PORTICO EJE 1 :
WD = 2.5 TN/M.
WL = 0.8 TN/M.
COMBINACIN : 1.4 WD + 1.7 WL
WL
WL
WD
WL
WD
WL
WD
WL
WL
WD
WL
WD
WL
WL
WL
WD
WL
WL
WL
WD
COMBINACIN :
1.25(WD + WL + WS)
FS
WL
WL
WD
WL
WD
FS
WL
FS
WL
WD
FS
FS
WL
WD
WL
WD
WL
FS
FS
WL
WL
WD
WL
WL
WL
WD
DISEO DE VIGAS
PRIMER PISO
PARA :
WD = 2.50 TN/M.
WL = 0.8 TN/M.
PS = 18.2 TN.
LA NORMA E-060
Mu (1)
= -7.79 Tn-m
INGRESO DE DATOS :
Mu = -7.79 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
As= 7.79 x 10^5
= 6.685 cm2
0.90x4200x0.9x34.25
a = 6.685x4200
4.719 cm
0.85x280x25
As= 7.79 x 10^5
= 6.461 cm2
0.90x4200x(34.25-4.719/2)
a = 6.461x4200
0.85x280x25
4.561 cm
= 6.446 cm2
0.90x4200x(34.25-4.561/2)
a = 6.446x4200
4.55 cm
0.85x280x25
As= 7.79 x 10^5
= 6.444 cm2
0.90x4200x(34.25-4.55/2)
a = 6.444x4200
4.549 cm
0.85x280x25
As= 7.79 x 10^5
= 6.444 cm2
0.90x4200x(34.25-4.549/2)
a = 6.444x4200
4.549 cm
0.85x280x25
= 0.0033
Pmin= 0.0033
Pmax= 0.75 Pb
Pb=
0.85*B1*(fc/fy)* (6000/(6000+fy))
Pb=
0.02833
Pmax= 0.0213
= 0.008
O.K
Mn = Asxfyx(d-a/2) = 6.809x4200(34.25-4.549/2)
Mn = 8.23 Tn-m > 7.79 Tn-m.
O.K
Mu (2)
= +6.69 Tn-m
INGRESO DE DATOS :
Mu = +6.69 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.476 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 ( 5.938 cm2)
N DE CAPAS :
1 CAPA
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0069 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.25 Tn-m > 6.69 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (3)
= -12.29 Tn-m
INGRESO DE DATOS :
Mu = -12.29 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.713 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 5/8 (12.509 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0157 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.13 Tn-m > 12.29 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (4)
= -10.84 Tn-m
INGRESO DE DATOS :
Mu = -10.84 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.127 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 1/2 (11.084 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0139 <
MOMENTO NOMINAL
Pmax = 0.0213
Mu (5)
= +5.27 Tn-m
INGRESO DE DATOS :
Mu = +5.27 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.257 cm2
p = 3/4 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.47 Tn-m > 5.27 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (6)
= -10.32 Tn-m
INGRESO DE DATOS :
Mu = -10.32 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.456 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0123 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.80 Tn-m > 10.32 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (7)
= -10.61 Tn-m
INGRESO DE DATOS :
Mu = -10.61 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.758 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0127 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.76 Tn-m > 10.61 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (8)
= +5.58 Tn-m
INGRESO DE DATOS :
Mu = +5.58 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.52 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.45 Tn-m > 5.58 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (9)
= -11.08 Tn-m
INGRESO DE DATOS :
Mu = -11.08 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.384 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 1/2 (11.084 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0139 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.83 Tn-m > 11.08 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (10)
= -11.59 Tn-m
INGRESO DE DATOS :
Mu = -11.59 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.938 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 1/2 (11.084 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0139 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.74 Tn-m > 11.59 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (11)
= +6.17 Tn-m
INGRESO DE DATOS :
Mu = +6.17 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.025 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.42 Tn-m > 6.17 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (12)
= -7.11 Tn-m
INGRESO DE DATOS :
Mu = -7.11 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.843 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0076 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.90 Tn-m > 7.11 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
SEGUNDO PISO
PARA :
WD = 2.47 TN/M.
WL = 0.64 TN/M.
PS = 22.2 TN.
Mu (1)
= -9.27 Tn-m
INGRESO DE DATOS :
Mu = -9.27 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.591 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 1/2 (11.084 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0165 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.70 Tn-m > 9.27 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (2)
= +6.08 Tn-m
INGRESO DE DATOS :
Mu = +6.08 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.959 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0089 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.62 Tn-m > 6.08 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
Mu (3)
= -11.75 Tn-m
INGRESO DE DATOS :
Mu = -11.75 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.208 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 3 5/8 (14.489 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0213 <
MOMENTO NOMINAL
Pmax = 0.0216
Mu (4)
= -10.41 Tn-m
INGRESO DE DATOS :
Mu = -10.41 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.191 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 5/8 (12.509 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0186 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.68 Tn-m > 10.41 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (5)
= +5.19 Tn-m
INGRESO DE DATOS :
Mu = +5.19 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.994 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.43 Tn-m > 5.19 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (6)
= -10.27 Tn-m
INGRESO DE DATOS :
Mu = -10.27 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.787 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.35 Tn-m > 10.27 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (7)
= -10.61 Tn-m
INGRESO DE DATOS :
Mu = -10.61 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.268 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 3 5/8 (13.855 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0204 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.98 Tn-m > 10.61 Tn-m
VERIFICACIN DEL b min.
b = 23.76 cm > 25 cm
Mu (8)
= +5.44 Tn-m
INGRESO DE DATOS :
Mu = +5.44 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.252 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 (5.938 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.15 Tn-m > 5.44 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (9)
= -10.75 Tn-m
INGRESO DE DATOS :
Mu = -10.75 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.468 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 3 5/8 (13.855 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0204 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.95 Tn-m > 10.75 Tn-m
VERIFICACIN DEL b min.
b = 23.76 cm > 25 cm
Mu (10)
= -10.99 Tn-m
INGRESO DE DATOS :
Mu = -10.99 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.815 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 3 5/8 (13.855 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0204 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.88 Tn-m > 10.99 Tn-m
VERIFICACIN DEL b min.
b = 23.76 cm > 25 cm
Mu (11)
= +5.61 Tn-m
INGRESO DE DATOS :
Mu = +5.61 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.529 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8
N DE CAPAS :
(5.938 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.14 Tn-m > 5.61 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (12)
= -8.52 Tn-m
INGRESO DE DATOS :
Mu = -8.52 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.439 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 1/2 (9.738 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0143 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 8.79 Tn-m > 8.52 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
TERCER PISO
PARA :
WD = 2.47 TN/M.
WL = 0.64 TN/M.
PS = 30.3 TN.
