Documentos de Académico
Documentos de Profesional
Documentos de Cultura
BY JOHN F. PROUD.
SEPTEMBER 1995 IIE SOLUTIONS
T
he master scheduler's real Job involves handling daily situations correctly—making critical
decisions using the information available. Although the master sched-ule itself may be
composed of several thousand numbers— which management uses to make decisions
dailv, the job of master scheduling goes well beyond simply creating numbers. For
instance, the numbers in a master schedute may indícate that the plant is in an
overloaded condition. How does the master scheduler get out of this overloaded condi-
tion? How does the company stay out of it?
Balancing the demand for a product with the supply is the biggest challenge of
master scheduling. This banlancing act requires creativity that goes well beyond the
numbers con-tained on the master schedule. For example, numbers may indícate that
customer orders are being received as forecasted. What does the master scheduler do
about it? What does the master scheduler do when customer orders exceed the forecast?
What if a product is recalled? How about dealing with a plant shutdown. either for a
period of time or permanently? Sometimes customers change their minds and want an
earlier or later dilevery. How should the master scheduler address moving scheduled
orders in and out when production stability is so important? Let's take a close look at tech-
niques that should be used to deal with these situations.
Inaccurate forecasts
The obvious place to start looking for problems is with ina- curate forecasts. Master
scheduling is a demand-driven process. Although a few companies build products strictlv
to customer orders or contratcs, some versión of forecasting takes place in most
companies prior o receiving the order. Companies have engineers on statf; skilled people in
the plant; inventory in the stockroom; and tooling in the crib. Why do they have these
materials and resources? Because they believe those materials and resources will be
needed to fulfill upcoming customer demand.
The first problems the company must face involve hiring engineers; hiring manufacturing
people; buying inventory; and possibly designing, making, and procuring needed tooling—
all based on a forecasi that is bound to have some inaccuracies. In Table 1, the actual
demand for the quarter is very close to this forccasted demand (102 percent). The accuracy
of the fore-cast becomes quite erratic, however, when it comes to the
Table 1
Periods July Auj;. Sept, Quarter
Forecast 5,000 5,000 5.000 15,000
Demands 6,200 2,800 6,300 15,300
Variance + 1,200 -2,200 +1,300 +300
124% 56% 126% 102%
Table 2
Periods July Aug Sept
Original Forecast 50 50 50
Actual Demand 35 22 14
Master Schedule 50 50 50
When expected orders don't materialize, several events occur. Marketing starts to wonder
why the forecast was so far off. Sales management begins to panic—thoughts turn to ‘’let’s
rnake a deal." Concurrently, manufacturing also moves into action. Sometimes the master
scheduler looks for work to eliminate idle capacity. This may be okay for the current period,
but what about the periods that follow? The optimist may continue to build product in the
hopes that orders will materialize. The pessimist may start to immediately reduce capacity
by laying of people prematurely.
The pragmatist looks at all the available alternatives. Maybe the right thing to do is to build
sets of common parts, or reschedule some of the material to a later date. Looking at the
manufacturing resources available, maybe some of the people can be assigned to other
useful work. Of course, this requires flexibility in the hands of the master scheduler.
At this juncture, company management must decide whether it wants to sell what is made
or make what is sold. This is a key decisión. Production-oriented companies contin ue to
work their technical capabilities; they may slow, but rarely stop production; and they invest in
sales marketing tool sets, such as price flexibility, attractive financing, and warrantee
extensions. Sales- and marketing-oriented companies answer brisk sales with a "Yes"
production response—the "You've done it before" attitude. Production slows accordingly if
sales are off.
Earlier delivery requested
"Reschedule our order" is not something that most manufacturing companies want to hear.
Although such requests may cause disruption and other unwanted problems, they are
better than the alternative, which is "Cancel our order." How does the master scheduler
handle these requests to satisfy the customer while keeping a stable schedule. Table 3
illustrates the situation.
Table 3
Periods July Aug. Sept
CUSTOMER ORDER 30 30 30
Revised order 30 40 20
Master Schedule 30 30 30
The first thing to note is that the customer's request is for change in timing, not a change
in volume. A timing request usually requires a shift in materials and resourees. When
responding, it's important for the scheduler to understand Why the request to
change in timing is being made. it could be that the customer needs the product. it
also could be that a sales representative wants the order moved up because of a
sales contest: an order clerk is simply reacting to an order point being tripped; or
safety stock needs replenishment. Some of these conditions may suggest that
shifting resources and expediting materials are inappropriate. But many such
requests do deserve positive responses.
There are several questions that need to be answered before the master
scheduler responds to such a request:
• Why is the request being made?
• Can the n ecessary materials be secured?
• Is capacity available?
• How much will this change cost ?
• Is t he master scheduler authorized to make the change?
Additionally the master scheduler should also ask, "What happens if the schedule
is not changed?" Most changes, especially if they occur within lead time, are
disruptive to the manufacturing floor and could well affect shop personnel morale. If
the master scheduler plans to change the schedule, he should ensure that positive
results occur.
Moving a manufacturing order to an earlier date
Pulling w ork forward is not always a bad thing to do. It might be manufacturing's
request to build early, and it may benefit the company. Maybe the pull-up is
required due to a pre-ship test surfacing a quality problem; the cyde counting
program uncovering an error in the inventory; or a new safe ty stock level needing
to be established.
Changes like the on e suggested in Table 4 may be diffi- cult are expensive to
implement. The key questions listed earlier must be answered before the master
scheduler changes the numbers.
Table 4
Periods July Aug. Sept
ANTICIPATE DEMAND 30 30 30
Master Schedule 30 30 30
Revised Schedule 30 35 25