Está en la página 1de 19

PEKERJAAN : JARINGAN DISTRIBUSI & GARDU DISTRIBUSI

LOKASI : PT.PLN (PERSERO) WIL. SUMATERA BARAT TERSEBAR


A. PEKERJAAN PEMBANGUNAN / PEMASANGAN BARU.
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
I. JARINGAN TEGANGAN MENENGAH :
1 Kons.JTM 3 Phasa A3C 240 mm2 KMS 1 96.000 7.500.000 7.596.000
MDU
1 Kawat JTM AAAC 240 mm2 Mtr 3105 PM
NON - MDU
1Join Sleeve 240 mm2 Bh 3 32.000 96.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 30,00 50.000 1.500.000
2 Tukang Listrik H/O 60,00 45.000 2.700.000
3 Pekerja H/O 60,00 35.000 2.100.000
4 Mandor H/O 30,00 40.000 1.200.000
Angkutan :
1 Angkutan Darat Ton/KM 319,75 - -
2 Kons. JTM 3 Phasa A3C 150 mm2 KMS 1 79.500 5.760.000 5.839.500
MDU
1 Kawat JTM AAAC 150 MM2 Mtr 3090 PM
NON - MDU
1Join Sleeve 150 mm2 Bh 3 26.500 79.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 24,00 50.000 1.200.000
2 Tukang Listrik H/O 45,00 45.000 2.025.000
3 Pekerja H/O 45,00 35.000 1.575.000
4 Mandor H/O 24,00 40.000 960.000
Angkutan :
1 Angkutan Darat Ton/KM 211,22 - -
3 Kons. JTM 3 Phasa A3C 70 mm2 KMS 1 58.500 4.020.000 4.078.500
MDU
1 Kawat JTM AAAC 70 mm2 Mtr 3075 PM
NON - MDU
1Join Sleeve 70 mm2 Bh 3 19.500 58.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 18,00 50.000 900.000
2 Tukang Listrik H/O 30,00 45.000 1.350.000
3 Pekerja H/O 30,00 35.000 1.050.000
4 Mandor H/O 18,00 40.000 720.000
Angkutan :
1 Angkutan Darat Ton/KM 101,23 - -
4 Kons.JTM 3 Phasa A3C 35 mm2 KMS 1 37.500 2.520.000 2.557.500
MDU
1 Kawat JTM AAAC 35 MM2 Mtr 3060 PM
NON - MDU
1Join Sleeve 35 mm2 Bh 3 12.500 37.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 12,00 50.000 600.000
2 Tukang Listrik H/O 18,00 45.000 810.000
3 Pekerja H/O 18,00 35.000 630.000
4 Mandor H/O 12,00 40.000 480.000
Angkutan :
1 Angkutan Darat Ton/KM 45,75 - -
5 Kons.Tiang Besi 9 Meter - 100 daN : Btg 1 107.000 99.750 206.750
MDU
1 Tiang Besi 9 Meter - 100 daN Btg 1 PM
NON-MDU
1 Cat u/Tiang,Goni & Aspal Set 1 49.100 49.100
2 Beton Manchet Bh 1 57.900 57.900
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 19,69 - -
6 Kons.Tiang Besi 11 Meter - 156 daN : Btg 1 110.150 87.750 197.900
MDU
1 Tiang Besi 11 Meter - 156 daN Btg 1 PM
NON-MDU
1 Cat u/Tiang,Goni & Aspal Set 1 52.250 52.250
2 Beton Manchet Bh 1 57.900 57.900
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 28,04 - -
DAFTAR ANALISA HARGA SATUAN
HARGA SATUAN JL. HARGA SATUAN
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
7 Kons.Tiang Besi 11 Meter - 200 daN : Btg 1 110.150 118.500 228.650
MDU
1 Tiang Besi 11 Meter - 200 daN Btg 1 PM
NON - MDU
1 Cat u/Tiang, Goni & Aspal Set 1 52.250 52.250
2 Beton Manchet Bh 1 57.900 57.900
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 34,02 - -
8 Kons.Tiang Besi 11 Meter - 300 daN : Btg 1 121.900 160.500 282.400
MDU
1 Tiang Besi 12 Meter - 350 daN Btg 1 PM
NON - MDU
1 Cat u/Tiang, Goni & Aspal Set 1 58.400 58.400
2 Beton Manchet Bh 1 63.500 63.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,80 45.000 81.000
3 Pekerja H/O 1,50 35.000 52.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan : -
1 Angkutan Darat Ton/KM 57,80 - -
9 Kons.Tiang Besi 12 Meter - 350 daN : Btg 1 121.900 174.000 295.900
MDU
1 Tiang Besi 14 Meter - 350 daN Btg 1 PM
NON - MDU
1 Cat u/Tiang, Goni & Aspal Set 1 58.400 58.400
2 Beton Manchet Bh 1 63.500 63.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 2,10 45.000 94.500
3 Pekerja H/O 1,50 35.000 52.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 101,12 - -
10 Konst.Verlingstuck (VS) dg UNP / TM 1- E pd T.Beton Btg 1 425.580 82.500 508.080
MDU
1 Pin Insulator 20 Kv Bh 3 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 1 126.700 126.700
2 UNP 100X50X6X2000 mm (Galv.) Bh 2 126.700 253.400
3 Bolt & Nut M 16X400 (Galv.) + Ring Bh 2 10.600 21.200
4 Bolt & Nut M 16X150 (Galv.) + Ring Bh 2 5.750 11.500
5 Aluminium Bending Wire 20 mm2 Mtr 4 3.550 12.780
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 5,45 - -
11 Konst.Verlingstuck (VS) dg UNP / TM 1- E pd T.Besi Btg 1 436.480 82.500 518.980
MDU
1 Pin Insulator 20 Kv Bh 3 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 1 126.700 126.700
2 UNP 100X50X6X2000 mm (Galv.) Bh 2 126.700 253.400
3 Bolt & Nut M 16X400 (Galv.) + Ring Bh 2 10.600 21.200
4 Band Steel Pole 4" komplit Bolt M 16X100 (Galv.) Set 2 11.200 22.400
5 Aluminium Bending Wire 20 mm2 Mtr 4 3.550 12.780
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 5,45 - -
12 Konst.Verlingstuck (VS) dg UNP / TM 2- E pd T.Beton Btg 1 656.710 94.500 751.210
MDU
1 Pin Insulator 20 Kv Bh 6 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2 126.700 253.400
2 UNP 100X50X6X2000 mm (Galv.) Bh 2 126.700 253.400
3 UNP 100X50X6X400 mm (Galv.) Bh 3 24.800 74.400
4 Aluminium Bending Wire 20 mm2 Mtr 7 3.550 25.560
5 Bolt & Nut M 16X150 (Galv.) + Ring Bh 5 5.750 28.750
6 Bolt & Nut M 16X400 (Galv.) + Ring Bh 2 10.600 21.200
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 9,07 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
13 Konst.Verlingstuck (VS) dg UNP / TM 2- E pd T.Besi Btg 1 657.910 94.500 752.410
MDU
1 Pin Insulator 20 Kv Bh 6 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2 126.700 253.400
2 UNP 100X50X6X2000 mm (Galv.) Bh 2 126.700 253.400
3 UNP 100X50X6X400 mm (Galv.) Bh 3 24.800 74.400
4 Aluminium Bending Wire 20 mm2 Mtr 7 3.550 25.560
5 Bolt & Nut M 16X150 (Galv.) + Ring Bh 5 5.750 28.750
6 Band Steel Pole 4" komplit Bolt M 16X100 (Galv.) Set 2 11.200 22.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 9,07 - -
14 Konst.Verlingstuck (VS) dg UNP / TM 5- E pd T.Besi Btg 1,00 726.740 101.250 827.990
MDU
1 Pin Insulator 20 Kv Bh 1,00 PM
2 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6,00
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2,00 126.700 253.400
2 UNP 100X50X6X2000 mm (Galv.) Bh 2,00 126.700 253.400
3 Tap Connegtor AL 150 - 240 mm2 tiga baut for AAAC Bh 6,00 28.580 171.480
4 Aluminium Bending Wire 20 mm2 Mtr 1,20 3.550 4.260
5 Bolt & Nut M 16X150 (Galv.) + Ring Bh 4,00 5.750 23.000
6 Bolt & Nut M 16X400 (Galv.) + Ring Bh 2,00 10.600 21.200
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,35 45.000 60.750
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 1,51 - -
15 Konst.Verlingstuck (VS) dg UNP / TM 10- E pd T.Besi Btg 1 727.940 101.250 829.190
MDU
1 Pin Insulator 20 Kv Bh 1 PM
2 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2 126.700 253.400
2 UNP 100X50X6X2000 mm (Galv.) Bh 2 126.700 253.400
3 Tap Connegtor AL 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
4 Aluminium Bending Wire 20 mm2 Mtr 1 3.550 4.260
5 Bolt & Nut M 16X150 (Galv.) + Ring Bh 4 5.750 23.000
6 Band Steel Pole 4" komplit Bolt M 16X100 (Galv.) Set 2 11.200 22.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,35 45.000 60.750
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 11,72 - -
16 Konst.Verlingstuck (VS) dg UNP / TM 10 - E pd T.Beton Btg 1 1.222.760 120.750 1.343.510
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
2 Post Insulator 20 KV Bh 2 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 6 126.700 760.200
2 Aluminium Bending Wire 20 mm2 Mtr 2 3.550 8.520