Mu (1)
= -9.56 Tn-m
INGRESO DE DATOS :
Mu = -9.56 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.811 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.50 Tn-m > 9.56 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (2)
= +5.95 Tn-m
INGRESO DE DATOS :
Mu = +5.95 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.784 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0089 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.68 Tn-m > 5.95 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
Mu (3)
= -11.66 Tn-m
INGRESO DE DATOS :
Mu = -11.66 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 13.81 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 3 5/8 (13.855 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0204 <
MOMENTO NOMINAL
Pmax = 0.0213
Mu (4)
= -10.32 Tn-m
INGRESO DE DATOS :
Mu = -10.32 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.857 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.34 Tn-m > 10.32 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (5)
= +5.17 Tn-m
INGRESO DE DATOS :
Mu = +5.17 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.974 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.43 Tn-m > 5.17 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (6)
= -10.27 Tn-m
INGRESO DE DATOS :
Mu = -10.27 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.787 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.35 Tn-m > 10.27 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (7)
= -10.62 Tn-m
INGRESO DE DATOS :
Mu = -10.62 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.497 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 5/8 (12.509 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0186 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.63 Tn-m > 10.62 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (8)
= +5.41 Tn-m
INGRESO DE DATOS :
Mu = +5.41 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.252 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0089 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.72 Tn-m > 5.44 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
Mu (9)
= -10.68 Tn-m
INGRESO DE DATOS :
Mu = -10.68 Tn-m.
p = 7/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.812 cm2
p = 5/8 pulg.
As ( suministrado) = 3 7/8 + 1 1/2 (12.905 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0194 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.76 Tn-m > 10.68 Tn-m
VERIFICACIN DEL b min.
b = 21.57 cm > 25 cm
Mu (10)
= -10.88 Tn-m
INGRESO DE DATOS :
Mu = -10.88 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.88 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 3/4 (14.251 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0212 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.04 Tn-m > 10.88 Tn-m
VERIFICACIN DEL b min.
b = 23.76 cm > 25 cm
Mu (11)
= +5.50 Tn-m
INGRESO DE DATOS :
Mu = +5.50 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.315 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8
N DE CAPAS :
(5.938 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.15 Tn-m > 5.50 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (12)
= -8.79 Tn-m
INGRESO DE DATOS :
Mu = -8.79 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.789 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0145 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 8.89 Tn-m > 8.79 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
CUARTO PISO
PARA :
WD = 2.47 TN/M.
WL = 0.64 TN/M.
PS = 27.7 TN.
Mu (1)
= -7.58 Tn-m
INGRESO DE DATOS :
Mu = -7.58 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.253 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.78 Tn-m > 7.58 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (2)
= +6.79 Tn-m
INGRESO DE DATOS :
Mu = +6.79 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.291 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125 <
MOMENTO NOMINAL
Pmax = 0.0213
Mu (3)
= -12.36 Tn-m
INGRESO DE DATOS :
Mu = -12.36 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 13.646 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 7/8 (14.014 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0195 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.69 Tn-m > 12.36 Tn-m
VERIFICACIN DEL b min.
b = 22.29 cm > 25 cm
Mu (4)
= -10.92 Tn-m
INGRESO DE DATOS :
Mu = -10.92 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.725 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 5/8 (12.113 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0168 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.28 Tn-m > 10.92 Tn-m
VERIFICACIN DEL b min.
b = 21.65 cm > 25 cm
Mu (5)
= +5.28 Tn-m
INGRESO DE DATOS :
Mu = +5.28 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.087 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.42 Tn-m > 5.28 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (6)
= -10.32 Tn-m
INGRESO DE DATOS :
Mu = -11.66 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.96 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0158 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.73 Tn-m > 10.32 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 25 cm
Mu (7)
= -10.61 Tn-m
INGRESO DE DATOS :
Mu = -10.61 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.327 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0158 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.68 Tn-m > 10.61 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 25 cm
Mu (8)
= +5.59 Tn-m
INGRESO DE DATOS :
Mu = +5.59 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.408 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 (5.938 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.14 Tn-m > 5.59 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (9)
= -11.15 Tn-m
INGRESO DE DATOS :
Mu = -11.15 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.023 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 5/8 (12.113 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0168 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.23 Tn-m > 11.15 Tn-m
VERIFICACIN DEL b min.
b = 21.65 cm > 25 cm
Mu (10)
= -11.66 Tn-m
INGRESO DE DATOS :
Mu = -11.66 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.696 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0180 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.93 Tn-m > 11.66 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 25 cm
Mu (11)
= +6.25 Tn-m
INGRESO DE DATOS :
Mu = +6.25 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.101 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0089 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.65 Tn-m > 6.25 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
Mu (12)
= -6.91 Tn-m
INGRESO DE DATOS :
Mu = -6.91 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.435 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.87 Tn-m > 6.91 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
PRIMER PISO
PARA :
WD = 4.76 TN/M.
WL = 1.55 TN/M.
PS = 18.2 TN.
Mu (1)
= -16.20 Tn-m
INGRESO DE DATOS :
Mu = -16.20 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
p = 1 pulg.
= 12.177 cm2
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0112 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.27 Tn-m > 16.20 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 30 cm
Mu (2)
= +12.53 Tn-m
INGRESO DE DATOS :
Mu = +12.53 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.489 cm2
p = 1 pulg.
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
(10.134 cm2)
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.53 Tn-m > 13.82 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -23.04 Tn-m
INGRESO DE DATOS :
Mu = -23.04 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 20.083 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 3 5/8 (21.139 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 24.25 Tn-m > 23.04 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (4)
= -20.73 Tn-m
INGRESO DE DATOS :
Mu = -20.73 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.654 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 1/2 (17.735 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0163 <
MOMENTO NOMINAL
Pmax = 0.0213
Mu (5)
= +10.20 Tn-m
INGRESO DE DATOS :
Mu = +10.20 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.371 cm2
p = 1 pulg.
As ( suministrado) = 1 1 + 2 1/2 (7.601 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0065 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.52 Tn-m > 10.20 Tn-m
Mu (6)
= -19.87 Tn-m
INGRESO DE DATOS :
Mu = -19.87 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 16.783 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 1/2 (17.735 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0163 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.00 Tn-m > 19.87 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (7)
= -20.38 Tn-m
INGRESO DE DATOS :
Mu = -20.38 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.297 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 1/2 (17.735 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0163 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 20.90 Tn-m > 20.38 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (8)
= +10.80 Tn-m
INGRESO DE DATOS :
Mu = +10.80 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.833 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.97 Tn-m > 10.80 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (9)
= -21.20 Tn-m
INGRESO DE DATOS :
Mu = -21.20 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.137 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 5/8 (19.160 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0176 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 22.40 Tn-m > 21.20 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (10)
= -21.74 Tn-m
INGRESO DE DATOS :
Mu = -21.74 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.669 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 5/8 (19.160 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0176 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 22.28 Tn-m > 21.74 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (11)
= +11.54 Tn-m
INGRESO DE DATOS :
Mu = +11.54 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.409 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.91 Tn-m > 11.54 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (12)
= -14.84 Tn-m
INGRESO DE DATOS :
Mu = -14.84 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 45 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.05 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0098 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.31 Tn-m > 14.84 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
SEGUNDO PISO
PARA :
WD = 4.72 TN/M.
WL = 1.24 TN/M.
