SUC CHALCO PLAZA VOLCANES PROPUESTA ECONOMICA FECHA: 25-Sep-13 PROGRAMA DE OBRA FECHA INTERVENCION 7/29/2013 PROGRAMA INICIAL 10.00 SEM % EJECUTADO 15.00% FECHA ACTUAL 9/23/2013 PROGRAMA ACTUAL 8.00 SEM % ACTUAL OBRA 40.00% FECHA S/LIBERACIONES 10/14/2013 * PROGRAMA S/LIBERAC 11.00 SEM * % S/LIBERACIONES 80.00% * FECHA TERMINO DESEADA 11/4/2013 PROGR FINAL DESEADO 13.00 SEM ** FECHA TERMINO PROPUESTA 11/18/2013 PROGR FINAL PROPUESTO 15.00 SEM *** RESUMEN PRESUPUESTO CONTROL DE ESTIMACIONES MONTOS % PROGR IMPORTE CONTRATADO 465,000.00 $ 100.00% 10 SEM COBRADO C/ANTICIPO 9/20/2013 181,000.00 $ 38.92% GASTO POR MCI 9/20/2013 276,166.92 $ 59.39% IMPORTE P/TERMINO DE OBRA ANALISIS: POR COBRAR CONTRATADO 284,000.00 $ 61.08% - ORDENES DE CAMBIO DIFERENCIA GASTO-COBRO 95,166.92 $ 20.47% **** - RETRASOS POR TERCEROS GASTO ADICIONAL P/TERMINO 142,000.00 $ 30.54% **** - SOBRECOSTO TOTAL: 521,166.92 $ 112.08% IMPORTE FINAL 702,166.92 $ 151.00% 11 SEM 8 SEM MCI MANTENIMIENTO CORPORATIVO, S.A. DE C.V. REMODELACION BBVA BANCOMER SUC CHALCO PLAZA VOLCANES PROPUESTA ECONOMICA FECHA: 25-Sep-13 NOTAS: (*) FECHA EN LA QUE SE TERMINAN LOS TRABAJOS QUE ESTAN DENTRO DE LOS ALCANCES DE MCI, A ESPERA DE LA LIBERACION DE LAS AREAS DE ATM Y BOVEDA, LA CUAL CUENTA CON FECHA INDEFINIDA POR PARTE DE BANCOMER Y LEND LEASE. (**) EN CASO DE QUE SE PROGRAMEN Y LIBEREN CON ANTICIPACION LOS PUNTOS MARCADOS EN EL PUNTO "(*)". LA FECHA DE ENTREGA SE RECORRERA 3 SEMANAS (04-NOV-13), PROGRAMANDO LA VISITA DE PRE-ENTREGA EL DIA 28/10/2013 (***) EN CASO DE QUE NO SE LIBEREN Y SE PROGRAMEN LA LIBERACION DE LAS AREAS DE CAJEROS Y BODEGA DESPUES DE LA FECHA 21-OCT-13, SE CONTEMPLARA UNA FECHA DE PRE-ENTREGA DEL 11-NOV-13 Y UNA FECHA DE ENTREGA DE 18-NOV-13 (****) COMPRENDE TRABAJOS EXTRAORDINARIOS (ORDENES DE CAMBIO), RETRASOS POR TERCEROS (CYVSA, GUNNEBO, RIVIERA, ENTRE OTROS) OCACIONANDO REPROGRAMACIONES, ADEMAS DE FALTA DE SUMINISTRO DE MATERIALES Y UN ERRONEO ANALISIS DE LA OBRA MCI MANTENIMIENTO CORPORATIVO, S.A. DE C.V. REMODELACION BBVA BANCOMER SUC CHALCO PLAZA VOLCANES PROPUESTA ECONOMICA FECHA: 25-Sep-13 PROGRAMACION PAGOS: IMPORTE ESTIMACION FINAL 521,166.92 $ 100.00% EST 07 9/27/2013 104,233.38 $ 20.00% EST 08 10/4/2013 104,233.38 $ 20.00% EST 09 10/11/2013 