TABLA DE SALARIOS

CARGO

SALARIO BASE

FSR

SALARIO REAL
PARA ANALISIS
DE PRECIOS

PEON

$185.71

1.74

$323.14

AYUDANTE FIERRERO

$214.28

1.74

$372.85

AYUDANTE CARPINTERO

$214.28

1.74

$372.85

ALBAIL

$285.71

1.74

$497.14

CABO

$357.14

1.74

$621.42

OF. CARPINTERO

$428.57

1.74

$745.71

OF. FIERRERO

$400.00

1.74

$696.00

OF. ESPECIALIZADO

$500.00

1.74

$870.00

VELADOR

$214.28

1.74

$372.85

BODEGUERO

$321.42

1.74

$559.27

PRECIOS PARA SALARIOS SUPERIORES AL MINIMO, OBRA PRIVADA NO HABITACIONAL

INTEGRACION DE CUADRILLAS
No.

COMPOSICION

OPERACIONES

1/20 DE CABO + 1 PEON

0.05 (621.42) + 323.14

1/10 DE CABO + 1 OF. ALBAIL + 4 PEON

IMPORTE

FACTOR
FACTOR
DE
DEL
HERRAMIENTA
MAESTRO

COSTO TOTAL
DE
LA
CUADRILLA

ACTIVIDADES

$354.21

1.03

1.07

0.10 (621.42) + 497.14 + 4 (323.14)

$1,851.82

1.03

1.07

$2,040.89 PLANTILLAS, FIRMES, VACIADO DE CONCRETO ETC.

1/10 DE CABO + 1 OF. CARPINTERO + 1 AYUDANTE

0.10 (621.42) + 745.71 + 372.85

$1,180.70

1.03

1.07

$1,301.25 HABILITADO Y CIMBRA DE MADERA

1/10 DE CABO + 1 OF. FIERRERO + 1 AYUDANTE

0.10 (621.42) + 696.00 + 372.85

$1,130.99

1.03

1.07

$1,246.46 HABILITADO Y ARMADO DE ACERO DE REFUERZO

1/10 DE CABO + 1 OF. ALBAIL + 1 PEON

0.10 (621.42) + 497.14 + 323.14

$882.41

1.03

1.07

1/10 DE CABO + 1 OF. ESPECIALISTA + 1 AYUDANTE 0.10 (621.42) + 870.00 + 372.85

$1,304.99

1.03

1.07

$1,438.23 COLOCACIONES DE CERAMICA

1/4 DE CABO + 5 PEONES

$1,771.03

1.03

1.07

$1,951.86 ELABORACION DE CONCRETO

0.25 (621.42) + 5 (323.14)

$390.37 EXCAVACIONES, ACARREOS, RELLENOS, ETC

$972.51 TRABAJOS DE ALBAILERIA