PS = 22.2 TN.
Mu (1)
= -17.35 Tn-m
INGRESO DE DATOS :
Mu = -17.35 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.598 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 1/2 (17.735 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0189 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.48 Tn-m > 17.35 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (2)
= +10.71 Tn-m
INGRESO DE DATOS :
Mu = +10.71 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.111 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.91 Tn-m > 10.71 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -20.78 Tn-m
INGRESO DE DATOS :
Mu = -20.78 Tn-m.
p = 9/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 22.641 cm2
p = 9/8 pulg.
As ( suministrado) = 3 9/8 + 2 5/8 (23.198 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0210 <
MOMENTO NOMINAL
Pmax = 0.0213
Mu (4)
= -18.65 Tn-m
INGRESO DE DATOS :
Mu = -18.65 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.176 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 7/8 (17.893 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0177 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.43 Tn-m > 18.65 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (5)
= + 9.27 Tn-m
INGRESO DE DATOS :
Mu = +9.27 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.789 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0113 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.57 Tn-m > 9.27 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (6)
= -18.42 Tn-m
INGRESO DE DATOS :
Mu = -18.42 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.979 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 5/8 (19.160 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0204 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 18.60 Tn-m > 18.42 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (7)
= -19.00 Tn-m
INGRESO DE DATOS :
Mu = -19.00 Tn-m.
p = 9/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.689 cm2
p = 9/8 pulg.
As ( suministrado) = 3 9/8
N DE CAPAS :
(19.239 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0191 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 20.67 Tn-m > 19.00 Tn-m
VERIFICACIN DEL b min.
b = 24.19 cm > 30 cm
Mu (8)
= + 9.75 Tn-m
INGRESO DE DATOS :
Mu = +9.75 Tn-m.
p = 7/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.181 cm2
p = 7/8 pulg.
As ( suministrado) = 2 7/8 + 1 1/2 (9.026cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0089 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.76 Tn-m > 10.76 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 30 cm
Mu (9)
= -19.27 Tn-m
INGRESO DE DATOS :
Mu = -19.27 Tn-m.
p = 9/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.998 cm2
p = 9/8 pulg.
As ( suministrado) = 3 9/8 (19.239 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0191 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 20.60 Tn-m > 19.27 Tn-m
VERIFICACIN DEL b min.
b = 24.19 cm > 30 cm
Mu (10)
= -19.43 Tn-m
INGRESO DE DATOS :
Mu = -19.43 Tn-m.
p = 9/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.182 cm2
p = 9/8 pulg.
As ( suministrado) = 3 9/8 (19.239 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0191 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 20.56 Tn-m > 19.43 Tn-m
VERIFICACIN DEL b min.
b = 24.19 cm > 30 cm
Mu (11)
= + 9.87 Tn-m
INGRESO DE DATOS :
Mu = +9.87 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.335 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.00 Tn-m > 9.87 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (12)
= -15.98 Tn-m
INGRESO DE DATOS :
Mu = -15.98 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.295 cm2
p = 1 pulg.
(15.201 cm2)
As ( suministrado) = 3 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0150 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 16.99 Tn-m > 15.98 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
TERCER PISO
PARA :
WD = 4.72 TN/M.
WL = 1.24 TN/M.
PS = 30.3 TN.
Mu (1)
= -17.74 Tn-m
INGRESO DE DATOS :
Mu = -17.74 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 16.171 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 7/8 (17.893 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.63 Tn-m > 17.74 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (2)
= +10.55 Tn-m
INGRESO DE DATOS :
Mu = +10.55 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.962 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.93 Tn-m > 10.55 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -20.67 Tn-m
INGRESO DE DATOS :
Mu = -20.67 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.50 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.48 Tn-m > 20.67 Tn-m
Mu (4)
= -18.52 Tn-m
INGRESO DE DATOS :
Mu = -18.52 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.031 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 7/8 (17.893 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0177 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.46 Tn-m > 18.52 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (5)
= +9.28 Tn-m
INGRESO DE DATOS :
Mu = +9.28 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.798 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.06 Tn-m > 9.28 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (6)
= -18.45 Tn-m
INGRESO DE DATOS :
Mu = -18.45 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 16.953 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 7/8 (17.893 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0177 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.47 Tn-m > 18.45 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (7)
= -19.03 Tn-m
INGRESO DE DATOS :
Mu = -19.03 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.603 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 7/8 (17.893 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0177 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.34 Tn-m > 19.03 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (8)
= + 9.73 Tn-m
INGRESO DE DATOS :
Mu = +9.73 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.207 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.01 Tn-m > 9.73 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (9)
= -19.18 Tn-m
INGRESO DE DATOS :
Mu = -19.18 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.772 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 7/8 (17.893 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0177 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.31 Tn-m > 19.18 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (10)
= -19.29 Tn-m
INGRESO DE DATOS :
Mu = -19.29 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.897 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.85 Tn-m > 19.29 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (11)
= + 9.73 Tn-m
INGRESO DE DATOS :
Mu = +9.73 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.207 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.01 Tn-m > 9.73 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (12)
= -16.36 Tn-m
INGRESO DE DATOS :
Mu = -16.36 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.693 cm2
p = 1 pulg.
(15.201 cm2)
As ( suministrado) = 3 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0150 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 16.93 Tn-m > 16.36 Tn-m
CUARTO PISO
PARA :
WD = 4.72 TN/M.
WL = 1.24 TN/M.
PS = 27.7 TN.
Mu (1)
= -14.66 Tn-m
INGRESO DE DATOS :
Mu = -14.66 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.94 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0128 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 14.71 Tn-m > 14.66 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 30 cm
Mu (2)
= +11.88 Tn-m
INGRESO DE DATOS :
Mu = +11.88 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.213 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.26 Tn-m > 11.88 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (3)
= -21.71 Tn-m
INGRESO DE DATOS :
Mu = -21.71 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 20.754 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 1 9/8 (21.614 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0213 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 22.61 Tn-m > 21.71 Tn-m
VERIFICACIN DEL b min.
b = 28.96 cm > 30 cm
Mu (4)
= -19.51 Tn-m
INGRESO DE DATOS :
Mu = -19.51 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.148 cm2
p = 1 pulg.
As ( suministrado) = 4 1 (20.268 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.79 Tn-m > 19.51 Tn-m
Mu (5)
= + 9.45 Tn-m
INGRESO DE DATOS :
Mu = +9.45 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.952 cm2
p = 1 pulg.
