Está en la página 1de 24

opening remarks

ello again, and welcome to our second edition of Midwest Building! In todays market, new construction financing has become more critical than ever, in part because of interest rates, banking changes, security issues, and overall market concerns. So for this issue, we concentrated on our pre-engineered building expertise. Highlighted in this issue are buildings that are efficient to build, multifunctional, and can even be designed to limit potential future obsolescence.Whether you are a small business just starting out or a large business that is expanding, we can customize an engineered building for you.

Steve Kuepers Executive Vice President Kuepers Inc., Architects & Builders

MN LIC 0002599

Doug Kuepers President Steve Kuepers Executive Vice President Dan Kuepers Production Manager Jennifer Solseth The Hearth Room Executive Vice President Michael Patrick Controller, CPA Leah Heggerston Director of Marketing Sean Kaneski Director of Project Development Mark Cross Architect, AIA, NCARB Michael Angland Architect, AIA Chris Raimann Architect, AIA Michael Carpenter Mechanical Engineer, PE

Jeremy Adams Property Management & Maintenance Manager Ray Austin Field Operations Manager Todd DeChaine Landscape & Irrigation Supervisor

Project Development Kristopher Solseth Eric Carder Amy Collins Lee Wangstad Dale Ditter Ryan Blank Architecture Eric Larson Sam Koob Andy Waletzko Sarah Goodrow Sarah Schmidt Sarah Rutz

Project Management Bruce Weaver Dan Kennedy Cale LaVoie Paul Reier Mike Hays Roger Lorenz Eric Halbert Nate Holzer Dan Richter Joe Klemmetsen Interior Design/Showroom The Hearth Room Sara Raimann Gwen Burggraff Genevieve Kec Alyssa Barkley Paula Kovatovich Catherine Deutschlander Kendra Johnson Laurie Meller Kate Johnson Anna Struss

14643 Edgewood Drive, Suite 115 Baxter, MN 56425 (888) 829-0707 (218) 829-0383 fax www.kuepers.com

in this issue

Features
Minnesota Inboard Water Sports An industrial building that doesnt look industrial .............................................. 5 Tanner Honda Redefining the pre-engineered steel building .......................................................... 12 Bear Pause Theater Uncommon construction for the ultimate movie-going experience ........................... 19

Industry Reports
Operating Kuepers Green Environmental protection goes beyond just building green ..................................... 8 Taming the Elements Excellence in heating, cooling, and ventilating by Kuepers ............................................ 11
About the Cover: When Tanner Honda in Brainerd/ Baxter planned to renovate an existing structure for its Honda dealership, it called upon Kuepers Inc. to construct a new facility that would combine elements of the owners overall plan with the automobile manufacturers Honda Dealership Image Program.

A Change in Scenery Kuepers landscape design blends nature and construction ......................................... 16

12

21

Midwest Building is published by QuestCorp Media Group, Inc., 885 E. Collins Blvd., Ste. 102, Richardson, TX 75081. Phone (972) 447-0910 or (888) 860-2442, fax (972) 447-0911, www.qcmedia.com. QuestCorp specializes in creating and publishing corporate magazines for businesses. Inquiries: Victor Horne, vhorne@qcmedia.com. Editorial comments: Darren Nielsen, dnielsen@qcmedia.com. Please call or fax for a new subscription, change of address, or single copy. Single copies: $5.95. This publication may not be reproduced in part or in whole without the express written permission of QuestCorp Media Group, Inc. To advertise in an upcoming issue of this publication, please contact us at (888) 860-2442 or visit us on the Web at www.qcmedia.com. April 2008
MIDWEST BUILDING 3

4 MIDWEST BUILDING

After lunch was over, Pam kept the napkin and the couple went looking for an architect and builder to help them turn their second location into a reality. One of the firms they talked to was Kuepers Inc., Architects & Builders. The Muellers chose Kuepers for a number of reasons, not the least of which was its ability to match its designs with what Pam had in her mind and on her napkin. I brought the napkin to Kuepers and said this is what I want. I came back a week or two later, and

