EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO Armenio Flaubert Galindez Ore1, Julia Y. Acua Azarte2 SUMMARY This research was made at Huanuco province, it was based in the pursuit of six watering work, they were located in the following small watersheds : a) Cochatambo: Taprag Canal Improvement, Millpo Canal Improvement and Nocturnal Reservoirs Construction. b) Mito: Cedron Canal Construction, San Pablo de Mitotambo Canal Construction. c) Acomayo: Nueva Independencia Reservoir Construction. d) Pusucraga: La Esperanza, the Forest Nursery, Reservoirs Construction. In this buildings it was register and systematized the perfomance and units cost by budget approvement. The period of evaluation was since the instalation until the finichied of work (January 1997 to January 1998). It got values of perfomance of labor, especifically in the construction of canals and reservoirs, ecuation of zones with similar climatic condition, topographics and the common peoples organization, unit costs and budget for each buildings in pursuit. Finally the real time of ejecution of the six works in research was slowed down in 100% as a consequence of the expansion of the initial phisical goals we obtain values of profit hand work especifially in the buildins of canals and reservoirs for the common people contribution and the own difficulties of transport of materials (Lima Huanuco). RESUMEN El presente estudio se desarroll en la provincia de Hunuco, a base del seguimiento de seis obras de riego; ubicadas en las siguientes microcuencas que seguidamente se detallan. En Cochatambo: Mejoramiento Canal Taprag, Mejoramiento Canal Millpo y Construccin Reservorio Nocturno.En Mito:Construccin Canal Cedrn y Construccin Canal San Pablo de Mitotambo. En Acomayo:Construccin Reservorio Nueva Independencia. Por ltimo en Pusucraga: Construccin Reservorio Vivero Forestal La Esperanza. En estas obras se registr y sistematiz datos de rendimientos y costos unitarios por partida ejecu1

Profesor Principal de la Facultad de Ingeniera Agrcola, en el Dpto. de Mecanizacin Agrcola Egresada de la UNALM

284

Anales Cientficos UNALM

tada en cada obra. El, periodo de evaluacin comprendi desde la instalacin hasta la liquidacin de obra (Enero 1997 a Enero 1998). Se obtuvo valores de rendimientos de mano de obra especficamente en la construccin de canales y reservorios, ecuaciones de estimacin para zonas con similares condiciones climticas, topogrficas y de organizacin comunal, costos unitarios y presupuestos por cada obra en seguimiento. Finalmente el tiempo real de ejecucin de las seis obras en estudio se retras el 100%, como consecuencia de la ampliacin de las metas fsicas iniciales originado por el aporte comunal y las dificultades propias de transporte de materiales (Lima- Hunuco ). I. INTRODUCCION Existen valores estandarizados de rendimientos de mano de obra, emitidos por la Cmara Peruana de Constructores (CAPECO), para obras de edificacin urbanas. Rendimientos que han sido obtenidos con cuadrillas totalmente remuneradas. Por carencia de sta informacin para obras de riego, slo se estiman tomando como base lo especificado por CAPECO. Sobre la base de esta estimacin, se formulan los expedientes tcnicos de los proyectos para obras rurales; ocasionando desfases en el cumplimiento de la programacin e incompatibilidad entre las valorizaciones presupuestadas y las reales. Por lo tanto, se realiz la evaluacin de rendimientos y costos unitarios en la construccin de canales y reservorios; ejecutadas con apoyo de mano de obra comunal. Estrategia de trabajo que al Ministerio de Agricultura le permite financiar la construccin de mayor nmero de pequeas obras de riego en las zonas andinas del Per, con la finalidad de satisfacer la demanda de agua de agricultores, ganaderos, empresas de saneamiento, etc., siendo las comunidades las mayores beneficiadas quienes con su aporte de mano de obra contribuyen en la ejecucin del proyecto. Empero, la desventaja que presenta esta metodologa es la prolongacin del plazo de ejecucin, debido a factores sociales, topogrficos y climticos influyendo en el rendimiento de la mano de obra y por consiguiente en los costos unitarios de cada partida ejecutada. Por todo lo antes mencionado el objetivo que se plantea es : Determinar y evaluar los rendimientos y costos unitarios en la construccin de canales y reservorios con participacin comunal en la provincia de Hunuco . II. REVISION BIBLIOGRAFICA 2.1 LAS CUENCAS HIDROGRFICAS Y SU MANEJO La cuenca hidrogrfica, es el rea delimitada por la divisoria de aguas, y esta comprendida dentro de una formacin topogrfica en la cual las aguas de escurrimiento concurren a un mismo cauce. La cuenca es definida como el espacio geogrfico idneo, que sirve de base para la planificacin de actividades, constituye el marco prctico y objetivo para el desarrollo y crecimiento econmico con equidad y sustentabilidad ambiental. La disponibilidad de agua a nivel mundial viene disminuyendo por di-

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

285

versos motivos como : la deforestacin de las cuencas, el uso irracional de sus recursos naturales y la contaminacin creciente de los cursos del agua, factores que nos estn llevando a una dramtica situacin en la que la demanda de agua es mayor que la oferta, hacindo es necesario optimizar el manejo del recurso hidrulico ejecutando un conjunto de acciones para el uso y control del agua en todas sus formas y manifestaciones con el fin de incrementar su oferta. ROCHA (1993) menciona que los proyectos de aprovechamiento y control de los recursos hidrulicos contribuyen al desarrollo social, econmico y calidad de vida. Consta de 3 elementos: el agua, el hombre y la naturaleza. Todo proyecto de aprovechamiento hidrulico buscar cubrir la demanda hdrica de los cultivos y disminuir la errtica distribucin temporal y espacial. Las comunidades campesinas son las ms vinculadas al agro y estn localizadas en la Sierra Sur y Sierra Central entre los 2000 a 4000 m.s.n.m., en las regiones Quechua y Suni y pocas se encuentran en la Sierra Norte y son mnimas en la regin costa y selva del Per. La Ley de la Reforma Agraria y el Estatuto Especial de Comunidades Campesinas define a las comunidades campesinas, como una agrupacin de familias que poseen y se identifican con un determinado territorio y estn ligados por rasgos sociales y culturales comunes, por el trabajo comunal y ayuda mutua.

2.2 RENDIMIENTO DE MANO DE OBRA El rendimiento de la mano de obra se define como la cantidad de trabajo desarrollado por persona o cuadrilla en una unidad de tiempo(da u hora). Por Resolucin Ministerial 175 del 9/ 04/1968 rigen normas para la aplicacin de los rendimientos mnimos oficiales de la mano de obra en la Industria de la Construccin Civil, en el Ramo de Edificacin para las provincias de Lima y Callao, ms no para obras de riego ejecutadas en zonas urbanas y rural; estimndose a base de ello las correspondientes para obras de riego ejecutadas con aporte comunal. COTRINA (1995) menciona que lo ms indicado para la consistencia de rendimientos en mano de obra es el promedio aritmtico o el promedio geomtrico y utiliza el aritmtico por ser el ms exacto. 2.3 ANALISIS DE COSTOS En el anlisis de costos se deber tener en cuenta los siguientes aspectos: Partidas.- Se entiende por Partida a la estructura de gastos para fines de medicin, evaluacin y pago. Costos.- son los valores econmicos de recursos reales o financiados utilizados para producir un bien, producto o servicio. Esta conformada por recursos de capital, esfuerzo de trabajo y tiempo. La forma comn de clasificar es por el objeto de gasto en costos directos e costos indirectos;

286

Anales Cientficos UNALM

y de acuerdo a la variacin de la cantidad producida en costos fijos y costos variables. Costo unitario.- Es el costo que corresponde a una sola unidad de medida de un determinado bien, producto o servicio. El anlisis de costos unitarios se evala por unidades de medicin establecidas (m3, m2, kg, m) que contienen las cantidades va lorizadas e insumos de materiales que necesita dicha unidad. 2.3.1 COSTOS DIRECTOS El costo directo (CD) comprende los gastos incurridos directamente en la construccin de las obras; como materiales, mano de obra, equipos y herramientas necesarios para construccin de una obra. Los precios unitarios y coeficientes de aporte de cada elemento se obtuvieron como sigue: 1. Materiales.- Son bienes de consumo utilizados, que pueden cuantificarse en unidades de comercializacin. Ejemplo: bolsas (bls) de cemento, metro cbico (m3) de arena, pie cuadrado (p2) de madera o kilogramo (kg) de acero. Los precios de adquisicin deben ser actualizados para el anlisis de costos en funcin al tiempo de ejecucin, condiciones topogrficas; a stos deben adicionarse el costo de transporte. El coeficiente de aporte es la cantidad de materiales que intervienen en la produccin de una partida de acuerdo a condiciones preestablecidas fsicas o geomtricas. Para fines de evaluacin de la presente se obtuvo de tablas

ajustadas con el 3% de desper dicios. 2. Mano de Obra .- Es la fuerza de trabajo utilizada en la ejecucin de las obras, cuyo coeficiente de aporte se estima a base del rendimiento diario, jornada de 8 horas da (h/d) .Se calcula para cada categora del personal. Ejemplo: Coeficiente pen = No de peones x No de horas de trabajo/ rendimiento diario Herramientas y Equipo-Maquinaria.- El costo por herramientas, se determina por un coeficiente de uso, determinado de acuerdo a la experiencia. En el caso de equipos-maquinarias su costo se determina en funcin del rendimiento de cada unidad. El coeficiente esta en funcin a la incidencia de utilizacin de herramientas. Generalmente se designa el 5% del costo total de la mano de obra de una partida especfica. Para el caso de equipos-maquinaria se recopilo de la publicacin mensual del Grupo S-10 (Costos, mayo1998) .

3.

2.3.2 COSTOS INDIRECTOS Los costos indirectos estn conformadas por la suma de todos los gastos que no intervienen de manera intrnseca en el avance de una obra; pero que son necesarios y aplicables en su construccin; estos gastos son aquellos que deben incurrirse para el apoyo y administracin durante la construccin. Los costos indirectos estn constituidos por:

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

287

A.

Gastos generales no relacionados con el tiempo de ejecucin de obra. Este, corresponde a los gastos requeridos en el proceso de contratacin e instalacin. Gastos generales relacionados con el tiempo de ejecucin de la obra, son gastos que representan el mayor porcentaje de los gastos generales y esta comprendido por Sueldos del residente, Gastos de traslado del personal: maestro de obra, Botiqun (accidentes del personal tcnico), Papelera y tiles de escritorio, Gastos en pasajes y viticos para viajes del personal administrativo, etc.

Aspectos Concernientes a los Proyectos de Riego en Estudio En las cuatro microcuencas seleccionadas se ubican las 11 comunidades en estudio, donde se ejecutaron 10 obras; de las cuales se seleccionaron slo seis obras a base de los criterios de accesibilidad, altura sobre el nivel del mar y la distancia de la ciudad de Hunuco a la obra. Las caractersticas de cada uno de ellos fueron: 1. Proyecto Costruccin Canal Cedrn (P1) Se ubica en las coordenadas de Latitud 9524 y Altitud de 3,276 m.s.n.m.; comunidad de Raccha Cedrn-Microcuenca Mito, al margen derecho del ro Mito. Beneficia a 25 familias con la captacin de 6 lts./seg. de la quebrada Raccha e incorpora 12 hectreas bajo riego. La accesibilidad a la obra es relativamente tediosa por la presencia de una topgrafa abrupta entre 45% a 55 % de pendiente. La distancia de la ciudad de Hunuco a la obra es de 35 Km. Y las metas fsicas a alcanzar fueron: construccin de una bocatoma de concreto ciclpeo con fc = 140 Kg/cm2 + 30%PG, 1.0 Km. De canal y obras de arte de concreto simple, en un plazo de ejecucin de 3 meses. 2. Proyecto Construccin Canal San Pablo de Mitotambo (P2) Se ubica en las coordenadas geogrficas de Latitud de 9 7 31, Longitud 76 25 18 y Alti-

B.