As ( suministrado) = 2 1
N DE CAPAS :
(10.134 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.010 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.04 Tn-m > 9.45 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (6)
= -18.51 Tn-m
INGRESO DE DATOS :
Mu = -18.51 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.098 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 2 5/8 (19.160 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0204 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 18.57 Tn-m > 18.51 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 30 cm
Mu (7)
= -18.97 Tn-m
INGRESO DE DATOS :
Mu = -18.97 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.535 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.93 Tn-m > 18.67 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (8)
= +10.03 Tn-m
INGRESO DE DATOS :
Mu = +10.03 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.482 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.98 Tn-m > 10.03 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (9)
= -19.93 Tn-m
INGRESO DE DATOS :
Mu = -19.93 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.362 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.68 Tn-m > 19.93 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (10)
= -20.51 Tn-m
INGRESO DE DATOS :
Mu = -20.51 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.311 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 21.53 Tn-m > 20.51 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (11)
= +10.93 Tn-m
INGRESO DE DATOS :
Mu = +10.93 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.316 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0100 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.89 Tn-m > 10.93 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (12)
= -13.41 Tn-m
INGRESO DE DATOS :
Mu = -13.41 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.694 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 5/8 (12.113 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.012 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.89 Tn-m > 13.41 Tn-m
PRIMER PISO
PARA :
WD = 2.36 TN/M.
WL = 0.75 TN/M.
PS = 18.2 TN.
Mu (1)
= -6.65 Tn-m
INGRESO DE DATOS :
Mu = -6.65 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.441 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 (5.938 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0069 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.26 Tn-m > 6.65 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (2)
= + 6.60 Tn-m
INGRESO DE DATOS :
Mu = +6.60 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.398 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 (5.938 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0069 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.26 Tn-m > 6.60 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (3)
= -11.82 Tn-m
INGRESO DE DATOS :
Mu = -11.82 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.045 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.71 Tn-m > 11.82 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (4)
= -10.43 Tn-m
INGRESO DE DATOS :
Mu = -10.43 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.57 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0123 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.79 Tn-m > 10.43 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (5)
= + 5.02 Tn-m
INGRESO DE DATOS :
Mu = +5.02 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.046 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.48 Tn-m > 5.02 Tn-m
Mu (6)
= - 9.74 Tn-m
INGRESO DE DATOS :
Mu = -9.74 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.860 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0123 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.88 Tn-m > 9.74 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (7)
= -10.00 Tn-m
INGRESO DE DATOS :
Mu = -10.00 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.126 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0123 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.84 Tn-m > 10.00 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (8)
= + 5.32 Tn-m
INGRESO DE DATOS :
Mu = +5.32 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.299 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.47 Tn-m > 5.32 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (9)
= -10.62 Tn-m
INGRESO DE DATOS :
Mu = -10.62 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.768 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 5/8 (9.897 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0123 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.76 Tn-m > 10.62 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (10)
= -11.18 Tn-m
INGRESO DE DATOS :
Mu = -11.18 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.358 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0147 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.82 Tn-m > 11.18 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (11)
= + 6.08 Tn-m
INGRESO DE DATOS :
Mu = +6.08 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.948 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.42 Tn-m > 6.08 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (12)
= - 6.05 Tn-m
INGRESO DE DATOS :
Mu = -6.05 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.922 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0061 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.42 Tn-m > 6.05 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
SEGUNDO PISO
PARA :
WD = 2.33 TN/M.
WL = 0.60 TN/M.
PS = 22.2 TN.
Mu (1)
= - 7.32 Tn-m
INGRESO DE DATOS :
Mu = -7.32 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.933 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.82 Tn-m > 7.32 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (2)
= + 5.66 Tn-m
INGRESO DE DATOS :
Mu = +5.66 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.481 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8
N DE CAPAS :
(5.938 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.13 Tn-m > 5.66 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (3)
= -10.68 Tn-m
INGRESO DE DATOS :
Mu = -10.68 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.368 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 4 1/2 (12.982 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0191<
MOMENTO NOMINAL
Pmax = 0.0213
Mu (4)
= - 9.35 Tn-m
INGRESO DE DATOS :
Mu = -9.35 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.528 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 3 1/2 (11.718 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0172<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.41 Tn-m > 9.35 Tn-m
VERIFICACIN DEL b min.
b = 23.76 cm > 25 cm
Mu (5)
= + 4.57 Tn-m
INGRESO DE DATOS :
Mu = +4.57 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.362 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.47 Tn-m > 4.57 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (6)
= - 9.05 Tn-m
INGRESO DE DATOS :
Mu = -9.05 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.130 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.61 Tn-m > 9.05 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (7)
= - 9.32 Tn-m
INGRESO DE DATOS :
Mu = -9.32 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.488 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.55 Tn-m > 9.32 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (8)
= + 9.82 Tn-m
INGRESO DE DATOS :
Mu = +9.82 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.164 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.45 Tn-m > 9.82 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (9)
= - 9.61 Tn-m
INGRESO DE DATOS :
Mu = -9.61 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.878 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.49 Tn-m > 9.61 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (10)
= -10.03 Tn-m
INGRESO DE DATOS :
Mu = -10.03 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.453 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.40 Tn-m > 10.03 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (11)
= + 5.22 Tn-m
INGRESO DE DATOS :
Mu = +5.22 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.025 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.43 Tn-m > 5.22 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (12)
= - 6.69 Tn-m
INGRESO DE DATOS :
Mu = -6.69 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.571 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 3/4 (6.809 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0093<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.93 Tn-m > 6.69 Tn-m
TERCER PISO
PARA :
WD = 2.33 TN/M.
WL = 0.60 TN/M.
PS = 30.3 TN.
Mu (1)
= - 7.64 Tn-m
INGRESO DE DATOS :
Mu = -7.64 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.340 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.77 Tn-m > 7.65 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (2)
= + 5.52 Tn-m
INGRESO DE DATOS :
Mu = +5.52 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.335 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
(5.938 cm2)
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.14 Tn-m > 5.52 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (3)
= - 10.6 Tn-m
INGRESO DE DATOS :
Mu = -10.60 Tn-m.
p = 3/4 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.468 cm2
p = 3/4 pulg.
As ( suministrado) = 3 3/4 + 2 5/8 (12.509 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0186<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.64 Tn-m > 10.60 Tn-m
VERIFICACIN DEL b min.
b = 20.62 cm > 25 cm
Mu (4)
= - 9.23 Tn-m
INGRESO DE DATOS :
Mu = -9.23 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.368 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.57 Tn-m > 9.23 Tn-m
Mu (5)
= + 4.58 Tn-m
INGRESO DE DATOS :
Mu = +4.58 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.372 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.47 Tn-m > 4.58 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (6)
= - 9.07 Tn-m
INGRESO DE DATOS :
Mu = -9.07 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.156 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.61 Tn-m > 9.07 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (7)
= - 9.35 Tn-m
INGRESO DE DATOS :
Mu = -9.35 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.528 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.55 Tn-m > 9.35 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (8)
= + 4.81 Tn-m
INGRESO DE DATOS :
Mu = +4.81 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.606 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.46 Tn-m > 4.81 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (9)
= - 9.52 Tn-m
INGRESO DE DATOS :
Mu = -9.52 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.757 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.51 Tn-m > 9.52 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (10)
= - 9.94 Tn-m
INGRESO DE DATOS :
Mu = -9.94 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.329 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.42 Tn-m > 9.94 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (11)
= + 5.10 Tn-m
INGRESO DE DATOS :
Mu = +5.10 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.902 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.44 Tn-m > 5.10 Tn-m
VERIFICACIN DEL b min.
b = 19.35 cm > 25 cm
Mu (12)
= - 7.00 Tn-m
INGRESO DE DATOS :
Mu = -7.00 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.906 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 1 1/2 (7.205 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0099<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.30 Tn-m > 7.00 Tn-m
CUARTO PISO
PARA :
WD = 2.33 TN/M.