3 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
4 Double Arm Bolt & Nut M 14X300 + Washer (Galv) Bh 4 12.800 51.200
5 Arm Brace Besi L,40,40,4 (Galv.) Bh 8 17.350 138.800
6 Bolt & Nut M 16X50 + Washer (Galv.) Bh 8 3.400 27.200
7 Bolt & Nut M 16X400 (Galv,) u/Cross Arm & Brace Bh 2 10.600 21.200
8 Bolt Eye M 16X300 (Galv.) u/Down Guy Bh 2 10.580 21.160
9 Bolt & Nut M 16X150 + Washer (Galv.) Bh 4 5.750 23.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
17 Konst.Verlingstuck (VS) dng UNP / TM 10 - E pd T.Besi Btg 1 1.222.760 120.750 1.343.510
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
2 Post Insulator 20 KV Bh 2 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 6 126.700 760.200
2 Aluminium Bending Wire 20 mm2 Mtr 2 3.550 8.520
3 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
4 Double Arm Bolt & Nut M 14X300 + Washer (Galv) Bh 4 12.800 51.200
5 Arm Brace Besi L,40,40,4 (Galv.) Bh 8 17.350 138.800
6 Bolt & Nut M 16X50 + Washer (Galv.) Bh 8 3.400 27.200
7 Bolt & Nut M 16X400 (Galv,) u/Cross Arm & Brace Bh 2 10.600 21.200
8 Bolt Eye M 16X300 (Galv.) u/Down Guy Bh 2 10.580 21.160
9 Bolt & Nut M 16X150 + Washer (Galv.) Bh 4 5.750 23.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
18 Kons Tiang Penyangga pd T.Beton (TM-1) Unit 1 181.390 57.000 238.390
MDU
1 Post Insulator 20 KV Bh 3 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 1 126.700 126.700
2 Aluminium Bending Wire 20 mm2 Mtr 3,6 3.550 12.780
3 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 2 10.580 21.160
4 Arm Brace Besi L,40,40,4 (Galv.) Bh 1 17.350 17.350
5 Bolt & Nut M 16X50 + Washer (Galv.) Bh 1 3.400 3.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 4,54 - -
19 Kons Tiang Penyangga Ganda pd T.Beton (TM-2) Unit 1 223.300 75.750 299.050
MDU
1 Post Insulator 20 KV Bh 6 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 1 126.700 126.700
2 Aluminium Bending Wire 20 mm2 Mtr 3,6 3.550 12.780
3 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 4 10.580 42.320
4 Arm Brace Besi L,40,40,4 (Galv.) Bh 2 17.350 34.700
5 Bolt & Nut M 16X50 + Washer (Galv.) Bh 2 3.400 6.800
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,90 45.000 40.500
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 9,07 - -
20 Kons Tiang Tarik Awal Beton / Besi (TM-3) Unit 1 175.740 74.250 249.990
MDU
1 String Insulator 20KV lengkap Acc & Strain Clamp Set 3 PM
2 Post Insulator 20 KV Bh 1 PM
NON - MDU
1 Tap Connector 150 - 240 mm2 for AAAC u/3 Baut Bh 6 28.580 171.480
2 Alumunium Bending Wire 20 mm2 Mtr 1,2 3.550 4.260
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 6,62 - -
21 Konstruksi Tiang Akhir T.Beton (TM-4) Unit 1 889.960 74.250 964.210
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 3 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 6 126.700 760.200
2 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 2 12.800 25.600
3 Arm Brace Besi L,40,40,4 (Galv.) Bh 4 17.350 69.400
4 Bolt & Nut M 16X50 + Washed (Galv.) Bh 4 3.400 13.600
5 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 2 10.580 21.160
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 5,10 - -
22 Konstruksi Tiang Tarik Ganda T.Beton (TM-5) Unit 1 558.900 95.250 654.150
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
2 Post Insulator 20 KV Bh 1
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2 126.700 253.400
2 Aluminium Bending Wire 20 mm2 Mtr 1,2 3.550 4.260
3 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
4 Double Arm Bolt & Nut M 14X300 + Washer (Galv) Bh 2 12.800 25.600
5 Arm Brace Besi L,40,40,4 (Galv.) Bh 4 17.350 69.400
6 Bolt & Nut M 16X50 + Washer (Galv.) Bh 4 3.400 13.600
7 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 2 10.580 21.160
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 11,72 - -
23 Konstruksi T Pencabangan pd T Beton (TM-6) Unit 1 666.940 106.500 773.440
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 3 PM
2 Post Insulator 20 KV Bh 4
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 3 126.700 380.100
2 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 3 28.580 85.740
3 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 3 12.800 38.400
4 Arm Brace Besi L,40,40,4 (Galv.) Bh 6 17.350 104.100
5 Bolt & Nut M 16X50 + Washed (Galv.) Bh 6 3.400 20.400
6 Bolt & Nut M 16X300 (Galv.) u/Arm Brace Bh 2 10.580 21.160
7 Allumunium Bending Wire 20 mm2 Mtr 4,8 3.550 17.040
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,45 40.000 18.000
Angkutan :
1 Angkutan Darat Ton/KM 8,13 - -
24 Konst T Pencab pd penyangga ganda T Beton (TM-6A) Unit 1 4.921.100 126.750 5.047.850
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 3 PM
2 Post Insulator 20 KV Bh 7
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 4 332.350 1.329.400
2 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 3 29.700 89.100
3 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 3 40.500 121.500
4 Arm Brace Besi L,40,40,4 (Galv.) Bh 8 24.250 194.000
5 Bolt & Nut M 16X50 + Washed (Galv.) Bh 8 353.350 2.826.800
6 Bolt & Nut M 16X300 (Galv.) u/Arm Brace Bh 5 1.500 7.500
7 Allumunium Bending Wire 20 mm2 Mtr 8,4 42.000 352.800
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,45 40.000 18.000
Angkutan :
1 Angkutan Darat Ton/KM 8,13 - -
25 Konstruksi pd Tiang Existing T.Beton (TM-7) Unit 1 475.380 76.500 551.880
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 3 PM
2 Post Insulator 20 KV Bh 1
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2 126.700 253.400
2 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 3 28.580 85.740
3 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 3 12.800 38.400
4 Arm Brace Besi L,40,40,4 (Galv.) Bh 4 17.350 69.400
5 Bolt & Nut M 16X50 + Washed (Galv.) Bh 4 3.400 13.600
6 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 1 10.580 10.580
7 Allumunium Bending Wire 20 mm2 Mtr 1,2 3.550 4.260
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 8,13 - -
26 Konstruksi Pencab T Sudut pd Existing T.Beton (TM-8) Unit 1 479.640 76.500 556.140
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 3 PM
2 Post Insulator 250 KV Bh 2
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv.) Bh 2 126.700 253400
2 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 3 28.580 85740
3 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 3 12.800 38400
4 Arm Brace Besi L,40,40,4 (Galv.) Bh 4 17.350 69400
5 Bolt & Nut M 16X300 + Washer (Gal.) Bh 1 10.580 10580
6 Bolt & Nut M 16X50 (Galv.) + Washer (Galv.) Bh 4 3.400 13600
7 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8520

Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 11,15 - -
27 Kons Tiang Penyangga Side Arm pd T.Beton (TM-9) Unit 1 202.140 57.000 259.140
MDU
1 Post Insulator 20 KV Bh 3 PM
NON - MDU
1 Crossarm UNP 100X50X6X2000 mm (Galv.) Bh 1 126.700 126.700
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 2 17.350 34.700
3 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 2 10.580 21.160
4 Bolt & Nut M 16X50 + Washed (Galv.) Bh 2 3.400 6.800
5 Allumunium Bending Wire 20 mm2 Mtr 3,6 3.550 12.780
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 4,54 - -