III. MATERIALES Y METODOS 3.1 MATERIALES Los materiales utilizados para realizar el presente estudio fueron los siguientes: Teodolito, Mira, Altmetro, Wincha, Cronmetro, Escalmetro, Carta E:1/ 100000 de la Provincia de Hunuco, Expedientes Tcnicos, Liquidaciones de Obra y Cuadernos de Obra. 3.2 METODOLOGIA Area de estudio El presente estudio, se desarroll en el mbito de trabajo del PRONAMACHCS-Hunuco, ubicadas en las microcuencas: Cochatambo, Acomayo, Mito y Pusucraga. Ubicndose en ellas 6 obras de riego: 5 ejecutadas con mano de obra calificada ms aporte comunal y 1 (uno) sin aporte comunal.

288

Anales Cientficos UNALM

tud de 3200 m.s.n.m.; perteneciente a la comunidad San Pablo de Mitotambo-Microcuenca Mito, al margen izquierdo del ro Mito. Beneficia a 50 familias con la captacin de 30 Lts/seg. de la quebrada Uncumarca y Huancamarca. Incorpora 60 Has. bajo riego; la accesibilidad a la obra es moderadamente dificultosa, limitada por una topografa cuya pendiente est entre los 35% a 45%. Las distancia a la ciudad de Hunuco es de 29 Km. Las metas fsicas a ejecutarse fueron: Construccin de bocatoma en concreto ciclpeo fc = 140 Kg./cm2 + 30% P.G., 1.7 Km. de canal y obras de arte en concreto simple, en un plazo de ejecucin de 3 meses. 3. Proyecto Mejoramiento Canal Millpo y Construccin Reservorio Nocturno (P3) Se ubica en las coordenadas geogrficas de Latitud 9 14 15, Longitud 762 35, Alitud 3150 m.s.n.m.; perteneciente a la co munidad San Rafael de Millpo. Microcuenca Cochatambo. Beneficia a 60 familias, con la captacin de 6 lts/seg. de la quebrada Tinhuinllin e incorpora 30 Has bajo riego. La accesibilidad a la obra es limitada por la topografa abrupta de 45% a 55% de pendiente. La distancia a la ciudad de Hunuco es 35 Km. Las metas fsicas a ejecutarse fueron: La construccin de una bocatoma de concreto armado fc = 175 Kg/cm2, reservorio de 250 m3 de capacidad, apoyado en tierra, 1.5 Km de canal y obras

4.

de arte de concreto simple, con un plazo de ejecucin de 3 me ses. Proyecto Mejoramiento Canal Taprag (P4) Se ubica en las coordenadas geogrficas de Latitud 9 14 46, Longitud 76230 y Altitud 2800 m.s.n.m.; perteneciente a la comunidad de Nuevo Progreso de Taprag- Microcuenca Cochatambo. Beneficia a 80 familias, con la captacin de 30 lts/seg. de la quebrada Cochatambo e incorpora 60 Has bajo riego. La accesibilidad a la obra es moderada pues la topografa es de 30% a 40% de pendiente. La distancia a la ciudad de Hunuco es 33 Km. Las metas fsicas a ejecutarse fueron: La construccin de una bocatoma de concreto ciclpeo fc = 175 Kg/cm2 + 30 %PG., 1.6 Km. de canal y obras de arte de concreto simple, con un plazo de ejecucin de 3 meses.

5. Proyecto Construccin Reservorio Nueva Independencia (P5) Se ubica en las coordenadas geogrficas de Latitud 9 13 54, Longitud 7649 y Altitud 2400 m.s.n.m.; perteneciente a la comunidad de Nueva Independencia- Microcuenca Acomayo. Beneficia a 35 familias, con la captacin de 6 lts/seg. de la quebrada Micharragra e incorpora 40 Has bajo riego. La accesibilidad a la obra es moderada pues la topografa es de 30% a 40% de pendiente. La distancia a la ciudad de Hunuco es 30 Km. Las metas fsi-

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

289

cas a ejecutarse fueron: La construccin de un reservorio de 640 m3 de capacidad, impermeabilizado con GV1 y obras de arte de concreto simple, con un plazo de ejecucin de 2.5 meses. 6. Proyecto Construccin Reservorio Vivero Forestal La Esperanza (P6) Se ubica en las coordenadas geogrficas de Latitud 9 6 6, Longitud 761258 y Altitud 1940 m.s.n.m.; perteneciente a la comunidad La Esperanza - Microcuenca Pusucragra. Beneficia a 12 familias, con la captacin de 6 lts/seg. de la quebrada Pusucragra e incorpora 12 Has bajo riego. La accesibilidad a la obra es suave pues la topografa es de 10% a 20% de pendiente. La distancia a la ciudad de Hunuco es 5 Km. Las metas fsicas a ejecutarse fueron: La construccin de un reservorio de 90 m3 de capacidad, en concreto armado, fc = 175 Kg/cm2 y obras de arte de concreto simple, con un plazo de ejecucin de 1.5 meses. Aspectos Concernientes al Levantamiento de Informacin El registro de informacin se realiz a base de los siguientes criterios: 1. Clasificacin de la informacin de ubicacin geogrfica de las seis obras segn el grado de accesibilidad, altitud y costo de transporte. 2. Elaboracin y distribucin de formatos para la recopilacin de rendimientos y costos unitarios a los

respectivos residentes y operarios de cada obra. 3. Las mediciones de avance de obra por partida, se efectuaron a base del reglamento de metrados para obras, el tiempo efectivo en la ejecucin y el nmero de participantes de la comunidad por partida ejecutada. La toma de datos fue diaria en los proyectos P2 y P5; semanalmente en los proyectos P1, P3, P4, P6 Las caractersticas de las obras se detalla en el Anexo N 01. Procedimiento de Evaluacin a) Evaluacin de Rendimientos de Mano de Obra Para determinar los rendimientos de mano de obra se analiz los datos de avances y tiempos de ejecucin por partidas consolidndose con el anlisis de tendencia central, como son los promedios de las tres medias: aritmtica, gemtrica y armnica. Los factores de accesibilidad fortaleza fsica y organizacin comunal, no intervinieron en el anlisis, por ser variables cualitativas y hasta cierto punto subjetivas. Los rendimientos se han evaluado para 1h, 5.5 h y 8 h (ver Anexo 1.3), remunerndose a la cuadrilla conformada por capataz (cap), operario (op), oficial (of) y pen (pn). Para evitar confusiones, el aporte comunal se identific como faenero. La valorizacin de los jornales tanto, del capataz, oficial y pen, se hizo en funcin al grado de participacin de estos en las diferentes actividades. La evaluacin se efectu entre los valores de rendimientos presupues-

290

Anales Cientficos UNALM

tados, a base de una estimacin de los rendimientos mnimos para obras de edificacin; y los ejecutados en el campo. Se agrup en partidas de primer orden, determinndose por unidad de cuadrilla, para su anlisis. La variabilidad de este resultado con respecto a los datos de las observaciones, se calcul con la frmula de Desviacin Estndar. La estimacin de rendimientos consider la influencia sobre ste, a cuatro variables cuantificables: Tiempo Efectivo, cantidad de participantes comunales, temperatura promedio diaria y precipitacin diaria. Siendo afianzada por un anlisis de regresin mltiple. Los datos de precipitacin, temperatura mxima y mnima diarios, fueron obtenidos de la Estacin Meteorolgica Cayhuayna y San Rafael, ubicados a una altitud de 1950 y 2950 m.s.n.m. en las provincias de Hunuco y Ambo respectivamente. b) Evaluacin de Costos Unitarios La determinacin de los costos unitarios, comprendi cotizaciones de materiales, herramientas, equipo y maquinaria de tres empresas ubicadas en la ciudad de Hunuco, estimndose el precio promedio de cada artculo. Los costos de mano de obra fueron los valores remitidos por la Direccin Tcnica de Infraestructura Rural (DTIR), donde consideraba que la hora hombre (hh) capataz, operario, oficial es de S/. 4.62, S/. 4.22, S/.3.83 respectivamente. El coeficiente de aporte para materiales, herramientas, equipos y IV. 4.1

maquinaria, se recopil de las tablas CAPECO y se reajust con el 3% por desperdicios y desgaste. Los presupuestos reales por obra, se obtuvo a base de los costos unitarios evaluados, el metrado de liquidacin; adicionndose los gastos generales (6% C.D.). El tiempo de ejecucin se esquematiz con el diagrama de Gantt y la ruta crtica con el mtodo PERT-CPM. RESULTADOS Y DISCUSION RENDIMIENTOS DE MANO DE OBRA En el Cuadro No 1 se muestra los rendimientos de mano de obra, habindose obtenido un resultado ptimo para P3 con 200 m2/d/h y el menor rendimiento de 175 m2/d/ h para P4. Para reservorios se realiz manualmente, observndose que los resultados estuvieron en funcin de las dimensiones de la capacidad de almacenamiento. En el Cuadro No 2 se presenta los rendimientos por acarreo de materiales: hormign, piedras, cemento y tubos. Considerndose los parme-tros de fuente de extraccin, distancia de acarreo y modalidad de traslado. En el Cuadro No 3. La excavacin de plataforma(remocin de ladera de 1.3m de ancho por 1m de altura) y zanjas (secciones cuadradas). El mayor rendimiento fue desarrollado por P4 en material suelto, normal seco y roca suelta, justificndose que a mayor compactacin de los suelos, los rendimientos de mano de

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

291

obra disminuyen. En el caso de relleno con material propio en canales, P 4 obtuvo 4.14 m3/d/h y para reservorio (P 6 ), fue de 1.42 m3/d/h, observndose una diferencia del 34.30%. En el Cuadro N 4 que corresponde a la excavacin manual (P1), se de-

termin 3.64 m3/d/h y para (P3), se consigui 2.59 m3/d/h, diferencindose en 28.85%; ya que al P1 se les remuner en mano de obra en esta actividad. Y en la excavacin a maquinaria (cargador frontal WA 320) P6 obtuvo 147.6 m3/d/h en material suelto y para el P5 se lleg a 70.97 m3/ d/h en material de rocas suelta.

