POZO
LONGUITUD
H SALIDA PROMEDIO
ANCHO
SALIDA
(M)
(M)
(M)

282.05

5.97

243.05