28 Kons Tiang Belokan / sudut pd T.Beton (TM-10) Unit 1 950.760 125.250 1.076.010
MDU
1 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
2 Post Insulator 250 KV Bh 2 PM
NON - MDU
1 Crossarm UNP 100X50X6X200 mm (Galv.) Bh 4 126.700 506.800
2 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
3 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
4 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 6 12.800 76.800
5 Arm Brace Besi L,40,40,4 (Galv.) Bh 8 17.350 138.800
6 Bolt & Nut M 16X50 (Galv.) + Washer (Galv.) Bh 8 3.400 27.200
7 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 2 10.580 21.160

Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,35 45.000 60.750
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,45 40.000 18.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
29 Konstruksi Tiang Opstijg Cable pd T.Beton (TM-11) Unit 1 5.335.320 615.000 5.950.320
MDU
1 Terminating Outdoor XLPE 3x240 mm2 Set 1 2.480.000 2.480.000
2 Lighting Arrester 24 KV , 10 ka Bh 3 520.000 1.560.000
NON - MDU
1 Crossarm UNP 100X50X6X2000 mm (Galv.) Bh 1 126.700 126.700
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 2 17.350 34.700
3 Bolt & Nut M 16X50 (Galv.) + Washer (Galv) Bh 2 3.400 6.800
4 Bolt & Nut M 16X300 (Galv.) + Washer (Galv) Bh 1 10.580 10.580
5 Band Pole for Arm Brace (Galv) Bh 1 13.300 13.300
6 Copper Conductor 25 mm2 u/Jumper Mtr 6 7.200 43.200
7 Pipa Galvanized 4" x 6 meter + klem Pipa & Klem Kabel Btg 1 332.350 332.350
8 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 3 28.580 85.740
9 Tap Connector AL/CU 25-20 /150-240 mm2 u/Jumper Bh 3 36.800 110.400
10 Kabel Schoon AL 150 - 240 mm2 Bh 6 29.700 178.200
11 Grounding Tegangan menengah (GTM) Set 1 353.350 353.350
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 6,00 45.000 270.000
3 Pekerja H/O 6,00 35.000 210.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 4,54 - -
30 SKTM 20 KV 3x240 mm2 Type XLPE 8.460.000 8.550.000 17.010.000
MDU
1 Ground Kabel 20 KV 3x240 mm2 type XLPE KMS 1 PM
NON - MDU
1 Batu Bata Bh 10.000 360 3.600.000
2 Pasir Urug M3 120 40.500 4.860.000
3 Tanah Urug M3
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 15,00 50.000 750.000
2 Tukang Listrik H/O 30,00 45.000 1.350.000
3 Pekerja H/O 150,00 35.000 5.250.000
4 Mandor H/O 30,00 40.000 1.200.000
Angkutan :
1 Angkutan Darat Ton/KM 2,95 - -
31 UGC 20 KV 3x(1x240) mm2 Type XLPE 1 Saluran 8.460.000 9.030.000 17.490.000
MDU
1 Ground Kabel 20 KV 3x150 mm2 type XLPE KMS 3 PM
NON - MDU
1 Batu Bata Bh 10.000 360 3.600.000
2 Pasir Urug M3 120 40.500 4.860.000
3 Tanah Urug M3
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 15,00 50.000 750.000
2 Tukang Listrik H/O 36,00 45.000 1.620.000
3 Pekerja H/O 156,00 35.000 5.460.000
4 Mandor H/O 30,00 40.000 1.200.000
Angkutan :
1 Angkutan Darat Ton/KM 1,84 - -
32 Pemasangan Centre Bracket u/TM - 1 Unit 1 59.920 37.500 97.420
MDU
1 Post Insulator 20 KV Bh 1 PM
NON - MDU
1 Centre Bracket Bh 1 34.500 34.500
2 Allumunium Bending Wire 20 mm2 Mtr 1,2 3.550 4.260
3 Bolt & Nut M 16x300 (Galv.) Bh 2 10.580 21.160
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,15 40.000 6.000
Angkutan :
1 Angkutan Darat Ton/KM 1,75 - -
33 Pemasangan Centre Bracket u/TM -2 Unit 1 98.680 44.250 142.930
MDU
1 Post Insulator 20 KV Bh 2 PM
NON - MDU
1 Centre Bracket Bh 2 34.500 69.000
2 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
3 Bolt & Nut M 16x300 (Galv.) Bh 2 10.580 21.160
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,45 45.000 20.250
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,15 40.000 6.000
Angkutan :
1 Angkutan Darat Ton/KM 3,50 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
34 Kons Portal / Single - Arm 2 T.Beton (TM-16) Unit 1 575.960 102.000 677.960
MDU
1 Post Insulator 20 KV Bh 2 PM
2 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
NON-MDU
1 Crossarm UNP 100X50X6X2000 mm (Galv.) Bh 2 126.700 253.400
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 4 17.350 69.400
3 Bolt & Nut M 16X300 (Galv.) u/Cross Arm & Brace Bh 2 10.580 21.160
4 Bolt & Nut M 16X50 + Washed (Galv.) Bh 4 3.400 13.600
5 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
6 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
7 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 3 12.800 38.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
35 Kons Portal / Double - Arm T.Beton (TM-16A) Unit 1 971.920 102.000 1.073.920
MDU
1 Post Insulator 20 KV Bh 2 PM
2 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
NON-MDU
1 Crossarm UNP 100X50X6X200 mm (Galv.) Bh 4 126.700 506.800
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 8 17.350 138.800
3 Bolt & Nut M 16x50 + Washer (Galv.) Bh 8 3.400 27.200
4 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
5 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
6 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 6 12.800 76.800
7 Bolt & Nut M 16x300 (Galv.) u/Brace Bh 4 10.580 42.320

Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
36 Grounding / Pentanahan T.Beton / Besi (GTM) Unit 1 352.350 85.500 437.850
NON-MDU
1 Copper Conductor 50 mm2 Mtr 10 18.900 189.000
2 Pipa Galvanis 3/4" - 3 meter Btg 1 48.100 48.100
3 Copper Clad (Grounding Rod) 5/8"x8 F With Clamp Bh 1 56.350 56.350
4 Tap Connector AL/CU 50 mm2 Bh 1 36.800 36.800
5 Stainless Stell Strip Mtr 4,5 2.800 12.600
6 Stoping Buckle (Yoke for Stainless Stell Strip) Bh 5 1.500 7.500
7 Link Bh 2 1.000 2.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,02 - -
37 Down Guy / Trekschoor Komplit T.Beton (E-1) Unit 1 317.600 78.000 395.600
NON-MDU
1 Guy Insulator (u/TM) Bh 1 24.250 24.250
2 Turn Buckle / Spanscroef 5/8 " Bh 1 24.150 24.150
3 Anchor Rod 5/8" x 2400 MM (Galv.) + Beton Blok Komplit Set 1 38.950 38.950
4 Bridle for Heavy Guy Wire Set 1 -
5 Staal Drad Clamp 70 mm2 Bh 8 10.490 83.920
6 Band Pole for Bridle Bh 1 -
7 Kaos Baja / Guy Wire Thimble Bh 1 2.550 2.550
8 Galvanized Steel Wire ( Stall Draad) 70 mm2 Mtr 14 10.270 143.780

Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,47 - -
38 Span Guy / Kontramast Komplit T.Beton (E-2) Unit 1 552.690 91.500 644.190
NON-MDU
1 Guy Insulator (u/TM) Bh 1 24.250 24.250
2 Bridle for Heavy Guy Wire Bh 2 -
3 Turn Buckle / Spanscroef 5/8 " Bh 1 24.150 24.150
4 Anchor Rod 5/8" x 2400 MM (Galv.) + Beton Blok Komplit Set 1 38.950 38.950
5 Staal Drad Clamp 70 mm2 Bh 12 10.490 125.880
6 Band Pole for Bridle u/Tiang Beton Bh 2 -
7 Kaos Baja / Guy Wire Thimble Bh 4 2.550 10.200
8 Galvanized Steel Wire ( Stall Draad) 70 mm2 Mtr 30 10.270 308.100
9 Eye Bolt & Nut M 16 x 300 + Washer Bh 2 10.580 21.160
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,90 45.000 40.500
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,95 -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
39 Strut Pole / Drukschoor Komplit T.Beton (E-3) Unit 1 231.520 118.500 350.020
MDU
1 Tiang Besi 11 Meter - 200 daN Btg 1 PM
NON-MDU
1 Strut Support / UNP (Galv) Set 1 21.480 21.480
2 Strut Band / Klem Beugle (Galv) Set 1 16.790 16.790
3 Pipa Galvanized 2,5" - 2 mtr Btg 1 91.100 91.100
4 Plat Beton Bertulang 1:2:3 0 500 x 500mm Bh 1 28.750 28.750
