Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Calculo de Catidades de Obras Ejectuadas
Calculo de Catidades de Obras Ejectuadas
BOX COULVER N 1
EXCAVACIN A MQUINA - PLACA DE FONDO
17 ml X 6 ml X 1.2 ml = 122.4 M
3
EXCAVACIN A MQUINA - ALETAS
4 ml X 1.5 ml 7 X 1 ml X 4 Unid = 24 M
3
TOTAL EXCAVACION= 146.4 M
3
RELLENO EN PIEDRA
17 ml X 6 ml X 0.65 ml = 66.3 M
3
4 ml X 1.5 ml X 0.65 ml X 4 ml= 15.6 M
3
TOTAL RELLENO EN PIEDRA= 81.9 M
3
SUELO CEMENTO
17 ml X 6 ml X 0.30 ml = 30.6 M
3
4 ml X 1.5 ml X 0.30 ml X 4 ml = 7.2 M
3
TOTAL SUELO CEMENTO = 37.8 M
3
PLANTILLA 0.05mt.
17 ml X 6 ml = 102 M
3
4 ml X 1.5 ml X 4 ml = 24 M
3
TOTAL PLANTILLA = 126 M
3
ACERO DE REFUERZO PLACA DE FONDO
73 X 5.30 ml X 2 = 773.8 Kg
51 5/8 X 17 ml X 1.56 X 2 = 2705.4 Kg
51 5/8 X 2 ml X 1.56 X 2 = 318.24 Kg
TOTAL ACERO PLACA DE FONDO = 3797.08 Kg
ACERO DE REFUERZO MUROS
51 5/8 X 6 ml X 1.56 = 477.36 Kg
51 3/4 X 7.10 ml X 2.24 X 2 = 1622.2 Kg
51 5/8 X 4.40 ml X 1.56 X 2 = 700.128 Kg
51 3/4 X 4.40 ml X 2.24 X 4 = 2010.6 Kg
21 3/8 X 5.30 ml X 0.56 X 8 = 498.6 Kg
TOTAL ACERO REFUERZO MURO = 5279.36 Kg
CONCRETO DE 4000 PSI PARA PLACA DE FONDO
16 ml X 5 ml X 0.35 ml = 28 M
3