CUADRO No 1. RENDIMIENTOS EN TRAZO, NIVELES Y REPLANTEO. CANALES Rend. Presupuestado Proyectos Ca p C. Cedrn (P1) C. Mitotambo (P2) C. Millpo (P3) C. Taprag (P4) RESERVORIOS R. Cedrn (P1) R. Millpo (P3) R. Independencia(P5) R. La Esperanza (P6) 1 1 No presupuestado No presupuestado 1 1 3 1 400 100 80.00 33.33 1 1 1 1 1 1 1 1 6 5 5 2* 323 390 285 408 40.38 55.71 40.71 102.0 1 1 1 1 1 1 1 1 3 4 3 3 400 500 400 400 80.00 83.33 80.00 80.00 1 1 1 1 1 1 1 1 6 5 4 6 1600 1350 1200 1400 200.00 192.86 200.00 175.00 Cuadrilla op Top pn Rendimiento m2/d m2/d/h cap op Rend. Ejecutado Cuadrilla Top fae Rendimiento m2/d m2/d/h

CUADRO No 2. RENDIMIENTOS EN ACARREO MATERIALES Rend. Ejecutado Proyectos Con esfuerzo humano C. Cedrn (P 1). A 0.3km C. Mitotam. (P 2). A 0.3km C. Taprag (P 4) . A 0.3km C. Millpo (P 3). A 0.3 km C. Millpo (P 3) . A 0.5km R. Indepen. (P 5). A 0.05km Con esfuerzo animal C. Cedrn (P 1) . A 1km C. Mitotambo (P 2). A 1.5km 0.1 0.1 1* 2* 1.0 0.91 6 12 5.45 5.71 9 8.2 0.1 0.1 0.1 0.1 0.1 0.1 1* 1 1 1 1 1 2.20 0.95 0.88 2.30 2.00 0.86 0.80 2.09 1.40 1.05 0.92 0.82 1.50 1.27 0.95 0.84 0.75 1.36 4 3 4 3 5 3.64 2.73 3.64 2.73 4.55 12 11 10.9 10.0 Cuadrilla Cap Fae Hormign m 3/d m 3/d/h Piedra M 3/d m 3/d/h Cemento bls/d bls/d/h Tubos u/d u/d

*pen, a excepcin del acarreo de tubos en P 1 que se realiz con faenero.

292

Anales Cientficos UNALM

CUADRO No EN MOVIMIENTO DE DE TIERRA. PLATAFORMA - ZANJAS CUADRO N 3. 3.RENDIMIENTOS RENDIMIENTOS EN MOVIMIENTO TIERRA. PLATAFORMA-ZANJAS Rend. Presupuestado Proyectos Cap EX.DE PLATAFORMA C. Cedrn (P1) C. Millpo (P3) C. Taprag (P4) EX. DE ZANJAS C. Cedrn (P1) C. Mitotambo (P2) C. Millpo (P3) C. Taprag (P4) 0.1 0.1 0.1 0.1 1 1 1 1 3.5 3.5 3.5 3.5 3.18 3.18 3.18 3.18 3.20 3.40 3.00 3.80 2.91 3.09 2.73 3.18 3.00 2.75 3.12 3.30 2.73 2.50 2.84 3.00 2.10 2.30 2.30 2.45 1.91 2.09 2.09 2.23 0.1 0.1 0.1 1 1 1 3.5 3.5 3.5 3.18 3.18 3.18 2.65 2.80 3.20 2.41 2.55 2.91 2.35 2.20 2.55 2.14 2.00 2.32 1.85 2.00 2.35 1.68 1.82 2.14 Cuadrilla pn m /d
3

Rend. Ejecutado Mat. Suelto Normal seco m /d


3

Roca suelta m /d
3

m /d/h

m /d

M /d/h

m /d/h

m3/d/h

En el Cuadro No 5 se muestran los resultados de los rendimientos de mano de obra en encofrado y desencofrado (E-D) de reservorio para el P5, donde se obtuvo 7.74, 6.45, 5.00 m2/d/h para alturas de trabajo de 1.2, 2.4 y 3.6 m respectivamente. Para E-D de obras de arte a doble muro, en el P3 se obtuvo 6.09 m2/d/ h por la experiencia del operario en tareas similares y para E-D en canales a un solo muro, para P4 se obtuvo 4.06 m2/d/h; y a doble muro en P1 se obtuvo 2.4 m2/d/h siendo estos los ms ptimos. En el Cuadro No 6 se observa los rendimientos en concreto simple (C.S.), destacando coincidentemente P1 y P6. Habindose obtenido 0.85m3/d/h en concreto fc = 140 Kg./cm2. En mampostera de piedra asentada en concreto fc = 140Kg./m2, P3 obtuvo 3.77 m2/d/h como el ms ptimo. Cabe sealar, que en las mezclas de C.C. fc= 140 Kg/cm2 + 30%PG y C.C.

fc=175Kg/m2 + 30% PG se obtuvo en P1 0.61 m3/d/h y en P4 se obtuvo 0.57 m3/d/h respectivamente como los ms ptimos. En el Cuadro No 7 se detallan los resultados en acero 3/8, y 5/8 el rendimiento ptimo fue realizado por P6, logrndose 72.58 Kg/d/h y 56.45 Kg/d/h para los dos primeros dimetros, mientras en P5 alcanz para el ltimo nivel de dimetro 34.63 Kg/d/h slo con mano de obra remunerada. En el Cuadro No 8 los rendimientos obtenidos en P5 fue de 4.02 m2/d/h en mortero c/a 1:4 y P3logr 3.51 m2/ d/h utilizando mortero paja-arena ar cillosa (p/a , 1:10). En el Cuadro No 9 la instalacin de Tubera PVC C-5 en el P3 se obtuvo 36 m/d/h como rendimiento ptimo en a instalacin de tuberas de 4 de dimetro. Debido a la flexibilidad del material que habilit su acople en curvas.

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

293

CUADRO No 4. RENDIMIENTOS EN EXCAVACION DE RESERVORIO Y RELLENO CON MATERIAL PROPIO


Rend. Presupuestado Proyectos Cap EXCAV. RESERVORIO R Esperanza Suelto Maq. (P6) R. Cedron. Manual (P1) R. Millpo. Manual (P3) R. Independencia. Maq. (P5) C. Cedrn (P1) C. Millpo (P3) C. Taprag (P4) R. La Esperanza (P6) 0.1 0.32 0.32 0.32 RELLENO CON MATERIAL PROPIO 1 3.2 3.2 3.2 1 5.0 5.0 5.0 3.5 1.42 1.42 1.42 0.64 0.1 0.1 0.1 0.1 1 1 1 1 2* 4.20 4.50 4.55 4.40 3.82 4.09 4.14 1.42 0.1 1 3.5 3.18 0.1 0.1 0.1 3.18 0.1 1 1 1 1 1* 1 2 310 4.00 2.85 220 147.6 3.64 2.59 70.97 No presupuestado No presupuestado 1 3.5 Cuadrilla Op of Pn
3

Rend. Ejecutado Cuadrilla


3

Rend. M /d M /d/h cap

Rend. fae m /d
3

op

of

M3/d/h

CU AD RO No 5. RENDIM IENTOS E N E NCOFRADO Y DES E NCOFR ADO (E -D) Rend. Presupuestado P ro yectos cap C. Cedrn (P 1 ). Bocat. C. Mitotam bo (P 2 ). Bocat. C. Millpo (P 3 ). Bocat. C. Taprag (P 4 ). Bocat. R. Esperanza (P 6 ) . Reser. R. Indepen (P 5 ) . Reser. A 2.4m A 3.6m OBRAS DE ARTE C. Cedrn (P 1 ) C. Mitotam bo (P 2 ) C. Millpo (P 3 ) C. Taprag (P 4 ) R. Independencia (P 5 ) CAN ALE S C. Mitotam bo (P 2 ) a 2m uro C. Taprag (P 4 ) a 2 m uro C. Cedrn (P 1 ) a 1 m uro C. Mitotam bo (P 2 ) a 1m uro C. Taprag (P 4 ) a 1 m uro 0.1 0.1 0.1 0.1 0.1 0.7 0.7 0.7 1.0 0.7 0.7 0.7 0.7 1.0 0.7 3 8 8 8 12 8 5.23 5.23 5.23 2.35 5.23 0.1 0.1 0.1 0.1 0.1 1 1 1 1 1 1 1 1 1 1 3.0 2.5 2.0 3.0 3.2 15.0 12.0 13.5 20.4 21.5 2.94 2.61 3.29 4.00 4.06 0.1 0.1 0.1 0.1 0.1 0.7 1.0 0.7 0.7 0.7 0.7 1.0 0.7 0.7 0.7 3 8 12 8 8 8 5.23 2.35 5.23 5.23 5.23 0.1 0.1 0.1 0.1 0.1 1 1 1 1 1 1 1 1 1 1 2.0 3.0 2.0 2.5 4.0 16.8 22.5 25.0 21.5 15.5 4.10 4.41 6.09 4.67 2.54 0.1 0.1 0.1 Cuadrilla op 1 1 1 1 1 1 1 1 of 1 1 1 1 1 1 1 1 pn 2 2 2 2 1 Rend. m 2/d 12 12 12 12 12 12 12 12 m 2 /d/h 3.00 3.00 3.00 3.00 4.00 5.71 5.71 5.71 cap 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 op 1 1 1 1 1 1 1 1 Rend. Ejecutado Cuadrilla of 1 1 1 1 2 2 2 2 fae 3.6 4.2 3.5 3.0 1* Rend. m 2 /d 21.8 18.9 22.8 25.0 18.0 24.0 20.0 15.5 m 2/d/h 3.82 3.00 4.07 4.90 4.39 7.74 6.45 5.00

M UROS DE RESE RVO RIO-BO CATOM A

294

Anales Cientficos UNALM

CUADRO No 06. RENDIMIENTOS EN CONCRETO


Rend. Presupuestado Proyectos cap CONCRETO ARMADO C.A. fc=175 kg/cm2 C. Millpo (P3). Bocat. R. La Esperanza (P6). Res. C.C. fc=175kg/cm + 30%PG R. Independencia (P5). Res. A 2.4m A 3.6m CONCRETO SIMPLE C.C. fc=175kg/cm2 + 30%PG C. Taprag (P4). B. C.C. fc=140kg/cm + 30%PG C. Cedrn (P1). B. C. Mitotambo (P2).B. C. S. fc=140 kg/cm
2 2 2

Rend. Ejecutado Cuadrilla cap op of fae


3

Cuadrilla op Of pn
3

Rend. m /d m /d/h
3

Rend. m /d m /d/h
3

0.1 0.1 0.2

1 1 1

1.6 1.0 1

5 8 8

6.0 6.0 5.2

0.78 0.59 0.51

0.2 0.2 0.1 0.1 0.1

1 1 1 1 1

1 2 2 2 2

4 3* 35 30 23

2.95 4.45 8.25 7.50 6.85

0.48 0.72 0.22 0.23 0.26

0.1 0.1 0.1 0.1 0.1 0.1 0.1


2

1 1 1 1 1 1 1

1.6 1 1 1 1 1 1

5 8 8 5 5 8 4

6.0 6.0 6.0 6.0 6.0 5.0 4.2

0.78 0.59 0.59 0.85 0.85 0.78 0.69

0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1

1 1 1 1 1 1 1 1 1 1 1

1 1 2 1 1 1 1 1 1 1 1

5 5 4 2.5 2.0 5.0 2 4.0 3.5 2.2 2.2

4.05 4.35 4.20 2.5 3.5 4.2 3.5 15.50 16.20 15.00 16.20

0.57 0.61 0.59 0.54 0.85 0.59 0.85 2.54 2.89 3.49 3.77

C. Taprag (P4). Canal C. Cedrn (P1) . O.A. C. Mitotambo (P2). O.A. R. Esperanza (P6). O.A. Mamp. de piedra fc=140kg/cm . C. Cedrn (P1). Canal C. Mitotambo (P2). Canal C. Taprag (P4). Canal C. Millpo (P3). O.A.