WL = 0.60 TN/M.
PS = 27.7 TN.
Mu (1)
= - 5.54 Tn-m
INGRESO DE DATOS :
Mu = -5.54 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.356 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8
N DE CAPAS :
1 CAPAS
(5.938 cm2)
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.14 Tn-m > 5.54 Tn-m
Mu (2)
= + 6.43 Tn-m
INGRESO DE DATOS :
Mu = +6.43 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.293 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0089<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.63 Tn-m > 6.43 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
Mu (3)
= -11.22 Tn-m
INGRESO DE DATOS :
Mu = -11.22 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 13.153 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 + 3 5/8 (13.855 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.82 Tn-m > 11.22 Tn-m
Mu (4)
= - 9.95 Tn-m
INGRESO DE DATOS :
Mu = -9.95 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.343 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.42 Tn-m > 9.95 Tn-m
Mu (5)
= + 4.63 Tn-m
INGRESO DE DATOS :
Mu = +4.63 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.423 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.47 Tn-m > 4.63 Tn-m
Mu (6)
= - 9.03 Tn-m
INGRESO DE DATOS :
Mu = -9.03 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.104 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
MOMENTO NOMINAL
Pmax = 0.0213
Mu (7)
= - 9.25 Tn-m
INGRESO DE DATOS :
Mu = -9.25 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.395 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
MOMENTO NOMINAL
Pmax = 0.0213
Mu (8)
= + 4.96 Tn-m
INGRESO DE DATOS :
Mu = +4.96 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.759 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.45 Tn-m > 4.96 Tn-m
Mu (9)
= -10.08 Tn-m
INGRESO DE DATOS :
Mu = -10.08 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.522 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.39 Tn-m > 10.08 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (10)
= -10.64 Tn-m
INGRESO DE DATOS :
Mu = -10.64 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.366 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0158<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.67 Tn-m > 10.64 Tn-m
Mu (11)
= + 5.90 Tn-m
INGRESO DE DATOS :
Mu = +5.90 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.372 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8
N DE CAPAS :
(5.938 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.11 Tn-m > 5.90 Tn-m
Mu (12)
= - 5.03 Tn-m
INGRESO DE DATOS :
Mu = -5.03 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 4.83 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 1 1/2 (5.225 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0071<
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 5.44 Tn-m > 5.03 Tn-m
PRIMER PISO
PARA :
WD = 2.06 TN/M.
WL = 0.65 TN/M.
PS = 18.2 TN.
Mu (1)
= - 8.57 Tn-m
INGRESO DE DATOS :
Mu = -8.57 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
RESULTADOS :
fy = 4200 kg/cm2
h= 40 cm
AREA DE ACERO
As (requerido)
= 7.686 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0105 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.45 Tn-m > 8.57 Tn-m
Mu (2)
= + 7.01 Tn-m
INGRESO DE DATOS :
Mu = +7.01 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
RESULTADOS :
fy = 4200 kg/cm2
h= 40 cm
AREA DE ACERO
As (requerido)
= 5.755 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0076 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.91 Tn-m > 7.01 Tn-m
Mu (3)
= -13.96 Tn-m
INGRESO DE DATOS :
Mu = -13.96 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
RESULTADOS :
AREA DE ACERO
fy = 4200 kg/cm2
h= 40 cm
As (requerido)
= 12.590 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 14.40 Tn-m > 13.96 Tn-m
Mu (4)
= -15.33 Tn-m
INGRESO DE DATOS :
Mu = -15.33 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.077 cm2
p = 1 pulg.
As ( suministrado) = 3 1 (15.201 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0180 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 16.55 Tn-m > 15.33 Tn-m
Mu (5)
= + 8.05 Tn-m
INGRESO DE DATOS :
Mu = +8.05 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
p = 5/8 pulg.
= 7.176 cm2
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0105 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.50 Tn-m > 8.05 Tn-m
Mu (6)
= - 9.98 Tn-m
INGRESO DE DATOS :
Mu = -9.98 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.105 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 1/2 (9.738 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0121 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.67 Tn-m > 9.98 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
SEGUNDO PISO
PARA :
WD = 2.06 TN/M.
WL = 0.52 TN/M.
PS = 22.2 TN.
Mu (1)
= - 9.14 Tn-m
INGRESO DE DATOS :
Mu = -9.14 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.249 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 3 5/8 (11.876 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0175 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.59 Tn-m > 9.14 Tn-m
Mu (2)
= + 6.26 Tn-m
INGRESO DE DATOS :
Mu = +6.26 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.662 cm2
p = 5/8 pulg.
As ( suministrado) = 3 5/8 + 2 1/2 (8.472 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.96 Tn-m > 6.26 Tn-m
Mu (3)
= - 12.54 Tn-m
INGRESO DE DATOS :
Mu = -12.54 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 13.896 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 7/8 (14.014 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0195 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.65 Tn-m > 12.54 Tn-m
Mu (4)
= - 13.96 Tn-m
INGRESO DE DATOS :
Mu = -13.96 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.832 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 3 1/2 (19.002 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0200 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 14.09 Tn-m > 13.96 Tn-m
Mu (5)
= + 7.07 Tn-m
INGRESO DE DATOS :
Mu = +7.07 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.12 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.06 Tn-m > 7.07 Tn-m
Mu (6)
= - 10.54 Tn-m
INGRESO DE DATOS :
Mu = -10.54 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.238 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0158 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.69 Tn-m > 10.54 Tn-m
TERCER PISO
PARA :
WD = 2.06 TN/M.
WL = 0.52 TN/M.
PS = 30.3 TN.
Mu (1)
= 9.35 - Tn-m
INGRESO DE DATOS :
Mu = +9.35 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.765 cm2
p = 1 pulg.
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
(10.134 cm2)
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.70 Tn-m > 9.35 Tn-m
Mu (2)
= + 6.22 Tn-m
INGRESO DE DATOS :
Mu = +6.22 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.069 cm2
p = 5/8 pulg.
As ( suministrado) = 2 5/8 + 2 1/2 (6.492 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.65 Tn-m > 6.22 Tn-m
Mu (3)
= - 12.41 Tn-m
INGRESO DE DATOS :
Mu = -12.41 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 13.716 cm2
p = 1 pulg.
As ( suministrado) = 3 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
(15.201 cm2)
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.75 Tn-m > 12.41 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 25 cm
Mu (4)
= - 13.88 Tn-m
INGRESO DE DATOS :
Mu = -13.88 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.669 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 3 1/2 (19.002 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0213 <
Pmax = 0.0213
a) cambio de dimensiones
b) mejorar el fc
c) disear como seccion doblemente reforzada.