5 Band Pole 3 Lobang + Bolt & Nut (Galv) Bh 4 15.250 61.000
6 Band Pole 2 Lobang + Bolt & Nut (Galv) Bh 1 12.400 12.400
7 Cat u/Tiang, Goni & Aspal Set 1 - -
8 Beton Manchet Bh 1 - -
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
40 Konstruksi Tiang Penyangga pd T.Besi (TM-1) Unit 1 184.730 57.000 241.730
MDU
1 Post Insulator 20 KV Bh 3 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 1 126.700 126.700
2 Allumunium Bending Wire 20 mm2 Mtr 3,6 3.550 12.780
3 Band Pole for Arm Brace (Galv) Set 1 13.300 13.300
4 Arm Brace Besi L.40,40,4 (Galv) Bh 1 17.350 17.350
5 Bolt & Nut M 16x50 + Washer (Galv) Bh 1 3.400 3.400
6 Klem Beugel + Bolt & Nut (Galv) Set 1 11.200 11.200
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 4,54 - -
41 Konst T Penyangga Ganda pd T.Besi (TM-2) Unit 1 384.960 75.750 460.710
MDU
1 Post Insulator 20 KV Bh 6 PM
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 2 126.700 253.400
2 Allumunium Bending Wire 20 mm2 Mtr 7,2 3.550 25.560
3 Double Arm Bolt & Nut M 14X300 + Washer (Galv.) Bh 4 12.800 51.200
4 Arm Brace Besi L.40,40,4 (Galv) Bh 2 17.350 34.700
5 Bolt & Nut M 16x50 + Washer (Galv) Bh 2 3.400 6.800
6 Band Pole for Arm Brace (Galv) Set 1 13.300 13.300
7 Adaptor UNP 80,45,5,300 (Galv) Set 0 22.500 -
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,90 45.000 40.500
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 9,07 - -
42 Konst T Tarik Awal pd T.Besi (TM-3) Unit 1 76.200 74.250 150.450
MDU
1 String Insulator 20 KV Set 3 PM -
2 Post Insulator 20 KV Set 1 PM -
NON - MDU
1 Tap Connector 150-240 mm2 for AAAC Bh 6 - -
2 Allumunium Bending Wire 20 mm2 Mtr 1,2 63.500 76.200
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 5,10 - -
43 Konstruksi Tiang Tarik Akhir pd T.Besi (TM-4) Unit 1 498.500 74.250 572.750
MDU
1 String Insulator 20 KV Set 6 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 2 - -
2 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 4 57.900 231.600
3 Arm Brace Besi L.40,40,4 (Galv) Bh 4 52.250 209.000
4 Bolt & Nut M 16x50 + Washer (Galv) Bh 4 - -
5 Band Pole for Arm Brace (Galv) Set 1 57.900 57.900
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 11,72 - -
44 Konstruksi Tiang Tarik Ganda T.Besi (TM-5) Unit 1 576.640 95.250 671.890
MDU
1 String Insulator 20 KV Set 6 PM -
2 Post Insulator 20 KV Bh 1 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 2 126.700 253.400
2 Allumunium Bending Wire 20 mm2 Mtr 1,2 3.550 4.260
3 Tap Connector 150-240 mm2 for AAAC Bh 6 28.580 171.480
4 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 4 12.800 51.200
5 Arm Brace Besi L.40,40,4 (Galv) Bh 4 17.350 69.400
6 Bolt & Nut M 16x50 + Washer (Galv) Bh 4 3.400 13.600
7 Band Pole for Arm Brace (Galv) Set 1 13.300 13.300
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 11,72 - -
45 Konst T Pencabangan pd T.Besi (TM-6) Unit 1 716.880 106.500 823.380
MDU
1 String Insulator 20 KV Set 3 PM -
2 Post Insulator 20 KV Bh 4 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 3 126.700 380.100
2 Tap Connector 150-240 mm2 for AAAC Bh 3 28.580 85.740
3 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 4 12.800 51.200
4 Arm Brace Besi L.40,40,4 (Galv) Bh 6 17.350 104.100
5 Bolt & Nut M 16x50 + Washer (Galv) Bh 6 3.400 20.400
6 Allumunium Bending Wire 20 mm2 Mtr 4,8 3.550 17.040
7 Klem Beugel + Bolt & Nut (Galv) Set 1 13.300 13.300
8 Band Pole for Arm Brace (Galv) Set 2 22.500 45.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,05 45.000 47.250
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,45 40.000 18.000
Angkutan :
1 Angkutan Darat Ton/KM 8,13 - -
46 Konst T Pencab pd penyangga ganda T.Besi (TM-6A) Unit 1 5.194.000 126.750 5.320.750
MDU
1 String Insulator 20 KV Set 3 PM -
2 Post Insulator 20 KV Bh 7 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 4 332.350 1.329.400
2 Tap Connector 150-240 mm2 for AAAC Bh 3 29.700 89.100
3 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 8 40.500 324.000
4 Arm Brace Besi L.40,40,4 (Galv) Bh 8 24.250 194.000
5 Bolt & Nut M 16x50 + Washer (Galv) Bh 8 353.350 2.826.800
6 Allumunium Bending Wire 20 mm2 Mtr 8,4 42.000 352.800
7 Band Pole for Arm Brace (Galv) Set 2 38.950 77.900
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,75 35.000 26.250
4 Mandor H/O 0,45 40.000 18.000
Angkutan :
1 Angkutan Darat Ton/KM 8,13 - -
47 Konst Percab. pd T Existing T.Besi (TM-7) Unit 1 576.640 76.500 653.140
MDU
1 String Insulator 20 KV Set 3 PM -
2 Post Insulator 20 KV Bh 1 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 2 126.700 253.400
2 Tap Connector 150-240 mm2 for AAAC Bh 6 28.580 171.480
3 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 4 12.800 51.200
4 Arm Brace Besi L.40,40,4 (Galv) Bh 4 17.350 69.400
5 Bolt & Nut M 16x50 + Washer (Galv) Bh 4 3.400 13.600
6 Allumunium Bending Wire 20 mm2 Mtr 1,2 3.550 4.260
7 Band Pole for Arm Brace (Galv) Set 1 13.300 13.300
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 6,62 - -
48 Konstruksi Percab T Sudut pd Existing T.Besi (TM-8) Unit 1 495.160 76.500 571.660
MDU
1 String Insulator 20 KV Set 3 PM -
2 Post Insulator 20 KV Bh 2 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 2 126.700 253.400
2 Tap Connector 150-240 mm2 for AAAC Bh 3 28.580 85.740
3 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 4 12.800 51.200
4 Arm Brace Besi L.40,40,4 (Galv) Bh 4 17.350 69.400
5 Bolt & Nut M 16x50 + Washer (Galv) Bh 4 3.400 13.600
6 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
7 Band Pole for Arm Brace (Galv) Set 1 13.300 13.300
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,75 45.000 33.750
3 Pekerja H/O 0,45 35.000 15.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 11,15 - -
49 Kons Tiang Penyangga Side Arm pd T.Besi (TM-9) Unit 1 249.980 57.000 306.980
MDU
1 Post Insulator 20 KV Bh 3 PM
NON - MDU
1 Crossarm UNP 100X50X6X2000 mm (Galv.) Bh 1 126.700 126.700
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 2 17.350 34.700
3 Klem Beugel + Bolt & Nut (Galv) Set 2 - -
4 Bolt & Nut M 16X50 + Washed (Galv.) Bh 2 3.400 6.800
5 Allumunium Bending Wire 20 mm2 Mtr 3,6 3.550 12.780
6 Band Pole for Arm Brace (Galv) Set 2 34.500 69.000
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 4,54 - -
50 Konstruksi T. Belokan / Sudut T. Besi (TM-10) Unit 1 981.800 125.250 1.107.050
MDU
1 String Insulator 20 KV Set 6 PM -
2 Post Insulator 20 KV Bh 2 PM -
NON - MDU
1 Crossarm UNP 100x50x6x2000 mm (Galv) Bh 4 126.700 506.800
2 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
3 Tap Connector 150-240 mm2 for AAAC Bh 6 28.580 171.480
4 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 8 12.800 102.400
5 Arm Brace Besi L.40,40,4 (Galv) Bh 8 17.350 138.800
6 Bolt & Nut M 16x50 + Washer (Galv) Bh 8 3.400 27.200
7 Band Pole for Arm Brace (Galv) Set 2 13.300 26.600
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,35 45.000 60.750
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,45 40.000 18.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
51 Konstruksi Tiang Opstijg Cable pd T.Besi (TM-11) Unit 1 5.335.940 615.000 5.950.940
MDU
1 Terminating Outdoor XLPE 3x240 mm2 Set 1 2.480.000 2.480.000