No presupuestado 0.1 1 1 2 20 6.45 No presupuestado No presupuestado


2 2

0.1 0.1 0.1

Mampostera de piedra fc=140kf/cm evaluado en m /d/h

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

295

CUADRO No 07. RENDIMIENTOS EN ACERO FY=4200 KG/CM


Rend. Presupuestado Proyectos cap Acero =3/8 C. Cedrn (P1) C. Millpo (P3) C. Taprag (P4) R. La Esperanza (P6) Acero =1/2 R. Independencia (P5) R. La Esperanza (P6) Acero =5/8 R. Independencia (P5) 1 1 1 180 60 1 1 1 1 2 180 150 60 50 0.01 0.01 0.04 1.00 0.04 0.05 1.00 0.05 1.00 2 2 25 60 25 150 25 15 25 50 Cuadrilla op of pn Rend. kg/d kg/d/h

Rend. Ejecutado Cuadrilla cap 0.1 0.1 0.1 0.1 0.1 0.1 0.1 op 1 1 1 1 1 1 1 of 1 1 1 2 1 2 1 fae 2.2 2.5 2.0 2.0 2.0 Rend. kg/d 195 200 206 225 162 175 142 kg/d/h 45.35 43.48 50.24 72.58 39.51 56.45 34.63

CUADRO No 08. RENDIMIENTOS EN REVOQUES Y ENLUCIDOS


Rend. Presupuestados Proyectos cap R. Millpo (P3) a/p R. Independen. (P5) a/c Cuadrilla op of pn No presupuestado No presupuestado Rend. m2/d cap 0.1 0.1 Op 1 1 Rend. Ejecutado Cuadrilla of 1 1 fae 5 3* Rend. m2/d 25.0 20.5 m2/d/h 3.51 4.02

CUADRO No 09. RENDIMIENTOS EN INSTALACIN DE TUBERA PVC C-5


Rend. Presupuestados Proyectos cap Tubera de =4 C. Cedrn (P1) C. Millpo (P3) C. Taprag (P4) Tubera de =6 R. Independencia (P5) C. Taprag (P4) = 8 0.2 0.2 2 2 2 2 22 22 5.24 5.24 0.2 0.2 1 1 1 1 3.0 3.2 120 142 23.1 26.3 0.2 0.2 0.2 2 2 2 2 2 2 22 22 22 5.24 5.24 5.24 0.2 0.2 0.2 1 1 1 1 1 1 3.3 3.5 4.0 139 205 185 25.3 36.0 30.0 Cuadrilla op Of pn Rend. m/d m/d/h Cap op Rend. Ejecutado Cuadrilla of fae Rend. m/d m/d/h

296

Anales Cientficos UNALM

CUADRO No 10. RENDIMIENTOS EN INSTALA. DE GEOMEMBRANA VINIMANTA DE 1MM


Rend. Presupuestados Proyectos cap R. Cedrn (P1) R. Millpo (P3) R. Independencia (P5) 0.1 1 Cuadrilla op Of pn No presupuestado No presupuestado 2 270 87.01 Rend. m2/d m2/d/h Cap 0.1 0.1 0.1 op 2 2 2 Rend. Ejecutado Cuadrilla of fae 10 15 25 162 190 230 Rend. m2/d m2/d/h 12.37 11.11 8.48

CUADRO N 11. R RENDIMIENTO CONEXAS C UA D R O N o 11. E ND IM IE NT O E NEN O BOBRAS R A S CO N E XA S


R end. P resupuestado Proyectos cap C . C edrn (P 1 ). C . M itotam bo (P 2 ). R . Independencia (P 5 ) R . Esperanza (P 6 ) SE L L A D O D E JU N T A S C . C edrn (P 1 ) C . M itotam bo (P 2 ) C . Taprag (P 4 ) 1 1 N o presupuestado 2 60 15 N o presupuestado 1 1 1 1 1 1 2.5 4.0 3.0 65 82 75 14.44 13.67 15.00 0.1 0.1 0.1 1 1 1 C uadrilla Op of Pn 2 2 2 R end . Pza/d 1 1 1 Pza/d/h 0.32 0.32 0.32 cap 0.1 0.1 0.1 0.1 op 1 1 1 1 R end. E jecutado C uadrilla of 1 1 1 fae 2 2 6 1.0 1.0 0.5 1.0 R end . Pza/d Pza/d/h 0.24 0.24 0.07 0.48

N o presupuestado

En el Cuadro No 10 se muestra la Impermeabilizacin de reservorio, que comprendi actividades de tendido, tensado y pegado. Los resultados mostrados son globales; varan segn la seccin a instalar y la cantidad de aporte comunal. En P1 se logr los rendimientos ptimos por el eficiente despliegue de su cuadrilla, obtetenindose 12.37 m2/d/h. En el Cuadro No 11 las obras conexas se han agrupado en: Preparacin e Instalacin de compuertas metlicas, Instalacin de Vlvulas y Sellado de Juntas. En Instalaciones de Vlvulas Esfricas de PVC de 3 y 4 de dimetro; en P1 y P3 se obtuvo 1.4 pza/d/h, ejecutado con una cuadrilla de 0.1 cap., 1 op. y 1 fae. Y en P6 se obtuvo 2.86 pza/d/h, instalado con 0.1cap., 1 op., y 1 pn. Fue superior este ltimo por que se

remuner la partida. En el Sellado de Juntas, en P4 se logr el mejor rendimiento, obtenindose 15 m/d/h debido a la destreza de la cuadrilla. 4.2 COSTOS UNITARIOS En el Cuadro N 12 los resultados indican que el costo econmico por trazo, niveles y replanteo en canales variaron de 2.36 a 2.50 soles/m2. Para reservorios fluctu entre 0.97 y 1.16 soles/m. En el Cuadro No 13, el costo econmico por acarreo de hormign y piedra para P1 fue de 30 y 100 Soles/m3 respectivamente, diferencindose en 233.33% por el flete(40Km). Por acarreo de cemento con transporte animal, en P1 y P2 lleg a 2.0

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

297

Soles/bolsa para 1Km y 2.3 Soles/ bls, para 1.5 Km. Y para el transpor te de tubos PVC C-5 de 4 de dimetro, los costo variaron de 1.14 a 1.52 Soles/unid., debido al poco peso del material y al aporte comunal de 0.8 a 1.10 Soles/unid.

En el Cuadro No 14 , se observa los menores costos por m3 en excavacin de plataforma y zanjas en material suelto, normal y roca suelta fue de 4.41, 5.53, 6.00 Soles/m3 y de 4.03, 4.27, 5.76 Soles/m3 respectivamente obtenidos en P4.

CUADRO No 12. COSTOS UNITARIOS EN TRAZO, NIVELES Y REPLANTEO


C.U. Aporte estatal Proyectos CANALES C. Cedrn (P1) C. Mitotambo (P 2 ) C. Millpo (P 3) C. Taprag (P 4) RESERVORIO R. Cedrn (P1) R. Millpo (P 3) R. Independen. (P 5) R. La Esperanza (P 6) No presupuestado No presupuestado 1.05 1.45 1.16 0.97 1.07 1.08 1.06 0.88 0.89 1.08 0.10 0.09 0.18 0.00 1.33 1.58 1.33 1.33 2.47 2.48 2.50 2.36 2.44 2.45 2.47 2.34 0.03 0.03 0.03 0.02 S/ x m
2

C.U. Evaluado S/. x m Costo econmico Val. Fin. sin apo.

Aporte comunal

CUADRO No 13. COSTOS UNITARIOS EN ACARREO DE MATERIALES


C.U. Evaluados Proyectos Hormign S/xm Costo econ. A esfuerzo propio P1 a 1km P3 a 0.5km P1 a 0.3km P2 a 0.3km P3 a 0.3km P4 a 0.3km P5 a 50m A animales P1 a 1 km P2 a 1.5 km 2.3 2.0 2.3 2.0 0.0 0.0 30.00 16.03 6.91 9.86 6.13 30.00 4.67 2.37 2.90 1.80 0.00 11.3 4.54 6.96 6.43 30.00 13.44 22.80 15.30 9.40 30.00 3.91 6.60 4.50 2.74 0.00 10.4 16.2 10.8 6.7 3.5 3.4 4.6 2.7 1.01 0.92 1.23 0.74 2.50 2.50 3.4 1.96 1.52 1.25 1.14 0.41 0.34 0.31 1.1 0.9 0.8 Val. Fi. Sin ap.
3 3

Piedra S/ x m Costo Val.F.S econ. /Ap.

Cemento S/x bls Cost Val. F. C/A com

Tubos 4 S/xunid Costo V Fin. econ s/apor A/c

C/A Com.

Apor.

comu. econ s/apor

298

Anales Cientficos UNALM

CUADRO No 14. COSTOS UNITARIOS EN MOVIMIEN. DE TIERRA . PLATAFORMA- ZANJAS


C.U. Ap. Proyectos Estatal S/ x m EX. DE PLATAFORMA C. Cedrn (P1) C. Millpo (P3) C. Taprag (P4) EX. DE ZANJAS C. Cedrn (P1) C. Mitota. (P2) C. Millpo (P3) C. Taprag (P4) 1.45 12.3 1.45 1.45 4.41 4.15 4.70 4.03 1.28 1.21 1.37 1.17 3.13 2.94 3.33 2.86 4.7 6.72 4.52 4.27 1.37 1.96 1.32 1.24 3.33 4.76 3.20 3.03 6.72 4.95 5.76 1.96 1.44 1.68 4.76 3.51 4.08 1.45 1.45 1.45 5.32 5.04 4.41 1.55 1.47 1.28 3.77 3.57 3.13 6.00 6.41 5.53 1.75 1.87 1.61 4.25 4.54 3.92 7.63 7.05 6.00 2.22 2.05 1.75 5.41 4.00 4.25
3

C.U. Evaluado S/ x m3 Mat. suelto Costo Econ. Val.F. s/ap. Con a/com Mat. Normal seco Costo Econ. Val.F. s/ap. Con a/com Mat. Roca suelta Costo Econ. Val.F. s/ap. Apor. Comu

En el Cuadro No 15 el costo econmico en E-D de reservorio y bocatoma a 1.2m de altura flucta de 17.40 a 21.50 soles/m2 y para alturas de 2.4 y 3.6m fue de 22.60 a 24.36 soles/m2 respectivamente por el uso de andamio y escalera (P5). En el Cuadro No 16 se muestran los costos unitarios en concreto armado en funcin a la altura de vaceado y calidad de concreto. En C.A. fc=175 kg/cm2 vara de 194.70 a 2 1 9 . 5 3 s o l e s / m 3, e n C . C . fc=175kg/cm 2 + 30% PG solo se ejecut en P5 observndose la fluctuacin de 214.89, 212.89, 207.49 soles/m 3 a 1.2 m, 2.4 m y 3.6 m respectivamente. En el Cuadro No 17 los costos econmicos aumentan al habilitar aceros de mayores dimetros. Para acero 3/8 el habilitado ejecutado con apor te comunal flucta de 1.90 a 2.54

soles/kg y con mano de obra calificada fue de 1.89soles/kg (P6); para acero de y 5/8 se ejecut solo con mano de obra calificada variando el primero de 2.36 a 2.38 soles/kg y el segundo fue de 2.99 soles/kg. El Cuadro No 18 nos muestra los costos econmicos para morteros difieren debido a la obrabilidad del tipo de mezcla. El mortero c/a tiene como finalidad impermeabilizar los taludes del reservorio. En el P 5 se obtuvo 188.84 soles/m2 y en el P3 con mortero paja/ar para fines de proteccin de la GV1 cost 26.16 soles/m2 . En el Cuadro No 19 se muestra los costos econmicos para la instalacin de tubera PVC C-5 para 4 fluc tan de 10.23 a 14.22 soles/m para la instalacin de tubera de 6 y 8 de dimetro cost 16.98 y 21.54 soles/m respectivamente, estos costos ascendieron por el flete aplicados a es tos materiales.