Minnesota Inboard Water Sports


An industrial building that doesnt look industrial
By Mark W. Anderson

We created a hybrid system, integrating postand-beam construction with a conventional continuous concrete footing system, and that really worked well. -Mark Cross
Kuepers architecture plans were right on, she said. There was hardly anything we needed to change as far as the design. As it turns out, Pam and Joes experience matches up with the very approach with which Kuepers prides itself. We have a philosophy at Kuepers that were not the ones who live in the building, our customers are, said Mark Cross, the architect at Kuepers who designed the Muellers building. As a result, we dont shoehorn projects into a design style. We are custom builders, and with that in mind, we design whatever fits the customers needs. The 7,211-square-foot building Kuepers created for Minnesota Inboard needed to meet two key requirements simultaneously: it needed a large showroom space yet had to be easy to convert into another type of business should >>
MIDWEST BUILDING 5

or Pam and Joe Mueller, building a store in Baxter all began with a sketch on the back of a napkin. The couple owns and operates the Excelsior, Minnesota-based boat and marine equipment dealer Minnesota Inboard Water Sports. When they decided to expand to a second location in the fall of 2005, they settled on the Brainerd Lakes Area, a popular boating and water sports region in North Central Minnesota. The area is home to a large number of the companys customers in the summer months when the population of outdoor recreation enthusiasts explodes. As operators of a successful business, the Muellers knew what they wanted and went looking for a building in the area that would serve their needs. Unfortunately, they couldnt find

an existing structure that was right for them, so they decided to start from scratch. They found a suitable piece of land, and on the afternoon that they closed on the property, Pam and Joe went to lunch at a local restaurant to talk about their plans. Excitedly, Pam began drawing a sketch of what they wanted their new building to look like on the back of a napkin. If we didnt have this business, I think I would be a designer because I love working with how things are laid out and the design of buildings both inside and out, she said. The Muellers had some clear ideas about what they wanted to see in their new location, such as a large stone fireplace in the main showroom. I had in my mind exactly what I wanted, and I actually drew it on a napkin, she said.

the Muellers decide to sell the building at some point in the future. As the exclusive dealer statewide for the popular and respected line of Malibu boats and other water sports equipment, Minnesota Inboard also wanted the best possible showroom for its products. And Kuepers delivered. When a customer wants a building that can be remodeled, it means that structurally, we think about it as if all the interior walls will be torn out and it can be one big open box, Cross said. As a result, you design it in an entirely different frame of mind. In this case, we created a hybrid system, integrating post-and-beam construction with a conventional continuous concrete footing system, and that really worked well for the project. The building, which boasts approximately 5,000 square feet of showroom space, had to meet the citys architectural guidelines that called for an up north feel for the exteriors of new buildings. As a result, the new building has log siding and a green roof, which is what the Muellers wanted as well. The building site contained part of a wetland, which required Cross and the rest of the Kuepers team to build a storm water containment system and design an ecologically sensitive parking scheme.

Minnesota Inboard was built as a post-and-beam structure so that it could easily be remodeled for a different purpose if need be.

Finally, the Muellers also had some clear ideas about how they wanted to position their display boats around the property. So we created some multi-dimensional sites for the boats to sit and built up some landscaping so you can see the boat and not the trailer, Cross said.

In the spring of 2006, the Muellers opened a dealership in the Brainerd Lakes Area. Minnesota Inboard, open year-round, provides residents with a diverse selection of direct drive inboard boats.

For her part, Pam Mueller says everybody at Minnesota Inboard Water Sports is pleased with the result. The folks at Kuepers from Steve Kuepers himself to everyone who helped construct the building were so easy to work with, she said. Everything went smoothly. From the very beginning, I walked the site with the guys and they always listened to my ideas. Pam and Joe were so pleased, in fact, that they ended up asking Kuepers to do some remodeling work on their vacation cabin. I think you can genuinely tell the employees enjoy working there, Pam said. We built the new location throughout the winter, and despite how cold and miserable it got, everybody I talked to genuinely loved their work. It was a really good experience, and I have recommended them to many people. And the napkin? As far as Pam knows, it stayed with Kuepers in their project files, an integral part of the communication necessary to build a good building.