MOMENTO NOMINAL
Mn = 14.13 Tn-m > 13.88 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 25 cm
Mu (5)
= + 7.01 Tn-m
INGRESO DE DATOS :
Mu = +7.01 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.055 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.07 Tn-m > 7.01 Tn-m
Mu (6)
= - 10.76 Tn-m
INGRESO DE DATOS :
Mu = -10.76 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.519 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 5/8 (12.113 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0168 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.32 Tn-m > 10.76 Tn-m
VERIFICACIN DEL b min.
b = 21.65 cm > 25 cm
CUARTO PISO
PARA :
WD = 2.06 TN/M.
WL = 0.52 TN/M.
PS = 27.7 TN.
Mu (1)
= - 6.97 Tn-m
INGRESO DE DATOS :
Mu = -6.97 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.01 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.68 Tn-m > 6.97 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
Mu (2)
= + 6.91 Tn-m
INGRESO DE DATOS :
Mu = +6.91 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.944 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.09 Tn-m > 6.91 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
Mu (3)
= -13.82 Tn-m
INGRESO DE DATOS :
Mu = -13.82 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 18.832 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 3 1/2 (19.002 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0289 <
Pmax = 0.0213
Mu (4)
= -15.01 Tn-m
INGRESO DE DATOS :
Mu = -15.01 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 21.116 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 3 5/8 (21.139 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0322 <
Pmax = 0.0213
Mu (5)
= + 7.99 Tn-m
INGRESO DE DATOS :
Mu = +7.99 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.162 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.92 Tn-m > 7.99 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
Mu (6)
= - 8.19 Tn-m
INGRESO DE DATOS :
Mu = -8.19 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.393 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.89 Tn-m > 8.19 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
PRIMER PISO
PARA :
WD = 4.04 TN/M.
WL = 1.28 TN/M.
PS = 18.2 TN.
Mu (1)
= -14.03 - Tn-m
INGRESO DE DATOS :
Mu = -14.03 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
p = 5/8 pulg.
= 8.831 cm2
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0059 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 14.59 Tn-m > 14.03 Tn-m
VERIFICACIN DEL b min.
b = 27.53 cm > 35 cm
Mu (2)
= +14.75 Tn-m
INGRESO DE DATOS :
Mu = -14.75 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.312 cm2
p = 5/8 pulg.
As ( suministrado) = 5 5/8
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
(9.897 cm2)
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.68 Tn-m > 14.75 Tn-m
VERIFICACIN DEL b min.
b = 27.84 cm > 35 cm
Mu (3)
= -29.11 Tn-m
INGRESO DE DATOS :
Mu = -29.11 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.864 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0132 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.70 Tn-m > 29.11 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 35 cm
Mu (4)
= -31.30 Tn-m
INGRESO DE DATOS :
Mu = -31.30 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 21.602 cm2
p = 1 pulg.
(25.335 cm2)
As ( suministrado) = 5 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0165 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 36.71 Tn-m > 31.30 Tn-m
VERIFICACIN DEL b min.
b = 32.77 cm > 35 cm
Mu (5)
= +17.15 Tn-m
INGRESO DE DATOS :
Mu = +17.15 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.069 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0074 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.66 Tn-m > 17.15 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 35 cm
Mu (6)
= -16.40 Tn-m
INGRESO DE DATOS :
Mu = -16.40 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.552 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0074 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.72 Tn-m > 16.40 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 35 cm
SEGUNDO PISO
PARA :
WD = 3.99 TN/M.
WL = 1.02 TN/M.
PS = 22.2 TN.
Mu (1)
= -16.22 Tn-m
INGRESO DE DATOS :
Mu = -16.22 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.55 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.53 Tn-m > 16.22 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (2)
= +12.82 Tn-m
INGRESO DE DATOS :
Mu = +12.82 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.199 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.85 Tn-m > 12.82 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -25.58 Tn-m
INGRESO DE DATOS :
Mu = -25.58 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.521 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.59 Tn-m > 25.58 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (4)
= -28.13 Tn-m
INGRESO DE DATOS :
Mu = -28.13 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.573 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.13 Tn-m > 28.13 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (5)
= +14.81 Tn-m
INGRESO DE DATOS :
Mu = +14.81 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.564 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.69 Tn-m > 14.81 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (6)
= -18.71 Tn-m
INGRESO DE DATOS :
Mu = -18.71 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.328 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0099 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.71 Tn-m > 18.71 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 30 cm
TERCER PISO
PARA :
WD = 3.99 TN/M.
WL = 1.02 TN/M.
PS = 30.3 TN.
Mu (1)
= -16.66 Tn-m
INGRESO DE DATOS :
Mu = -16.66 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.86 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.49 Tn-m > 16.66 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (2)
= +12.72 Tn-m
INGRESO DE DATOS :
Mu = +12.72 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.131 cm2
p = 1 pulg.
As ( suministrado) = 2 1 (10.134 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.85 Tn-m > 12.72 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -25.30 Tn-m
INGRESO DE DATOS :
Mu = -25.30 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.300 cm2
p = 1 pulg.
As ( suministrado) = 3 1 + 1 3/4 (18.051 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0137 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 26.40 Tn-m > 25.30 Tn-m
VERIFICACIN DEL b min.
b = 27.05 cm > 30 cm
Mu (4)
= -27.95 Tn-m
INGRESO DE DATOS :
Mu = -27.95 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.426 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.16 Tn-m > 27.95 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (5)
= +14.66 Tn-m
INGRESO DE DATOS :
Mu = +14.66 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.460 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.53 Tn-m > 16.22 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (6)
= -19.16 Tn-m
INGRESO DE DATOS :
Mu = -19.16 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.654 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0099 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.66 Tn-m > 19.16 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 30 cm
CUARTO PISO
PARA :
WD = 3.99 TN/M.
WL = 1.02 TN/M.
PS = 27.7 TN.
Mu (1)
= -11.63 Tn-m
INGRESO DE DATOS :
Mu = -11.63 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.307 cm2
p = 5/8 pulg.
As ( suministrado) = 4 5/8 (7.917 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0060 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 12.60 Tn-m > 11.63 Tn-m
VERIFICACIN DEL b min.
b = 23.76 cm > 30 cm
Mu (2)
= +14.23 Tn-m
INGRESO DE DATOS :
Mu = +14.23 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.163 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.74 Tn-m > 14.23 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (3)
= -28.37 Tn-m
INGRESO DE DATOS :
Mu = -28.37 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.163 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.74 Tn-m > 14.23 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (4)
= -30.25 Tn-m
INGRESO DE DATOS :
Mu = -30.25 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 23.251 cm2
p = 1 pulg.
As ( suministrado) = 4 1 + 3 1/2 (24.069 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0194 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 31.31 Tn-m > 30.25 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (5)
= +16.70 Tn-m
INGRESO DE DATOS :
Mu = +16.70 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.888 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.49 Tn-m > 16.70 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (6)
= -13.65 Tn-m
INGRESO DE DATOS :
Mu = -13.65 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.765 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.78 Tn-m > 13.65 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
PRIMER PISO
PARA :
WD = 4.00 TN/M.