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

299

CUADRO No 15. COSTOS UNITARIOS EN ENCOFRADO Y DESENCOFRADO


Proyectos BOCATOMA C.Cedrn(P1)B.A1.2m C.Mitot..(P2)B.A 1.2m C.Taprag (P4)B.A1.2m C.Millpo(P3).B.A1.2m R.Indep.(P5)B.A1.2m R.La Esp.(P6)B.A1.2m R. Independ(P5)A2.4m R. Independ.(P5) A3.6 OBRAS DE ARTE C. Cedrn (P1) C. Mito (P2) C. Millpo (P3) C. Taprag (P4) R. Independencia (P5) CANALES C. Mito.(P2)A 2 muros C.Cedrn(P1)A 1muro C.Taprag(P4)A 1 muro 11.42 15.74 15.75 14.40 11.13 11.79 12.40 10.05 10.3 2.00 1.08 1.49 15.74 11.42 15.50 15.50 15.50 14.21 13.47 13.50 14.08 17.59 13.02 9.47 12.70 11.50 17.59 1.19 4.00 0.80 2.58 0.00 15.50 11.42 15.50 15.50 13.66 27.71 13.66 13.66 17.40 19.46 12.99 18.43 21.50 19.83 22.60 24.36 15.75 10.13 10.62 16.90 21.50 19.83 22.60 24.36 1.65 9.33 2.37 1.53 0.00 0.00 0.00 0.00 C.U. Aporte Estatal S/ x m
3

C.U. Evaluados S/ x m Costo econmico Val. F. Sin aporte

Aporte comunal

En el Cuadro No 20 se observa que slo se program la instalacin con GV en P5 con un aporte estatal ascendente a 24.76 soles/m2 sin embargo se ejecut con un costo de 51.15 soles/m2; esta diferencia origin el agotamiento de su financiamiento porque el transporte de ma teriales en temporadas lluvias encareci los costos . Caso contrario ocurri en P1 y P3 la temporada seca favoreci el traslado pero se encare ci por la lejana de traslado fluctuando sus costos de 56.64 a 62.39 soles/m2. En el Cuadro No 21 respecto a la instalacin de compuertas metlicas, se observa que el aporte estatal para

P5 fue menor en 312.92 soles con respecto al costo econmico debido a que las medidas y materiales iniciales se cambiaron al finalizar la obra ocasionando dficit en el financiamiento; para las restantes obras de riego el costo econmico vari 285.03 a 410.00 soles/pza . En el Cuadro No 22 el costo econmico de Sellado de Juntas vari de 7.81 a 8.18 soles/m debido a que el costo de asfalto lquido RC250 fue transportado de Lima. En el Cuadro No 23 los presupuestados difieren significativamente de los financiados por la variacin en los

300

Anales Cientficos UNALM

rendimientos y el costo de transporte. El aporte comunal representa el 9.11%, 11.56%, 13.32%, 7.83% y 7.18% de sus costos en P1, P2, P3, P4 y P5 respectivamente. En P6 el aporte comunal fue nulo. Cabe men-

cionar que para el tendido de tubera PVC C-5 y reservorios impermeabilizados con GV se ha estimado una vida de 5 aos, para canales de con creto simple 10 aos y para reservorio de concreto armado 30 aos.

CUADRONo 16. COSTOS UNITARIOSENCONCRETO


Proyectos C.U. Aporte Estatal S/ x m3 CONCRETO ARMADOC. A. fc=175 kg/cm C. Millpo (P3). B. R. Esperanza (P6) C.C. fc=175kg/cm + 30%PG R. Indepen (P5)a 1.2m a 2.4m a 3.6m C. Taprag (P4). B. C. C. fc=140kg/cm + 30 %PG C. Cedron (P1) B. C. Mitotambo (P2) B. C. S. fc=140 kg/cm
2 2 2 2

C.U. Evaluado S/ x m Costo econmico 219.53 194.70 214.87 212.89 207.49 165.03 130.76 189.52 153.68 157.91 188.11 156.18
2

Val. Fin. Sin aporte 205.97 194.70 172.45 173.15 173.92 152.69 119.27 132.05 147.96 146.01 178.11 156.18 13.64 13.66

Aporte comunal 13.56 0.00 42.42 39.74 33.57 13.34 11.49 67.47 5.72 11.90 10.00 0.00 2.58 2.06

225.45 170.65 156.83 156.83 156.83


2

CONCRETOSIMPLE fc=175kg/cm + 30%PG 191.21 131.77 161.02 -

C. Cedrn (P1) O.A. C. Mitotam. (P2) O.A. C. Taprag (P4) O.A. R. Esperanza (P6) O.A.

Mampostera de piedra asentada en fc=140kg/cm . C. Cedrn (P1) Canal No presupues. (P2) No presupues. 16.22 15.72

I.

Mito. Canal

C. Taprag (P4) Canal

No presupues.

16.19
2 2

14.72

1.47

Los costos en mampostera de piedra asentada en fc=140kg/cm es por m 2.1 Los costos en mapostera de piedra asentada en Fc= 140kc/cm2 es por m2

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

301

CUADRO No 17. COSTOS UNITARIOS EN ACERO FY=4200 KG/CM


Proyectos C.U. Aporte Estatal S/ x kg Acero =3/8 C. Cedrn (P1) C. Millpo (P3) C. Taprag (P4) R. Esperanza (P6) Acero =1/2 R. Independencia (P5) R. Espera (P6) R. Indep. (P5) =5/8 2.39 2.24 3.20 2.36 2.38 2.99 2.36 2.38 2.99 2.20 2.15 2.20 2.24 1.90 2.54 2.51 1.89 1.78 2.42 2.41 1.89 Costo econmico

C.U. Evaluados S/ x kg Val. Fin. Sin aporte Aporte comun. 0.12 0.12 0.10 0.00 0.00 0.00 0.00

CUADRO No 18. COSTOS UNITARIOS EN REVOQUES Y ENLUCIDOS


Proyectos Mortero c/a R. Independ. (P5) 1:4 Mortero p/ar R. Millpo (P3) 1:10 No presupuesta. 26.16 24.16 2.00 No presupuesta. 188.84 187.37 1.47 C.U. Aporte Estatal S/ x m2 Costo econmico C.U. Evaluados m2 Val. Fin .Sin aporte Aporte comun.

CUADRO No 19. COSTOS UNITARIOS EN LA INSTALACIN DE TUBERA PVC C-5


Proyectos Tubera de =4 C Cedrn (P1) C. Millpo (P3) C. Taprag (P4) Tubera de =6 R. Indepen. (P5) Tubera de =8 C. Taprag (P4) 21.54 21.31 0.23 26.72 16.98 16.73 0.25 15.11 11.84 14.22 10.78 10.23 14.00 10.00 10.06 0.22 0.78 0.17 C.U. Aporte Estatal S/. X m Costo econmico C.U. Evaluados S/. M Val. Fin. s/aporte Aporte comun.

302

Anales Cientficos UNALM

CUADRO No 20. COSTOS UNITARIOS EN IMPERMEABILIZACIN DE RESERVORIO


Proyectos R. Cedrn (P1) R. Millpo (P3) R. Independencia (P5) C.U. Aporte Estatal S/ x m 24.76
2

C.U. Evaluados S/ x m2 Costo econmico 56.64 62.36 51.15 Val. Fin. s/aporte 50.46 50.52 50.07 Aporte comunal 6.18 11.84 1.08

CUADRO No 21. COSTOS UNITARIOS EN INSTALACIN DE COMPUERTAS METLICA


Proyectos C. Cedrn (P1) C. Mitotambo (P2) R. Independencia (P5) R. La Esperanza (P6) C.U. Aporte Estatal S/. m2 314.01 555.68 650.00 Costo econmico 410.00 285.03 868.60 390.00 C.U. Evaluado S/. x unid Val. Fin. s/aporte 370.60 265.03 508.68 390.00 Aporte comunal 39.40 20.00 359.92 0.00

CUADRO No 22. COSTOS UNITARIOS EN SELLADO DE JUNTAS


Proyectos C. Cedrn (P1) C. Mitotambo (P2) C. Taprag (P4) C.U. Aporte Estatal S/. x m 3.94 Costo econmico 7.81 8.18 7.83 C.U. Evaluados S/ x m Val. Fin. s/aporte 7.43 7.69 7.43 Aporte comunal 0.38 0.49 0.40

CUADRO No 23. PRESUPUESTOS PROGRAMADOS Y EVALUADOS


Presupuestos Proyecto C. Cedron (P1) C. Mitotambo (P2) C. Millpo (P3) C. Taprag (P4) C. Independencia (P5) C. La esperanza (P6) Programados 33646.50 52690.83 33650.00 45951.00 33498.57 16855.96 46614.94 54278.69 39365.24 50228.24 36508.18 17305.96 Presupuestos Evaluados Costo econmico V. Fin. Sin aporte 42366.03 48001.78 34118.14 46295.32 33887.22 17305.96 Aporte comunal 4248.91 6276.91 5247.10 3932.92 2620.96 0.00

P1, P2, P3 proyectos de zona alta P4, P5, P6 proyectos de zona media

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

303

V. CONCLUSIONES 1. Los rendimientos de mano de obra y cuadrillas ptimas fueron: a) En Zonas Altas
Partida Trazo, niveles y replanteo preliminares Acarreo de tubos PVC C-5 f=4 a 1km Excav. De reservorio en material roca suelta Instalacin de tubera PVC C-5 f=4 Rend 1600 11 2.85 205 Unid m 2/d unid/d m 3/d m/d cap 1.0 0.1 0.1 0.2 top 1 op 1 of 1 fae 4.0 1.0 1.0 3.0

b) En Zonas Medias
Partida Excavacin de zanjas en material suelto Mampos. de piedra asentada en fc=140kg/cm Instalacin de tubera de =8 Sellado de juntas
2