6 MIDWEST BUILDING

MIDWEST BUILDING 7

Environment

Operating Kuepers Green

Environmental protection goes beyond just building green

perating green whenever possible is as important as building green. Kuepers continues to take steps in its day-to-day functions to maintain and promote green operations. We recycle as much waste as possible in the office and on jobsites. Materials such as cardboard, oil, scrap metal, and copper are always separated from the rest of construction waste on jobsites for recycling. Kuepers will recycle anything at the request of the client; however, it may be at additional cost and time. In the case of a demolition for remodels, a project has to be taken apart piece by piece, dramatically slowing down the building schedule.

There are many other ways that Kuepers prevents construction waste U  sing durable products, such as stone and ceramic tile U  sing building products made from recycled material U  sing salvaged or reclaimed building materials M  inimizing the use of products with excessive packaging B  uying locally produced building materials, which reduces energy use and transportation pollution P  rotecting trees and topsoil during construction C  entralizing cutting operations to reduce waste and simplify sorting E  ducating our crews about recycling procedures D  onating salvaged items to local organizations like Habitat for Humanity Kuepers continues to look for more economical ways to operate green, from purchasing recycled office supplies to providing project managers with fuel-efficient cars for driving to and from jobsites.

8 MIDWEST BUILDING

MIDWEST BUILDING 9

10 MIDWEST BUILDING

Energy Efficiency

Taming the Elements


Excellence in heating, cooling, and ventilating by Kuepers

By Michael D.Carpenter, PE Mechanical Engineer

he unpredictability of Minnesota weather wont affect your comfort level when you work or live in a building environment with a heating and cooling system from Kuepers Inc., Architects and Builders. Our in-house mechanical experts design heating, cooling, and ventilating systems (HVAC) with your year-round comfort in mind. There are many benefits to having an in-house mechanical team. As a mechanical engineer I am involved early on in new construction and remodeling projects. I work alongside our architects to ensure that each buildings climate and moisture control needs are properly addressed. The sizing of equipment, placement, and number of supplies and returns are all factored into the design. We install equipment known for optimal performance, reliability, and energy efficiency. Kuepers will learn your heating and cooling needs, assist you with any challenges, and customize a mechanical system so it works for you.

Kuepers Heating, Cooling, and Ventilating


 Commercial and Residential  New Construction and Remodeling  On-call Service Technician 24/7  Seasonal and Preventive Maintenance Programs

Types of Equipment/Systems
Numerous options are available at Kuepers: Forced Air Furnaces Multiple or single zone furnaces heat and circulate air through a ductwork system. They are rated for energy efficiency by an Annual Fuel Utilization Efficiency (AFUE) percentage. The higher the AFUE rating, the higher the systems efficiency. In-floor Radiant Heat/Hot Water Boiler System Water is heated by a boiler through flexible tubing beneath the floor. Heat Recovery Ventilators Todays tighter buildings are designed to improve energy efficiency by eliminating heat loss around doors, windows, and other areas prone to drafts. Without a heat recovery ventilator (HRV), pollutants can be trapped inside, creating poor indoor air quality. HRVs provide better ventilation by bringing fresh outside air into the building while expelling stale polluted air. The core transfers heat from the outgoing air to preheat the incoming fresh air. Central Air Conditioning Central air works with a furnace or air handler to remove heat from indoor air. Cooled air is then transferred throughout the building through ductwork. The level of energy efficiency is measured by the Seasonal Energy Efficiency Ratio (SEER). The minimum SEER standard is currently 13. When your HVAC system is designed by Kuepers, you can be assured that we have looked at the big picture without overlooking the smallest of details.
MIDWEST BUILDING 11