WL = 1.26 TN/M.
PS = 18.2 TN.
Mu (1)
= -13.91 Tn-m
INGRESO DE DATOS :
Mu = -13.91 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
p = 1 pulg.
= 8.858 cm2
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0066 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.91 Tn-m > 13.91 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 35 cm
Mu (2)
= +14.51 Tn-m
INGRESO DE DATOS :
Mu = +14.51 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.263 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0066 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.88 Tn-m > 14.51 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 35 cm
Mu (3)
= -28.70 Tn-m
INGRESO DE DATOS :
Mu = -28.70 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.543 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0132 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.77 Tn-m > 28.70 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 35 cm
Mu (4)
= -31.00 Tn-m
INGRESO DE DATOS :
Mu = -31.00 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 21.361 cm2
p = 1 pulg.
(25.335 cm2)
As ( suministrado) = 5 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0165 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 36.77 Tn-m > 31.00 Tn-m
VERIFICACIN DEL b min.
b = 32.77 cm > 35 cm
Mu (5)
= +16.80 Tn-m
INGRESO DE DATOS :
Mu = +16.80 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.827 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0074 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.69 Tn-m > 16.80 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 35 cm
Mu (6)
= -16.31 Tn-m
INGRESO DE DATOS :
Mu = -16.31 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 35 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.49 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0074 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.73 Tn-m > 16.31 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 35 cm
SEGUNDO PISO
PARA :
WD = 3.95 TN/M.
WL = 1.01 TN/M.
PS = 22.2 TN.
Mu (1)
= -16.10 Tn-m
INGRESO DE DATOS :
Mu = -16.10 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.465 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0074 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.54 Tn-m > 16.10 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (2)
= +12.66 Tn-m
INGRESO DE DATOS :
Mu = +12.66 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.090 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.86 Tn-m > 12.66 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -25.30 Tn-m
INGRESO DE DATOS :
Mu = -25.30 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.300 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.64 Tn-m > 25.30 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (4)
= -27.88 Tn-m
INGRESO DE DATOS :
Mu = -27.88 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.368 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.18 Tn-m > 27.88 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (5)
= +14.57 Tn-m
INGRESO DE DATOS :
Mu = +14.57 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.398 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.71 Tn-m > 14.57 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (6)
= -18.64 Tn-m
INGRESO DE DATOS :
Mu = -18.64 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.227 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 2 1/2 (12.668 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0096 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 19.23 Tn-m > 18.64 Tn-m
VERIFICACIN DEL b min.
b = 25.15 cm > 30 cm
TERCER PISO
PARA :
WD = 3.95 TN/M.
WL = 1.01 TN/M.
PS = 30.3 TN.
Mu (1)
= -16.54 Tn-m
INGRESO DE DATOS :
Mu = -16.54 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.775 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.50 Tn-m > 16.54 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (2)
= +12.55 Tn-m
INGRESO DE DATOS :
Mu = +12.55 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.016 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.87 Tn-m > 12.55 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -25.02 Tn-m
INGRESO DE DATOS :
Mu = -25.02 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 17.080 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.69 Tn-m > 25.02 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (4)
= -27.70 Tn-m
INGRESO DE DATOS :
Mu = -27.70 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.222 cm2
p = 1 pulg.
(20.268 cm2)
As ( suministrado) = 4 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.54 Tn-m > 16.10 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (5)
= +14.41 Tn-m
INGRESO DE DATOS :
Mu = +14.41 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.288 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.72 Tn-m > 14.41 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (6)
= -19.10 Tn-m
INGRESO DE DATOS :
Mu = -19.10 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.6111 cm2
p = 1 pulg.
(15.201 cm2)
As ( suministrado) = 3 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0116 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 23.02 Tn-m > 19.10 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
CUARTO PISO
PARA :
WD = 3.95 TN/M.
WL = 1.01 TN/M.
PS = 27.7 TN.
Mu (1)
= -11.55 Tn-m
INGRESO DE DATOS :
Mu = -11.55 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.342 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.94 Tn-m > 11.55 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (2)
= +14.04 Tn-m
INGRESO DE DATOS :
Mu = +14.04 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.033 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.75 Tn-m > 14.04 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
Mu (3)
= -28.02 Tn-m
INGRESO DE DATOS :
Mu = -28.02 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 19.483 cm2
p = 1 pulg.
As ( suministrado) = 4 1 (20.268 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0154 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 29.15 Tn-m > 28.02 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (4)
= -30.01 Tn-m
INGRESO DE DATOS :
Mu = -30.01 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 23.021 cm2
p = 1 pulg.
As ( suministrado) = 4 1 + 2 5/8 (24.227 cm2)
N DE CAPAS :
2 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0196 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 31.58 Tn-m > 30.01 Tn-m
VERIFICACIN DEL b min.
b = 27.69 cm > 30 cm
Mu (5)
= +16.41 Tn-m
INGRESO DE DATOS :
Mu = +16.41 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 10.683 cm2
p = 1 pulg.
As ( suministrado) = 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0087 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 17.51 Tn-m > 16.41 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 30 cm
Mu (6)
= -13.62 Tn-m
INGRESO DE DATOS :
Mu = -13.62 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 30 cm
fy = 4200 kg/cm2
h= 50 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.744 cm2
p = 1 pulg.
As ( suministrado) = 2 1 (10.134 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0077 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 15.78 Tn-m > 13.62 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 30 cm
PRIMER PISO
PARA :
WD = 1.99 TN/M.
WL = 0.63 TN/M.
PS = 18.2 TN.
Mu (1)
= - 8.93 Tn-m
INGRESO DE DATOS :
Mu = -8.93 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
RESULTADOS :
AREA DE ACERO
fy = 4200 kg/cm2
h= 40 cm
As (requerido)
= 7.597 cm2
p = 1 pulg.
(10.134 cm2)
As ( suministrado) = 2 1
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0120 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.91 Tn-m > 8.93 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
Mu (2)
= + 6.61 Tn-m
INGRESO DE DATOS :
Mu = +6.61 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.406 cm2
p = 5/8 pulg.
As ( suministrado)= 2 5/8 + 2 1/2
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
(6.492 cm2)
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.94 Tn-m > 6.61 Tn-m
VERIFICACIN DEL b min.
b = 23.12 cm > 25 cm
Mu (3)
= -13.15 Tn-m
INGRESO DE DATOS :
Mu = -13.15 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.739 cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 5/8
N DE CAPAS :
(12.113 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0143 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.57 Tn-m > 13.15 Tn-m
VERIFICACIN DEL b min.
b = 21.65 cm > 25 cm
Mu (4)
= -14.47 Tn-m
INGRESO DE DATOS :
Mu = -14.47 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 13.136 cm2
p = 1 pulg.
As ( suministrado)= 3 1
N DE CAPAS :
(15.201 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0180 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 16.74 Tn-m > 14.47 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 25 cm
Mu (5)
= + 7.59 Tn-m
INGRESO DE DATOS :
Mu = +7.59 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.267 cm2
p = 5/8 pulg.
