PRESENTATION ON

FLOW-SHOP SCHEDULING
SUBMITTED TO:
Dr. V.K. Pathak

SUBMITTED BY:
Akanksha Shukla
III C.S.E.
552/07
FLOWSHOP SCHEDULING

• In a general flowshop we may have,


n jobs each having m tasks T1i ,T2i ,…Tmi ,
where 1≤i≤n
• Task Tji is to be performed on processor Pj,
where 1≤j≤m.
• The time required to complete task Tji is tji .
FLOWSHOP SCHEDULING
A schedule for the n jobs is an
assignment of tasks to time intervals on
the processors.
• No processor may have more than one
task assigned to it in any time interval.
• For any job i the processing of tasks Tji,
j >1, will not be started until task Tj-1,i has
been completed.
FLOW SHOP SCHEDULING
Given: A set of jobs each having some
tasks to be performed.
Processors for each of the tasks.

Main Objective- To determine the order of


assigning the tasks to processors such that
the sum finishing time is minimal.
EXAMPLE
Two jobs have to be scheduled on three
processors. The task times are given in the
matrix below

2 0 T11 T12
[j]= 3 3 = T21 T22
5 2 T31 T32
Time 0 2 5 6 10 12

P1 T11

P2 T22 T21 T22

P3 T31 T32

Figure (a)

This is a preemptive schedule.


A preemptive schedule is the one which
allows the processing of a task to be
terminated before its completion.
Time 0 2 3 5 6 10 11
P1 T11

P2 T22 T21

P3 T32 T31

Figure (b)

This is a non-preemptive schedule.


A non-preemptive schedule is a schedule in
which the processing of a task on any
processor is not terminated until the task is
complete.
FINISH TIME OF JOBS
The finish time fi(S) of job i is the time at
which all tasks of job i have been
completed in schedule S.

In figure (a), f1(S)=10 and


f2(S)=12

In figure (b), f1(S)=11 and


f2(S)=5
OBJECTIVE FUNCTIONS
The Finish Time F(S) of a schedule S is
given by ;
F(S)=max{fi(S)}
where 1 ≤ i ≤ n.

The Mean Flow Time, MFT(S) is defined


to be:
MFT(S)=(Σfi(s))/n
where 1 ≤ i ≤ n
RELATED TERMS
• OFT: Optimal Finish Time schedule for a
given set of jobs is a non-preemptive
schedule S for which F(S) is minimum over
all non-preemptive schedules.
• POFT: Preemptive Optimal Finish Time
schedule for a given set of jobs is a
preemptive schedule S for which F(S) is
minimum over all preemptive schedules.
MORE RELATED TERMS
• OMFT: Optimal Mean Flow Time for a
given set of jobs is a non-preemptive
schedule S for which MFT(S) is minimum
over all non-preemptive schedules.
• POMFT: Preemptive Optimal Mean Flow
Time schedule for a given set of jobs is a
preemptive schedule S for which MFT(S)
is minimum over all preemptive schedules.
CONSTRAINT
The general problem of obtaining
schedules for m > 2 is computationally
difficult, dynamic programming leads to
an efficient algorithm to obtain OFT
(optimal finish time) schedules for the
case m=2(tasks=2).
ASSUMPTIONS
• t1i  ai, where t1i is time of task1 of job i
• t2i bi, where t2i is time of task2 of job i
• Case being considered,
ai≠0, 1 ≤ i ≤ n
• Special case,
If ai=0 , then
All jobs with ai≠0 are optimally scheduled and
then all jobs with ai=0 are simply added to it.
DERIVATION
Let σ1, σ2, σ3,…..σk be a permutation prefix
defining a schedule for jobs T1, T2, T3,…Tk.
f1time taken by T1, T2,…Tk on processor p1
f2time taken by T1, T2,…Tk on processor p2
Let t=f2-f1
DERIVATION
g(S,t)= length of an optimal schedule for
the subset of jobs S under the assumption
that p2 is not available until time t.