Redefining the pre-engineered steel building

Tanner Honda

12 MIDWEST BUILDING

anner Companies in Brainerd renovated an existing auto dealership for a new facility that would conform to the Honda Dealership Image Program (HDIP). The theme of Hondas design philosophy was to redefine the Honda experience with the following goals:  Establish a consistent image where there was no consistency.  Create a customer-friendly environment where there was apprehension.  Enhance dealership efficiency and capacity to prepare for the future.  Create a unique shopping experience and inspire loyalty. John Tanner was not convinced, however, that Hondas prototype HDIP blueprints would fit with the needs of his employees or customers. While Tanner was contemplating his options, he learned that a major road construction project would be taking place during his dealership construction. This would result in road construction on three sides of the Tanner Honda property. Construction plans were put on hold until it was determined how much of the owners property would be lost to the road construction as the Minnesota Department of Transportation and the City of Brainerd negotiated the right-of-way boundaries. The owner ultimately decided to take advantage of the road construction and eliminate several older buildings on the prop-

erty and proceed with a new Honda building that would provide better visibility and customer access. According to Honda, other than our great products, there is no clearer way to show off our quality than through our dealership facilities. It was evident, however, that the majority of the HDIP prototypes were intended for larger markets and simply would not fit the owners property or operating methods. In the car dealership business for 30-plus years, Tanner had specific ideas regarding the design, layout, and features he wanted incorporated into the new building, which would be constructed as a pre-engineered steel building. It was the goal of Kuepers architectural staff to create a plan that would please both the owner and Honda. The architectural staff received an HDIP manual to provide them with design ideas and planning guidance. Essential elements of the HDIP design included  the entry cylinder with Honda H logo  the Honda Wave, a curved edge canopy with upswing smile at the end  curvilinear shapes to create a unique image and define functional spaces that flow easily to one another  a color palette of specified colors for interior/exterior walls and furnishings to complement the Honda Blue  roadside signage designed for consistency in design, color scheme, and curvilinear shape  building signage with specific guidelines for placement and fascia type/size. Patterns and materials used at >>

According to Honda, other than our great products, there is no clearer way to show off our quality than through our dealership facilities.

MIDWEST BUILDING 13

the building exterior were chosen to showcase the signage by providing a suitable backdrop highlighting the essential image elements  service center placement near front of facility to give the same degree of courtesy, respect, and professionalism to the customers as demonstrated in sales areas  showroom areas, reception, information center, kids play area, vehicle displays, and sales consultation stations designed to create an inviting, nonthreatening customer environment The Kuepers architectural staff came up with a preliminary design for the pre-engineered steel building, tailoring the HDIP design elements with Tanners requirements. Negotiations between Hondas architect in California, the owner, and Kuepers architectural staff went back and forth until the parties involved arrived at an agree able design.

Obstacles to Overcome
Zoning During the preliminary plan review process with the city, it was discovered that the previous dealership did not have the necessary zoning classification changes to the property. The property was zoned industrial rather than commercial. As a result, formal rezoning process resulted in a one-month delay in the start of the project. Steel Crisis Financial strife in the chosen steel building suppliers company changed initial delivery time from six to eight
14 MIDWEST BUILDING

weeks to more than 14 weeks. This instability of the company led to a last-minute decision to find another steel building supplier who could fulfill the contract and meet the timetable. Design and engineering processes previously initiated with the first company had to be repeated with the subsequent steel building supplier. Site Work One of the early goals was to complete the exterior concrete and base course of paving prior to winter. Before this could begin, extensive site work had to be accomplished. An existing 50x100 pole building on the property was dismantled and donated to a local nonprofit group. Originally, the site had been used as a concrete ready-mix plant (thus the industrial zoning), and one corner of the property had been used as a dumping ground for unused concrete 2,907 cubic yards of concrete rubble had to be removed from the site. A fiber optic line also had to be moved before site grading and building excavation could begin. Construction Phase Concrete work began in the fall. By the end of September, the storm sewer system was being installed and underground rough-in utilities and inflammable waste system were under way. By October, the concrete slab and sidewalks were being poured. When the steel building contractors progress in setting the steel began to lag, it had to increase the size of its crew to get back on schedule. Rains and early snows also put the paving contractor behind schedule, but by the end of October, the base course of paving was placed. Landscaping crews were planting trees and shrubs at the perimeter of the parking lot. This gave the owner more

