the process of rebar inspection, whether the inspection is done by their own forces or by an inspector re p resenting the owner or building o fficial. The goal of inspection or q u a l i t y - c o n t rol programs is to ensure that contract documents and building codes are followed. The programs al- so ensure structural safety and arc h i- tectural aesthetic compliance. Inspection and testing do not add quality to the product, but only con- firm whether it meets the established criteria. Quality during construction is achieved mostly by the contractor s quality-assurance program, involving workers and field supervisors. The c o n t r a c t o rs inspectors are separate f rom the inspectors mandated by the owner or local building department. The contractors quality-control in- spection helps assure that the finished c o n s t ruction meets the owners re- q u i rements. Inspections by the mater- ial producer and supplier assure that p roducts meet material specifications. Inspectors should be familiar with the project contract documents (espe- cially structural and rebar placing drawings) and building code re- q u i rements, and have access to mate- rial standards and re f e rences, codes, and industry manuals or re p o r t s . The inspection program should be established at a pre - c o n s t ruction con- f e rence. The size or complexity of the p roject determines the scope of the i nspection program. This meeting should be attended by re p re s e n t a t i v e s of outside inspection agencies, the general contractors superintendent, c o n c rete subcontractors superinten- dent, the suppliers re p resentative, the i ronworker foreman, and others, such as the architect, engineer, or engineer s site re p resentative. At the meeting, a checklist of pro c e d u res and minimum re q u i rements for inspection accep- tance should be established. Checklist The list should cover (but not be limited to) the following: A construction schedule f ro m the general contractor is important so the inspector can follow the placing c rew and inspect in-place rebar be- f o re the scheduled placing and fin- ishing of the concre t e . Certified mill test or bar coating r e p o r t s may accompany material shipped to the jobsite. If the reports are sent to the contractor, they should still be made available to the inspector. Independent testing laboratory r e p o r t s on samples taken at the fab- r i c a t o rs shop or the jobsite offer ver- ification of the pro d u c e rs mill test re p o r t . Approved placing drawings should be available for review and study by field-placing personnel and the inspector at least 1 day before the actual placing of the re b a r. A material shipment schedule should be provided and updated as necessary so in-place inspections can be scheduled. Potential problems should be discussed to identify diff i c u l t - t o - p l a c e details, lack of specifics on the con- tract documents, possible engineer- ing drawing discrepancies, detailing or placing errors, and approval of im- plemented field changes. Tolerances should be discussed to identify those which are critical, the method of measurement, and the ba- sis for rejection or acceptance. Periodic meetings should be held to discuss previous inspection reports, problems and solutions, and the schedule of upcoming work. Material inspection In-place inspection of rebar starts with the mill test report and may be supplemented by a report from an independent testing laboratory. Re- ports should state grade of steel, ten- sile properties, chemical composition (and carbon equivalent if rebar is to be welded), and spacing and height of deformations. Compare these val- ues with those in the applicable ASTM standard. Examination of the bar mill markings will identify the p roducing mill, the type and grade of steel, and the bar size. Reinforcing bar inspection Visually check bar diameter and shape (if bent); measure bar lengths, spacing, embedment, and bearing on a wall or beam. In a slab, count the total number of pieces and measure the slab bar spacing. Check these fig- u res against the approved placing drawings in conjunction with the s t ructural drawings. Similarly, check beam longitudinals, column verti- cals, and stirrup and tie spacings. Bar supports M e a s u re chair heights to verify that the specified cover and clear- ances will be satisfied. It is extre m e l y important to check the chairs or standees supporting slab and mat top bars for height. The entire mat and cages also should be checked for s t a b i l i t y, since they can easily be dis- placed during concrete placement. Normally side supports are not pro- vided unless called for in the contract documents. Where specifications re- q u i re corro s i o n - p rotection measure s , verify the class of protection of the bar supports furnished. Rebar inspect ion Establish a checklist of procedures and determine minimum requirements for inspection acceptance Rebar tying requirements R e i n f o rcing bars are tied together to form a rigid mat for footings, walls, and slabs. A rigid cage is formed when beam or column longitudinals a re tied to the stirrups and ties. Iro n- workers usually tie a minimum num- ber of rebar intersections. If the speci- fications are not precise about the number of tied intersections, the work should be accepted unless it is appar- ent the mats or cages of re i n f o rc i n g steel will be displaced from their in- spected position during concre t i n g . The placer is responsible for tying bars so they will remain in position. Tack welding of rebar to rebar should not be allowed, and only coated tie w i re should be used to tie coated bars. Splices Length and location of lap splices should be specified in the contract documents and on the approved plac- ing drawings. If mechanical connec- tions are re q u i red in lieu of lap splices, the placing foreman or the mechanical connection supplier should pro v i d e the inspector with evidence that the a rchitect or engineer has approved use