Rend 3.2 15 142 75

unid m /d m /d m/d m/d


2 3

cap 0.1 0.1 0.2 1.0

top -

op 1 1 1

of 1 1 -

Fae 1.0 2.2 3.2 3.0

2. Los rendimientos de mano de obra de cuadrillas con aporte comunal obtenidos en para zona alta y media se diferenciaron entre 10% a 18%. Y a su vez son inferiores en 26.69% a los rendimientos de obtenidos con cuadrillas totalmente remuneradas. 3. No hay diferencias significativas en cuanto a la evaluacin de los costos unitarios para obras construidas en zona alta y media debido a que se desarrollaron a 33km y 31.5km respecto de la ciudad (excepto P6 , a 5km de la ciudad). 4. El costo por metro lineal en la construccin de canal segn altitud cost: a) En Zona Alta Mampostera de piedra asentada en fc=140kg/cm2 Tendido de tubera PVC C-5 de f=4 b) En Zona Media Concreto Simple fc=140kg/cm2 Tendido de tubera PVC C-5 de f=8 Tendido de 2 tubos en paralelo de f=4 27.34 23.30 22.40 10.20 8.69 8.37 S/. 20.03 12.61 U.S. $ 7.47 4.71

304

Anales Cientficos UNALM

El costo por ml de tendido de tubera en zona alta son inferiores en 37.04% respecto al de mampostera de piedra asentado en fc=140kg/cm2 . En zona media fue la instalacin de tubera en paralelo aventajando al de C.S. en 17.92 %.5. El costo por metro cubico de construccin de reservorio fue de: a) Para zona alta Con geomembrana vinimanta de 1mm de espesor (GV1) b) Para zona media Con geomembrana vinimanta de 1mm de espesor(GV1) En Concreto Armado fc=175kg/cm
2

S/. 83.49 81.94 202.50

U.S. ($) 31.15 30.57 75.56

La construccin con GV1 en zona alta y media se diferencian en 2% justificando su costo para ambas altitudes en comparacin con la habilitacin con concreto armado. VI. RECOMENDACIONES ble a agotarse por la prolongacin del plazo de ejecucin. VII. BIBLIOGRAFIA 1. CAMARA PERUANA DE LA CONSTRUCCION (1990) Reglamento de metrados para obras de edificacin. Lima, Fondo editorial CAPECO. Octava edicin. COTRINA MATOS TITO W. (1995) Relacin de costos entre edificaciones convencionales y no convencionales de Hunuco y Ambo. Tesis UNIV. NAC. HEMILIO VALDIZAN. GRUPO PERMANENTE DE ESTUDIO SOBRE RIEGO (1993) Gestin del agua y crisis institucional. Quinta edicin. MONTALVO TORRES, JUAN (1993). Determinacin de costos por Ml de construccin y revestimiento de canales de riego. PRONAMACHCS. RAMOS SALAZAR, JESUS (1998) Costos y presupuestos en edificacin. Lima, Editorial Gesco S.R.L. Sptima edicin. ROCHA FELICES, ARTURO (1993) Re cursos hidrulicos. Libro 16. Lima. Edicin Captulo de Ingeniera Civil. Primera edicin.

Para la recopilacin de datos deber incluirse la capacitacin de los miembros del Comit de Obra, que son comuneros encargados de la administracin del financiamiento de cada proyecto, ya que estos ayudaran a obtener la mayor cantidad de informacin conllevando a obtener resultados con niveles de confianza mucho mayores. Seguir promoviendo la participacin de la comunidad desde la gestacin del proyecto hasta su termino, buscando la participacin voluntaria a travs de su aporte de mano de obra, ya que con ello podrn comprender que las acciones en ejecucin son necesarias y que estas se traducirn en beneficios tangibles de su comunidad. Realizar la evaluacin de rendimientos y costos unitarios en la construccin de canales y reservorios con mano de obra comunal en zonas ubicada en la sierra sur y sierra norte del pas con el fin de estimar rendimientos y costos en dichas zonas. Incrementar los gastos generales de los proyectos a ejecutar bajo esta modalidad, en 1.7%, ya que este rubro es suscepti-

2.

3.

4.

5.

6.

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

305

VIII ANEXO ANEXO No 1. ANEXO No 1.1 EVALUACION DE RENDIMIENTOS DE MANO DE OBRA

APORTE COMUNAL (JORNALES ACUMULADOS) DURANTE LA CONSTRUCCIN DE LAS OBRAS DE RIEGO ANEXO No 1.1.1 PROYECTO CONSTRUCCIN CANAL CEDRN

Mes 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total

Julio 97 9* 12 13 15 12 15 18 22 30 12 9 10 14 8 6 205

Agosto 97 4 4 5 8 9 2 4 8 4 1 5 4 1 3 1 2 1 3 3 82

Setiembre 97 8 10 8 6 6 7 10 10 6 8 10 8 10 8 7 7 8 7 8 8 5 4 169

Octubre 97 3 5 4 3 3 3 3 4 7 5 4 3 2 2 4 5 3 4 4 5 4 4 5 91

Noviembre 97 5 5 6 5 5 5 4 5 12 6 4 4 4 3 4 4 15 10 106

Diciembre 97 2 3 4 2 4 2 3 2 4*

24

Total Diario 12 25 32 32 18 22 28 35 30 45 55 27 20 33 26 26 28 15 18 17 5 13 13 17 14 16 7 18 9 8 11 675

306

Anales Cientficos UNALM

ANEXO No No 1.1.2 1.1.2 PROYECTO PROYECTO CONSTRUCCIN CANAL S.P. MITOTAMBO ANEXO CONSTRUCCIN CANAL S.P. MITOTAMBO
Mes 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total 16 18 16 20 8 4 87 14 10 2 93 5* Enero 97 Febrero 97 18 10 10 8 10 9 Marzo 97 4 4 8 3 2 4 2 2 1 11 2 8 2 10 8 10 4 8 93 Abril 97 3 5 6 7 6 5 4 2 2 2 5 7 8 9 5 4 6 6 92 Mayo 97 8 5 2 5 6 1 3 4 6 3 3 3 5 4 4 4 66 71 Junio 97 8 3 4 6 5 7 2 4 5 4 4 3 4 3 4 2 3 6* Total Diario 0 11 8 14 35 32 15 17 2 2 13 4 6 15 6 17 22 12 13 34 28 33 23 19 41 15 27 8 16 14 8 503

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

307

ANEXO No 1.1.3 PROYECTO MEJORAMIENTO CANAL MILLPO Y CONSTRUCCIN RESERVORIO NOCTURNO


Mes 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total Julio 97 5* 10 12 8 10 10 12 11 15 13 11 14 12 16 13 16 18 15 221 Agosto 97 4 6 5 5 4 7 5 8 5 8 5 7 9 10 7 4 2 8 10 9 8 8 8 3 153 Setiembre 97 8 8 10 9 1 10 8 13 8 7 5 4 4 5 6 7 17 15 17 17 8 8 10 205 Octubre 97 8 5 5 3 18 18 17 17 4 12 10 15 9 10 11 8 10 14 12 10 214 Noviembre 97 15 12 10 15 12 18 15 15 18 12 142 69 Diciembre 97 8 8 7 6 8 8 7 6 8 7 15 5 1 4* Total Diario 29 31 49 42 35 48 42 58 36 37 35 29 22 8 14 4 11 10 15 29 28 50 39 55 51 33 49 56 40 37 10 1004

308

Anales Cientficos UNALM

ANEXO No 1.1.4 PROYECTO MEJORAMIENTO CANAL TAPRAG


Mes 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total 2 3 2 2 4 3 2 5 1 2 4 2 3 4 8 7 8 8 8 115 8* 18 8 1 2 Agosto 97 Setiembre 97 12 12 20 25 22 25 16 20 8 6 8 12 4 4 2 22 24 25 18 3 4 13 10 315 Octubre 97 12 9 10 9 8 9 8 9 10 9 6 4 5 5 4 2 3 8 11 2 2 4 4 3 4 3 3 166 Noviembre 97 15 18 19 20 3 4 2 2 4 11 11 6 5 3 4 4 5 5 141 Diciembre 97 2 2 3 2 3 18 16 18 22 86 47 Enero 98 4 3 4 3 6 4 3 2 3 4 6 3 4* Total Diario 26 23 28 29 42 50 23 37 45 33 37 23 42 29 22 16 15 6 17 3 35 52 51 33 14 15 16 15 47 40 8 672

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

309

ANEXO No No1.1.5 1.1.5PROYECTO PROYECTO CONSTRUCCION CONSTRUCCIN RESERVORIO ANEXO RESERVORIONUEVA NUEVAINDEPENDENCIA INDEPENDENCIA Mes 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 TOTAL 8* 2 4 1 2 3 20 Enero 97 Febrero 97 1 2 4 20 2 2 2 2 2 2 5 5 12 5 10 53 Marzo 97 2 35 2 2 2 2 2 2 2 23 4 8 1 5 4 5 78 Abril 97 6 9 5 10 15 Mayo 97 111 Octubre 97 3 3 4 4 6 4 4 4 8 10 1 18 3 5* Total Diario 4 3 4 4 2 22 39 4 6 2 10 6 12 25 26 0 23 7 2 5 7 2 13 12 10 16 0 18 15 0 0 268

* Fecha de inicio y finalizacin de las obras

310

Anales Cientficos UNALM

ANEXO No 2.2 ECUACIONES DE ESTIMACION DE RENDIMIENTOS DE M.O. ANEXO N 2.2 ECUACIONES DE ESTIMACION DE RENDIMIENTOS DE M.O. ANEXO N No2.2.1 2.2.1 PROYECTO PROYECTO CONSTRUCCIN CANAL CEDRON ANEXO CONSTRUCCION CANAL CEDRON
PARTIDA Intercepto s/u b TRABAJOS PRELIMINARES - Acarreo de Hormign a 1km - Acarreo de Cemento a 1km MOVIMIENTO DE TIERRA Excavaciones de Plataforma - Material Suelto - Material Normal Seco - Material Roca Suelta Excavaciones de Zanjas - Material Suelto - Material Normal Seco - Material Roca Suelta Excavacin de Reservorio - Material Roca Suelta ENCOFRADO-DESENCOFRADO E-D. Bocatoma E-D. Obras de artes E-D. Canal a 1 muro CONCRETO C. C. fc=175kg/cm + 30% PG. Bocatoma C. S. fc=140kg/cm . Mamp. de piedra en fc=140kg/cm . Canal Instalacin de Tubera PVC C-5 4 IMPERME. DE RESERVORIO - Tendido, tensado y pegado de mantas 153.09 16.86 -9.13 4.05
2 2 2

Tiempo (T) a1 -0.26 -6.94

Mano de O. (MO) a2 -0.59

Temperatura Precipita ( C) a3 3.09 1.44


o

. (P) a4 1.428 0.18

47.731 -20.86

-444.32 24.34 99.44 -28.736 5.33 -30.47 -72.13 11.82 -25.56 -8.87 1.562 -0.427 32.71 79.78

23.61 2.50 -36.03 2.57 2.23 -16.02 4.69 0.798 86.40 2.12 -0.13 0.39 -1.09 1.62

-0.001 3.296 -0.965 -0.06 6.18 0.419 -1.344 88.19 1.899 -0.0004 -0.28 -0.87 2.18

20.61 -1.28 3.228 2.18 0.04 4.25 2.94 -0.18 0.08 0.269 -0.28 -0.85 0.08

2.187 2.198 0.10 26.84 0.46 -0.06 -19.93

-37.80 1090.33

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

311

ANEXO No 2.2.2 PROYECTO CONSTRUCCIN CANAL S.P. DE MITOTAMBO


PARTIDA Intercepto Tiempo s/u b TRABAJOS PRELIMINARES Trazo, niveles y replanteo de canal - Acarreo de Hormign a 300m - Acarreo de Piedras a 300m MOVIMIENTO DE TIERRA. Zanjas - Material Suelto - Material Normal Seco ENCOFRADO-DESENCOFRADO E-D. Canal a 2 muros E-D. Canal a 1 muro CONCRETO C. C. fc=140kg/cm + 30%PG. C. S. fc=140kg/cm . OBRAS CONVEXAS Sellado de Juntas seccin de 1x2 -109.03 9.16 -2.077 7.4 2 2