2 Lighting Arrester 24 KV , 10 ka Bh 3 520.000 1.560.000
NON - MDU
1 Crossarm UNP 100X50X6X2000 mm (Galv.) Bh 1 126.700 126.700
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 2 17.350 34.700
3 Bolt & Nut M 16X50 (Galv.) + Washer (Galv) Bh 2 3.400 6.800
4 Klem Beugel + Bolt & Nut (Galv) Bh 1 11.200 11.200
5 Band Pole for Arm Brace (Galv) Bh 1 13.300 13.300
6 Copper Conductor 25 mm2 u/Jumper Mtr 6 7.200 43.200
7 Pipa Galvanized 4" x 6 meter + klem Pipa & Klem Kabel Btg 1 332.350 332.350
8 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 3 28.580 85.740
9 Tap Connector AL/CU 25-20 /150-240 mm2 u/Jumper Bh 3 36.800 110.400
10 Kabel Schoon AL 150 - 240 mm2 Bh 6 29.700 178.200
11 Grounding Tegangan menengah (GTM) Set 1 353.350 353.350
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 6,00 45.000 270.000
3 Pekerja H/O 6,00 35.000 210.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 4,54 - -
52 Kons Portal / Single - Arm 2 T.Besi (TM-16) Unit 1 607.000 102.000 709.000
MDU
1 Post Insulator 20 KV Bh 2 PM
2 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
NON-MDU
1 Crossarm UNP 100X50X6X200 mm (Galv.) Bh 2 126.700 253.400
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 4 17.350 69.400
3 Band Pole for Arm Brace (Galv) Set 2 13.300 26.600
4 Bolt & Nut M 16X50 + Washed (Galv.) Bh 4 3.400 13.600
5 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
6 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
7 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 5 12.800 64.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
53 Kons Portal / Double - Arm T.Besi (TM-16A) Unit 1 1.034.000 90.000 1.124.000
MDU
1 Post Insulator 20 KV Bh 2 PM
2 String Insulator 20 KV lengkap Acc & Strain Clamp Set 6 PM
NON-MDU
1 Crossarm UNP 100X50X6X200 mm (Galv.) Bh 4 126.700 506.800
2 Arm Brace Besi L,40,40,4 (Galv.) Bh 8 17.350 138.800
3 Bolt & Nut M 16x50 + Washer (Galv.) Bh 8 3.400 27.200
4 Tap Connector 150 - 240 mm2 tiga baut for AAAC Bh 6 28.580 171.480
5 Allumunium Bending Wire 20 mm2 Mtr 2,4 3.550 8.520
6 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 10 12.800 128.000
7 Band pole for Arm Brace (Galv.) Set 4 13.300 53.200
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 1,20 45.000 54.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 13,23 - -
54 Down Guy / Trekschoor Komplit T.Besi (E-1) Unit 1 317.600 78.000 395.600
NON-MDU
1 Guy Insulator (u/TM) Bh 1 24.250 24.250
2 Turn Buckle / Spanscroef 5/8 " Bh 1 24.150 24.150
3 Anchor Rod 5/8" x 2400 MM (Galv.) + Beton Blok Komplit Set 1 38.950 38.950
4 Bridle for Heavy Guy Wire Bh 0 -
5 Staal Drad Clamp 70 mm2 Bh 8 10.490 83.920
6 Kaos Baja / Guy Wire Thimble Bh 1 2.550 2.550
7 Galvanized Steel Wire ( Stall Draad) 70 mm2 Mtr 14 10.270 143.780
8 Band Pole for Bridle u/Tiang Besi Bh 1 -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,950 - -
55 Span Guy / Kontramast Komplit T.Besi (E-2) Unit 1 531.530 91.500 623.030
NON-MDU
1 Guy Insulator (u/TM) Bh 1 24.250 24.250
2 Bridle for Heavy Guy Wire Bh 0 -
3 Turn Buckle / Spanscroef 5/8 " Bh 1 24.150 24.150
4 Anchor Rod 5/8" x 2400 MM (Galv.) + Beton Blok Komplit Set 1 38.950 38.950
5 Staal Drad Clamp 70 mm2 Bh 12 10.490 125.880
6 Band Pole for Bridle u/Tiang Besi Bh 2 -
7 Kaos Baja / Guy Wire Thimble Bh 4 2.550 10.200
8 Galvanized Steel Wire ( Stall Draad) 70 mm2 Mtr 30 10.270 308.100
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,90 45.000 40.500
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,95 - -
56 Strut Pole / Drukschoor Komplit T.Besi (E-3) Unit 1 231.520 118.500 350.020
MDU
1 Tiang Besi 11 Meter - 200 daN Btg 1 PM
NON-MDU
1 Strut Support / UNP (Galv) Set 1 21.480 21.480
2 Strut Band / Klem Beugle (Galv) Set 1 16.790 16.790
3 Pipa Galvanized 2,5" - 2 mtr Btg 1 91.100 91.100
4 Plat Beton Bertulang 1:2:3 0 500 x 500mm Bh 1 28.750 28.750
5 Band Pole 3 Lobang + Bolt & Nut (Galv) Bh 4 15.250 61.000
6 Band Pole 2 Lobang + Bolt & Nut (Galv) Bh 1 12.400 12.400
7 Cat u/Tiang, Goni & Aspal Set 1 - -
8 Beton Manchet Bh 1 - -
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 1,50 45.000 67.500
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
II. GARDU DISTRIBUSI :
1 Pemasangan Trafo Tiang Konstruksi Satu Tiang Unit 1 7.243.750 990.000 8.233.750
3 Phasa 25/50 lengkap dengan LS.Board (GD-3)
MDU
1. Transformator 3 Phasa 20 KV. 220 V - 25/50 KVA Bh 1 - -
2. Cut Out 20 KV Bh 3 - -
3. Fuse Link 2 Amp. Bh 3 - -
4. Lightning Arrester 20 KV Bh 3 - -
NON-MDU
1 Crossarm UNP 100X50X6X2000 mm u/Dudukan LA & CO. Bh 2 126.700 253.400
2 Crossarm UNP 80X50X6X800 mm u/Dudukan LS.Board Bh 2 64.500 129.000
3 Klem Beugel 6" + Bolt & Nut (Galv) Bh 2 27.850 55.700
4 LS.Board 2 Jurusan Konst Satu Tiang (Hefboom 200 A) Set 1 -
5 Arm Brace Besi L,40,40,4 (Galv.) Bh 2 17.350 34.700
6 Double Arm Bolt & Nut M 14x300 + Washer (Galv.) Bh 4 12.800 51.200
7 Bolt & Nut M 16X50 (Galv.) + Washer (Galv) Bh 2 3.400 6.800
8 Band pole for Arm Brace (Galv.) Set 1 13.300 13.300
9 Klem Double / Band Pole u/Pipa + Bolt & Nut Galv. Set 6 25.500 153.000
10 Kabel Schoen CU 25 - 50 mm2 Bh 16 7.500 120.000
11 Konst Dudukan Trafo Satu Tiang (Galv) Set 1 665.000 665.000
12 Pondasi Tiang Set 1 140.000 140.000
13 Grounding Arrester & Accessories (GTM) Set 1 353.350 353.350
14 Grounding Body Trafo & Accessories Set 1 315.550 315.550
15 Grounding Neutral & Accessories (GTR) Set 1 315.550 315.550
16 Pipa Galvanized 2,5" - 6 Mtr Btg 3 267.500 802.500
17 Boch 2,5" Galv. Bh 9 9.500 85.500
18 BC 25 mm2 u/Aftak Trafo Mtr 6 7.200 43.200
19 Tap Conector AL/CU 25-35 / 25-70 mm2 Bh 3 14.500 43.500
20 Plat Tanda Bahaya Bh 1 22.500 22.500
21 Kabel NYY 1x50 mm2 Mtr 40 91.000 3.640.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 12,00 45.000 540.000
3 Pekerja H/O 9,00 35.000 315.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 67,450 - -
2 Pemasangan Trafo Tiang Konstruksi Dua Tiang Unit 1 10.774.350 1.230.000 12.004.350
3 Phasa 100/160 lengkap dengan LS.Board
MDU
1. Transformator 3 Phasa 20 KV. 220 V - 100/160 KVA Bh 1 PM -
2. Cut Out 20 KV Bh 3 PM -
3. Fuse Link 2 Amp. Bh 3 PM -
4. Lightning Arrester 20 KV Bh 3 PM -
NON-MDU
1 Crossarm UNP 100X50X6X2200 mm u/Dudukan LA & CO. Bh 2 158.700 317.400
2 Crossarm UNP 80X50X6X2200 mm u/Dudukan LS.Board Bh 2 158.700 317.400
3 Klem Beugel 6" + Bolt & Nut (Galv) Bh 4 27.850 111.400
4 LS.Board 4 Jurusan Konst Dua Tiang (Hefboom 630 A) Set 1 -
5 Double Arm Bolt & Nut M 16x300 + Washer (Galv.) Bh 5 12.800 64.000
6 Klem Double / Band Pole u/Pipa + Bolt & Nut Galv. Set 6 25.500 153.000
7 Kabel Schoen CU 25 - 35 mm2 Bh 6 7.500 45.000
8 Kabel Schoen CU 50 - 70 mm2 Bh 15 7.500 112.500
9 Kabel Schoen CU 120 - 150 mm2 Set 8 25.500 204.000
10 Kabel Schoen AL/CU 70 mm2 Bh 3 16.000 48.000
11 Konst Dudukan Trafo Dua Tiang (Galv) Set 1 1.675.000 1.675.000
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
12 Pondasi Tiang Set 1 265.000 265.000
13 Grounding Arrester & Accessories (GTM) Set 1 353.350 353.350
14 Grounding Body Trafo & Accessories Set 1 315.550 315.550
15 Grounding Neutral & Accessories (GTR) Set 1 315.550 315.550