As ( suministrado)= 2 5/8 + 1 3/4
N DE CAPAS :
(6.809 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0080 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 8.25 Tn-m > 7.59 Tn-m
VERIFICACIN DEL b min.
b = 19.99 cm > 25 cm
Mu (6)
= -10.33 Tn-m
INGRESO DE DATOS :
Mu = -10.33 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 40 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.922 cm2
p = 1 pulg.
As ( suministrado)= 2 1
N DE CAPAS :
(10.134 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0120 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.73 Tn-m > 10.33 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
SEGUNDO PISO
PARA :
WD = 1.99 TN/M.
WL = 0.50 TN/M.
PS = 22.2 TN.
Mu (1)
= - 9.27 Tn-m
INGRESO DE DATOS :
Mu = -9.27 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.668 cm2
p = 1 pulg.
As ( suministrado)= 2 1
N DE CAPAS :
(10.134 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.72 Tn-m > 9.27 Tn-m
VERIFICACIN DEL b min.
b = 17.53 cm > 25 cm
Mu (2)
= + 5.92 Tn-m
INGRESO DE DATOS :
Mu = +5.92 Tn-m.
p = 5/8 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.753 cm2
p = 5/8 pulg.
As ( suministrado)= 3 5/8
N DE CAPAS :
(5.938 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0081 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 6.11 Tn-m > 5.92 Tn-m
VERIFICACIN DEL b min.
b = 19.67 cm > 25 cm
Mu (3)
= -11.84 Tn-m
INGRESO DE DATOS :
Mu = -11.84 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.937 cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0180 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.88 Tn-m > 11.84 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 25 cm
Mu (4)
= -13.23 Tn-m
INGRESO DE DATOS :
Mu = -13.23 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.877 cm2
p = 1 pulg.
As ( suministrado)= 3 1
N DE CAPAS :
(15.201 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0211 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.52 Tn-m > 13.23 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 25 cm
Mu (5)
= + 6.78 Tn-m
INGRESO DE DATOS :
Mu = +6.78 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.800 cm2
p = 1 pulg.
As ( suministrado)= 1 1 + 2 1/2 (7.601 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0106 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.58 Tn-m > 6.78 Tn-m
VERIFICACIN DEL b min.
b = 20.07 cm > 25 cm
Mu (6)
= -10.63 Tn-m
INGRESO DE DATOS :
Mu = -10.63 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.353cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 1/2(11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0158 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.68 Tn-m > 10.63 Tn-m
VERIFICACIN DEL b min.
b = 21.34 cm > 25 cm
TERCER PISO
PARA :
WD = 1.99 TN/M.
WL = 0.50 TN/M.
PS = 30.3 TN.
Mu (1)
= - 9.47 Tn-m
INGRESO DE DATOS :
Mu = -9.47 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 9.91 cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 1/2 (11.401 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0158 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.89 Tn-m > 9.47
Tn-m
Mu (2)
= + 5.87 Tn-m
INGRESO DE DATOS :
Mu = +5.87
Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 5.81
cm2
p = 1 pulg.
As ( suministrado)= 1 1 + 2 1/2 ( 7.601 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0106 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.68
Tn-m >
5.87 Tn-m
Mu (3)
= -11.72 Tn-m
INGRESO DE DATOS :
Mu = -11.72 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 12.776 cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 3/4 (12.984 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0180 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.91 Tn-m > 11.72 Tn-m
VERIFICACIN DEL b min.
b = 21.97 cm > 25 cm
Mu (4)
= -13.16 Tn-m
INGRESO DE DATOS :
Mu = -13.16 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.775 cm2
p = 1 pulg.
As ( suministrado)= 3 1
N DE CAPAS :
(15.201 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0211 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.54 Tn-m > 13.16 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 25 cm
Mu (5)
= + 6.72 Tn-m
INGRESO DE DATOS :
Mu = +6.72 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.734 cm2
p = 1 pulg.
As ( suministrado)= 1 1 + 2 1/2 (7.601 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0106 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.59 Tn-m > 6.72 Tn-m
VERIFICACIN DEL b min.
b = 20.07 cm > 25 cm
Mu (6)
= -10.83 Tn-m
INGRESO DE DATOS :
Mu = -10.83 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 11.609 cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 5/8 (12.113 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0168 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 11.30 Tn-m > 10.83 Tn-m
VERIFICACIN DEL b min.
b = 21.65 cm > 25 cm
CUARTO PISO
PARA :
WD = 1.99 TN/M.
WL = 0.50 TN/M.
PS = 27.7 TN.
Mu (1)
= - 7.41 Tn-m
INGRESO DE DATOS :
Mu = -7.41 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.502 cm2
p = 1 pulg.
As ( suministrado)= 1 1 + 2 5/8 (9.026 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0125 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 8.91 Tn-m > 7.41 Tn-m
VERIFICACIN DEL b min.
b = 20.70 cm > 25 cm
Mu (2)
= + 6.48 Tn-m
INGRESO DE DATOS :
Mu = +6.48 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 6.471 cm2
p = 1 pulg.
As ( suministrado)= 1 1 + 2 1/2 (7.601 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0106 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 7.61 Tn-m > 6.48 Tn-m
Mu (3)
= -12.96 Tn-m
INGRESO DE DATOS :
Mu = -12.96 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 14.489 cm2
p = 1 pulg.
As ( suministrado)= 3 1
N DE CAPAS :
(15.201 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0211 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 13.60 Tn-m > 12.96 Tn-m
VERIFICACIN DEL b min.
b = 22.61 cm > 25 cm
Mu (4)
= -14.11 Tn-m
INGRESO DE DATOS :
Mu = -14.11 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 16.183 cm2
p = 1 pulg.
As ( suministrado)= 2 1 + 1 9/8 (16.547 cm2)
N DE CAPAS :
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0230 <
Pmax = 0.0213
Mu (5)
= + 7.50 Tn-m
INGRESO DE DATOS :
Mu = +7.50 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 7.604 cm2
p = 1 pulg.
As ( suministrado)= 2 1
N DE CAPAS :
(10.134 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 10.00 Tn-m > 7.50 Tn-m
VERIFICACIN DEL b min.
b = 17.84 cm > 25 cm
Mu (6)
= - 8.64 Tn-m
INGRESO DE DATOS :
Mu = -8.64 Tn-m.
p = 1 pulg.
fc= 280 kg/cm2
a
= d/5
= 25 cm
fy = 4200 kg/cm2
h= 35 cm
RESULTADOS :
AREA DE ACERO
As (requerido)
= 8.918 cm2
p = 1 pulg.
As ( suministrado)= 2 1
N DE CAPAS :
(10.134 cm2)
1 CAPAS
VERIFICACIN DE CUANTIAS
Pmin = 0.0033 < P = 0.0141 <
Pmax = 0.0213
MOMENTO NOMINAL
Mn = 9.82 Tn-m > 8.64 Tn-m
VERIFICACIN DEL b min.
b = 17.84 cm > 25 cm