Kuepers architectural staff came up with a design for the pre-engineered steel building, tailoring the HDIP design elements with the owners requirements until all parties arrived at an agreeable design.

usable space for displaying car inventory during the remainder of construction. Changes to materials and design were implemented throughout the project. The architectural staff was concerned that decorative tiles specified for the exterior of the building could pose a water penetration issue. Due to the fluctuating weather of northern Minnesota, water penetration and freezing temperatures could cause the tiles to pop out of place. Plastic architectural panels in gray were substituted for the tiles. Routers were used to create grooves in the panels and the grooves were filled with grout for a simulated tile effect. Another concern was the design and structural support of the Honda Wave. Changing to a tubular steel construction will prevent snow from accumulating on the canopy. Bymidwinter, interior work was well under way. The project had been designed to meet Uniform Building Codes, but changes were required during construction when the International Building Codes went into effect. Owner-requested changes were also made during construction to the service department area. The size of the oil storage room was increased, and insulation was added to the walls to reduce the noise of the air compressor. An oil and air distribution system was also added to each service bay. By early spring, the new state-of-the-art Honda dealership was substantially completed. The final numbers for this costplus project were within less than 1 percent of the original cost estimate.
MIDWEST BUILDING 15

Environment

A Change in

Scenery
Kuepers landscape design blends nature and construction
By Todd DeChaine, Landscape and Irrigation Supervisor

andscaping your home or commercial property makes an impressive statement and is an important investment. Additionally, a key focus of landscape design and maintenance today is about promoting and protecting the environment. Landscaping is both science and art, requiring good observation and design skills. A good landscaper understands the elements of nature and construction, and blends them accordingly. At Kuepers Inc., Architects & Builders, our in-house landscape design and irrigation specialists are Minnesota Landscape Association (MNLA) certified. Their training and continuing education ensures that they are abreast of changing methods, techniques, original design, and environmental regulations. From perimeter plantings to outdoor kitchens, shoreline restorations to swimming pools, recreational courts, or fire pits, the design and implementation of each Kuepers landscape project is a combination of creative planning, accurate estimating, and beautiful workmanship. Furthermore, Kuepers offers spring and fall maintenance, lawn care services, and general property maintenance ensuring that your lawn, plantings, and focal points will continue to thrive and look beautiful for years to come. Landscape planning at Kuepers can occur before or after a home or building exists. Kuepers has all the options available for
16 MIDWEST BUILDING

you to consider, including retaining walls, stone, rock, ponds, water features, swimming pools, decks and patios, driveways and sidewalks, pavers and timbers, pergolas and trellises, natural screenings, sod, irrigation systems, landscape lighting, flower beds, trees and shrubs, fencing, beaches, rip-rap, and more. If you can envision it, we can design it. When planning your landscaping project, let the experts at Kuepers manage and coordinate the details. Kuepers landscaping department is equipped to handle all aspects of a project, including:  irrigation/lawn maintenance needs  drainage and storm water runoff issues, ground water quality, and topography impervious coverage limitations b  each and shoreline guidelines p  ermitting requirements and processes Kuepers will learn your needs, assist you with challenges, and customize your landscaping project so it works for you. Kuepers Landscaping Services will ultimately save you time and money, and provide you with a fun, creative planning experience, resulting in a beautifully completed project.