16 Pipa Galvanized 3" - 6 Mtr Btg 3 267.500 802.500
17 Boch 3" Galv. Bh 9 9.500 85.500
18 BC 25 mm2 u/Aftak Trafo Mtr 6 7.200 43.200
19 Tap Conector AL/CU 25-35 / 25-70 mm2 Bh 3 14.500 43.500
20 Plat Tanda Bahaya Bh 1 22.500 22.500
21 Kabel NYY 1x120 mm2 Mtr 40 71.500 2.860.000
22 Kabel NYY 1x50 mm2 Mtr 80 32.750 2.620.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 15,00 45.000 675.000
3 Pekerja H/O 12,00 35.000 420.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 67,45 - -
III. JARINGAN TEGANGAN RENDAH :
1 Penarikan LVTC 3x25+1x25 mm2 (JTR Murni) KMS 1 41.400 1.470.000 1.511.400
MDU
1 LVTC 3x25+1x25 mm2 Mtr 1030 PM -
NON MDU
1 Comp.Joint/Insulated Non Tension Joint 25 mm2 Bh 3 10.350 31.050
2 Comp.Joint/Insulated Tension Joint 25 mm2 Bh 1 10.350 10.350
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 15,00 45.000 675.000
3 Pekerja H/O 15,00 35.000 525.000
4 Mandor H/O 3,00 40.000 120.000
Angkutan :
1 Angkutan Darat Ton/KM 70,60 - -
2 Penarikan LVTC 3x25+1x25 mm2 (JTR Numpang) KMS 1 41.400 1.125.000 1.166.400
MDU
1 LVTC 3x25+1x25 mm2 Mtr 1030 PM -
NON MDU
1 Comp.Joint/Insulated Non Tension Joint 25 mm2 Bh 3 10.350 31.050
2 Comp.Joint/Insulated Tension Joint 25 mm2 Bh 1 10.350 10.350
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 15,00 45.000 675.000
3 Pekerja H/O 9,00 35.000 315.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 70,60 - -
3 Penarikan LVTC 3x35+1x25 mm2 (JTR Murni) KMS 1 50.000 1.710.000 1.760.000
MDU
1 LVTC 3x35+1x25 mm2 Mtr 1030 PM -
NON MDU
1 Comp.Joint/Insulated Non Tension Joint 35 mm2 Bh 3 12.500 37.500
2 Comp.Joint/Insulated Tension Joint 25 mm2 Bh 1 12.500 12.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 18,00 45.000 810.000
3 Pekerja H/O 18,00 35.000 630.000
4 Mandor H/O 3,00 40.000 120.000
Angkutan :
1 Angkutan Darat Ton/KM 90,32 - -
4 Penarikan LVTC 3x35+1x25 mm2 (JTR Numpang) KMS 1 50.000 1.365.000 1.415.000
MDU
1 LVTC 3x35+1x25 mm2 Mtr 1030 PM -
NON MDU
1 Comp.Joint/Insulated Non Tension Joint 35 mm2 Bh 3 12.500 37.500
2 Comp.Joint/Insulated Tension Joint 25 mm2 Bh 1 12.500 12.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 18,00 45.000 810.000
3 Pekerja H/O 12,00 35.000 420.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 90,32 - -
5 Penarikan LVTC 3x70+1x50 mm2 (JTR Murni) KMS 1 72.000 2.430.000 2.502.000
MDU
1 LVTC 3x70+1x50 mm2 Mtr 1035 PM -
NON MDU
1 Comp.Joint/Insulated Non Tension Joint 70 mm2 Bh 3 19.500 58.500
2 Comp.Joint/Insulated Tension Joint 50 mm2 Bh 1 13.500 13.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 27,00 45.000 1.215.000
3 Pekerja H/O 27,00 35.000 945.000
4 Mandor H/O 3,00 40.000 120.000
Angkutan :
1 Angkutan Darat Ton/KM 160,96 - -
6 Penarikan LVTC 3x70+1x50 mm2 (JTR Numpang) KMS 1 72.000 2.010.000 2.082.000
MDU
1 LVTC 3x70+1x50 mm2 Mtr 1035 PM -
NON MDU
1 Comp.Joint/Insulated Non Tension Joint 70 mm2 Bh 3 19.500 58.500
2 Comp.Joint/Insulated Tension Joint 50 mm2 Bh 1 13.500 13.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,50 50.000 75.000
2 Tukang Listrik H/O 30,00 45.000 1.350.000
3 Pekerja H/O 15,00 35.000 525.000
4 Mandor H/O 1,50 40.000 60.000
Angkutan :
1 Angkutan Darat Ton/KM 160,96 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
7 Konst. SKUTR T. Penyangga (TR-1) Set 1 40.200 26.250 66.450
NON MDU
1 Suspension / Small Angle Ass (Komplit + Platic Strap) Set 1 32.500 32.500
2 Stainless Stell Strap Mtr 1,2 3.500 4.200
3 Stoping Buckle (Yoke for Stainless Strip) Bh 2 1.750 3.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,15 35.000 5.250
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,03 - -
8 Konst. SKUTR T. Sudut dan Belokan (TR-2) Set 1 52.250 31.500 83.750
NON MDU
1 Large Angle Assembly (Komplit + Platic Strap) Set 1 44.550 44.550
2 Stainless Stell Strap Mtr 1,2 3.500 4.200
3 Stoping Buckle (Yoke for Stainless Strip) Bh 2 1.750 3.500
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,07 - -
9 Konst. SKUTR T. Awal / Akhir (TR-3) Set 1 389.650 75.000 464.650
NON MDU
1 Fixed Dead End Assembly (Komplit + Platic Strap) Set 1 36.750 36.750
2 Stainless Stell Strap Mtr 2,7 3.500 9.450
3 Stoping Buckle (Yoke for Stainless Strip) Bh 4 1.750 7.000
4 Link Bh 2 2.200 4.400
5 Pipa PVC 40 - 600 mm Bh 1 3.500 3.500
6 Bundle End Protection for LCTV Bh 4 3.250 13.000
Grounding SKUTR (GTR) Set 1 315.550 315.550
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,07 - -
10 Konst. SKUTR T. Penyangga pd Persimp (TR-4) Set 1 131.400 48.500 179.900
NON MDU
1 Suspension / Small Angle Ass (Komplit + Platic Strap) Set 2 32.500 65.000
2 Stainless Stell Strap Mtr 2,4 3.500 8.400
3 Stoping Buckle (Yoke for Stainless Strip) Bh 4 1.750 7.000
4 Tap Conector 35 - 70 mm2 Bh 4 12.750 51.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,40 35.000 14.000
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,07 - -
11 Konst. SKUTR T. Penegang (TR-5) Set 1 52.150 31.500 83.650
NON MDU
1 Fixed Dead End Assembly (Komplit + Platic Strap) Set 1 36.750 36.750
2 Stainless Stell Strap Mtr 2,4 3.500 8.400
3 Stoping Buckle (Yoke for Stainless Strip) Bh 4 1.750 7.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,07 - -
12 Konst. SKUTR T. Pencabangan (TR-6) Set 1 135.650 26.250 161.900
NON MDU
1 Fixed Dead End Assembly (Komplit + Platic Strap) Set 1 36.750 36.750
2 Suspension / Small Angle Ass (Komplit + Platic Strap) Set 1 32.500 32.500
3 Stainless Stell Strap Mtr 2,4 3.500 8.400
4 Stoping Buckle (Yoke for Stainless Strip) Bh 4 1.750 7.000
5 Tap Conector 35 - 70 mm2 Bh 4 12.750 51.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,15 35.000 5.250
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,07 - -
13 Konst. SKUTR T. Pencab pd T.Sudut/ Belokan (TR-6A) Set 1 147.700 31.500 179.200
NON MDU
1 Fixed Dead End Assembly (Komplit + Platic Strap) Set 1 36.750 36.750
2 Large Angle Assembly (Komplit + Platic Strap) Set 1 44.550 44.550
3 Stainless Stell Strap Mtr 2,4 3.500 8.400
4 Stoping Buckle (Yoke for Stainless Strip) Bh 4 1.750 7.000
5 Tap Conector 35 - 70 mm2 Bh 4 12.750 51.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,30 35.000 10.500
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,07 - -
14 Konst. SKUTR Penyambungan dg Existing (TR-7) Set 1 95.450 26.250 121.700
NON MDU
1 Fixed Dead End Assembly (Komplit + Platic Strap) Set 1 36.750 36.750
2 Stainless Stell Strap Mtr 1,2 3.500 4.200
3 Stoping Buckle (Yoke for Stainless Strip) Bh 2 1.750 3.500
4 Tap Conector 35 - 70 mm2 Bh 4 12.750 51.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,30 45.000 13.500
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
3 Pekerja H/O 0,15 35.000 5.250
4 Mandor H/O 0,00 40.000 -
Angkutan :
1 Angkutan Darat Ton/KM 0,32 - -
15 Grounding / Pentanahan T.Beton / Besi (GTR) Unit 1 323.550 61.500 385.050
NON-MDU
1 Copper Conductor 50 mm2 Mtr 8 18.900 151.200
2 Pipa Galvanis 3/4" - 3 meter Btg 1 48.100 48.100
4 Copper Clad (Grounding Rod) 5/8"x8 F With Clamp Bh 1 56.350 56.350
4 Tap Connector AL/CU 50 mm2 Bh 1 36.800 36.800
5 Stainless Stell Strip Mtr 4,5 3.500 15.750
6 Stoping Buckle (Yoke for Stainless Stell Strip) Bh 5 1.750 8.750
7 Link Bh 3 2.200 6.600
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,02 - -