M. de obra (MO) a2

Temperatura Precipita( C) a3
o

(T) a1

cin (P) a4

233.04 -7.62 0.679 11.55 -32.51 1.066 7.13 0.657 -0.586

-55.61 0.95 0.148 2.819 -2.56 1.92 0.957 -0.235 0.317

382.019 -0.107 -0.145 3.427 3.85 -0.145 0.157 0.002 0.309

-36.906 0.39 0.038 -1.45 1.74 -0.04 -0.10 0.08 -0.02

-579.07 0.99 2.15 0.268 -

312

Anales Cientficos UNALM

ANEXO No No 2.2.3 MEJORAMIENTO CANAL MILLPO Y CONSTRUCCIN ANEXO 2.2.3PROYECTO PROYECTO MEJORAMIENTO CANAL MILLPO Y CONSTRUCCION RESERVORIO NOCTURNO RESERVORIO NOCTURNO
PARTIDA Intercepto s/u b TRABAJOS PRELIMINARES Trazo, niveles y replanteo de canal Acarreo de Materiales - Acarreo de Hormign a 500m - Acarreo de Piedras a 300m - Acarreo de cemento a 300m - Acarreo de Tubos 4 PVC C-5 MOVIMIENTO DE TIERRA Excavaciones de Plataforma - Material Suelto - Material Normal Seco - Material Roca Suelta Excavaciones de Zanjas - Material Suelto - Material Normal Seco - Material Roca Suelta Excavacin de Reservorio - Material Roca Suelta Relleno - Relleno con material propio ENCOFRADO-DESENCOFRADO E-D. Bocatoma CONCRETO C. A. fc=175kg/cm . Mamp. de piedra en fc=140kg/cm . Instalacin de Tubera PVC C-5 4 Acero 3/8 fy=4200kg/cm
2 2 2

Tiempo (T) a1

M. de obra (MO) a2

Temperatura ( C) a3
o

Precipitacin (P) a4

-.279E18 0.18 0.329 -1.68 7260.82

323.7 0.37 -0.33 1.74 -86.36

3.98E17 -0.04 0.0125 -3.62E-15 -243.99

-104.9 -0.066 -0.03 0.076 -313.36

1.59E18 0.07 0.08 -

125.847 16.56 -74.159 -31.60 -11.07 1.41 7.27 -12.746 -39.24 -4.35 -0.61 -2851.92 150.06 -286.86 2262.73

-2.28 3.41 10.61 0.92 1.23 -1.85 0.63 11.866 -1.05 0.77 0.07 81.38 32.05 4.56 -108.79

-2.17 0.038 0.079 -1.27 1.365 0.98 -0.4007 -2.87 1.727 -0.49 0.009 -34.83 -18.52 7.057 -80.39

-4.14 -0.76 3.25 3.19 0.38 0.298 0.5495 -0.148 2.68 0.315 0.09 155.96 -8.33 14.038 -9.50

0.442 0.238 -38.89 -2.112 -34.83 -78.73

REVOQUE Y ENLUCIDO IMPERME. DE RESERVORIO - Tendido, tensado y pegado de la manta

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

313

ANEXO CANAL TAPRAG ANEXON No2.2.4 2.2.4PROYECTO PROYECTOMEJORAMIENTO MEJORAMIENTO CANAL TAPRAG
PARTIDA Intercepto s/u b TRABAJOS PRELIMINARES Trazo, Niveles y replanteo. Canal Acarreo de Materiales - Acarreo de Piedras a 300m - Acarreo de Cemento a 300m - Acarreo de Tubos 8 PVC C-5 - Acarreo de Tubos 4 PVC C-5 MOVIMIENTO DE TIERRA Excavaciones de Plataforma - Material Suelto - Material Normal Seco - Material Roca Suelta Excavaciones de Zanjas - Material Suelto - Material Normal Seco - Material Roca Suelta Relleno - Relleno con material propio ENCOFRADO-DESENCOFRADO E-D. Bocatoma E-D. Obras de artes. E-D. Canal a 2 muros CONCRETO C.C. fc=175kg/cm +30%PG. Bocatoma C. S. fc=140kg/cm . Cajas Mam. de piedra en fc=140kg/cm . TUBERIA Instalacin de Tubera PVC C-5 4 Instalacin de Tubera PVC C-5 8 Acero 3/8 fy=4200kg/cm
2 2 2 2

Tiempo (T) a1

M. de obra (MO) a2

Temperatura ( C) a3
o

Precipita cin (P) a4

41067.4 -108.34 18.72 32.12 43.12

-25581 18.98 0.41 12.82 2.466

12768 -0.12 -1.137 -7.05 -1.27

3316.4 0.729 -0.547 -0.745 -1.45

192.05 -3.29 -0.108

7.40 -6.79 1.19 -74.08 65.385 17.80 40.20 -1.89 25.73 -31.55 -1.56 -3.03 -69.78 116.68 47.11 2007

-4.83 2.42 9.40E-14 1.48 -0.548 1.33 0.19 1.74 -1.24 7.175 -0.13 0.066 3.491 -2.542 21.59 6.66

0.209 1.008 -1.042 -1.52 -1.066 0.147 1.04 1.46 -2.67 0.1875 -0.0004 0.106 -6.54 -7.646 14.35 1.50

1.69 0.185 1.04 4.25 -1.95 -0.46 1.93 0.148 -0.22 0.70 0.269 0.195 3.52 2.68 -5.64 -91.66

-1.23 0.21 -0.15 0.1875 0.263 -15.49 20.67 -

314

Anales Cientficos UNALM

ANEXO No 2.2.5 PROYECTO CONSTRUCCIN RESERVORIO NUEVA INDEPENDENCIA


PARTIDA Intercepto b TRABAJOS PRELIMINARES Acarreo de Materiales - Acarreo de Hormign a 50m - Acarreo de Piedras a 50m - Acarreo de Cemento a 50m MOVIMIENTO DE TIERRA Excavacin de Reservorio - Material Roca Suelta ENCOFRADO-DESENCOFRADO E-D. Reservorio a 1.2m E-D. Reservorio a 2.4m E-D. Reservorio a 3.6m Acero 58 fy=4200kg/cm
2 2

Tiempo (T) a1

M. de obra (MO) a2

Temperatura Precipita( C) a3
o

cin (P) a4

8.07 7.55 -3.05 -403.35

3.58 0.47 2.17 49.186

-2.0427 -0.34 -0.969 13.13

-0.47 -0.33 0.459 13.517

0.702 0.17 -0.55 0.482

97.22 31.91 5.86 29.23 334.06 80.77

-5.457 6.547 1.75 6.476 14.88 -0.37

-4.83 4.6

-1.2449 -2.52 -0.22 0.586 -14.44 -2.16

-0.188 -0.806 -0.104 11.115 15.135

Acero 1/2 fy=4200kg/cm

IMPERME. DE RESERVORIO - Tendido, tensado y pegado de mantas

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

315

ANEXO No 2.2.6 PROYECTO CONSTRUCCIN RESERVORIO VIVERO FORESTAL LA ESPERANZA


PARTIDA Intercepto B TRABAJOS PRELIMINARES Eliminacin de roca MOVIMIENTO DE TIERRA Relleno - Relleno con material propio ENCOFRADO-DESENCOFRADO E-D. Muros de reservorio E-D. Obras de artes. CONCRETO C. C. fc=175kg/cm C. S. fc=140kg/cm
2

Tiempo (T) a1

M. de obra (MO) a2

Temperatura Precipita( C) a3
o

cin (P) a4

-0.037

0.53

0.53

-0.117

-5.122 -891.79 0.40 3.59

0.12 0.8 0.43 -0.237 329.07 22.36

0.369 50 -0.007 0.046 -3.169 0.73

0.45 7.591 -110.63

2 2 2

Acero 1/2 fy=4200kg/cm Acero 3/8 fy=4200kg/cm

-860.4 7.30

* Rend. = b + a1 T + a2 MO + a3 To + a4 P Coeficientes : a1 , a2 , a3 ,a4

316

Anales Cientficos UNALM

ANEXO No 3. EVALUACION DE COSTOS UNITARIOS POR PARTIDAS ANEXO No 3.01 CONSIDERACIONES PARA CALCULAR EL APORTE DE MATERIALES
CLAVOS DIMENSIN TIPOS Y/O No (BWG) 14 13 11 10 9 8 8 16 CANT/KG 1028 582 272 180 128 94 KG/M 0.111 0.017 1.552 0.994 0.559 0.248 ISO 9971 NOVAFORT PESO APROXIMA. POR TUBO EN KG. 11.04 15.96 23.22

1 2 2 3 3 4 ALAMBRE (mm) 4.191 1.691 ACERO 5/8 3/8

DE TUBERIA PVC C-5: FABRICADAS SEGN NORMA ISO 4435 SERIE 25. ISO 4435 SERIE 25 ISO SERIE 20 PESO APROXIMA. f NOMINAL f EXTERIOR PESO APROXIMA. (Pulg) 6 8 10 (mm) 160 200 250 POR TUBO EN Kg. 13.939 21.133 32.020 POR TUBO EN Kg. 17.229 26.537 41.704

TABLA DE PORCENTAJE DE DESPERDICIOS DESCRIPCIN Mezcla de concreto Mortero Clavos Madera Acero de refuerzo: f = 5/8 f = f = 3/8 f = Pintura /esmalte % DE DESPERDICIOS 5 10 15 10 3 5 7 8 15

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO
3 MATERIALES MATERIALES PARA PARA m m3 DE DE CONCRETO CONCRETO ARMADO ARMADO

317

MEZCLA TIPO (kg/cm ) 140 175


2

CEMENTO (bls) 7.2 7.7

PIEDRA f (m ) 1.01 0.98


3

ARENA (m ) 0.52 0.46


3

AGUA (m ) 0.21 0.19


3

PROPORCIN DE AGREGADO 1; 2; 4 1; 2; 3

APORTEPOR POR m m3 DE DE CONCRETO CONCRETO SIMPLE A Fc=140Kg/cm APORTE SIMPLE EQUIVALENTE EQUIVALENTE A Fc=140Kg-cm2
PROPORCIN 1:6 1:7 1:8 1:8 + 25% PM 1:10 + 30% PM a/c 0.8 0.8 0.8 0.8 0.8 CEMENTO (bls) 6.20 5.50 5.00 3.70 2.90 HORMIGN (m ) 1.05 1.09 1.13 0.85 0.83
3