MIDWEST BUILDING 17

18 MIDWEST BUILDING

Bear Pause Theater


Uncommon construction for the ultimate movie-going experience

ith a year-round population of 285 residents, the small community of Hackensack, Minnesota, and its surrounding area swells to approximately 100,000 during the summer months and on weekends year-round as people flock to nearby cabins and resorts. A four-season tourist destination, the town boasts 127 lakes in a 10-mile radius, attracting fishing, boating, and snowmobile enthusiasts. To take advantage of this population explosion in 2005, the Bear Pause Theater was built. The location of the theater required extensive research. Choosing the Hackensack area for its Up North atmosphere provided the opportunity for permanent and seasonal residents alike to enjoy the big screen without having to drive 45 to 60 miles. After choosing the Hackensack community, the owners took their research a step further and asked the Minnesota Department of Transportation to perform traffic counts to see how

many vehicles traveled the road going past the proposed building site. The owners wanted to create a stateof-the-art theater, so they traveled throughout the state visiting other theaters and experiencing for themselves the

Scheduling issues and setbacks were a challenge throughout the project. From a bad shipment of concrete to weather issues and delays, the project manager and foreman were busy juggling construction crews to meet the schedule.

Pre-engineered steel eliminated the load-bearing walls commonly associated with theater designs, reducing the amount of functional obsolescence if the building is converted to another use in the future.
features they thought their patrons would enjoy. A great deal of planning went into the Bear Pause Theater project by its owners prior to the design and construction of the building itself. The owners goal was to provide the ultimate movie-going experience in the region. Site work began in August 2005 and involved bringing in 10,000 yards of fill. Winters early snows and ice, followed by springs soupy mud made maneuvering equipment tricky. Keeping the project moving forward was adroitly handled by Kuepers Project Management staff, who brought the project to completion on schedule, within budget, and, most important, to the >> customers satisfaction.
MIDWEST BUILDING 19

After discussing different types of building construction, and with the owners overall budget in mind, pre-engineered steel construction was chosen.

theater equipment contractor because there were few comparable projects in the Minnesota/Wisconsin area to learn from.

Dcor inside and out was carefully coordinated with the interior designers at The Hearth Room, a division of Kuepers.
Pre-engineered steel eliminated the load-bearing walls commonly associated with theater designs, reducing the amount of functional obsolescence if the building is converted to another use in the future. As a money-saving alternative to the concrete block construction typically used for movie theaters, the pre-engineered steel building presented its own set of unique challenges. Finding solutions to those challenges was a challenge in itself for Kuepers and the A major challenge was sound transmission. A combination of inventive and unique steps were taken to address this:  Sand-filled concrete masonry walls separate common areas and theater bays. An expansion joint allows for movement of the steel building without adversely affecting the stability of the block walls.  A ll seams were sealed with a rubber membrane.

T  he building features a Simple Saver Roof System. S  pecialty sound control panels provide additional soundproofing. T  here are two layers of gypsum board on each side of the common walls. T  he HVAC ductwork was insulated to eliminate air rattles. A decibel test was conducted to measure sound transmission between theater bays, proving these additional construction techniques to be successful. The theaters total seating capacity is 495 including a handicap seating capacity of 16. Although the size of the building remained the same, the number of theater bays was changed from three to four during the design phase. Safety concerns related to the stadium seating were addressed by providing adequate lighting, handrails, and two exits to meet handicap accessibility requirements.

Pre-engineered steel was chosen for the building construction. This method eliminated the load-bearing walls commonly associated with theater designs, reducing the amount of functional obsolescence if the building is converted to another use in the future.

20 MIDWEST BUILDING

For the concession stand awnings, Kuepers personnel literally dug rusted tin from beneath a snow bank. The distressed look of the material turned out to be exactly what the owners wanted.

The platform seating system was made up of foam block with a metal edge forming the platform risers. The size and configuration of this platform-type seating meant pumping the concrete in to each theater from the concrete truck, taking eight men to perform the task. Technology by 1Better, LLC, offers professionally produced full-motion movie screen advertising complete with voice narration and background music. Innovative Hitachi audio, digital, and video technology presents multipurpose opportunities at Theater Bay 1, including gaming tournaments, training programs (currently utilized by the Department of Natural Resources), and local church services. A VIP room with an individual sound system, two rows of stadium seating, couches, a kitchenette, and restrooms for private groups overlooks Theater Bay 1. The 24-foot-long concession stand offers more than the standard popcorn/ candy fare. A private room located near the lobby and concession area is available for small parties and events, and an arcade room keeps kids entertained between movie starting times. Dcor inside and out was carefully coordinated with the interior designers