104,233.38 $ 20.00% EST 10 10/18/2013 78,175.04 $ 15.00% EST 11 10/25/2013 78,175.04 $ 15.00% EST 12 11/1/2013 52,116.69 $ 10.00% ------ 11/8/2013 IMPORTE ESTIMACION FINAL 521,166.92 $ 100.00% EST 07 9/27/2013 78,175.04 $ 15.00% EST 08 10/4/2013 78,175.04 $ 15.00% EST 09 10/11/2013 78,175.04 $ 15.00% EST 10 10/18/2013 78,175.04 $ 15.00% EST 11 10/25/2013 52,116.69 $ 10.00% EST 12 11/1/2013 52,116.69 $ 10.00% EST 13 11/8/2013 52,116.69 $ 10.00% EST 14 11/15/2013 52,116.69 $ 10.00% ------ 11/22/2013 (FONDO DE GARANTIA) (FONDO DE GARANTIA) MCI MANTENIMIENTO CORPORATIVO, S.A. DE C.V. REMODELACION BBVA BANCOMER SUC PROGRESO NACIONAL PROPUESTA ECONOMICA FECHA: 22-Sep-13 PERSONAL POR SEMANA SUELDO CANTIDAD IMPORTE SEMANA 23-SEP-13 A 29-SEP-13 RESIDENTE DE OBRA 3,500.00 $ 1.00 3,500.00 $ ENCARGADO SEGURIDAD 2,500.00 $ 1.00 2,500.00 $ ENCARGADO ELECTRICO 3,500.00 $ 1.00 3,500.00 $ CABO 3,200.00 $ 1.00 3,200.00 $ OF TABLAROQUERO 2,800.00 $ 4.00 11,200.00 $ OF PINTOR 2,500.00 $ 5.00 12,500.00 $ OF ELECTRICISTA 2,800.00 $ 4.00 11,200.00 $ AY LIMPIEZA FINA 1,500.00 $ 3.00 4,500.00 $ OF ALBAIL 2,700.00 $ 1.00 2,700.00 $ AYUDANTE 1,800.00 $ 20.00 36,000.00 $ TOTAL: 90,800.00 $ SEMANA 30-SEP-13 A 06-OCT-13 RESIDENTE DE OBRA 3,500.00 $ 1.00 3,500.00 $ ENCARGADO SEGURIDAD 2,500.00 $ 1.00 2,500.00 $ ENCARGADO ELECTRICO 3,500.00 $ 1.00 3,500.00 $ CABO 3,200.00 $ 1.00 3,200.00 $ OF TABLAROQUERO 2,800.00 $ 1.00 2,800.00 $ OF PINTOR 2,500.00 $ 4.00 10,000.00 $ OF ELECTRICISTA 2,800.00 $ 3.00 8,400.00 $ OF ALBAIL 2,700.00 $ 1.00 2,700.00 $ AY LIMPIEZA FINA 1,500.00 $ 2.00 3,000.00 $ AYUDANTE 1,800.00 $ 9.00 16,200.00 $ TOTAL: 55,800.00 $ SEMANA 30-SEP-13 A 06-OCT-13 RESIDENTE DE OBRA 3,500.00 $ 1.00 3,500.00 $ ENCARGADO SEGURIDAD 2,500.00 $ 1.00 2,500.00 $ MCI MANTENIMIENTO CORPORATIVO, S.A. DE C.V. REMODELACION BBVA BANCOMER SUC PROGRESO NACIONAL PROPUESTA ECONOMICA FECHA: 22-Sep-13 ENCARGADO ELECTRICO 3,500.00 $ 1.00 3,500.00 $ CABO 3,200.00 $ 1.00 3,200.00 $ OF TABLAROQUERO 2,800.00 $ 1.00 2,800.00 $ OF PINTOR 2,500.00 $ 2.00 5,000.00 $ OF ELECTRICISTA 2,800.00 $ 1.00 2,800.00 $ OF ALBAIL 2,700.00 $ 1.00 2,700.00 $ AY LIMPIEZA FINA 1,500.00 $ 1.00 1,500.00 $ AYUDANTE 1,800.00 $ 5.00 9,000.00 $ TOTAL: 36,500.00 $ MONTO PROX 3 SEMANAS 183,100.00 $