of the connection, and provide litera- t u re describing the recommended in- stallation pro c e d u re s . Special attention may be needed in the inspection of mechanical connec- tions or welded splices, as well as crit- ical components and activities that are not routine for either the placer, con- t r a c t o r, or inspector. Coatings Inspectors should not reject re b a r with a light coating of rust. Howev- e r, dirt, grease, or other deleterious adhesions must be removed before c o n c rete placement. Wa t e r- s o l u b l e cutting oils do not significantly af- fect bond. Review the contract doc- uments for acceptance or re j e c t i o n criteria if there is damaged epoxy or damaged galvanized coating. Cor- rective actions should follow re c- ommended touch-up pro c e d u re s and should be completed before ac- ceptance by the inspector. Tolerances Tolerances establish permissible variations in dimensions and loca- tions, and should neither be overly restrictive or lenient. The engineer or a rchitect usually specifies the stan- d a rd tolerances to be followed, nor- mally by re f e rence to ACI 117. The inspector will establish a range of ac- c e p t a b i l i t y. Incompatible tolerances should be re f e r red to the design pro- fessional for re s o l u t i o n . Fabricating tolerances for rebar are tabulated by ACI 117, the ACI Detail- ing Manual, and the Concrete Rein- f o rcing Steel Institute (CRSI) Manual of Standard Practice. F a b r i c a t i n g shops do not have problems meeting the recommended tolerances. Ty p i- c a l l y, the tolerance for length of straight bars and out-to-out dimen- sion of bars with hooks or bends at one or both ends is 1 inch. Placing tolerances recognize the im- p recise nature of the placing opera- tion and allow deviation criteria. ACI 117 indicates bar placing tolerances including clear distance to forms and resulting concrete surfaces (varies with member size, 1 2 inch for mem- bers 12 to 24 inches), uniform spacing or positioning of bars in slabs or walls ( 3 inches), stirrup and tie spacing in beams and columns (one-twelfth beam depth or column width), loca- tion of bar bends and bar ends ( 2 inches, except 1 inch at discontinu- ous ends of members), length of lap splices (-1 1 2 inches), and embedded lengths (-1 inch for bar sizes from #3 to #11). Tolerances also are stated for beam and column form dimensions. Potential problems develop when tolerances of fabricated bars and form- work conflict. For example, in a 16x16- inch interior column with specified 1 1 2 inch cover to ties, the fabrication toler- ance on stirrup size is 1 2 inch and the form size tolerance is + 1 2 / - 3 8 inch. If the ties are + 1 2 and the forms are - 3 8, the concrete cover would be re d u c e d to 7 16 inch, which conflicts with pro v i- sion 2.2.2 of ACI 117 that permits only a 1 2-inch reduction in cover for this ex- ample. Conflicts like this are best re- solved with assistance from the de- signer and when discovered early. Inspection of bar placement in walls and slabs is usually straightforward . I ronworkers often shift rebar to avoid o b s t ructions, such as small openings, pipe sleeves, electrical outlets, and sim- ilar items. This usually is acceptable if the total number of bars is not re d u c e d . Consult Appendix C in CRSIs M a n u a l of Standard Practice to determine first bar spacing, if that information is not shown in the contract documents. In-place bending and rebending One of the more controversial con- s t ruction pro c e d u res is the practice of bending and rebending installed re- b a r. CRSIs EDR No. 12 can be used as a guide. When the contractor requests using planned prebent dowels or straight dowels, the engineer should accept the pro c e d u re and notify the inspec- t o r. The inspector should discuss the bending pro c e d u re for straight dow- els with the placing foreman to assure that the bends conform to ACI 315. W h e re large diameter bars are in- volved, some preheating may be re c- ommended by the designer to avoid brittle failure . Conclusions Mistakes can and will happen, but an inspector is expected to find them and have them corrected. A quality- c o n t rol program by the contractor helps reduce errors and makes final inspection easier. The inspector should p e rceive his job as supplementary to the workers in support of good con- s t ruction techniques and practice. References For further information on inspection, tolerances, industry s tandard prac- tices, placing, fabricating, welding, and mechanical connections, consult the following references: Standard Specifications for Tolerances for Concrete Construction and Materi- als (ACI 117-90), American Concrete Institute (ACI). ACI Detailing Manual1988, ACI. In- cludes Details of Concrete Reinforce- ment (ACI 315-80) (Revised 1986). Building Code Requirements for Rein- forced Concrete (ACI 318-89) (Revised 1992), ACI. Standard Specification for Deformed and Plain Billet-steel Bars for Concrete Reinforcement (A 615-92b), ASTM, Philadelphia. Standard Specification for Low-alloy Steel Deformed Bars for Concrete Re- inforcement (A 706-92b), ASTM. Standard Specification for Epoxy- coated Reinforcing Steel Bars (ASTM A 775-92), ASTM. Manual of Standard Practice, 25th ed., CRSI, 1990. Placing Reinforcing Bars, 6th ed., CRSI, 1992. Reinforcement: Anchorages, Lap Splices and Connections, 3rd ed., CRSI, 1990. Field Corrections to Rebars Partially Embedded in Concrete, Engineering Data Report No. 12, CRSI. Guidelines for Inspection and Accep- tance of Epoxy-coated Reinforcing Bars at the J ob Site, CRSI, 1986. Structural Welding CodeReinforcing Steel (ANSI/AWS D1.4-92), American Welding Society, Miami, 1992. Acknowledgment This article is adapted from CRSIs En- gineering Data Report No. 36, Field In- spection of Rebar. For a copy of the report, contact CRSI, 933 N. Plum Grove Rd., Schaumburg, IL 60173 (708-517-1200; fax: 708.517.1206). P U B L I C ATION #C930027 Copyright 1993, The Aberdeen Group All rights reserved