Thus, for S={1, 2,..n},


g(S,t)=g({1,2,..n},0)

g({1,2,…n},0)=min{ai+g({1,2,…n}-{i},bi)},
where 1≤i≤n
DERIVATION
• The task,T2i cannot be started until max{ai,t}.
Hence, f2-f1= bi+max{ai,t}-ai= bi+max{t-ai,0}

g(S,t)= min{ai+g(S-{i},bi+max{t-ai,0})} (1)


where i belongs to S
Now, let R be any schedule for a job subset
S. Let i and j be the first two jobs.
DERIVATION
• g(S,t)=ai+g(S-{i},bi+max{t-ai,0})
g(S,t)=ai+aj+g(S-{i,j},bj+max{bi+max{t-
ai,0}-aj,0}
(2)
Above equation can be simplified as,
tij=bj+max{bi+max{t-ai,0}-aj,0}
=bj+bi-aj+max{max{t-ai,0},aj-
bi}
=bj+bi-aj+max{t-ai,aj-bi,0}
tij=bj+bi-aj-ai+max{t,ai+aj-bi,ai}
DERIVATION
• If jobs i and j are interchanged in R, then
g’(S,t)=ai+aj+g(S-{i,j},tji) (3)

where tji=bj+bi-aj-ai+max{t,ai+aj-bj,aj}

max{t,ai+aj-bi,ai} ≤ max{t,ai+aj-bj,aj} (4)

comparing, eqns. (1)and(3) , if eqn. (4)


holds, then g(S,t) ≤ g’(S,t)
DERIVATION

For eqn. (4) to hold,


max{ai+aj-bi,ai} ≤ max{ai+aj-bj,aj}

or max{-bi,-aj} ≤ max{-bj,-ai}

or min{bi,aj} ≥ min{bj,ai} (5)


CONCLUSION
• There exists an optimal schedule in which for
every pair(i,j) of adjacent jobs,
min{bi,aj} ≥ min{bj,ai}, holds true.
• For making an optimal scedule,
If min{a1,a2, …an,b1,b2,…bn} is ai, then job i
should be the first job.
If min{a1,a2, …an,b1,b2, …bn} is bj, then job j
should be the last job.
• The above procedure helps positioning one of
the n jobs and we need to reapply the eqn.(5)
to position the remaining n-1 jobs.
SCHEDULING RULE
• Sort all the ai’s and bj’s into nondecreasing
order.
• If the next number in the sequence is aj
and job j hasn’t yet been scheduled,
schedule job j at the leftmost available
spot. If the next number is bj and job j
hasn’t yet been scheduled, schedule job j
at the rightmost available spot. If j has
already been scheduled go to the next
number in the sequence.
EXAMPLE
Let n=4
(a1,a2,a3,a4)=(3,4,8,10) and
(b1,b2,b3,b4)=(6,2,9,15)
Now sort all these tasks into nondecreasing
order:
(b2,a1,a2,b1,a3,b3,a4,b4)=(2,3,4,6,8,9,10,15)
Let σ1,σ2,σ3,σ4 be the optimal schedule.
Since the smallest number is b2, we set
σ4=2.
The next number is a1 and we set σ1=1.
The next number is a2 but job2 has already
been scheduled.
The next number is b1 but job1 has already
been scheduled.
The next is a3 and we set it to σ2.
This leaves σ3 free and job 4 unscheduled.
Thus σ3=4.
Time 0 3 9 11 20 21 25 36 38

P1 a1 a3 a4 a2

P2 b1 b3 b4 b2
TIME COMPLEXITY
• Solving eqn.(1), g(S,t)= min{ai+g(S-
{i},bi+max{t-ai,0})} directly for g({1,2,…
n},0) for the optimal schedule will take
Ώ(2n).
• The scheduling rule above can be
implemented to run in time 0(n log n).