16 Down Guy / Trekschoor Komplit T.Besi (E-1) Unit 1 232.350 61.500 293.850
NON-MDU
1 Guy Insulator (u/TR) Bh 1 9.500 9.500
2 Turn Buckle / Spanscroef 1/2 " Bh 1 17.800 17.800
3 Anchor Rod 5/8" x 1800 MM (Galv.) + Beton Blok Komplit Set 1 34.450 34.450
4 Bridle for Heavy Guy Wire Bh 0 -
5 Staal Drad Clamp 35 mm2 Bh 8 7.250 58.000
6 Kaos Baja / Guy Wire Thimble Bh 1 2.550 2.550
7 Galvanized Steel Wire ( Stall Draad) 35 mm2 Mtr 12 8.150 97.800
8 Band Pole for Bridle u/Tiang Besi Bh 1 12.250 12.250
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,30 45.000 13.500
3 Pekerja H/O 0,60 35.000 21.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,95 - -
17 Span Guy / Kontramast Komplit T.Besi (E-2) Unit 1 305.650 85.500 391.150
NON-MDU
1 Guy Insulator (u/TR) Bh 1 9.500 9.500
2 Bridle for Heavy Guy Wire Bh 0 -
3 Turn Buckle / Spanscroef 1/2 " Bh 1 17.800 17.800
4 Anchor Rod 5/8" x 1800 MM (Galv.) + Beton Blok Komplit Set 1 34.450 34.450
5 Staal Drad Clamp 35 mm2 Bh 12 7.250 87.000
6 Band Pole for Bridle u/Tiang Besi Bh 2 12.250 -
7 Kaos Baja / Guy Wire Thimble Bh 4 2.550 10.200
8 Galvanized Steel Wire ( Stall Draad) 35 mm2 Mtr 18 8.150 146.700
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,30 50.000 15.000
2 Tukang Listrik H/O 0,60 45.000 27.000
3 Pekerja H/O 0,90 35.000 31.500
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,95 - -
18 Strut Pole / Drukschoor Komplit T.Besi (E-3) Unit 1 208.020 102.000 310.020
MDU
1 Tiang Besi 11 Meter - 200 daN Btg 1 PM
NON-MDU
1 Strut Support / UNP (Galv) Set 1 21.480 21.480
2 Strut Band / Klem Beugle (Galv) Set 1 16.790 16.790
3 Pipa Galvanized 2,5" - 2 mtr Btg 1 91.100 91.100
4 Plat Beton Bertulang 1:2:3 0 500 x 500mm Bh 1 28.750 28.750
5 Band Pole 3 Lobang + Bolt & Nut (Galv) Bh 3 12.500 37.500
6 Band Pole 2 Lobang + Bolt & Nut (Galv) Bh 1 12.400 12.400
7 Cat u/Tiang, Goni & Aspal Set 1 - -
8 Beton Manchet Bh 1 - -
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,15 50.000 7.500
2 Tukang Listrik H/O 0,90 45.000 40.500
3 Pekerja H/O 1,20 35.000 42.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
B. PEKERJAAN BONGKAR / PASANG.
I. JARINGAN TEGANGAN MENENGAH :
1 Menurunkan JTM 3 Phasa A3C 150 mm2 KMS 1 - 2.157.000 2.157.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 3,30 50.000 165.000
2 Tukang Listrik HO 23,88 45.000 1.074.375
3 Pekerja HO 25,88 35.000 905.625
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
2 Menurunkan JTM 3 Phasa A3C 70 mm2 KMS 1 - 1.917.000 1.917.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 25,00 45.000 1.125.000
3 Pekerja H/O 18,00 35.000 630.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
3 Menurunkan JTM 3 Phasa A3C 35 mm2 KMS 1 - 1.682.650 1.682.650
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 2,65 50.000 132.650
2 Tukang Listrik H/O 21,53 45.000 968.760
3 Pekerja H/O 16,26 35.000 569.240
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
4 Bkr-Psg Konst T. Penyangga pd T.Beton (TM-1) Unit 1 - 52.020 52.020
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,11 50.000 5.700
2 Tukang Listrik HO 0,43 45.000 19.305
3 Pekerja HO 0,43 35.000 15.015
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
5 Bkr-Psg Konst T.Penyangga ganda pd T.Beton (TM-2) Unit 1 - 66.525 66.525
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,15 50.000 7.300
2 Tukang Listrik HO 0,58 45.000 26.190
3 Pekerja HO 0,60 35.000 21.035
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - - -
6 Bkr-Psg Konst T.Tarik Awal pd T. Beton (TM-3) Unit 1 - 62.530 62.530
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,14 50.000 6.850
2 Tukang Listrik HO 0,55 45.000 24.570
3 Pekerja HO 0,55 35.000 19.110
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - -
7 Bkr-Psg Konst.Tiang Akhir pd T.Beton (TM-4) Unit 1 - 62.530 62.530
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,14 50.000 6.850
2 Tukang Listrik HO 0,55 45.000 24.570
3 Pekerja HO 0,55 35.000 19.110
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - -
8 Bkr-Psg Konst.Tiang Tarik Ganda pd T.Beton (TM-5) Unit 1 - 130.400 130.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,32 50.000 16.000
2 Tukang Listrik HO 1,28 45.000 57.600
3 Pekerja HO 1,28 35.000 44.800
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
9 Bkr-Psg Konst.Tiang Pencab. pd T. Beton (TM-8) Unit 1 - 130.400 130.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,32 50.000 16.000
2 Tukang Listrik HO 1,28 45.000 57.600
3 Pekerja HO 1,28 35.000 44.800
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
10 Bkr-Psg Konst.T. Belokan Sudut pd T. Beton (TM-10) Unit 1 - 362.625 362.625
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,83 50.000 41.250
2 Tukang Listrik HO 4,95 45.000 222.750
3 Pekerja HO 2,48 35.000 86.625
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
11 Bkr-Psg Konst.Opstijg Kabel pd T. Beton (TM-11) Unit 1 - 386.000 386.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,88 50.000 44.000
2 Tukang Listrik HO 5,28 45.000 237.600
3 Pekerja HO 2,64 35.000 92.400
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
12 Bkr-Psg Konst.T.Portal/Single Arm pd T. Beton (TM-16) Unit 1 - 130.400 130.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,32 50.000 16.000
2 Tukang Listrik HO 1,28 45.000 57.600
3 Pekerja HO 1,28 35.000 44.800
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
13 Bkr-Psg Konst.PTS/LBS pd T. Beton (TM-19) Unit 1 - 672.000 672.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 1,20 50.000 60.000
2 Tukang Listrik HO 9,60 45.000 432.000
3 Pekerja HO 4,80 35.000 168.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
14 Bkr-Psg Konst T. Penyangga pd T.Besi (TM-1) Unit 1 - 54.340 54.340
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,11 50.000 5.700
2 Tukang Listrik HO 0,46 45.000 20.610
3 Pekerja HO 0,46 35.000 16.030
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM - - -
15 Bkr-Psg Konst T.Penyangga ganda pd T.Besi (TM-2) Unit 1 - 65.860 65.860
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,15 50.000 7.300
2 Tukang Listrik HO 0,58 45.000 26.190
3 Pekerja HO 0,58 35.000 20.370
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - - -
16 Bkr-Psg Konst T.Tarik Awal pd T. Besi (TM-3) Unit 1 - 92.870 92.870
Jasa Konstruksi :
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
1 Kepala Tukang Listrik / Mandor HO 0,22 50.000 10.950
2 Tukang Listrik HO 0,87 45.000 39.330
3 Pekerja HO 0,87 35.000 30.590
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - -
17 Bkr-Psg Konst.Tiang Akhir pd T.Besi (TM-4) Unit 1 - 92.870 92.870
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,22 50.000 10.950
2 Tukang Listrik HO 0,87 45.000 39.330
3 Pekerja HO 0,87 35.000 30.590
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - -
18 Bkr-Psg Konst.Tiang Tarik Ganda pd T.Besi (TM-5) Unit 1 - 130.400 130.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,32 50.000 16.000
2 Tukang Listrik HO 1,28 45.000 57.600
3 Pekerja HO 1,28 35.000 44.800
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM - - -
19 Bkr-Psg Konst.Tiang Pencab. pd T. Besi (TM-8) Unit 1 - 130.400 130.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,32 50.000 16.000
