FEL Modules Adapted from Strategic Project Planner, b y Westney Consultants International, Inc.

FRONT END LOADING WORK FLOW PROCESS


10% FEL 2 PROCESS Engineering Alternative Selection
Create Permitting Plan
Lessons Learned

25-30% of Engineering

SCOPE DEFINITION PHASE FEL 3


Line List SP List Lessons Learned Instrument Index Tie-In List

INITIATE PERMITTING PROCESS

PROCESS SIMPLIFICATION

PDRI
FEL-L Information Management Plan

PDRI
FEL- B: Materials Management Plan

INITIATE FORMAL MANAGEMENT OF CHANGE PROCESS

Preliminary Hazards Review

FEL- G: Schedule FEL- A: Design Management Plan Constructability Check List Formal Review FEL- F: Cost Management Plan Management Plan

FEL- I: QA/QC Management Plan

FEL 2
PFD's
PLOT PLAN EQUIPMENT LIST
Team Integration Session 1 FEL-E Specialist Participation Plan Responsibility Matrix

Risk Analysis Contingency Setting

FEL 3
P&ID'S ISSUED FOR COMMENT Team Integration Session 2

VALUE ENGINEERI NG

PDRI

15%
P&ID's ISSUE FOR APPROV AL CONDUCT HAZ ARDS REVIEW P&ID's ISSUE FOR DESIGN

Risk Analysis Contingency Setting

CLASS III ESTIMATE Decision DEVELOP P&ID'S -25%, +30 %

CLASS III ESTIMATE -10% , +10%

Contract & Procurement Strategy

DEFINE: AREAS/CBS/WBS

Detailed Contract & Procurement PLAN INTERACTIVE PLANNING

FEL- M: Change Management Plan FEL-H Commissioning & Startup Plan FEL- J: Safety Management Plan

FEL-C Construction Management Plan

EQUIPMENT Responsibility Matrix LOCATION DRAWINGS

SCHEDULE LEVEL: III Engineering II Construction

DEVELOP MATERIALS MANAGEMENT PLANNING FOR ENGINEERED EQUIP , FABRICATED PIPE/STEEL, THEN BULKS ENGINEERED EQUIPMENT - DEVELOP EQUIPMENT DATA SHEETS

Ford, Bacon & Davi s, LLC


John Fish FELW FD-2.PPT Rev 14 Sept 2004

ENGINEERED EQUIPMENT - INQUI RY & BID EVALUATION TO DEFI NE P RICING/DELIVERIES


OPERABILITY, RELIABILITY, & MAINTAINABILITY PLANNING & REVIEWS

DESIGN FOR SAFETY & CONSTRUCTABILITY: Establish Philosophy and then conduct Ongoing Constructability/Safety Reviews