at The Hearth Room, a division of Kuepers. Rustic Up North touches stone wainscot, log and stone columns, log trusses and trim soften the stark appearance of the steel at the buildings front facade. Interior walls feature warm v-joint paneling and log accents. Reclaimed tin roofing material used for the awnings above the concession stand and ticket booth areas adds an old-time camp

flavor. After locating a supplier for the roofing material, Kuepers personnel literally dug the tin out from beneath a snow bank, all the while wondering how the owners would react to the tin that had rusted from the moisture of the snow. Fortunately, it was exactly what the owners were looking for and no additional aging or distressing techniques were needed. A path leading from the ticket booth to the concession stand was ground into the stained concrete flooring. Stained a darker color to resemble a well-worn dirt trail, closer inspection reveals a set of bear tracks. The authentic bear tracks were created with a mold of the paws of a real mounted bear owned by one of the theater owners. Much attention was given to the project by the community and local media. Excitement and anticipation built along with the construction progress. The Grand Opening, held on March 31, 2006, was a gala event as community members, business leaders, and silver screen fans eager for buckets of hot, buttery popcorn welcomed the new theater with open arms.

For Hackensack and surroundi n g c o m m u n i t i e s o f n o r t h e r n Minnesota, moviegoers are able to watch first-run films in a state-of-theart cinema theater without having to drive 45 to 60 miles out of the way. Bear Pause Theater is a 144-footby-90-foot building with four theater screens. The largest theater seats 189 people, another 123 people, and the two smaller theaters seat about 90 people. Bear Pause offers many other amenities including a party room and a VIP room that can be rented for special events such as birthdays,anniversaries,Christmas parties, etc.

Features:
 Open seven days a week  Four theater screens  Seating capacity 497  Top of the line stadium seating complete with cup holders.  Large lobby  Refreshments  Arcade room  Private party and VIP room  The latest film projection technology  Digital sound  Handicapped seating and hearing impaired devices

MIDWEST BUILDING 21

Directory

Acucraft Fireplace Systems ................................................. see page 17 Aitkin Glass Service . ........................................................... see page 22 Brainerd Glass, Inc. . ........................................................... see page 18 Brainerd Waterproofing . ..................................................... see page 18 Bremer Bank . ...................................................................... see page 18 Brothers Fire Protection . ..................................................... see page 9 Detroit Drywall . ................................................................... see page 7 Electrical Systems ................................................. see inside back cover Ferguson Enterprises, Inc. ..................................................... see page 7 First Federal ....................................................................... see page 17 Holden Electric Co., Inc. . ................................................... see page 18 JBerd Mechanical Contractors, Inc. . .................................. see page 17 Jims Electric Co., Inc. . ......................................................... see page 8 Kurilla Real Estate ............................................................... see page 4 Les Jones Roofing Inc. ......................................................... see page 17 Marco Business Products . .................................................... see page 9 Midwest Security & Fire, Inc................................................. see page 18 Nardini Fire Equipment ........................................................... see page 4 North Country Plumbing & Heating...................................... see page 18 Positive GMAC Real Estate.................................................... see page 9 ................................................................. see page 10 RRC Specialties .. Scenic Sign Corp. PO Box 881 Saint Cloud, MN 56302 (320) 252-9400 (320) 252-4260 Fax www.scenicsign.com Schwartz Redi-Mix. .............................................................. see page 22 Short Elliot Hendrickson, Inc. . ........................................... see page 15 Simonson Lumber.................................................................. see page 10 Stellmach Drywall, Inc. . ....................................................... see page 4 The Hearth Room . .............................................................see back over Twin City Acoustics 2655 Cheshire Ln. N. Plymouth, MN 55447 (763) 535-6697 (763) 535-5309 Fax www.tcacoustics.com W W Thompson Concrete .................................................... see page 10

22 MIDWEST BUILDING

Kuepers Inc., Architects & Builders 14643 Edgewood Drive, Suite 115 Baxter, MN 56425

También podría gustarte