2 Tukang Listrik HO 1,28 45.000 57.600
3 Pekerja HO 1,28 35.000 44.800
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
20 Bkr-Psg Konst.T. Belokan Sudut pd T. Besi (TM-10) Unit 1 - 245.750 245.750
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,55 50.000 27.500
2 Tukang Listrik HO 3,30 45.000 148.500
3 Pekerja HO 1,65 35.000 57.750
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
21 Bkr-Psg Konst.Opstijg Kabel pd T. Besi (TM-11) Unit 1 - 460.000 460.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 1,60 50.000 80.000
2 Tukang Listrik HO 3,20 45.000 144.000
3 Pekerja HO 6,40 35.000 224.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
22 Bkr-Psg Konst.T.Portal/Single Arm pd T. Besi (TM-16) Unit 1 - 130.400 130.400
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,32 50.000 16.000
2 Tukang Listrik HO 1,28 45.000 57.600
3 Pekerja HO 1,28 35.000 44.800
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
23 Bkr-Psg Konst.PTS/LBS pd T. Besi (TM-19) Unit 1 - 672.000 672.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 1,20 50.000 60.000
2 Tukang Listrik HO 9,60 45.000 432.000
3 Pekerja HO 4,80 35.000 168.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton KM 0,00 - -
24 Bongkar Tiang Beton 9 Meter - 100 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
25 Bongkar Tiang Beton 9 Meter - 200 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
26 Bongkar Tiang Beton 11 Meter -200 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Jasa Konstruksi :
1 Angkutan Darat TonKM 0,00 - -
27 Bongkar Tiang Beton 11 Meter - 350 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
28 Bongkar Tiang Besi 9 Meter - 100 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
29 Bongkar Tiang Besi 9 Meter - 156 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
30 Bongkar Tiang Besi 11 Meter - 156 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Jasa Konstruksi :
1 Angkutan Darat TonKM 0,00 - -
31 Bongkar Tiang Besi 11 Meter - 200 daN : Batang 1 - 74.145 74.145
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor HO 0,16 50.000 7.900
2 Tukang Listrik HO 0,47 45.000 21.240
3 Pekerja HO 0,94 35.000 33.005
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat TonKM 0,00 - -
32 Bongkar JTM 3 Phasa A3C 70 mm2 KMS 1 - 1.917.000 1.917.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 25,00 45.000 1.125.000
3 Pekerja H/O 18,00 35.000 630.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
33 Bongkar JTM 3 Phasa A3C 35 mm2 KMS 1 - 1.682.650 1.682.650
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 2,65 50.000 132.650
2 Tukang Listrik H/O 21,53 45.000 968.760
3 Pekerja H/O 16,26 35.000 569.240
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
II. GARDU DISTRIBUSI.
1 Bkr-Psg Trafo Tiang Konst Satu Tiang 3 Ph 25/50 KVA Unit 1 - 862.000 862.000
lengkap dengan LS.Board (GD-3)
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,00 50.000 50.000
2 Tukang Listrik H/O 10,00 45.000 450.000
3 Pekerja H/O 10,00 35.000 350.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
2 Bkr-Psg Trafo Tiang Konst Dua Tiang 3 Ph 100/160 KVA Unit 1 - 1.022.000 1.022.000
lengkap dengan LS.Board (GD-1)
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,00 50.000 50.000
2 Tukang Listrik H/O 12,00 45.000 540.000
3 Pekerja H/O 12,00 35.000 420.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 0,00 - -
3 Bongkar Trafo Tiang Konst Satu Tiang 3 Ph 25/50 KVA Unit 1 - 862.000 862.000
lengkap dengan LS.Board (GD-3)
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,00 50.000 50.000
2 Tukang Listrik H/O 10,00 45.000 450.000
3 Pekerja H/O 10,00 35.000 350.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 67,45 - -
4 Bongkar Trafo Tiang Konst Dua Tiang 3 Ph 100/160 KVA Unit 1 - 1.022.000 1.022.000
lengkap dengan LS.Board (GD-1)
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 1,00 50.000 50.000
2 Tukang Listrik H/O 12,00 45.000 540.000
3 Pekerja H/O 12,00 35.000 420.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 67,45 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
III. JARINGAN TEGANGAN RENDAH :
1 Bongkar-Pasang LVTC 3x25+1x25 mm2 KMS 1 - 2.332.000 2.332.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 28,00 45.000 1.260.000
3 Pekerja H/O 26,00 35.000 910.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
2 Bongkar-Pasang LVTC 3x35+1x25 mm2 KMS 1 - 2.332.000 2.332.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 28,00 45.000 1.260.000
3 Pekerja H/O 26,00 35.000 910.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
3 Bongkar-Pasang LVTC 3x50+1x35 mm2 KMS 1 - 2.027.750 2.027.750
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 31,35 45.000 1.410.750
3 Pekerja H/O 13,00 35.000 455.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
4 Bongkar-Pasang LVTC 3x70+1x50 mm2 KMS 1 - 2.252.000 2.252.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 34,00 45.000 1.530.000
3 Pekerja H/O 16,00 35.000 560.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
5 Bkr-Psg Konst. SKUTR T. Penyangga (TR-1) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
6 Bkr-Psg Konst. SKUTR T. Sudut dan Belokan (TR-2) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
7 Bkr-Psg Konst. SKUTR T. Awal / Akhir (TR-3) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
8 Bkr-Psg Konst. SKUTR T. Penyangga pd Persimp (TR-4) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
9 Bkr-Psg Konst. SKUTR T. Penegang (TR-5) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
10 Bkr-Psg Konst. SKUTR T. Pencabangan (TR-6) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
11 Bkr-Psg Konst. SKUTR T. Pencab pd T.Sudut (TR-6A) Set 1 - 27.010 27.010
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 0,03 50.000 1.650
2 Tukang Listrik H/O 0,17 45.000 7.515
3 Pekerja H/O 0,17 35.000 5.845
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM - - -
12 Bongkar LVTC 3x25+1x25 mm2 KMS 1 - 2.332.000 2.332.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 28,00 45.000 1.260.000
3 Pekerja H/O 26,00 35.000 910.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 70,60 - -
HRG. SATUAN
NO URAIAN PEKERJAAN / MATERIAL STN VOL. MATERIAL JASA MATERIAL JASA PEKERJAAN
(RP) (RP) (RP) (RP) (RP)
HARGA SATUAN JL. HARGA SATUAN
13 Bongkar LVTC 3x35+1x25 mm2 KMS 1 - 2.332.000 2.332.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 28,00 45.000 1.260.000
3 Pekerja H/O 26,00 35.000 910.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 90,32 - -
14 Bongkar LVTC 3x50+1x35 mm2 KMS 1 - 2.027.750 2.027.750
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 31,35 45.000 1.410.750
3 Pekerja H/O 13,00 35.000 455.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 114,53 - -
15 Bongkar LVTC 3x70+1x50 mm2 KMS 1 - 2.252.000 2.252.000
Jasa Konstruksi :
1 Kepala Tukang Listrik / Mandor H/O 3,00 50.000 150.000
2 Tukang Listrik H/O 34,00 45.000 1.530.000
3 Pekerja H/O 16,00 35.000 560.000
4 Mandor H/O 0,30 40.000 12.000
Angkutan :
1 Angkutan Darat Ton/KM 160,96 - -
SUMATERA BARAT
Tim Perumus,
Padang, 25 Nopember 2005