PIEDRA MEDIANA (m ) 0.40 0.48


3

AGUA (m ) 0.21 0.19 0.17 0.13 0.10


3

318

Anales Cientficos UNALM

ANEXO No 3.02 COTIZACIONES DE PRECIOS PERIODO ENERO-DICIEMBRE 97


DESCRIPCIN FERROESTRADA Jr. Los Jaminez-Hco No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 Materiales/Herram. Alambre No 8 Alambre No 16 Clavos 2 Clavos 3 Clavos 4 Clavos 6 Acero liso Acero 3/8corrugado Acero corrugado Acero 5/8corrugado Esmalte Pegamento Bolsa de yeso Cemento andino T-1 Wincha 30m Manguera Pala cuchara Pala recta Carretilla buggi Barreta 11/2x 1.8m Zapapico Comba 12 lbs. Unid kg kg kg kg kg kg kg varilla varilla varilla gln gln kg bls unid m pza pza pza pza pza pza P. Unitario S/. 2.5 2.5 2.5 2.5 2.7 2.7 2.8 9.0 13.5 18.0 35.0 48.0 1.0 15.0 35.0 0.70 30.0 36.0 130.0 65.0 38.0 36.0 DISTRIBUIDORAS ATACHAGUA Primer Km de Hco. P. Unitario S/. 2.5 2.5 2.5 2.5 2.7 2.7 2.8 10.5 15.5 18.5 35.0 48.0 0.80 15.0 30.0 0.70 30.0 36.0 135.0 68.0 36.0 28.0 FERROVISION Av. V.T. 141-Hco P. Unitario S/. 2.5 2.5 2.5 2.5 2.7 2.7 2.8 8.5 14.5 18.5 35.0 48.0 1.00 15.0 35.0 0.70 30.0 36.0 138.0 55.0 32.0 30.0

* Precios sin considerar flete ANEXO No 3.03 PROCEDIM IENTO PAR A OBTENER COSTOS UNITARIOS
COEFICIENTE DE APORTE Materiales Mano de obra Equipo (cantidad) (H-H) (H-M) PRECIO UNITARIO (P.U) (P.U.) (J.H.) (CH) COSTOS PARCIALES (A) Cantidad x P.U. H-H x J.H. H-H x C.H. Sum a de (A) Sum a de (A) Sum a de (A) COSTOS TOTALES

COSTO UNITARIO H-H Hora hombre.

= Total de m ateriales + Total mano de obra + Total equipo

J.H. Jornal horario, C.H. Costo horario,

ANEXO No 5.02.02 APLICACION DEL PERT - CPM PARA EL PROYECTO MEJORAMIENTO CANAL MILLPO Y CONSTRUCCIONES RESERVORIO NOCTURNO
DESCRIPCION DURACION TIEMPO OPTIMO TIEMPO PESIMISTA DIAS T I T I T I T I 2.0 1.0 1.0 1.0 1.0 1.0 18.0 1.0 0.5 1.0 0.5 0.5 0.5 0.5 0.3 0.5 0.5 0.3 0.5 0.5 0.2 0.2 0.5 0.5 0.5 0.3 0.5 0.5 0.3 12.0 1.0 0.5 0.5 0.5 0.0 2.0 3.0 3.0 4.0 4.0 4.0 5.0 5.0 22.0 22.5 22.5 23.0 23.5 24.0 24.3 24.8 24.8 25.3 25.8 25.8 26.3 26.6 27.1 27.6 27.1 28.1 28.1 28.6 28.9 40.9 40.4 41.4 47.9 2.0 3.0 4.0 4.0 5.0 5.0 22.0 22.5 22.5 22.5 24.3 24.3 23.5 24.0 24.3 24.8 25.3 25.8 25.8 26.3 26.6 26.6 27.1 27.6 28.1 28.1 28.6 28.9 28.9 40.9 41.9 41.4 41.9 48.4 0.0 2.0 3.0 3.0 20.5 4.0 4.0 21.5 22.0 22.0 22.5 22.5 23.0 23.5 24.0 24.3 24.8 24.8 25.3 25.8 25.8 26.3 26.6 27.1 27.6 27.1 28.1 28.1 28.6 28.9 40.9 40.9 47.1 47.9 2.0 3.0 20.5 4.0 21.5 22.0 22.0 22.5 22.5 22.5 24.3 24.3 23.5 24.0 24.3 24.8 25.3 25.8 25.8 26.3 26.6 26.6 27.1 27.6 28.1 28.1 28.6 28.9 28.9 40.9 41.9 47.1 47.6 48.3 0.0 0.0 16.5 0.0 16.5 17.0 0.0 16.5 17.0 0.0 1.3 1.3 0.0 0.0 0.0 0.0 0.0 0.7 0.0 0.0 0.6 0.1 0.0 0.0 0.0 0.7 0.0 0.3 0.0 0.0 0.0 6.2 5.7 0.0 C C N.C. C N.C N.C. C N.C. N.C. C N.C. N.C. C C C C C N.C. C C N.C. N.C. C C C N.C. C N.C. C C C N.C. N.C. C HOLGURA DE UNA CONDICION ACTIVIDAD HA ij

EVALUACION DE RENDIMIENTOS Y COSTOS UNITARIOS, EN LA CONSTRUCCION DE CANALES Y RESERVORIOS CON MANO DE OBRA COMUNALM, EN LA PROVINCIA DE HUANUCO

SUCESO INICIAL FINAL

i 0 1 2 2 4 3 3 7 5 6 8 9 9 10 11 12 13 13 14 15 15 16 17 18 19 18 20 20 21 22 23 23 25 26

j 1 2 4 3 7 5 5 8 8 8 9 12 10 11 12 13 14 15 15 16 17 17 18 19 20 20 21 22 22 23 24 25 27 29

Tiempo de autorizacin del financiamiento al proyecto Reunin entre la comunidad y residente de obra estrategia de trabajo Limpieza de terreno Trazo, Niveles y replanteo del eje de canal Identificacin de cantera de hormign, piedra, madera Construccin de almacn Excavacin al 100% de plataforma de canal Acarreo de hormign y piedra Transporte de herramientas y equipos a almacn Excavacin de zanjas de cimiento para la bocatoma Vaceado de cimiento izquierdo bocatoma Vaceado de cimiento izquierdo de bocatoma Encofrado del muro derecho de la bocatoma Preparacin y vaceado de concreto del muro dere. de la bocatoma Desencofrado del muro derecho de la bocatoma Encofrado del muro izquierdo dela bocatoma Preparacin y vaceado de concreto del muro izqui. de la bocatoma Desencofrado del muro derecho de la bocatoma Encofrado del barraje Preparacin y vaceado de concreto en el barraje Desencofrado del barraje Instalacin de rejilla Excavacin de zanjas para canal abierto y obras de arte Encofrado del muro del canal Preparacin y vaceado del muro de canal Desencofrado del muro del canal Encofrado de muros de obras de arte (desarenador, rompe presin) Preparacin y vaceado de muros de obras de arte Desencofrado del muro de obras de arte Excavacin de zanjas instalacin de tubera de 4 de dimetro 50% Nivelacin de camas de tubera 50% Excavacin de secciones 1x1m para cajas repartidoras Encofrado del muro de cajas repartidoras Prueba hidrulica al 50% de la tubera

319

vienen...
SUCESO INICIAL FINAL i 27 28 24 29 30 30 32 34 35 31 33 36 37 38 38 39 40 41 41 42 43 44 45 46 46 46 48 49 47 50 51 51 52 53 54 j 28 29 26 30 31 32 34 35 36 33 36 37 38 39 40 40 41 42 43 44 44 45 46 47 48 49 50 50 50 51 52 53 53 54 55 DESCRIPCION DURACION DIAS TIEMPO OPTIMO T I T I TIEMPO PESIMISTA HOLGURA DE UNA CONDICION T I T I ACTIVIDAD HA ij

320

Preparacin y vaceado del muro de cajas repartidoras Desencofrado del muro de cajas repartidoras Instalacin de tubera de 4 de dimetro 50% Excavacin de zanjas para la insta. tubera de 4 de dimetro 50% Nivelacin de camas de tubera 50% Excavacin de secciones 1x1m para cajas reparadoras Encofrado de cajas repartidoras Preparacin y vaceado del muro de cajas repartidoras Desencofrado de cajas repartidoras Instalacin de tubera de 4 de dimetro de 50% Prueba hidrulica del 50% de tubera tendida Relleno con material propio de la tubera de 4 de dimetro 50% Encofrado de cajas colectoras Preparacin y vaceado del muro de cajas colectoras Desencofrado de cajas colectoras Concreto para tapas Explanacin de reservorio Trazo y niveles de plataforma del reservorio Excavacin de seccin trapezoidal del reservorio 100% Traslado de herramientas al almacn Nivelacin de fondo y corona de reservorio Relleno de arena el fondo del reservorio Excavacin de zanjas en el permetro del 0.40x0.40m Tendido y tensado de la geomembrana Prueba hidrulica del 50% de tubera tendida Anclage perimtrico de la geomembrana Supervisin del pegado Cerco perimtrico Camino de mantenimiento Encofrado de caja de vlvulas Concreto de cajas de vlvulas Desencofrado de cajas de vlvulas Instalacin de vlvulas Limpieza total del terreno Entrega

0.5 0.3 6.0 12.00 0.50 0.50 0.50 0.50 0.30 6.00 0.50 1.00 0.50 0.50 0.30 0.30 6.00 0.50 18.00 0.50 0.50 0.25 0.25 0.25 0.50 0.25 0.25 1.00 0.75 0.50 0.50 0.30 0.25 1.00 1.00

41.9 42.4 41.9 48.4 60.4 60.4 61.4 61.9 62.4 62.4 74.4 74.9 75.9 76.4 76.4 76.0 77.2 83.2 83.2 83.7 101.2 101.5 101.8 102.0 102.0 102.0 102.3 102.3 102.3 103.3 103.6 103.6 103.9 104.1 105.1

42.4 48.4 47.9 60.4 62.4 61.4 61.9 62.4 74.9 74.4 74.9 75.9 76.4 76.9 77.2 77.2 83.2 83.7 101.2 101.5 101.8 101.8 102.0 102.3 102.3 102.3 103.3 103.3 103.3 103.6 103.9 104.1 104.1 105.1 106.1

47.6 48.1 41.9 48.4 60.4 60.4 73.6 74.1 74.6 62.4 74.4 74.9 75.9 76.4 76.4 76.9 77.2 83.2 83.2 101.0 101.2 101.5 101.8 102.0 102.0 102.0 103.0 102.3 102.5 103.3 103.6 103.6 103.9 104.1 105.1

48.1 48.4 47.9 60.4 62.4 73.6 74.1 74.6 74.9 74.4 74.9 75.9 76.4 76.9 77.2 77.2 83.2 101.0 101.2 101.5 101.5 101.8 102.0 102.5 103.0 102.3 103.3 103.3 103.3 103.6 103.9 104.1 104.1 105.1 106.1

5.7 5.7 0.0 0.0 1.5 12.7 12.2 12.2 12.2 6.0 0.0 0.0 0.0 0.0 0.5 0.9 0.0 17.3 0.0 17.3 0.0 0.0 0.0 0.3 0.5 0.0 0.8 0.0 0.3 0.0 0.0 0.3 0.0 0.0 0.0

N.C. N.C. C C N.C N.C. N.C. N.C. N.C. N.C. C C C C N.C. N.C. N.C. N.C. C N.C. C C C N.C. C N.C. N.C. C N.C. C C N.C. C C C